SCOPE OF WORK Amount Pct Wt.

START FINISH DURATION WK1


45000000 46% WK 1 WK 5 5 9%
14000000 14% WK 3 WK 6 4
12000000 12% WK 4 WK 7 4
26000000 27% WK 5 WK 8 4
Total Amount 97000000 100%

WEEKLY PROGRESS TOTAL 9%


CUMMULATIVE PROGRESS 9%
ACTUAL WEEKLY 12%
ACTUAL CUMMULATIVE 12%

S-CURVE
120%

100%

80%

60%

40%

20%

0%
WK1 WK2 WK3 WK4 WK5 WK6 WK7 WK8
WK2 WK3 WK4 WK5 WK6 WK7 WK8
9% 9% 9% 9%
4% 4% 4% 4%
3% 3% 3% 3%
7% 7% 7% 7%

9% 13% 16% 23% 13% 10% 7%


19% 31% 47% 70% 84% 93% 100%
15% 26% 10% 11% 9% 5% 12%
27% 53% 63% 74% 83% 88% 100%