Work Schedule

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Name M-1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21

2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25
1 TEMBUSU PRELIMINARY LEVEL 2 PROGRAMME (REV.A)
2 Key Milestones
3 Start
4 End
5 MCD
6 BOMBA Inspection
7 Authority Submission & Approval
8 DO Submission & approval
9 Building Plan Submission & approval
10 Obtain Early Commencement Letter
11 Project Execution Plan & Procedures
12 Engineering
13 Basic Engineering
14 Detail Engineering
15 HAZOP Review
16 Pre-construction HSSE Review
17 Procurement
18 Spun Piles
19 Tank Plates
20 Pipes & Fittings
21 Product Pump
22 MLA
23 Gangway
24 Cable
25 VFD
26 ESV, XV Valves
27 Top up Material
28 Construction
29 Tank Terminal
30 Site Preparation
31 Civil & Structure
32 Piling Work
33 Admin & CCR Building
34 Loading Pump Pit
35 LCS Building
36 Underground Piping
37 Tank Foundation
38 Bundwall, Sleepers & Other supports
39 Road Ramp, Road & Premix and Drainage
40 Steel Structure Fabrication & Erection
41 Blasting & Painting
42 Tank
43 Scaffolding
44 Piping
45 Mechanical Installation
46 Electrical & Instrumental
47 Jetty
48 Site Preparation
49 Dredging Works
50 Dredge Adjacent at Trestle & Berths area
51 Dredge remaining area
52 Piles procurement & Piling Work
53 Piles Procurement & Fabrication Work
54 Piling Work
55 Trestle
56 U-Beam Fabrication
57 U-Beam Installation
58 Main Trestle Part A (Firepump Platform)
59 Main Trestle Part B (FP to End)
60 Outer Arm Trestle
61 Pipe Loops, Fire Pump Platform & S Craft Habour
62 Misc RC Platforms
63 Berths
64 Berth 6305
65 Berth 6304
66 Berth 6303
67 Fittings & Accessories
68 Others
69 Module Installation
70 Ship Arrestor's upper structure
71 Piping & Top Sides
72 Trestle
73 Berth 6305
74 Berth 6304
75 Berth 6303
76 Commissioning
77 Pre-comm & Comissioning
78 PSSR

Project: Tembusu Project Level 2 Programme (Rev.A) Task Progress Summary External Tasks Deadline
Date: Fri 18/05/18 Split Milestone Project Summary External Milestone

Page 1