Professional Documents
Culture Documents
Mechanical Dewatering Alternatives Final Draft PDF
Mechanical Dewatering Alternatives Final Draft PDF
Objective
The objective of this technical memorandum (TM) is to identify suitable mechanical
dewatering alternatives for the City of Folsom (City). This TM covers an initial screening of
mechanical dewatering alternatives, further evaluation of the recommended alternative, and
recommendations for an interim plan until the permanent solution can be implemented.
Introduction
The Folsom water treatment plant (WTP) is owned and operated by City of Folsom Utilities
Department. It is designed to produce 50 million gallons per day (mgd) of treated drinking
water. The raw water feed to the plant comes from Folsom lake and generally has low turbidity,
but can experiences seasonal high turbidity events associated with rainfall in the watershed. The
WTP consists of following processes:
Rapid mix
Pretreatment: parallel processes of conventional flocculation(floc) /sedimentation
(sed) basin and Actiflo high rate clarification units
Conventional sand/anthracite dual media filter
Chlorine Contact Tank (CCT)
Backwash Reclamation Basins
Solids handling facilities: Sedimentation basins and sludge lagoons/drying beds.
The residual solids generated from Actiflo and dual media filter processes are thickened in
Floc/Sed Basins No. 1 through 4. The thickened sludge from Sed Basins 1 through 4 and
residual solids generated from Sed Basin 5 are discharged to sludge lagoons (lagoon) No. 1
through 3. Reclaimed backwash water (RBW) from the filters is recovered in Backwash
Reclamation Basins and deposits are discharged to Lagoon 1 through 3. Figure 1 shows
process flow diagram of the treatment plant.
The current residual solids handling method releases odors that have resulted in complaints
from residents near the plant. To maintain the WTP odor free, the City selected mechanical
solids dewatering as an alternative to their residual solids management plan.
This TM discusses and evaluates the dewatering alternatives discussed with the City at the
kick-off meeting. The evaluation includes advantages and disadvantages, anticipated
performance, estimated capital cost and operations and maintenance (O&M) costs. The TM
also covers further evaluation of the screw press alternative that was selected by the City at
the draft TM review meeting. The evaluation includes a conceptual layout of the dewatering
process and recommendations for an interim plan.
Background
Historically the City has used a contractor to periodically remove, dewater and dispose
residuals from the sludge lagoons. Since this process was expensive, the City started
implementing a residuals management plan based on Malcolm Pirnie’s Residuals
Management Evaluation and Plan report submitted in 2007. The plan was to implement non-
mechanical dewatering option by converting lagoons to sludge drying beds.
The proposed plan was to use first lagoon to receive 2 percent thickened sludge from Basins
1 through 4, second lagoon to drying bed and third lagoon to promote evaporative drying
process of dewatered sludge. Lagoon No. 1 is currently unlined to use as drying bed. In
early 2012, the City began to turn over the solids in one of the converted drying beds. A few
weeks later, the WTP received odor complaints from residents in the neighborhood of WTP.
To mitigate the odors, the City again capped the lagoons with a layer of water. In the
meantime, the City contracted HDR to perform an investigation as to the possible causes
and possible mitigation for the odors. In a TM dated February 22, 2013, HDR
recommended that conversion of the lagoons to drying beds not be implemented and the
mechanical dewatering be evaluated.
In meetings with the City in March 2013, the following dewatering alternatives were
identified for consideration in the initial screening evaluation:
Mechanical dewatering
Belt Filter Press (BFP)
Centrifuge
Screw Press (SP)
Plate and Frame Filter Press (PFFP)
Rotary Press (RP)
Discharge to sewer after thickening waste streams
Further, the City agreed to use plant historical data presented in Malcolm Pirnie’s Residuals
Management Evaluation and Plan in 2011 report and to add additional 25 percent to residual
solids production rate to account WTP’s design capacity. The City provided WTP’s data
from 2009 through 2012. This data was compared with the data presented in Malcolm Pirnie
report. The recent data was greater than what was presented in Malcolm Pirnie report and
used in this TM to calculate projected sludge production for evaluation.
The City suggested at the Kick-off meeting that the existing abandoned automatic back-
wash (ABW) filter building may be used to locate dewatering equipment and aqua ammonia
and chemical storage building which is not in service may be used to locate polymer storage
and blending. At the draft TM review meeting City decided to install dewatering equipment
outside of ABW filter building and build a canopy to cover the units, construct sludge
thickening tank in Lagoon No.1 and use aqua ammonia and chemical storage building to
install polymer storage and feed system.
The existing sewer connection from WTP has 100 gpm capacity.
The City requested the initial evaluation of these dewatering alternatives. Based on the
results of this initial screening and experience from site visits, the City selected screw press
alternative for further evaluation. The follow-up evaluation will refine the screw press
dewatering alternative capital and life cycle costs and also consider the constructability,
filtrate water quality, operation complexity and other non-economic factors.
Solids Production
The City provided HDR with monthly plant operating data [turbidity and Aluminum
Chlorohydrate (ACH)] from 2009 through 2012. This data was reviewed and compared to the
historical data presented in Malcolm Pirnie report 2007. The review resulted in to use flow data
from Malcolm Pirnie report and turbidity and ACH from recent plant operation data, and to add
25% to residual production to account build-out capacity. Table 1 provides solids production
estimated with seasonal fluctuation.
Based on Table 1, the dewatering alternative will be designed based on following conditions:
As in the current operation sludge from Sed Basins 1 through 5 will be continued discharging
to Lagoons No.1 through 3 and allowed to thicken. A remote controlled dredge will pump
thickened sludge from lagoons to a homogenization tank from which the dewatering equipment
will be fed. The dredge floats on the water and runs on a guide rail along the grid. The auger at
the front bottom of dredge excavates the thickened or settled sludge and directs to submersible
pump suction. The pump discharge (flexible pipe) will be connected to an outlet located at
shoreline, to discharge to homogenization tank. The dredge is movable from one lagoon to
another using a crane or forklift. Figure 2 shows illustrative image of dredge installation.
Figure 2. Remote controlled dredge with guide rail system (Liquid Waste Technology's dredge)
Dewatering Alternatives
Dewatering equipment removes water from thickened and conditioned sludge using an external
force to produce a sludge cake with a high solids concentration (15 to 30 percent solids). The
factors that influence selection of dewatering technologies include: type of solids being
processed, quantity and quality, continuous or batch process, and operation and maintenance
requirements (odor, noise, washwater, labor attention, chemical and energy consumption,
equipment repair and replacement and etc.). Performance of mechanical dewatering equipment
for water treatment residual solids may slightly vary depending on the raw water quality and
the chemicals being used in the treatment processes.
To minimize impacts to the City’s sewer collection system, the sludge disposal should occur
during the low-flow periods. Impact of sludge thickening is analyzed in following section.
Table 3. SRCSD Sewer Impact Fee for Industrial Users (Source: SRCSD Consolidated Ordinance)
Quantity Cost
Sludge flow 249,000 gal/month $10,707
Solids loading 41,400 lb/month $1,554,611
BOD loading 83 lb/month $1,043
Total (rounded) $1,566,000
Table 4 shows the estimated sewer impact fee for difference conditions:
Table 4 shows that there is no significant reduction in sewer impact fee by thickening the
sludge prior to discharge. However, this finding should be confirmed by SRCSD. Residual
sludge from Sed Basins 1 through 5 (0.3% solids) could be directly pumped to SRCSD sewer.
The City can negotiate and work on discharge schedule with SRCSD to discharge residual
sludge (0.3% solids) to sanitary sewer during off-peak hours. If a workable discharge schedule
cannot be found, annual operation and maintenance cost will also be performed to evaluate
impact of sludge thickening prior to sewer discharge.
New sludge pumps are required to pump sludge from Sed Basins to sanitary sewer. Two (1
duty and 1 standby) 100 gpm pumps are estimated for this purpose. Actual sewer impact fee
may be different from estimated fee. See Attachment C for sewer impact and discharge fee
calculation.
Sewer Rates
Table 5 provides monthly sewer rates for industrial users to use SRCSD sewer.
Sewer discharge fee for 2% thickened sludge at annual average condition shall be calculated as
follows:
Gravity zone: water in the feed is allowed to freely drain through porous belts
The BFP is open to the room and operates as continuous feed unit. Some installations have
hoods that can be located over the top of the units to collect foul air. The system may include
sludge feed pump, polymer mix and feed system, polymer sludge mixing device, BFP, belt
washwater booster pump, sludge discharge conveyor, and electrical control panel.
Belts have to be replaced with time due to tear and wear. The belts used in high pressure zone
have an estimated life of 2,000 to 3,000 hrs. Significant amount of water is required for
washwater and estimated amount varies from 25-30 gpm/meter of belt at 80 psi to 110
gpm/meter of belt at 130 psi pressure. Plant effluent can be used for washwater and a booster
pump may be required to deliver high pressure washwater.
Figure 4. Typical belt filter press schematic diagram –horizontal option (Source: EPA, 1986)
Centrifuge
A centrifuge operates by allowing sludge to enter at a stationary tube where it is fed into a
rotating bowl that contains an accelerating inlet rotor. The rotor rotates at speeds up to 3,400
revolutions per minute (rpm) creating centrifugal forces that push solids to the outer wall of the
bowl. A conveyor rotates in the opposite direction of the rotor collecting the solids and
discharging them to a chute at the end of the bowl. The liquid that is separated from the solids
is called centrate. During the process of separation, the liquid is conveyed to the opposite end
of the equipment from the solids.
Figure 5. Typical centrifuge thickening and dewatering system (EPA Biosolids Fact Sheet, EPA 832-F-00-053,
Sep 2000)
Polymer usage varies from 10 to 30 lbs per dry ton solids. Solids loading rate depends on
equipment size which depends on sludge residence time, pond volume, cake quality required,
and hours of operation.
Residuals production throughput capacity in dry tons per day determines the sizing and quantity
of screw presses in any particular design. Equipment manufacturers size the equipment based
on the sludge quality and quantity, and operational requirements. Generally polymer
consumption for a screw press ranges from 20 to 40 lb/DT solids, sludge retention time is
approximately 4 hours and motor speed is as low as 0.3 rpm.
The PFFP is one of the oldest solids separation methods that produce highest solids
concentration solids. It is widely used in industrial applications than in municipal. For large
application, automatic plate-shifting system is incorporated in the filter press to press plates and
filter cloths, sealing the edges of cloth, resist the filtration pressure developed by feed pump
and shift plates to discharge cake. In small application, the plates have to be manually clamped
and shifted to load slurry and to discharge cake.
The PFFPs are sized based on the volume of sludge to be processed. Additionally, seasonal
variation in sludge quantity and future sludge production should be taken into account in sizing
a PFFP. Selection of correct filter cloth is important to ensure release of cake, minimize
cleaning requirements and maximum service life. Solids concentration of cake produced is
independent of feed solids concentration. A schematic showing how a plate and frame press
operates is shown in Figure 6. A photo of the PacPress system is shown in Figure 7.
Multiple RPs can be mounted/connected to a single motor. It is a modular system and modules
can be added to meet high flow rates in near terms. On average, polymer consumption is 13 to
20 lb/DT and solids concentration in the cake varies from 12 to 28 percent.
Evaluation of alternatives
The following section compares the dewatering alternatives: BFP, centrifuge, SP, PFFP, and
RP. The information compares the alternatives in technology pre-screening are for the
following categories:
Table 8 describes the performance, environment and physical criteria of dewatering alternatives.
Performance Solids
Up to
concentration in 2% 0.3% 20% 25% 20% >25%
40%
cake
Solids capture
NA NA >95% ~95% 90-95% >95% >98%
rate
Operator attention
High High High Low Low Low High
required
Odor
Low Low Medium Low Low Low Medium
Operator health
Low Low High Low Low Low High
It is assumed that following items are same for all dewatering alternatives:
No redundancy is provided. When dewatering equipment fails, the residual sludge can
be temporarily stored in Lagoons No. 1 through 3 and treated once the unit is placed
back in service.
Dewatering process can be operated for more hours to meet max month sludge
production.
Dredge with pump to discharge residual sludge from lagoons to dewatering process
area
The residual sludge dewatering facility shall be constructed on the existing concrete
pad at the northwest end of high service pump station. The structural modification,
utilities and site work are same for all alternatives except discharge to sewer.
Homogenization tank
Cake conveyor and container
Pilot testing
Contingency is 30% of CSI Divisions 1 through 16
Engineering and Administration cost is 25% of construction cost
Table 9. Preliminary Capital Cost Estimate of Dewatering Alternatives (for Annual Average Condition)
Discharge Discharge
Plate and
to Sewer to Sewer Belt Filter Screw Rotary
Category \Technology Centrifuge Frame Filter
with without Press Press Press
Press
Thickening Thickening
Number of units 1 1 1 1 1
4 hrs/day, 7 10 – 12
days/week hrs/day, 7
Designed requirements days/week 6-8 hrs/ day, 4-5 days/week operation
Engineering and
$ 103 ,000 $ 19,000 $ 355,000 $ 376,000 $ 393,000 $ 384,000 $ 378,000
administration cost
Table 10 summarizes annual O&M cost and net present value (NPV) of dewatering alternatives.
See Attachment E for alternative cost opinion and Attachment F for alternative NPV calculation.
Assumptions:
Discharge Discharge
Plate and
to Sewer to Sewer Belt Filter Screw Rotary
Description Centrifuge Frame
with without Press Press Press
Filter Press
Thickening Thickening
Solids capture rate 7% 90%-100% 100% 0.07 100% 0.07 95% 0.04 95% 0.04 90% 0.00 95% 0.04 98% 0.06
Performance Operator attention required 6% High 0.03 High 0.03 High 0.03 Low 0.06 Low 0.06 Low 0.06 High 0.03
Reliability 10% High 0.10 High 0.10 High 0.10 High 0.10 High 0.10 Medium 0.07 High 0.10
Maintenance 9% Low 0.09 Low 0.09 Medium 0.06 Medium 0.06 Low 0.09 High 0.03 High 0.03
Noise 5% Low 0.05 Low 0.05 Low 0.05 Medium 0.03 Low 0.05 Low 0.05 Low 0.05
Environmental Odor 6% Low 0.06 Low 0.06 Medium 0.04 Low 0.06 Low 0.06 Low 0.06 Medium 0.04
factors
Operator health (exposure to
4% Low 0.04 Low 0.04 High 0.01 Low 0.04 Low 0.04 Low 0.04 High 0.01
operation)
Installation Foot print 15% Low 0.08 Low 0.08 Medium 0.12 Medium 0.12 Medium 0.12 Low 0.08 Medium 0.12
Annual O&M Cost 10% $ 19,000 - $ 97,000 $ 19,000 0.10 $ 24,000 0.09 $ 97,000 - $ 56,000 0.05 $ 42,000 0.07 $ 38,000 0.08 $ 70,000 0.03
NPW 5% $ 2,819,000 - $ 3,841,000 $ 3,389,000 0.02 $ 3,061,000 0.04 $ 3,841,000 - $ 3,158,000 0.03 $ 2,994,000 0.04 $ 2,819,000 0.05 $ 3,471,000 0.02
Total weighted score 100% 100% 0.701 0.771 0.63 0.77 0.79 0.73 0.70
1 This alternative does not include weighted score for cake solids concentration. This score is adjusted to balance the difference
Recommended alternative
Based on general, performance, installation and cost criteria, the dewatering alternatives were
given weighted score as provided in Table 11. Belt filter press has highest NPV and lowest
weighted score. Plate and frame filter press is labor intensive to assemble, load, unload,
dissemble and wash the plates. Thickening the residual sludge prior to discharging to SRCSD
sewer does not have any positive impact on project cost. RP (not many installations) may have
some potential savings as it has low annual O&M cost. Screw press, centrifuge and discharging
to sewer without thickening are promising alternatives. The City visited and contacted
water/wastewater treatment facilities which installed and operate centrifuge, screw press, belt
filter press and rotary press.
Considering experience of plants that operate dewatering equipment and above discussion, the
City selected screw press for further evaluation to implement as a solution to their residual
solids management. The screw press is a slow moving equipment, nearly 0.3 – 3 rpm speed and
its noise level is approximately 75 dB. Pilot testing by FKC screw press was conducted to
verify screw press performance in early of June, 2013.
Polymer consumption varies from 15 to 25 lb/dry ton solids. Additional jar test will
be required to select cost effective polymer.
Recommended Project
The screw press technology was selected for dewatering residual solids produced in the WTP.
The recommended project will consist of following components:
A homogenization tank with mixer or sludge recirculation pump to make and keep feed
sludge concentration uniform
Sludge conveyor
Process Description
The Actiflo blowdown and filter backwash are sent to Sed Basins No. 1 through 4 and
Backwash Recovery Basins No. 1 through 3 respectively. The supernatant is being discharged
to headworks and the sludge is transferred to Lagoons No.1 through 3 to thicken. Settled solids
from Sed Basin No. 5 are discharged to Lagoons No. 1 through 3. This process will remain
same in the recommended project.
The residual waste discharged from sedimentation basin contains solids varying from 0.2 to
1.03%. The screw press operating hours shall be reduced by thickening the residual waste from
sed. basins to approximately 2% in the lagoons. A dredge with pump shall excavate the settled
sludge from bottom of lagoons and pump to dewatering process. The residual sludge contains
silt carryover from Actiflo process. The silt will be the first thing to settle in the lagoons and
may form layers. If thickened sludge is directly pumped from lagoons to screw press
flocculation tank, frequent polymer adjustment may be required to flocculate different solids
and content. To discharge uniform sludge to dewatering process and to minimize frequent
polymer adjustment in flocculation basin, a homogenization tank will provide enough mixing to
keep solids (including silt) in suspension and uniform solids concentration.
The sludge from homogenization tank will be pumped to screw press flocculation basin where
the polymer will be added. The screw press will dewater the flocculated sludge. The centrate
from screw press will be sent back to headworks of the plant. Conveyor connected to screw
press will discharge cake to dumpsters to haul away.
Figure 11 shows the process flow schematic diagram of sludge dewatering process.
The dredge will pump thickened sludge at high flow rate for about 30 to 45 min. The
homogenization tank shall be sized to hold enough sludge volume required to dewater in a day.
The dewatering process shall be designed to have dewatering capacity of approximately 400
lb/hr, with no redundancy unit. The screw press shall be operated for 5 to 7 hrs a day and 4 days
a week under annual average sludge flow condition. The screw presses shall run more or less
hrs to meet min and maximum sludge production conditions. As in the current operation,
lagoons can hold thickened sludge when screw press is out of service.
CSI Division
2 Sitework $23,200
3 Concrete $13,090
4 Masonry -
5 Metals $177,500
9 Finishes $8,000
10 Specialties $17,500
11 Equipment $635,440
12 Furnishings -
15 Mechanical $22,000
16 Electrical $100,000
Subtotal $1,336,000
Contingency (20%) $236,000
Interim Plan
The City is looking for an interim solution to process residual solids produced in the processes
and to empty sludge stored lagoons until a permanent solution becomes fully operational. The
alternatives for interim plans are:
Discharge to SRCSD sewer – Discharge fresh residual solids and sludge stored in
lagoons for long time.
Contract an outsider to dewater fresh and stored sludge (The City will evaluate this
alternative)
Use Lagoon No. 1 to store residual sludge produced until the permanent solution is in
place (The City will evaluate this alternative)
The residual solids shall be temporarily discharged to the SRCSD sewer. The sanitary district will
evaluate the contents of sludge and capacity, and issue a temporary discharge permit for a year.
Temporary discharge fee is calculated to empty lagoon 2 and 3 and as follows:
Regional Charge 1:
0.84 million gal Million gallons x $318.46 = $267.51
0.042 lbs Thousand Pounds BOD x $191.89 = $8.07
140.112 lbs Thousand Pounds SS x $110.87 = $15,534.22
Subtotal $15,809.79
Administration fees
There is no limitation to volume discharged under temporary discharge permit. If more volume to
be discharged, the fee shall be adjusted accordingly. The City needs to submit an application for
temporary discharge permit to SRCSD.