Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

Contents lists available at ScienceDirect

Journal of Loss Prevention in the Process Industries


journal homepage: www.elsevier.com/locate/jlp

20 Years on lessons learned from Piper Alpha. The evolution of


concurrent and inherently safe design
Binder Singh a, *, Paul Jukes a, Ben Poblete a, b, Bob Wittkower a
a
IONIK1 ConsultingeJP Kenny Inc., 15115 Park Row, 3rd Floor, Houston, TX 77084, USA
b
Cameron, Houston, TX, USA

a r t i c l e i n f o a b s t r a c t

Article history: It has now been well over 20 years since the North Sea Piper Alpha disaster in 1988. There have been
Received 28 May 2010 many lessons learned; some documented others just etched in memory. The event chronicled many
Received in revised form significant changes in the offshore industry. The emanating point for most sweeping changes has been
15 July 2010
the Cullen Report and the UK North Sea industry. This paper reviews some of the critical lessons and
Accepted 30 July 2010
identifies many ‘secondary’ finer points that constitute important learnings. The paper looks at major
changes instigated by step changes in safety criticality. It is argued that the ‘second tier’ modes of failure
Keywords:
such as corrosion, materials degradation, environmental cracking, erosion, plant ergonomics, etc. need to
Integrity management
Safety
be better examined. These mechanisms are dangerous threats to the integrity of deep subsea assets, and
Corrosion it is noted that such root causes of failure as witnessed or predicted have yet to be fully appraised. The
ALARP authors’ use wide experiences and case histories to highlight such concerns, offering rational fit-for-
Key performance indicators purpose solutions. The industry disconnections between, urgency to build, knowledge transfer, and
Lessons learned management of change, are refocused. Powerful advances in risk-based mechanical, process, materials,
and corrosion engineering are emphasized and the use of key performance indicators (KPIs) are reasoned
for best life-cycle integrity. To keep up with the pace of growth in the deepwater sector, methods of
concurrent and inherently safe design have evolved in a world where the practicalities and costs of
modification, repair and retrofit are extremely difficult. Hence getting it right at the outset is paramount.
Thus the drive for purposeful investment, at design is more justifiable, than the traditional practice of
postponing costs (and problems) to operations. In this way the ominous ‘gray’ zone between the two cost
centers is better bridged for reasons of safety and commercial advantage.
Ó 2010 Elsevier Ltd. All rights reserved.

1. Introduction subject matter, in the context of inherently safe design, and the
allied second tier items of interest. These are the corrosion-related
After the recent 20th anniversary of the Piper Alpha offshore items that have been accepted as pertinent over the years, but often
disaster a paper was prepared and delivered to the OTC conference erroneously perceived with less priority. This is largely because the
in Houston Texas, in May 2009 and a upon invitation the exercise subject matter is considered too specialistic, or complex and often
was repeated for the Offshore Brazil conference in Macae, Brazil in requiring costly subject matter expertise. As a result, corrosion
June 2009. This paper is based on an adaptation of the OTC paper integrity is sometimes dangerously taken off the agenda by non-
(Singh, Jukes, Wittkower, & Poblete, 2009). subject-appreciative project or even industry leaders. This paper
On the 6th of July 1988, the world’s worst offshore oil industry delves into this contentious area, examines the role of corrosion
disaster occurred on the Piper Alpha platform in the UK sector of mechanisms in the root cause analyses of most significant failures
the North Sea. The loss of life was staggering: 167 dead, with 62 and virtually all loss of performance issues. The interpretations are
survivors, and dozens badly injured. Much has been written and made with the support of solid observations and new under-
debated on the incident. This paper examines a new angle on the standings in the direct context of integrity and corrosion manage-
ment. The authors come from a mixed blend of offshore disciplines,
with over 80 years of combined experience, predominantly from
* Corresponding author. Tel.: þ1 281 675 1020.
the North Sea and Gulf of Mexico. The objectives are aimed to be
E-mail address: binder.singh@wgim.com (B. Singh). educational and not controversial, but the opinions are strong, and
1
IONIK now rebranded to: Wood Group Integrity Management. considered very worthy of continued debate and development.

0950-4230/$ e see front matter Ó 2010 Elsevier Ltd. All rights reserved.
doi:10.1016/j.jlp.2010.07.011
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 937

expected in today’s computer driven age. The Cullen report has


tended to be the main stay reference source for all new offshore
design and operational guidelines the world over. Some regions
have used the findings rigorously whereas others have used them
less in depth. Overall the report led to the effective dissolution of
the prescriptive regulations sanctioned up to that point, and
replaced same with the evolution of the goal-setting integrity
regulations in the UK and with derivatives thereof. On the plus
side the major outcome of the disaster has been far better, safer,
and more efficient engineering practices for the oil industry. And
indirectly has supported strongly the need for inherently safe
designs and procedures. These have been realized by better, more
focused research, better applied knowledge management, and
a greater sense of public and industry responsibility by the new
generation of engineers and scientists. Many more offshore,
Fig. 1. Piper Alpha before accident e Courtesy Wood Group (Wood Group HSE Matters,
2008). subsea and integrity-related courses have evolved worldwide,
largely at postgraduate level, much to the advantage and
betterment of the industry. This has been promulgated by the
better realization by professionals in the industry that designing
The Piper Alpha accident was a monumental event, see Figs. 1 to build the asset, structure, pipeline, and pressure plant can no
and 2. It is, perhaps, in terms of impact a top-five engineering longer be based on projected revenues alone. Yes, the ultimate
disaster on the global scale, considered to be in the same league decision maker or breaker can and often is the commercial
as Chernobyl, Challenger, Three Mile Island, Flixborough, etc. sensibility, but a greater sense of responsibility to the public, and
(BP Booklet, 2004; Kletz, 1998; Lees, 1980; Lord Cullen Report, the environment, has fallen into place. This is largely regulatory
1990; Neal, 2007; NTSB). And in many ways it is historically driven, but one can still discern a good dose of professionalism,
comparable to other high-impact human events such as the merit and worthiness in the arena.
Kennedy assassination, New York 9/11, London 7/7, and Mumbai
11/27, in that people (certainly in the British Isles and the North 1.1. Root causes
Sea community) often remember where they were on the day. In
that way the Piper Alpha seems to have uniqueness about it, Regarding the accident there was, perhaps, no single root cause
which may be due to the fact that it was offshore and involved event that was to blame. Rather, it was a confluence of many critical
a heavily manned producing platform. The major differential has, factors that were almost the ‘perfect storm’ often described as the
with the benefit of hindsight, been that the disaster was de facto jigsaw or ‘Swiss Cheese’ effect, whereupon critical events occurring
man made, though not a deliberate act in any way, but human at a certain juncture in time, and as a consequence the failure jigsaw
and engineering errors were seen to hideously come into play. fell into place, with tragic results. In reality integrity management
Many studies have looked at that aspect, the center piece of most (IM) is far more complex than maintenance (a common misnomer),
if not all being the ensuing public inquiry and the Cullen Report the parameters affecting IM are non-linear and influential during IM
which was published in 1990 (Lord Cullen Report, 1990). This was pre-planning, post planning, action and reaction, etc., and indeed
the culmination of a thorough two year inquiry involving many the alignment of bad sequences, events or circumstances are
interviews with survivors, families, and subject-matter experts of invariably all time dependent and thus multi-dimensional in nature.
the day, with many others on the outside offering immediate This has traditionally made IM a difficult subject to grasp, especially
opinions on the many public affairs programs of the day, as since it transcends both the capital expenditure (CAPEX) and
seems to be the norm under such events. It was also commonly operating expenditure (OPEX) cost centers.
noted for truck loads of documents being delivered to the The Piper Alpha was commissioned in 1976, but was modified to
courthouses of London and Aberdeen, and that was a reflection of act as a major gas processing and gathering hub. This meant it was
the non-electronic transfer of documentation, as might be handling large amounts of high-pressure gas, with a dispersed plant
layout, making inspection, maintenance and repair difficult. The
rapid technology advances of the day, coupled with powerful
commercial pressures, clearly had a lot to do with the event, and this
paper looks at some of these important issues, with the benefit of
hindsight but also with strong opinions forged over time (BBC web
pages; Coastal Training Technology Corporation, 2007; Fontana,
1984; JP Kenny, 2005e2008, 2008; Private Correspondences with
Messrs Ben Poblete (LR/Cameron), 2000e2008; Singh, Britton, &
Flannery, 2003; Singh, Britton, Poblete, & Smith, 2005; Singh, Folk,
Jukes, Garcia, & Perich, 2006; Wood Group HSE Matters, 2008).
Regarding the best way forward it is important to identify all
integrity-related threats, some of which may be discerned as at
a secondary level, albeit with the potential to give similar disastrous
results if not taken fully into account. The majority of these are
materials performance and corrosion related. The latter is an
important point, and the paper takes a critical view of the changes
that have been instigated since Piper Alpha, not so much from the
Fig. 2. Piper Alpha explosion e adapted (Coastal Training Technology Corporation, large structural engineering angle, but more from the viewpoint of
2007; BBC web pages). these second tier issues, which usually arise within lower profile
938 B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

design parameters, for example pressure (leak) containment, materials, corrosion and integrity engineering (Ohio University,
corrosion analysis, erosion, wear and tear, inspection, monitoring, 2007; UMIST/University of Manchester Corrosion Center,
pigging, and maintenance, etc. 1983e1995; University of Tulsa, 2007; WGIM Internal Training
Due to the media frenzy of the day, the causes were variously Modules, 2000e2008). As these people pick up practical experi-
reported over the first year as: metal fatigue, poor maintenance, ence and supplement the traditional engineering and sciences, this
inadequate operating procedures, bad work practices, human error, can only be a boon to the integrity management discipline, and
etc. The full report is a public document, and much educational therefore better engineering practices for the offshore and energy
material, video s/DVDs, etc. are readily available for the interested industries generally. The concept of better work force involvement is
reader (BBC web pages; Coastal Training Technology Corporation, a sensitive issue since it is still commonly expressed by workers in the
2007; JP Kenny, 2005e2008). Essentially in the context of this field that an over exuberance with offshore safety at the metaphorical
paper the Cullen report, and other studies have highlighted many ‘coal face’ can lead to the ‘not required back’ (NRB) factor, which still
reasons for the disaster, the most damning of which were: has a tempering effect on employee involvement (Hibbert, 2008;
Private Correspondences with Messrs Ben Poblete (LR/Cameron),
 Poor plant design (including with regard to modifications and 2000e2008).
changes)
 Breakdown of the permit-to-work system 1.2. Industry changes
 Bad maintenance management
 Inadequate safety auditing, and training procedures The many ensuing industry changes identified since the disaster
 Poor communications (all levels) have, in fact, taken many years to come to fruition. Overall most
 Poor emergency management (including with regard to offshore regions, in particular the North Sea, Gulf of Mexico (GOM),
surrounding platforms) and Australia have embraced the new culture of safety. Although
there is sometimes a dangerous disconnect between theory and the
The Cullen report (Lord Cullen Report, 1990) made over 106 actual practice of implementation. The rest of the world (ROW) has
recommendations, which included in summary: responded in a slower manner, but with positive results, especially
the SE Asia regions and offshore India. The very heartening imple-
 The transfer of government responsibility for offshore health mentation of best practices (by choice, not necessarily regulation)
and safety to the Health and Safety Executive (HSE) was has given greater confidence for the new, challenging deepwater
generally received well. (Note: the public observed this as explorations and subsea tie backs in the GOM and the new frontier
government taking some responsibility, too.) Arctic regions (JP Kenny, 2008; Singh et al., 2006). The most notable
 The establishment of a Safety Case regime (This was to entail changes again in the context of this paper are interpreted as follows:
independent verification).
 Overall review of legislation, definition of best practices, and  Changes to offshore asset design, requirements for design
better use of loss prevention studies. review, more latitude for concept creativity, better rationale for
 Better work force involvement (crucial but sensitive). engineering conservatism and pragmatic safety.
 Verification and intervention when necessary.  New goal-setting legislation, i.e. the Safety Case.
 Permit-to-work systems (ideally fail safe and tamper proof).  The goal-setting idea replaces the prescriptive method. This
 Systematic approach to safety, responsibility of everyone has proved to be a step change in offshore safety and engi-
(senior management and down the line). neering performance.
 Emergency response and incident reporting (effectively by
training and changes in attitude and culture). For the important GOM region it has been stated that the
regulations conferred by the governing Mineral Management
It has to be said that most of the activities listed above still fall in Services (MMS) are ‘fit-for-purpose.’ This suggests the designs are
the grey area of judgment, and in that case best practices must suitable at construction, but the gradual drift of this meaning has
therefore be interpreted and applied through the identification of evolved to ‘life-cycle fitness-for-purpose’ and this appears to be
safety-critical systems and components, proactive risk analysis, risk adopted and embraced by the more recent generation of engineers
reduction, and therefore risk management (Singh et al., 2005). There (typically 5e10 years experience) as they enter the fray. The subtle
are many other important derivations from the Cullen report, but debate now ongoing is at the material selection stage. There are two
without unnecessarily going outside the scope of this paper, it is quite schools of thought, namely the distinction being made, whether to
clear that management of change (MOC) is and will continue to be the select carbon steel and then carefully manage the operational
best tool available in the ever-improving area of knowledge corrosion, or to select the corrosion-resistant alloy (CRA) option
management (Deepwater Corrosion Services Inc, 2008; DOT with minimal corrosion management. The contrary arguments are
Regulations; JP Kenny, 2008; JPKenny/University of Houston, 2008; usually cost-center based, with strong opinions tested for CAPEX
JPKeIonik, 2005e2008; Mueller, 2006; SCOTA/UKOOA, 1995; Singh, and OPEX scenarios. In other words, do we pick materials for
2007; Singh et al., 2007; UK HSE, 2001; UMIST/University of immediate fitness for service at fabrication (‘just build it’) or fitness
Manchester Corrosion Center, 1983e1995). The electronic age of for materials life-cycle performance? The answer is now emerging
software and modeling analyses has made documentation prepara- as a requirement for both, and to that effect the materials engi-
tion and transfer so much easier that we are only limited by our neering specialist is having an ever-more assertive role to play
ability to assimilate and interpret the information across multidis- within the large multidiscipline teams usually engaged on high
cipline areas (API 14E RP; Ramachandra, 2007). This is where core capital projects (JPKeIonik, 2005e2008; Singh et al., 2006; Singh &
personnel competencies come into play. For a better, safer, and more Krishnathasan, 2008).
efficient work force and management, suitably trained and educated
offshore engineers and scientists must be provided by our educa- 1.3. Implementation
tional institutes. To that effect first-rate universities across the North
American, European, and Australian regions in particular are churn- The implementation of the Cullen report recommendations
ing out scores of postgraduates annually in the key disciplines of has, it is believed, shown through various studies that reportable
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 939

incidents that impact safety issues in the UK sector have been These and other related points of view are made in the paper,
significantly reduced by some 75%; a major achievement (Private hopefully to reinforce some of the many lessons learned over the
Correspondences with Messrs Ben Poblete (LR/Cameron), past 20 years or so. In almost all major comparable disaster cases
2000e2008; SCOTA/UKOOA, 1995; UK HSE, 2001). This clearly the commonality has been the confluence of many variables
means the industry is on the right track, but there are still coming into a tragic alignment, sometimes referred as the jigsaw
problems and issues. It is argued that more attention should and or ‘Swiss Cheese’ effect. It is argued in this paper that in almost
must be made to the secondary tier items such as root cause all cases the loss of materials performance as stimulated by
corrosion mechanisms, advanced monitoring and inspection corrosion is the root cause effect. A close examination of the
techniques, etc. This aspect is best illustrated by an adaption of modes of failure reveals the uncanny role of corrosion dissolution
the ‘Swiss Cheese’ effect as shown in Fig. 3. It is to this effect that at either the macro or micro level (whether it be by alloy,
this paper is targeted, with the intent that by paying more embrittlement, crevice corrosion, mixed metal galvanic, etc.) the
focused attention to these parameters and findings that the outcome is the same: severe loss of material properties and/or
integrity management discipline will be more substantively load carrying capabilities (Fontana, 1984; UK HSE, 2001). The
improved. The Cullen report also identified two areas of under resolution of the corrosion aspect will, therefore, in virtually all
emphasis that may be appropriately reasoned, firstly the industry cases eliminate the closure of the jigsaw effect, thereby pre-
tendency to avoid the acceptance of external consultants’ advice venting the failure. On a positive note, the concepts of knowledge
if the recommendations are not supported by more experienced management, advanced inspection techniques, implementation
personnel, often even if the consultation seems logical and safety of MOC, and the more newly defined roles and responsibilities for
sensible. The case of the central riser argument for the Piper pertinent decision makers, etc., have all been very instrumental
Alpha is cited; here evidently the dangerous proximity of the in making this industry safer and better equipped to tackle the
risers to the control and radio room areas was, in fact, identified, challenges faced ahead. It is strongly argued that one new
but no action taken (design change, relocation, blast walling, recommendation that would be instrumental in helping improve
etc.). Nowadays virtually all new designs insist on the risers being this aspect an order of magnitude would be the ‘mandatory’
on the outside perimeter of the offshore asset. The second point requirement for each asset to submit a clear annual corrosion
of observation is the concept of addressing root cause effects. The integrity statement on the facility, and pertinent (safety-critical
Piper Alpha condensate pump problems that initiated the whole parts) thereof (JPKeIonik, 2005e2008). The burden for doing this
tragic sequence of events were plagued with corrosion problems is not high, but the results would be extremely positive.
the attendance to which was seemingly consistently delayed as
lower priority. Apparently some platform corrosion issues were 1.4. Threats to asset integrity
left for over four years (JPKeIonik, 2005e2008). If corrosion
management as a recognized discipline had been in place, rather It is very important for society to progress positively and look at
than an ad hoc to-do item, then again, with the benefit of hind- lessons learned in all disciplines from time to time. However, in the
sight, the tragedy could have been avoided. That, unfortunately, engineering field the need is most pressing. The world is changing
is how the learning and knowledge management process works. fast, with unprecedented population growth, and competition for
And it has to be said that companies today often have very sustaining resources such as water, food, and energy. The oil and
valuable lessons-learned meetings after major projects are gas industry is pivotal to such growth, and must, therefore, take
concluded. There is a strong case, and new initiatives, underway note of demand for production, and demands for best safe, efficient,
for such formal lesson learnings on an ongoing basis (BP Report, and environmentally friendly solutions. The structures, pipelines,
2004; JPKenny/Ionik; SCOTA/UKOOA, 1995; Singh, 2007). pressure plant, and parts thereof must be designed and operated at
The use of modern-day corrosion risk assessment techniques optimum conditions, whilst retaining mechanical integrity over the
are under development and application. It is hoped that ulti- life cycle. One of the greatest threats to any asset integrity is the
mately these will be implemented by the weight of motivation, degradation of the asset with respect to time, i.e. the design life or,
though in reality some degree of mandatory regulation may be more appropriately, the life cycle. In that context the most domi-
ultimately required (IONIK JIP, 2008; JPKeIonik, 2005e2008). nant degradation phenomena per se is corrosion. And in that regard

Fig. 3. The ‘Swiss Cheese’ Analogy as applied to materials engineering.


940 B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

there are many mechanisms of corrosion, all of which come into and it is believed that lobby led to the evolution of mechanical
play at varying levels of intensity. The early work by Fontana et al. integrity management. In time, mid-late 90s the terminology
(Fontana, 1984) suggested eight clearly defined corrosion mecha- seemed to reach a consensus at integrity management (IM). In
nisms, though more recent work is pointing to more than ten terms of proportion, IM is still effectively a corrosion management
(JPKeIonik, 2005e2008; SCOTA/UKOOA, 1995; Singh et al., 2003; exercise and that was argued in early pioneering studies by Prodger
WGIM Internal Training Modules, 2000e2008). For the upstream et al. (Prodger, 1997)., leading to the conclusion that IM was
oil and gas industry, it is common to delineate these into the major effectively 80% corrosion related, covering all assets (marine/
damage threats, whereupon many studies (Canadian/Russian in offshore/industry). The concept of a corrosion management
particular) over the past 10 years or so have shown that internal strategy (CMS) has therefore evolved, this supplies the high-level
corrosion is the dominant cause of failure, typically by over 50% in approach to IM, and is usually a system FEED-type study, quickly
practice (JPKenny/Ionik; WGIM Internal Training Modules, converting to a tactical (nuts and bolts detail) type corrosion
2000e2008). control manual, which forms the basis of the life-cycle IM plan. The
Whether the corrosion failure is on pipeline, riser or topsides plan is a live, ongoing document modified or revised as new data or
equipment there is in practice nearly always a precedent, thus findings become apparent and usually encompass detailed, risk,
working applied design life solutions can normally be formulated. reliability, inspection, intrusive probes and coupons, pigging, fluid
At the same time it is however, important to continue with sampling, chemical injection, and mitigation procedures, and
fundamental or near fundamental research to help understand studies. As with all good science and engineering it is vital to
failure mechanisms better so more permanent solutions can be quantify critical parameters, and to that effect the concept of key
implemented as time marches on. The concept and consolidation of performance indicator (KPI), has been modified and applied to IM
the corrosion and erosion JIPs have helped to bridge the link studies (Singh, 2007; Singh et al., 2006; Singh & Krishnathasan,
between industry and academia, with valuable results (Ohio 2008). Thus, the qualitative nature of risk-based judgments is
University, 2007; University of Tulsa, 2007). The trick however, is honed to a more easily repeatable and consensus-based decision
to ensure that the results are interpreted and applied by skilled and gate system. Some examples of recent KPI studies and their appli-
experienced personnel, preferably staffers who are very cognizant cation are presented later. These must always be considered and
of the JIP data being generated, and have had a role in the devel- applied and agreed on a project-specific basis, with the appropriate
opment of the laboratory and field testing programs. As an example sign-off from subject-matter experts in materials, corrosion,
the threat breakdown for risers, though quite similar, will have CP/coatings, etc. Most career offshore engineers do in fact observe
particular nuances to be taken account of, such as the translation of near misses on a regular basis, with incidents related to fire, leaks,
horizontal pipeline flow regimes to vertical regimes with a poten- mechanical integrity, topsides equipment, poor inspection, etc.,
tially high-risk corrosion activity at the base transition. Similarly, being responded to with duly diligent team actions. However the
topsides pressure equipment will be safety critical, and perhaps potential for mishaps is always there, especially where corners are
warranting greater latitude on the monitoring side, such as area cut to meet production and cost issues. This ‘Achilles heel’ will
ultrasonic testing (UT) mapping and thermal imaging in the high- always be there but hopefully minimized as leadership and the
risk underside (six o’clock positions). There should also be a greater industry progress.
emphasis on the external corrosion aspect, especially at supports
whereupon several major failures have been observed due to 1.6. ALARP, corrosion hazard, and inherently safe design
crevice corrosion being accelerated where wet marine air has
condensed out high chloride pockets in susceptible areas The commonly accepted approach to safety assurance or
(Deepwater Corrosion Services Inc, 2008; Singh et al., 2003, 2005). ALARP is now to ensure on the basis of suitable and sufficient
This is a significant problem in the GOM where warm temperatures evidence that risk is as low as reasonably practicable (ALARP).
(>21  C) and regional humidity levels are routinely >80%, pretty The concept of ALARP is often interwoven into the risk analysis
much year round. and/or safety management from the very beginning (JP Kenny,
On the plus side there are many fit-for-purpose solutions, such 2008; JPKeIonik, 2005e2008; Singh et al., 2006; Singh &
as the use of inert I-Rod type inserts, which if used correctly can Krishnathasan, 2008) Corrosion must be considered a func-
virtually eliminate crevicing geometries (Deepwater Corrosion tional hazard for this approach to be applicable. Fig. 4 depicts the
Services Inc, 2008; JPKeIonik, 2005e2008). The use of thermal ALARP triangle with the processes and descriptions for each
spray aluminum (TSA) coatings is also a very viable solution for all segment. Further, since there is a lack of code guidance per
topsides equipment external and internal surfaces. This is internal corrosion, one way forward is to use the concept of
a reflection of onshore technologies being carefully transferable to ALARP to define the limitations or boundaries of the corrosion
offshore applications, provided subject-matter expertise is wisely parameter, and therefore aid (technical and legal) argument
used and safety is not impaired (JPKeIonik, 2005e2008; Singh & defensibility. Since inherently safe design (ISD) is often perceived
Krishnathasan, 2008). as a costly CAPEX discipline, there is a forceful argument that
suggests that by strongly utilizing ISD in the Integrity Manage-
1.5. The aftermath ment basis (typically by best materials selection, geometries,
chemicals, etc.) then coupled with concurrent changes, revisions,
Post Piper Alpha, studies (late 80s and 90s) revealed the MOCs, etc. in the same vein, a truly best practices regime can be
important need for corrosion management. That concept was likely set up. The cost factors are easily justified by reduced OPEX costs
first coined by researchers at UMIST/Manchester when that group over the life cycle. However the ‘pay now or pay more’ later
realized that corrosion control really defaulted to corrosion theory has never fully made the grade, and in reality it usually
management as the discipline was a fine balance of integrity and takes an event like the Piper Alpha or Carlsbad (New Mexico,
finance management (UMIST/University of Manchester Corrosion USA) before significant paradigm shifts in attitudes are made,
Center, 1983e1995). Thereafter, the term seemed to be broadened even then only with the force of regulation. Alternatively the
to cover for monitoring, chemicals, pigging and inspection, thus Joint Industry Projects (JIP) might be seen as the conduit for best
leading to the term inspection management. It was, however, very technology advancement and best knowledge interpretation and
important to include the pressure vessel and piping community management in this regard. Once concurrent design and ISD
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 941

2. Corrosion mechanisms per upstream and subsea

Uniform corrosion Well addressed via theory, monitoring good-viable


Pitting corrosion Modeling difficult but R&D done, relevance high risk*
Crevice corrosion Relevant modeling used, relevance medium risk
Galvanic corrosion Modeling hard (danger ‘mesa’ scale related attack),
medium risk
Stress corrosion Empirical/experience, medium risk and reliability
in practice
Erosion corrosion Modeling used-relevance high risk*
Corrosion fatigue Interpretative used-relevance high risk
MIC Very subjective, separate JIPs underway at
Ohio/Tulsa Univ. e risk high*
CO2 corrosion Modeling underway used-relevance very high*
H2S corrosion Modeling underway used-relevance high
TOL Now better quantified e as part of separate
JIP study at Ohio University.

Note 1: perceptions asterisked (*) are best given as ‘localized,’ encompassing


multiple mechanisms. Also all high-risk phenomena can be mitigated down to low
risk with diligent, motivated, surveillance and corrosion management procedures
provided they are, in fact, fully implemented.
Note 2: the assessment of risk can be qualitative, or semi quantitative. The high-,
Fig. 4. The ALARP triangle depicting the importance of corrosion risk assessment in medium-, and low-risk (HML) nomenclature has been adopted for simplicity and
the risk management and loss prevention exercise. Having the right blend of multi- consistency. HML must always be assigned by materials/corrosion specialists and,
disciplined engineers is key to success if multi-facetted failure mechanisms and root where possible, have justifiable and defensible arguments as support.
causes are to be properly addressed. Note 3: the use of industry-accepted HML risk designations and simplified go/hold/
no go (green, amber, red) traffic signal type decision gates is a really good evolution
in the design and operational integrity management process.

move closer towards amalgamation then the case for concurrent


and inherently safe design (CISD) may become a university As with all engineering projects, commercial aspects, project
taught and thus industry practiced discipline. viability, return on investment (ROI), schedule, etc. are pivotal to
There are actually more than 10 recognized mechanisms of project success. The net effect is that in many, if not most, cases the
corrosion, viz: 1) uniform corrosion, 2) pitting, 3) crevice, 4) project remit becomes ‘design to build’ rather than the preferred
erosion (including impingement/cavitation), 5) galvanic, 6) ‘design for the life cycle’. This often adversarial development is, on
selective leaching, 7) intergranular, 8) fretting/wear, 9) stress the one hand, good in that it stimulates solid, provocative discus-
corrosion cracking (SCC), corrosion fatigue, hydrogen damage, sion, and thus best workable fit-for-purpose solutions can be
embrittlement, etc., 10) Other creep/embrittling, etc. (JPKenny/ attained, however if materials engineers are not strong enough to
University of Houston, 2008). For offshore and subsea condi- debate their corner hard and strong, weaknesses in design leading
tions the critical mechanisms are a function of reservoir to failures down the road can be expected. The only real question
composition; and the most dangerous threats are therefore CO2 being, where, and when, rather than if, as a result the competitive
(sweet) corrosion, H2S (sour corrosion and cracking), bottom of forces at work, namely the need for revenue as against best safe
line (BOL), top of line (TOL), and microbially influenced corrosion technology (BAST), is often a battle of being ‘smart to out smart’
(MIC). Once at the tactical stage it is found that corrosion under often identified as the Achilles heel in the IM process (JPKeIonik,
multiphase hydrocarbon flows presents the most challenging and 2005e2008; Singh et al., 2005). This is reflected in the weak
integrity-threatening condition. This problem area has plagued argument often used that the design complies with the regulations.
the industry for many decades. In the USA the challenge is being That alone is not enough, it may be a minimum requirement, but
met by the continued growth of two major JIPs, at Ohio Univer- life-cycle fitness-for-purpose is really about managing all
sity under the auspices of Nesic et al. (Ohio University, 2007), and mechanical and corrosion-related degradation mechanisms,
at Tulsa University under the guidance of Rybicki et al. including: stress overload, embrittlement and loss of material
(University of Tulsa, 2007). Both JIPs effectively tackle and model properties, and natural wear and tear i.e. dissolution of the metal
corrosion and erosion and MIC modes of failure through an under aggressive environments.
exhaustive combination of theoretical modeling, empirical
testing, and field trials. This work seems to be leading the way
globally and in the absence of bone fide codes of practice and 2.1. New build versus old build
standards, the JIPs are commonly used as a reference point. The
recommendations coming out of the JIPs are membership sup- Most new engineering applications (green field) invariably
ported (largely operator companies and key consultants, engi- involve a design code or recommended practice as a reference point.
neering companies, etc.), and thus their findings have received These are usually industry-accepted guidance documents that have
solid acceptance industry wide. The balance of academia and been developed over many years, been through many cycles of peer
industry ensures that the decision-making process is not skewed review, and tested via experience, case history, etc. Reference to
by overriding commercialism. Ultimately these will tend to be established codes gives the design and end client credence and
perceived as the industry standards, filling the void that has long confidence in its workability. One example of that is pipeline cathodic
been present. The results are applicable to all assets tension leg protection (CP) and coatings, whereupon code compliance (Det
platform (TLP), mobile drilling unit (MODU), spar, fixed, subsea, Norsk Veritas (DNV), International Standards Organization (ISO),
topsides, etc. provided the appropriate expertise is deployed to NACE International e The Corrosion Society.) is a good yardstick for
allow for the subtle differences across assets and systems, in successful external corrosion control. Unfortunately, that is not the
other words, from both sides of the aisle: from the operator and case for internal corrosion, largely because the mechanisms of
the engineering contractor (IONIK JIP, 2008; Jukes, Singh, Garcia, corrosion are complex and often multifaceted (Jepson & Research
& Delille; Singh et al., 2006). Workers, 1999e2002; Marsh, 2007; Nyborg, 2002; Nyborg &
942 B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

Dugstad, 2007; Ramachandra, 2007; Singh, Krishnathasan, & Ahmed, the Federal Register may be used to support the requirement for
2008). It has therefore been necessary to develop methods of reso- diligent corrosion assessment and management thereof
lution, the most popular being that of corrosion modeling. The most (JPKeIonik, 2005e2008; US DOI-MMS Federal Register, 2007). It is
common threat to pipeline integrity has been mixed CO2 or sweet recommended that these be used on a case-by-case basis, though
corrosion. In reality even with the large amount of corrosion work specific differences (usually more onerous may be relevant if
done over several decades, absolute values of corrosion rate still North Sea rules and the Safety Case are applied). In practice, for
cannot be reliably predicted without reservation using any of the 15 steel that means the development of a pragmatic corrosion
or so models available (IONIK JIP, 2008; JPKenny/Ionik; Nyborg, allowance. It has been found that the best way to do this in
2002). All the models can really do is give a general guidance as to a convincing and reasonable manner is to utilize interpretation of
the corrosivity of the media involved. Thus it can be construed that the relevant and available rules and codes of practice, suitable
the main objective of corrosion modeling or corrosion assessment modeling calculations, industry experience and best judgment.
has evolved to differentiating (at build) whether or not the carbon The US federal regulations have stirred debate in the US, and there
steel will be acceptable as the main flowline material, or, if not, are some criticisms as well as positives. Overall, the industry
weather the analysis justifies the use of CRAs as the design basis. The seems to have embraced the impending rules (DOT Regulations; JP
impact of this decision can be crucial since the CAPEX/OPEX ratio is Kenny, 2008; US DOI-MMS Federal Register, 2007). The main
greatly affected and will often make or break the project. Thus, the advancement is likely to be a greater specificity regarding internal
vital need for the corrosion predictions to be pragmatic and done to corrosion, perhaps more akin to the UK goal-setting requirements.
the best possible reliability. In practice the greatest criticisms of the The modeling we do should anticipate that and hopefully these
modeling approach have been the noneagreement of calculated guidelines presented will provide a framework for that. The rules
corrosion rates to the observed field values. For deepwater applica- are US-specific but should serve as a template for defensible
tions whether subsea at >4000 ft, at the steel catenary risers (SCR), or corrosion prediction, which is all the more important in an ever-
on the host facility (e.g. TLP/SPAR/MODU, etc.), there is little room for more litigatious society (IONIK JIP, 2008; NACE, 2007).
error, since repairs or retrofit can be very costly or practically As alluded to previously there are many models available,
impossible. Nevertheless the deepwater campaigns continue and it is (likely> 15) e.g. Norsok M506, Cassandra 93/95, ECE, Hydrocorr,
up to engineering companies to offer justifiable but realistic solutions Lipucor, Multicorp v4 (Ohio JIP), OLGAÒ (corrosion module
and where proven data or correlations are not available, reasonable inclusive), Predict/Socrates, Tulsa SPPS (Tulsa JIP), ULL model and
risk-based ALARP driven decisions are considered justifiable. The others, and whilst most have individual strengths and weak-
same arguments apply for old build (brown field), whereupon nesses, the common critique is invariably unreliable correlation
existing assets often badly corroded need to be assessed for to the laboratory and more importantly field experience (IONIK
remaining life and ongoing corrosion. This can be a challenge as JIP, 2008; Nyborg, 2002). As a rule almost all have little proven
critical parameters such as existing pre-corrosion condition and/or consistency of confidence to field observed corrosion rates. This
existing inspection data are not always readily available. Nevertheless is mainly due to the fact that the designs attend essentially only
predictive modeling does serve a useful purpose in this regard, to the base CO2 corrosion case, and exclude a truly meaningful
provided the caveats are defined, understood and accepted by the localized component, though some claim, and more and more are
client (Jepson & Research Workers, 1999e2002; Marsh, 2007; trying to include, this and other influencing parameters. The
Nyborg, 2002; Nyborg & Dugstad, 2007). problem seems to be that the localized component is rarely
addressed in a transparent manner, with no reference to local-
2.2. Rules, regulations and inherently safe design ized criteria or parameters such as crevice/deposit size, stagna-
tion fluid chemistry, crevice pH, differential aeration, etc.
Ultimately the integration of ISD into mainstream engineering Nevertheless, the use of a suitable modeling or JIP study would
practice will almost certainly happen, though as alluded to earlier no doubt be accepted as a supporting reference to the regula-
the combined efforts of academia and regulatory authorities will tions. Generally most models have a ‘black box’ critical analysis,
be the most likely catalyst. Whilst external sea water corrosion though the JIPs appear to be more transparent at least to the
control is regulatory driven, the case for internal corrosion is only member companies. The research is still closely guarded though
heavily implied though not specifically regulatory or code it has evolved to be more pragmatic and project risk-orientated
compliance driven, however that will probably change and regu- (deterministic/theoretical). It is expected to have solid calibration
lations in most regions will likely refer to best practice modeling capabilities with ultimately, a flow assurance-linked corrosion
or corrosion analyses to ensure that corrosion integrity is modeling package seemingly viable, perhaps, by individual
accounted for within the integrity management process (Singh member companies. The latter is difficult but would have the
et al., 2006). That change was expected to be imminent and may greatest impact if it could wrap up flow assurance, corrosion, and
still happen within the Federal Rules though there is a powerful safety inextricably to production and, therefore, revenue. This is
lobby against the changes such that the rule change approval may a controversial argument but one that would help eliminate the
be delayed (Singh & Krishnathasan, 2008; Wood Group HSE pressures on project managers, offshore installation managers
Matters, 2008). The onus is, therefore, on diligent designers to (OIM), and other decision makers to continue with producing,
ensure that best safe technologies and techniques are utilized to often under fault conditions. That was seen to be quite possibly
understand and predict corrosion mechanisms and corrosion the ultimate snafu in offshore history, when adjoining platforms
rates, such that failures can be eliminated or arrested to tolerable continued to fuel the fires on the hapless Piper Alpha (BP Booklet,
values. As far as the GOM region is concerned a mixture of 2004; Coastal Training Technology Corporation, 2007; Lord
prescriptive and performance related criteria are applicable. In Cullen Report, 1990; Singh et al., 2006).
particular the Government Mineral Management Services (MMS)
now slated to be the Bureau of Ocean Energy (BOE) have defined 3. Offshore corrosion failure case histories
potential incidents of non-compliance (PINCs), and these may be
interpreted as a corner stone boundary condition for predictive Even post Piper Alpha there have been many integrity and
corrosion control to help focus the designer’s attention and atti- corrosion-related failures, and some of the more important types
tude towards safety (Singh, 2007; US DOI-MMS, 2007). Similarly are presented for illustrative purposes only. It is clear that most are
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 943

solvable by better using existing knowledge and widely available Age 10 years, no on-line monitoring, produced water system
techniques, including more recently, existing modeling predictive sensitive to poor protective filming, adapted (Singh et al., 2003).
techniques, such as those offered by the JIPs, many of which are
now expanding beyond the closely knit operators to the engi-
neering design houses and consulting groups. This should be of
much advantage to the industry as a whole by infusing an alter-
native layer of checks and balances to drive the research for better
understandings and ergo better solutions. A number of examples
(Case Histories # 1e5) illustrate the role of corrosion in the integ-
rity management process. The first is, perhaps, the first US equiv-
alent of Piper Alpha, in that it led to strident changes in regulatory
requirements via the Dept of Transportation (DOT) (NTSB; DOT
Regulations). The remaining examples are chosen to represent
the types of failure most commonly witnessed; there are many
others available in the literature and industry project files (JP
Kenny, 2005e2008; Singh et al., 2003; WGIM Internal Training
Modules, 2000e2008).

3.1. Case history # 1


3.3. Case history #3
Top plate aftermath of the Carlsbad, NM, pipeline failure, Aug
2000. Tragically 12 outdoor campers were deceased. Root cause Catastrophic failure of choke sleeve on offshore facility. Failure
determined a combined corrosion mechanism dominated by mechanism analysed to be combined erosion/cavitation and
chloride/CO2/microbial as exemplified in the micro image below. impingement. Impinging cavitation forces can far exceed the proof
Noting that the corrosion was concentrated at the girth and seam stresses of most alloys adapted (Singh et al., 2003).
welds at the bottom position, with 72% wall loss, adapted (Kletz,
1998).

3.4. Case history #4

Sweet (CO2) corrosion is probably the most insidious type of


localized corrosion observed in pipelines and topsides pipework.
The many worldwide applied R&D projects are geared around this
dangerous mechanism. Adapted (Singh et al., 2003).

3.2. Case history # 2

Depicting failed manifold on a fixed platform due to isolated


erosion defect of the steel upstream of an inhibitor injection point.
944 B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

3.5. Case history #5 a three or six month basis at first year for new facility depending on
production water cut realized in practice and thereafter on an
The left hand side (LHS) showing over-active deep-sea anodes, annual basis, with ‘sign off’ by appropriate technical authorities. It is
possibly due to inadequate alloy chemistry, and/or high quantity considered that within the modern offshore industry, the major
presence of uncoated steel or local CRA components. The right hand corrosion-related threats are:
side (RHS) showing excessive flaking of Thermal Spray Aluminum
(TSA) coating accelerated by uncoated steel or possibly CRAs in the  Sweet/sour (CO2/H2S) corrosion (under close attention of JIPs)
immediate vicinity. Both thought to be within one year, observed at  Under-deposit corrosion (particulates or sand)
first ROV inspection (Deepwater Corrosion Services Inc, 2008).  Dead leg corrosion (mini or maxi stagnation fluid sites)
 Sand erosion high-velocity impacts at bends, tees, etc., but also
at straights
 Microbial episodic biofilms in particular
 TOL corrosion, mainly per gas lines
 Loss of passivity at the CRA surfaces must be assessed for all
(i.e. oil and gas lines)

All the above threats should be quantifiable with diligent inte-


grated on-line corrosion monitoring (coupons/probes/fluid analyses/
ultrasonic (U/T), etc).
The target corrosion rate for steel should be set at 0.1 mm/y and
all chemical, PTV adjustments focused around that threshold
number. As guidance deviations to 0.15 mm/y may be tolerated for
short periods (<2 weeks) and maximum of 0.2 mm/y accepted for
shorter periods (<3 days). Data beyond these frames would raise
a red flag, to be immediately attended to by the chemical inhibition
vendor. In contrast target corrosion rates for passivating surfaces
3.6. Case histories’ footnote can be <0.05 mm/y. Data beyond that should be re-examined and
other methods deployed to investigate. As a result of recent dia-
It is quite common for a precedent to be found in most failure logue between various company CAPEX and OPEX groups it seems
case examples, so that industry wide cross asset lessons learned are there is a moving away from target corrosion rates, and a closer
a powerful tool. However not all case histories are reported acceptance of best corrosion data within corrosion management
(company confidential), and so analysts often end up re-inventing strategies (API 1 7D). Threats perceived for passivation, must be
the wheel in terms of solutions, although every now and then examined via accelerated corrosion tests, using real fluid samples
a unique new mechanism or mode of failure is unveiled (API 580, for best representation. Risk-based matrices are often used to
2002). The most challenging corrosion failures are seen to be balance accepted risk (high-H, medium-M, low-L) against conse-
instigated during transient or excursionary physical or chemical quences and confidence levels (refer to Fig. 5 as a simplified
conditions, often at start up, commissioning or unplanned shut- example).
downs. The corrosion defect propagation is often during steady The pertinent interpretation and argument is that if corrosion
state operations, but must usually be addressed at initiation if were to be more formally recognized as a hazard risk, then the
corrosion control is to be effective. That invariably requires very formal techniques of hazard analysis will be better applied. Thus
close monitoring, recording and analysis of critical pressure, the better use of hazards and operability (HAZOP) studies and
temperature, velocity (PTV) data as well as close scrutiny and time failure modes and effects analysis (FMEA) as discussed later.
periodicity of inhibitor dosing losses, etc. That is more viable now
with the new generation of multiphase flow meters out on the 4.1. Engineering integrity, corrosion and flow aspects
market. As a rule, loss of corrosion inhibitor for more than
approximately two to three days in a row is not tolerable, and Essentially, the guidelines are based on second principles
a total of 18 days per annum is the equivalent to a 95% availability (applied) rather than the first principles (fundamental) as presented
factor. The ‘guaranteed’ performance of corrosion inhibitors under in the early text. This step change is often necessary in practice to
cocktailed (mixed flow assurance chemicals) is a vital requirement allow fit-for-purpose solutions to be identified. The data can quite
in many solution options (JPKeIonik, 2005e2008; Marsh, 2007; often then be revised as the more fundamental and experimental
Singh et al., 2008). data and equations are verified by subsequent testing, field extrap-
olations and project experience. The volume of work being done by
JIPs and the oil industry majors is prodigious, and as such this review
4. Hierarchy and rules can only be an insight, though an attempt has been made to focus on
relatively recent developments and practices evolving mainly over
Once the main corrosion threats are identified, it is usual to the past several years, post 2000 (Ohio University, 2007; University of
formulate a corrosion management strategy (CMS) plan of action. Tulsa, 2007). This draws, where possible, on a variety of standards,
The hierarchy or order of such events is best expressed as follows: recommended practices and technical papers as well as actual rela-
tively recent industry experiences via projects (API 1 7D; API 14E RP;
CMS > Inspection > Corrosion Monitoring > Pigging > Mitigation/ API 2RD RP; API 580, 2002; Baker, 2007; BBC web pages; BP Report,
Control 2004; Coastal Training Technology Corporation, 2007; Dalziell,
2004; Deepwater Corrosion Services Inc, 2008; DNV, 2000, 2002;
Once the sequence has been applied on a component-by- DOT Regulations; EEMUA, 2004; Fontana, 1984; JP Kenny,
component or segment-by-segment basis, an appropriate written 2005e2008, 2008; JPKenny/Ionik; JPKenny/University of Houston,
continued-fitness-for-purpose statement should be made, on 2008; JPKeIonik, 2005e2008; Massey, 1970; Mueller, 2006;
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 945

Fig. 5. Showing a 5  5 risk matrix based on high-, medium-, and low-risk corrosion events. The interpreted risk of failure is usually depicted as the product of probability and
consequence of the failure. Many matrices are used ranging from 3  3 to 10  10. The key is to quantify within the context of pre-agreed needs and ensure all parties understand
the implications (JPKeIonik, 2005e2008; Singh & Krishnathasan, 2008).

NORSOK Standard M001, 2004; Ohio University, 2007; Poblete, project-specific analyses. Either way, the real value of corrosion and
Singh, & Dalzell, 2007; Private Correspondences with Messrs Ben indeed erosion modeling is mostly in helping the decision-making
Poblete (LR/Cameron), 2000e2008; SCOTA/UKOOA, 1995; Shreir, process per materials selection and the differentiation between the
1994; Singh, 2007; Singh et al., 2003, 2005; 2006, 2007; Singh & use of carbon steel or the alternate CRAs (JP Kenny, 2008; Singh &
Krishnathasan, 2008; Smart, 1990; UK HSE, 2001; UK HSE/TUV- Krishnathasan, 2008).
NEL, 2003; UMIST/University of Manchester Corrosion Center,
1983e1995; University of Tulsa, 2007; US DOI-MMS, 2007; US DOI- 4.2. Guidance and caveats
MMS Federal Register, 2007; Vars Operator Standardization; WGIM
Internal Training Modules, 2000e2008; Wood Group HSE Matters, For carbon steel, typically for low-risk erosion rate scenarios this
2008) and as such may be used as a preliminary guidance docu- might be quantified at KPI values of 0.05 or 0.1 mm/y (JPKeIonik,
ment. Erosion corrosion is still a major threat to offshore and subsea 2005e2008). If medium or high risks of erosion are present then
assets, with related failures being thought to account for more than more advanced analyses available from independent testing or the
30% of all internal degradation-related hydrocarbon releases, or loss various JIPs already in place, such as at Ohio and Tulsa universities
of containment (Private Correspondences with Messrs Ben Poblete must be performed to assess this parameter (Ohio University, 2007;
(LR/Cameron), 2000e2008; JPKeIonik, 2005e2008; SCOTA/ University of Tulsa, 2007).
UKOOA, 1995). In practice such values could be up to and well in excess of
Since the mechanisms of corrosion and erosion acting together 10 mm/y. Therein sits the predicament for the corrosionist, namely
can be very intricate and multifaceted, in practice help to address what data to use to support one’s design rationale. The subject is
corrosion and erosion issues, engineers often resort to a ‘first pass’ ever complex and such decision making often has to rely on the
methodology of establishing corrosion rates and derived corrosion planned design economics and the project costs entailed capital
allowance (CA), and thereafter using an additive assessment for the expenditure (CAPEX) versus operating expenditure (OPEX) (Singh
erosion parameter. Useful guidance on the concept of CA can be et al., 2005, 2006). In any event the solutions must be fit for the
obtained from many sources (Kletz, 1998; Lees, 1980; Lord Cullen life-cycle targeted, and typically may either use thicker steel
Report, 1990; Mueller, 2006; Neal, 2007; NTSB). And if the corro- (greater corrosion allowances) or stipulate the use of a more
sion rate can be worked out from historical data or from modeling corrosion-resistant alloy (CRA). The latter may be solid pipe or steel
studies (i.e. the commercially available models or the publicly pipe lined or clad with CRA, typically at 3e4 mm thickness. Less
available freeware such as Norsok M506 or Cassandra 93/95) then than 3 mm is not recommended due to possible mechanical
an adjudged allowance (usually consensus agreed with the client) wrinkling effects that would impact the integrity of the liner
for erosion can be made (JPKeIonik, 2005e2008). (JPKeIonik, 2005e2008). Table 1 shows typical best practice CRAs
It should be remembered that the models only give general or considered for the offshore industry. Regarding the ongoing
uniform corrosion rates, and that the real value in corrosion evolution of inherently safe design it is interesting to note that even
modeling is not so much the absolute values but the trends and after so many years since the Piper Alpha there is still significant
changes. Also using more than one model allows a cross-checking project resistance to the formulation of safer designs, and better
device (use any three of the freewares available e Norsok, Cassandra more inherently safer materials selection, even though on balance
93 and Cassandra 95 at minimum, and use commercial models if total costs and economics are favorable over the complete life cycle.
available). In cases of major conflict or disagreement it is always
recommended to use the worst-case corrosion/thinning values for 5. Inherently safe design
best conservatism. There are many corrosion and erosion models
commercially available (>15) and if access to these is available these The technical challenge from an engineering perspective is to
should be explored, however, if not there are options outside that accept that corrosion initiation often occurs under non-steady
approach, since many similar software packages are often available conditions whilst propagation thereof is often under steady state
as in-house spreadsheets or issued by certain companies for operation. In practice such problems at excursionary conditions,
946 B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

Table 1 emphasis on reliability, and the use of CRAs, with attention to


CRA localized corrosion tendencies, as risk exemplified by pitting resistance all corrosion threats under all service or non-service
equivalent (PREN), critical crevice temperature (CCT) and critical pitting tempera-
ture (CPT), interpretation oilfield only.
conditions.
 ALARP and ISD e In future may likely be accepted legal terms
Alloy PREN CCT ( C) CPT ( C) Localized in a court of law. Both are strict but actually enforce better
corrosion risk
dialogue, greater accountability, more lateral thinking, and
304 Stainless steel (SS) 19 <0 15 High risk
ultimately promote safer life cycle, transparent, solutions. If
316SS 25 <0 20 Medium risk
Alloy 825 33 <5 30 Mediumelow risk applied diligently, they can offset CAPEX with reduced OPEX
22 Cr duplex (DSS) 37 20 30 Mediumelow risk (Dalziell, 2004; JPKeIonik, 2005e2008; Singh et al., 2005).
25 Cr super duplex (SD) 47 35 60 Low risk
Alloy 625 51 57 77 Low risk The values given are based on empirical formulae, composi-
tion, and testing and are sensitive to contact electrochemistry.
The alloy elemental compositions and mechanical properties are
can lead to conflict between the codes, inaccurate prediction of available in supplier’s literature. The order of corrosion resistance
erosion/corrosion, accelerated damage of chokes, bends, jumpers, is interpreted as:
and discontinuities, etc. Some of these difficult but definable trends
can be addressed via interrogation of commercially available Alloy 625 > SD > DSS z Alloy 825 > 316LSS > 304LSS.
computational fluid dynamic modeling (CFD) such as the various
flow assurance type modeling, as well as specific operator experi- The values are thought to be more applicable to static conditions
ences as for susceptible connecting jumpers in particular. And there and not sensitive to flow, though in principle if the flow regime can
are promising solution options with internal coatings/clad/liners, alter the pitting potential then some sensitivity could be recognized.
but care should be taken to alleviate changes in local surface Hence in principle standard laboratory assessments should always
polarization at undercut sites, localized eddies and temperature be supported by non-standard and fully representative testing and
gradients, etc. Nevertheless the intensive use of reliable corrosion field observations. To that effect authoritative suggestions for non-
and erosion monitoring such as intrusive (probes and coupons), standard, pressureetemperatureevelocity (PTV), upset, or chemical
and non-intrusive (acoustic transducers), field signature methods excursion corrosion testing, within the JIP test rigs, etc., can be
(FSMÔ), ring pair corrosion monitoring (RPCMÔ) spools (or made. Hitherto these would be considered strictly steady state only.
equivalents), guided wave ultrasonics, wall thickness mapping, From a predictive erosion perspective it is important to allow for
thermal imaging, etc., are proving to be very good early warning total wall thinning due to corrosion and erosion type degradation
systems for high-risk components (JPKeIonik, 2005e2008). The mechanisms. Generally if this calculation shows a total corrosion
close synergy between flow assurance and corrosion integrity is allowance (CA) value of CA > 10 mm then intervention via a suit-
now more apparent and many companies are now quite success- ably selected CRA material either as a solid material or as a lining or
fully, and to significant technical advantage amalgamating such cladding option is often considered. Some operators put this
groups (JPKeIonik, 2005e2008; Singh & Krishnathasan, 2008; threshold at 8 mm (or even 6 mm depending on the level of
Singh et al., 2008). conservatism supported). Either way the final decision is based on
From a mechanical integrity perspective it is very important for the economics of the project and the cost implications both at
engineers to think carefully beyond the immediate design codes of capital expenditure (CAPEX) and operating expenditure (OPEX)
practice, since corrosion and degradation can kick in fairly soon stages of the project. Another major factor is the length of the
after start up, often with major degradation issues and problems pipeline, generally speaking pipelines beyond 15 km length will
with continued operability or fitness for service. To that effect tend to look more closely at carbon steel with highly diligent and
engineers should consider utilizing the principles of inherently safe aggressive first-in-class chemical inhibition typically with >95%
design (ISD) to build in sufficient conservatism and safety (Dalziell, efficiency and >95% availability. Internal coating options are also
2004; JP Kenny, 2008; JPKeIonik, 2005e2008; Singh, 2007). Some feasible but would likely still need parallel inhibition schemes to
important definitions as part of broad ISD and integrity manage- cover for the protection of damaged coating sites. The inhibitors in
ment programs can be described as follows: that case would need to be highly proficient at addressing such
sites under crevice corrosion conditions. Designers should engage
 HAZARDS e Materials degradation, loss of mechanical prop- the services of experienced chemical vendors in this subject matter.
erties or corrosion must be considered a hazard, thus better Where required, the most frequently used alternative CRA material
legitimizing the risk-based approach, defining: corrosion choices tend to be the nickel alloys, alloy 625 and alloy 825, with
risk w probability corrosion failure  consequences. By the martensitic and austenitic stainless steels also commonly being
defining corrosion as a bone fide hazard, in this way allows the used, typically 13% Cr and 316SS respectively. Most projects these
more formal use of powerful advanced techniques such as days are often schedule driven, meaning that fast but detailed
HAZOP, FMEA (failure modes and effects analysis), FTA (fault advice is sought through guidelines from many sources, societies
tree analysis), ETA (event tree analysis), ISD (inherently safe (NACE, API, ISO, etc.), and the various JIPs, industrial and academic
design), etc. sources now available (JPKeIonik, 2005e2008; Ohio University,
 ALARP e Keeping material and corrosion failures ‘As Low as 2007; University of Tulsa, 2007).
Reasonably Practicable’. This provides the defensible risk
criteria basis for public and environmental concerns, subse- 6. Corrosion, ISD, integrity, and KPIs
quently reducing the critical gaming of financial incentives to
a less dominant and overriding parameter. As part of any inherently safe design or study, any corrosion
 ISD e Inherently safe design e designing such that material management strategy (CMS) used must be a fully auditable with
and corrosion failures are avoided or reduced to acceptable a unified approach to retaining integrity of the production facilities,
levels, design to ALARP can mean ‘fail safe’ or ‘safe life’ and to meet all goals for safe operation, environmental protection,
depending on objectives. In practice, used concurrently to save flowline availability, and revenue management. One proven method
time and money usually means less moving parts, greater for that is the quantifiable key performance indicator route.
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 947

The integrity management and (thus corrosion management i.e.  All inhibitors (including cocktail mixtures used) to be efficient
CMS) document will result in a campaign-driven prioritized at >95%;
inspection, chemical treatment, and monitoring of safety-critical  All inhibitors (including cocktail mixtures) to be available at
and economically critical elements within the facilities. This will be 100% (minimum ideally >95%, accept >90%);
best defined at the CAPEX i.e. design stage. Some studies have  Inhibitor dosing pumps to have >97% availability with redun-
previously examined these aspects, trying to take the best of Safety dancy as necessary;
Case interpretations for applicability to the GOM region in partic-  Topsides leak rates minimized e appropriate settings per
ular, and many such approaches have been successfully introduced, offshore asset MODU, TLP, etc.;
the process is ongoing however, and, as with all advanced offshore/  Key physical and chemical variables monitored for operational
subsea projects, is a continuing learning and improving process envelopes, and to be within 10% of steady state values, to
(IONIK JIP, 2008; JPKeIonik, 2005e2008). eliminate corrosion driving upset conditions;
The CMS will therefore form a vehicle to ensure continued  Ratio flow assurance steady states/unsteady states (excursions)
operability minimizing and controlling corrosion to acceptable to be defined, and monitored. More than 18 days p.a. total red
levels. This can be done by using relatively simple but meaningful flagged as corrosion stimulators and no more than three days
goal-setting targets, the key performance indicators (KPIs) (Singh, consecutively proposed be allowed;
2007; Singh et al., 2006; Singh & Krishnathasan, 2008). The focus  P, T, V, water cut, CO2, H2S, chlorides, iron counts, sulfide/sulfur,
of which is usually corrosion risk, but also other associated integrity sulfate reducing bacteria (SRB) counts, sand levels, etc., to be
threats within qualitative and quantitative ISD boundaries as defined and agreed with red flag alarms set. With regard to this
shown below: for accepted ‘clean’ systems consider the following rationale:

 Internal corrosion, external corrosion, corrosion under insu- Define HML risk criteria in context of failure modes and prob-
lation (CUI), erosion; Noting that CUI can be realized as a major ability, consequences thereof, and a quantified confidence level.
threat if piping/vessel insulation gets sodden e.g. via fire water The latter is a powerful new concept, relating HML, risk levels to
deluge testing. a confidence rating, ergo a better informed inspection interval, and
 Environmental cracking e stress corrosion cracking (SCC), thus more defensible monitoring philosophies and monitoring
sulfide stress cracking (SSC), hydrogen embrittlement, corro- detail.
sion fatigue/vibration/fretting damage, etc.;
 Embrittlement phenomena (clamps, flanges, premature 6.2. Water chemistry and microbial KPIs
fasteners/nuts/bolts failure due to intermetallic phases, seizing,
galling, etc.); Reservoir and condensing fluids/waters cannot be easily
controlled, however these all should remain within the design
Time dependent failure effects per localized corrosion, mechan- envelope, arbitrarily we can select guiding KPIs as follows:
ical fatigue and thermal creep, and conversely cold temperature loss
of properties, toughness, etc.;  pH 5.5e6.5, in absence of data use a pessimistic pH 4.5e5;
 Dissolved oxygen < 20 ppb;
 Damage resulting from accidental impact or structural over-  H2S < 5 ppm;
load, of particular interest to ‘live’ flowline segments, manifolds,  Sand < 10 ppm;
vessels, members, etc., linked to or carrying production fluids;  Microbial activity planktonic (in-stream) < 1 colony/ml
 Damage from welding stray currents during installation and (>10 colonies/ml e red flag);
commissioning operations on/offshore;  Microbial activity sessile (at wall) < 10 cells/cm2 (>100 colonies/
 Malfunction of protective safety devices, and loss of reliability cm2 e red flag);
to include corrosion scale build up, overheat for critical elec-  Total iron deposits < 1000 ppm (often arbitrary threshold,
trical cabinets, control units, electrostatic discharges, etc.; verify per chemical vendor);
 Design, material, fabrication and construction defects, prob-  Organic acids prefer <100 ppm (observe excursions
lems counteracted by specialty treatments such as flow >200 ppm, red flag > 500 ppm);
assurance additives, corrosion, and scaling inhibitors, etc.  Residual inhibitors to be defined and maintained e.g.
>125 ppm (or per vendor).
 Cleaning pig runs and sampling residues targeted at one per
6.1. Primary KPIs defined (corrosion) month minimum, or better as data dictates. Integrated pigging
and corrosion monitoring to adjust inhibitor dosing rates.
Individual corrosion rates interpreted from the coupon and ER Intelligent pig runs to be considered every 5 years.
data are time dependent, and can be defined via corrosion loops
(i.e. parts of the infrastructure or systems that are expected to yield
similar corrosion activity). For example, horizontal flowline 6.3. Other valuable KPIs
segments, vertical segments (SCR), hull piping, etc., or indeed such
loops may be defined to cover for a specific high-risk mechanism, Specific KPIs for external CP and external corrosion under
such as Corrosion under Insulation (CUI) across all systems. These insulation (CUI) usually need to be specifically developed, for
KPIs are guideline examples only and would be fine tuned on example the SCR/flowline CP potentials (versus Ag/AgCl cell) are
a case-by-case basis. Bearing that in mind we can define the now reasonably well established at:
primary corrosion KPIs as follows:
 900 to 1000 mV defined as well protected
 All corrosion rates to be <0.1 mm/y, (though this is often  <800 V defined as compliant-CP protected according to code.
challenged as the threshold may be too restrictive);  800 to 850 mV defined as marginal protection
 All CRAs to maintain passivity and exhibit corrosion rates  >800 mV defined as out of compliance (typically observed
<0.05 mm/y; 700 to 800 mV)
948 B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

KPI definitions for CUI are very project specific and temperature  Operating P, T, V, values and chemistry are maintained at
related and are omitted herein for reasons of brevity and steady state values (e.g. 10%). Excursions beyond that should
commercial sensitivity. be <2 days at a time unless reactive procedures (e.g. increased
dosing) can be accommodated.
6.4. Secondary KPIs defined (reliability)  Souring H2S levels remain negligible, <5 ppm (max 10 ppm). If
in the 50e120 ppm zone the combination of H2S and CO2 may
KPIs pertinent to reliability are described below for flowline be acceptable pending testing, however it appears that beyond
segments, pressure systems, and critical components. Most will be 120 ppm the scenarios must be closely looked at, especially if
data-base driven and using the TLP existing maintenance work the ratio approaches or exceeds 20. Recent research has shed
books as benchmarks: some interesting light on this combination and the impact on
surface passivity (Hahn, 2008; Lee, 2004; Thamala, 2008).
 Overall system production time availability e a commercial  The inhibitor cocktails must work at 90e95% efficiency with
target (e.g. >95%); a high availability not to fall below 95% unless specified
 Minimum system production availability e commercial circumstances are agreed. The greatest threat to inhibitor
decision; performance seems to be sand erosion at highly turbulent
 Ensure 100% inventory and spares for all critical items; cases and sand under-deposit corrosion within laminar flow
 Maintenance free operating period e MFOP w minimum regimes (IONIK JIP, 2008; JPKeIonik, 2005e2008).
failure free operating period, repair time e compare equivalent  There may be other defining caveats such as design envelope
items on similar assets constraints, and they would need to be identified by materials
 Overall run time e compare equivalent items similar assets engineers on a project-specific basis
 Failures rates (rotating items e.g. # failures per 100,000 h);
 Failures severity (HML equivalent to: dangerous, degraded,
incipient); 6.6. Monitoring tools
 Failure severity mitigation (HML equivalent to: urgent,
deferred, minor); It is recommended that the use of advanced U/T, inspection, and
 Failures rates per type of equipment e compare equivalent pigging must also be aligned to corrosion modeling predictions, as
items similar assets well as more appropriate methods of corrosion monitoring such as
 Damage rates per vibration/fretting issues e compare equiva- FSM or RPCM (instrumented spool techniques) (JPKeIonik,
lent items similar assets. 2005e2008; WGIM Internal Training Modules, 2000e2008) MIC
 Other decisions not covered directly may be addressed as analyses, thermal imaging, real time radiography, guided wave,
ALARP linked KPI issues. potential versus time (via platinum stud reference), best represen-
tative fluid sampling, etc. (IONIK JIP, 2008; JPKeIonik, 2005e2008).
Corrosion management is an ongoing discipline often required
6.5. Predictive modeling way past the available fundamental R&D; this time lag enforces
risk-based solutions to progress important energy projects. To that
The use of predictive corrosion modeling has been focused on the effect the use of pre-determined risk factors for localized corrosion
high-risk CO2/sweet corrosion areas pertinent to offshore applica- has been explored and recommended as an acceptable way
tions. This has been the case for core predictive tool for pipeline, forward, and usefully utilized, via fine tuning of project experience
flowline and piping corrosion integrity design. Unfortunately the and JIP data as accrued.
agreement between actual field practice and these predictions has It is therefore reasoned that pragmatic, advanced engineering is
tended to be poor; this is due to a number of factors, typically: key to safe and efficient operations, competitive advantage, and
sustainability in solving some of the most complex technical and
 Models assume uniform wastage (in reality hardly ever the case); political challenges that are facing the industry. Such engineering
 Models do not allow for localized corrosion, though some must involve the development of non-standard corrosion testing
claims are made; (field and laboratory) often under accelerating conditions.
 Models do not include other mechanisms (erosion, pitting, Clearly to quantify KPIs requires data, ideally live field data, and
microbial, etc.); to that effect there are many corrosion monitoring techniques
 Outputs can be erroneous because inputs are often non available. The most appropriate to offshore industry are commonly
representative; described and vetted for their advantages and disadvantages as
 Key parameters such as fluid shear stress at the wall are not they pertain to a successful project-specific corrosion and integrity
well defined. management regime (JPKeIonik, 2005e2008). Typically, the most
 Flow assurance aspects are not fully attended. efficient are the removable coupons, electrical resistance (ER)
probes, linear polarization resistance (LPR) probes, biostuds, fluid/
It is reasoned that the main materials selection and corrosion residue sampling, acoustic techniques, area U/T and various in situ
assessment output or deliverable should be accepted as being the spool mapping methods (JPKenny/Ionik; JPKeIonik, 2005e2008;
corrosion allowance, but with emphasis that this is but step one in SCOTA/UKOOA, 1995). Other advanced techniques such as a.c.
the corrosion management exercise (JPKeIonik, 2005e2008). impedance, electrochemical noise, hydrogen patch probes, etc., are
Nevertheless, this is the key variable that can quite literally decide available but are rarely used beyond the laboratory. Scale
the viability of a major subsea project. Therefore for a typical measurement devices with advanced monitoring and pigging are
project we can focus on the pipeline corrosion integrity, and also under review (JPKeIonik, 2005e2008).
confirm optimum CA values for effective life-cycle operations.
Invariably this will depend on the steady state design envelopes 6.7. Mechanical aspects and inherent safety
described and maintained, via compatible inhibitors diligently
applied. To deliver this, it is suggested a definition of project- Materials, corrosion, and the chemistry of the environment are
specific KPIs are made, and some examples are given below: rarely applied without the encompassing discipline of mechanical
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 949

engineering. To that effect it is vital for offshore teams to be mul-


tidisciplined, and typically that would require expertise in the areas
of pipeline, topsides, metallurgy, corrosion, cathodic protection/
coatings, process chemists, etc. These disciplines must cohesively
fit into an advanced offshore pipeline project, especially if new
(greenfield) designs are to be inserted into older (brownfield)
infrastructure. Thus strong technical leadership, and core compe-
tency are crucial to making the new challenging designs workable,
and to a degree inherently safe, and to that effect qualified and
experienced people are vital, with the will and motivation to
engage in contentious often adversarial debate. Much of which is
found to be best achieved at the interface between academia and
industry via the operator-sponsored JIPs. The role of academia
taking the lead in this process cannot be overemphasized as the
best placed ‘tempering’ organization.
For deepwater assets (>3000e10,000 ft) the arguments for asset
integrity become more critical since inspection, retrofit, repair, etc., Fig. 6. A typical pipe-in-pipe (PIP) system.
become extremely costly, dangerous and often impractical, thus
forcing materials engineering to be highly predictive in nature.
There are many parameters, most of which are interrelated, and cold Arctic applications. The PIP systems allow a range of advanced
should therefore not be considered in complete isolation. Invariably and highly efficient insulation materials to be used to achieve the
the key driver is the revenue and savings combination. If these requisite heat transfer properties required, and assures greater
targets cannot be met, the project may be blocked. Thus material degree of mechanical integrity, and is therefore an inherently safer
selection, corrosion, assessment, welding, CP/coatings must be design (JPKeIonik, 2005e2008; Jukes et al.).
inherently safe and optimized to be cost effective. These systems are important components of subsea develop-
These are real engineering challenges on top of basic mechanical ments where untreated well fluids may have to be transported large
design to resist stress, hydrostatic collapse, flow assurance, riser distances and wax and hydrate problems have to be effectively
systems, installation techniques, component operational perfor- managed. In addition for extreme cases such as LNG transportation,
mance, etc. Typically wall thicknesses have to be relatively thick, pipe-in-pipe-in-pipe (PIPIP) configurations (three concentric pipes,
making a heavy pipe string, and thus have significant impact on with typically a NiFe inner pipe high nickel (36%) steels being
installation lay barges and existing equipment capabilities. Once in selected for extra inherently safer/integrity characteristics (Singh
place there is little room for error, or remedial action, thus designs et al., 2005)). However monitoring the life-cycle integrity of such
have to take cognizance of best workable solutions, which are often systems can be a challenge but creative options are continually being
exercises in knowledge management across assets and indeed looked at (McLaury, Rybicki, & Shirazi, 1997; Singh et al., 2005).
regions (Singh et al., 2006).
There are a number of engineering challenges regarding the 6.10. Flow assurance solutions
flow assurance and related scaling issues within pipelines. Hydrate
formation, wax behavior, erosion, and multiphase flow (JPKeIonik, Hydrate formation, wax behavior, erosion, and multiphase flows
2005e2008). These are matters that need to be addressed. Inade- can be more critical design issues, especially for multiphase fluids
quate design in this area can lead to unwanted blockages, down transitioning from deepwater to shallow water. The flow assurance
time of pipelines, and therefore loss of valuable productivity. strategy comprises a combined design and management philosophy
for all of the following depending upon the fluid properties and
6.8. Design code application and limitations operating conditions such as: hydrate formation, wax/asphaltenes,
scale, forming, emulsion, slugging, and damaging erosion/corrosion
There is a considerable grey area of uncertainty regarding the (JPKenny/University of Houston, 2008).
interface between mechanical design codes and corrosion. Often
this needs to be plugged in by corrosion and integrity engineering  Hydrate management: To prevent and manage hydrate
using best risk-based judgments. formation, combination of either chemical treatment and/or
There are a number of pipeline design codes, and each one is thermal insulation may be used.
different. In the long term, uniformity in codes for pipeline design  Wax/asphaltene management: To prevent and manage
would be beneficial. Stress based design is not applicable for high paraffin deposition, a combination of thermal insulation,
temperatures, and could possibly lead to excessively thick pipe- chemical treatment and pigging may be used. A cost/benefit
lines. The use of strain based design codes, and limit state based analysis of these solutions should be conducted before final
design seems more applicable for complex high temperature selection of a paraffin management strategy is made.
designs. The integration of analysis tools with design codes is a key  Liquid slugging: Transient, dynamic analysis of the flowline
challenge; bringing in the effects of irregular corrosion thinning and risers must be conducted to evaluate the potential severity
complicates further. The use of JIP orientated corrosion modeling of liquid slugging. Based on this type of analysis, an appropriate
acting as de facto inherently safe promoting standards will have strategy to control slugging can be developed.
enormous benefits in this regard (IONIK JIP, 2008; Ohio University,  Erosion: Various types of sand and erosion monitors are
2007; University of Tulsa, 2007). available for installation within/on subsea tree and manifold
piping. These devices (ER e intrusive or acoustic non-intrusive)
6.9. Pipe-in-pipe options can be used to monitor erosion and optimize well flow rates,
often well above the API-recommended limits (API 14E RP).
The new pipe-in-pipe (PIP) options (Fig. 6) rapidly are becoming  Corrosion: The recommended material solution may be the
the design configuration of choice for deepwater and extremely use of carbon steel flowlines combined with near continuous
950 B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

inhibitor injection or the use of corrosion-resistant alloys in a very awkward position, trying to justify non-sour materials
(CRAs). The decision is usually made via corrosion modeling selection, when all predictions point to a sour service development
prediction techniques. The main threat to integrity is wetting of over the life cycle, albeit often in the distant future. Similar arguments
the annulus insulation by breeched inner wall, and the lack of and predicaments exist for advanced engineering criticality assess-
inspectability thereof. Much work is currently in progress in ment (ECA), and fitness for service (FFS) whereupon new flaw sizing
that regard (Jukes et al.; Singh et al., 2008). criteria need to be appraised at design and during service accordingly.
The combination of ISD, concurrent design, and standardization is
The typical strategy is best adopted early in the conceptual and a powerful tooling for challenging deepwater campaigns, and if
planning phase of the project prior to specifying and ordering the taught (included) within future engineering curricula a big step
main components of the system, such as downhole equipment, forward for the engineering community as a whole.
trees, flowlines, control system and topsides equipment.
Flow assurance strategy should also be applied during detailed 6.12. Materials and welding
system design, developing operating procedures as well as offshore
production operations to maximise profitability of the field devel- For both equipment and flowlines, a critical component of
opment. Based on the flow assurance analysis results, a design successful design for high pressure/high temperature (HP/HT) is
philosophy and functional specifications can be developed for the a thorough understanding of the materials and welding issues.
following elements: Management of detailed materials testing and quality procedures is
crucial, and the verification of drawing board detail to as received
 Sizing of well tubing and completion design; and built components is vital especially in the global market place.
 Sizing of all flowlines, risers and export system, including Also rigorous equipment specification is required, paying particular
subsea manifolds; attention to material selection for components, such as seals. In
 Thermal management (insulation or heating); addition, increased use of exotic materials, such as corrosion-
 Chemical injection, including the subsea chemical distribution, resistant alloys (CRAs), either solid or as liners, throughout the
umbilical, topsides chemical delivery system; system offers alternative solutions, though care must be taken at
 Pigging strategy (subsea or surface launching). interfaces, to minimize or eliminate junction galvanic effects.
Loadings that must be reviewed are:
One such solution is to make the pipeline more buoyant, to
reduce the span stress. To ensure that the pipeline does not get over  Axial, Lateral Movement;
stressed at the touch down point with the seabed, bend restrictors  Effective Axial Force;
can be used to limit the bending curvature.  Axial and Hoop Stress;
 Von Mises Stress;
6.11. Standardization of designs  Bending Moment;
 Plastic Strain, Buckling Curvature;
One major way forward still under development, is to generate
the standardization of designs, if the developments are similar in 7. HSE perspective
nature (water depths, pressure, temperature, corrosivity, etc.). The
main advantages from standardization are driving down costs, and Following review of the MMS (future BOE) and UK HSE step
reducing schedule time. If this approach can be suitably linked to changes in safety alerts, many recent insights have been identified
ISD there would be substantial benefit to the cause of CISD, The fear with respect to the potential for similar causes or similarities due to
seems to be that over exposure to materials selection and corrosion incidents that have happened since the Piper Alpha disaster. This
analysis is cost prohibitive. In reality the benefits to be exploited are: was done with a view to aid plausible corrective actions. The results
pointed to two main types of actions: those related to design safety
 Common health and safety culture down the supply chain; and those related to work permits and lockout/tagout. Thus, the use
 Support in the context of inherently safer designs; of meaningful corrosion and integrity management can also play
 Long-term supply chain relationships; a valuable role in such accident prevention. The review shows some
 Focused front end engineering design (FEED); uncanny parallels to the Piper Alpha case, such as initiating causes,
 Detail design, commonality of IM issues; with potentially similar outcomes. Prevention of these through
 Lessons learned (must be a continual process); diligent integrity management would clearly play a significant role
 Significant potential for integration within CMS programs; in prevention by design, predictive and proactive measures.
There have been many recent safety alert examples, and other
Used properly, standardization has the ability to collate, and relevant post accident studies, over the period (2000e2008), and
rationalize existing design methodologies, sift through best prac- details are readily available in the public domain (via CBS (Baker,
tices applicable to each region, and can therefore be expected to 2007), MMS and HSE web pages (JPKeIonik, 2005e2008)). It is
deliver significant improvements pertaining to; cost, schedule, more appropriate in the context of this paper, to identify the best
quality, operability, and predictability. actions derived from the alerts as exemplified below.
Major program standardizations are presently being undertaken
on projects in the GOM and overseas for major clients (JPKeIonik, 7.1. Actions from the alerts
2005e2008; Smart, 1990; University of Tulsa, 2007). The results are
attractive and promising in terms of scheduling, manpower  Compile and issue a shutdown specific isolation protocol, based
resources, and, therefore, budgets. However when unexpected vari- on review of practices elsewhere in the company and in other
ables enter the decision-making process, such as the possibility of worldwide affiliates. The document should cover vent/isolation
sour service being incurred post water injection scenarios, then tagging standards and documentation required for large-scale
difficulties can prove to be hard to surmount, especially if expensive shutdowns;
equipment has already been purchased or allocated. Under these  Lessees and operators should repair malfunctioning equipment
circumstances materials and corrosion engineers can find themselves in lieu of using alternative methods such as opening a manual
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 951

liquid dump valve when the automatic liquid dump valve fails necessary actions to ensure the safety and reliability of these
or blind flanging off a pressure relief line when a safety device critical components.
ruptures.  The national consensus standard for dynamic risers, API-
 Lessees and operators shall review piping to ensure that deck Recommended Practices are currently under revision (Baker,
drains have adequate trap mechanisms to prevent gases 2007). The revised version is expected to include guidance
(corrosion leaks) from migrating through, that deck drains are on integrity management for dynamic risers. The MMS will
not piped to a pressure line before entering a sump tank, and consider adopting this standard into its regulations for outer
that piping for produced water does not tie into the piping for continental shelf pipelines.
the wastewater from the living quarters.
 Lessees and operators should review flare boom lines to ensure A discussion of the findings shows three main types of recom-
that they are designed of proper length, height, and oriented in mendations that parallel the findings of Piper Alpha:
the proper position according to prevailing winds to minimize
the migration of gas back to the living quarters. Barrier and tag (a) There must be an effective work permit system including the
off for access under strict permit to work only. use of lockout/tagout, and
 Supervisors must provide adequate job instructions and plan- (b) There must be design review that is comprehensive enough to
ning prior to the work, without jeopardizing the scope inten- think ahead to the probable scenarios and consequences of the
tion of the work (applies particularly to contractors/inspectors design.
who can find themselves under pressure to complete and go). (c) Asset holders must have a formalized culture of safety which is
 Hazards must be identified as work proceeds, and a ‘stop work implemented and acted upon. Promoting life-cycle integrity
policy’ in place as the job scope changes. and parallel safety procedures, then not acting on them should
 Fire protection/deluge systems must not be compromised and be considered a zero option (Private Correspondences with
as a rule be ‘fail safe’ with 100% availability or redundancy. Messrs Ben Poblete (LR/Cameron), 2000e2008).
 Personnel must be familiar with and utilize lockout and tagout
procedures to isolate equipment and process piping during Noting that a very high proportion of equipment maintenance
work programs. work is corrosion, ageing or wear related, the clear evaluation is
 Simultaneous operations must be clearly communicated to all that potentially dangerous incidents continue from time to time at
appropriate parties, and made fail safe, detailing all site- offshore facilities. Corrosion prevention and detection and in the
specific procedures prior to work being implemented. larger view the use of integrity management systems are essential
 Lessees and designated operators should be able to trace the to proactively prevent these from occurring. In addition, safety in
history of ring gaskets in the field regardless of previous design is vital to building in prevention long before problems occur.
ownership, and/or determine the condition of the ring gaskets The MMS potential incidents of non-compliance (PINCs) were also
prior to the performance of future operations (gasket failure created to address that matter (US DOI-MMS, 2007). Finally, oper-
and ensuing corrosion-related leaks are very common ating best practices of work permit systems and lockout/tagout
offshore). remain a key to accident prevention generally.
 The Government requires lessees and operators to perform
strict maintenance and inspections, monitor the environ- 8. Corrosion risk management practice
mental conditions, and maintain records of these activities (API
14E RP; Singh & Krishnathasan, 2008). Since a failure on In reality the current corrosion business practices for most oil
a dynamic riser could pose a significant impact to safety, the and gas operations is a balance of three risk management
environment, and energy supply. Thus it is essential to perform methodologies. These methodologies are interrelated and must

Fig. 7. Schematic depicting the crucial relationships between reactive, proactive, and active corrosion analyses.
952 B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953

be balanced and reviewed on a continuous basis. The method- inspection interval, ergo monitoring philosophies and monitoring
ologies are: detail. The use of continually refreshed multidisciplinary teams is
paramount to enhancing creativity; the blend of experienced and
 Reactive Corrosion Monitoring; newly qualified engineers can help to minimize negative often
 Proactive Corrosion Monitoring; dysfunctional ‘group think,’ which can be a barrier to innovative
 Active Corrosion Monitoring. solutions (Edison, 2008; JPKeIonik, 2005e2008).
Corrosion, erosion, and MIC phenomena are major areas of
The decision on how to manage the corrosion business risk is weakness within failure mode and effects, understanding, and
highly dependent on the corporate senior management policy of control. However predictive modeling and JIP driven corrosion
handling their operational or capital expenditures. It is emphasized management programs are pushing for pragmatic solutions into
that these methodologies are equally important during the the right direction. The unique JIP blend of highly motivated and
conceptual to detailed design of an integrity management system. qualified researchers combined with experienced oilfield personnel
The inter-relations of the three methodologies are shown below in has led to many breakthroughs in offshore and subsea corrosion
Fig. 7. The importance of understanding the root cause (s) of any integrity issues (API 2RD RP; Singh & Krishnathasan, 2008). It is
corrosion issue is critical in providing pragmatic cost-effective therefore important for the engineering companies to stay abreast
corrosion risk management solutions. of safety-critical findings as they are unraveled and to participate in
It is considered that these corrosion risk management meth- such leading edge activities, with the offshore operators.
odologies will always be the underlying factors in the business Of the findings to date it is recommended to act on the Piper
decisions of all oil and gas operators. Management of change (MOC) Alpha findings and look beyond at the secondary issues pertinent
of the order required for meaningful ISD will in practice always be to offshore design integrity; such as materials performance, and
difficult, however the volume of literature now more openly corrosion, focusing on critical combinations such as corrosion
available in the industry will supply the required leverage needed. plus erosion, microbial activity, and corrosion plus souring
In particular operating company group standards and international activity, as matters of priority. It is also expedient to examine and
associations are clearly making the case quite forcefully better quantify the relationships between excursionary or non-
(International Association of Oil & Gas Producers (OGP), 2008; Vars steady corrosion phenomena, with the physical parameters, PTV,
Operator Standardization). and to find methods to enforce near continual chemical injection
when warranted, and assure that safe inspectability is always
9. Concluding remarks practical.
The use of an annual corrosion integrity statement by the asset
The Piper Alpha review has been a work in progress, with many operators is strongly recommended to ensure fitness-for-purpose is
derived findings, conclusions and specifically KPI-based recom- continually maintained. And since most offshore failures are the
mendations most of which are capable of being tailored to new and result of multiple parameters or events precipitating to a break
existing projects. The most valuable observation is the need for point, it is logical that resolution of same must involve multi-
continued life-cycle vigilance, most likely through diligent but disciplined engineering teams, with a strong materials engineering
limited regulatory control, since the North Sea experience has content.
shown that ‘over regulation’ can impose major financial burdens It is important for the future deepwater and arctic offshore
often to the detriment of the project, and sometimes to the crea- community to look more closely at new designs and new solutions
tivity of solutions. from both a materials fabrication and the materials performance
It is concluded that by applying the principles of concurrent and basis, especially for safety-critical elements such as steel catenary
inherently safe design, in tandem with best industry practices, to risers (SCR), and pressure containment plant, and potential leak
aggressive corrosion and erosion conditions, safer offshore assets sources at interfaces. Companies must continually re-educate staff
can be achieved. By using effective and simplified designs, creative so that lessons learned are not forgotten, and be prepared to look at
inspection, less maintenance, and less direct manpower, can help alternative approaches to design/operational issues even if they
better meet the life-cycle objectives, life-cycle integrity and fitness emanate from unconventional sources.
for service. Indeed if the combination of ISD, concurrent design, and History has shown that major step change progress is usually
standardization, is correctly deployed it can give a powerful made after major disasters and often through non-conventional
impetus for challenging deepwater projects, and if taught within means. The new solution sets, and developments will it is believed
future university engineering curricula give a major leadership role come from a closer liaison between industry and academia as
for the engineering discipline and community as a whole. exemplified by the JIPs already in place. The powerful role of
Setting the goals is paramount, and identifying the hazards, and Academia whether through JIPs or self driven changes in university
designing out the problem areas, is best done by multidisciplined curricula will be instrumental in the paradigm shift required and
project groups in small step sequences. A clear advantage would be perhaps expected. We owe it to the memory of Piper Alpha, and
for industry to accept corrosion as a hazard thereby opening it up to indeed other preventable disasters.
more formal written schemes of corrosion integrity risk analyses.
The use of commonly accepted high, medium, low, risk definitions Acknowledgements
and simplified go/hold/no go traffic signal type decision gates is
a significant evolution in the design and operational integrity The authors acknowledge the support of WGIM, J P Kenny, MCS
management process. Kenny, Wood Group, and Cameron. Educational material from
The methodology and KPI techniques advised require difficult Coastal Training Technology Corporation, and case history exam-
changes and lateral thinking, but serious traction, and a positive ples from Deepwater Corrosion Services, is gratefully acknowl-
paradigm shift has been noted when applied. The main advantage edged. Permission of the OTC Committee in Houston to use the OTC
being that it eliminates the erroneous premise that to comply with paper as template is appreciated. Thanks are due to Miss Sonia
codes and standards is all that is needed. Additionally the use of Singh for assistance with the re-write and formatting. Finally the
new quantifiable confidence grading is a powerful new concept, findings, interpretation and opinions expressed are those of the
relating HML risk levels to a repeatable confidence level, thus authors, and not necessarily those of the companies.
B. Singh et al. / Journal of Loss Prevention in the Process Industries 23 (2010) 936e953 953

References NACE. (2007). Nashville plenary lecture. Corrosion, crime, and punishment (panel
session e Garrity, K., et al.). Nashville.
Neal, M. (January 2007). JIMECHE Publication. The Causes of Accidents. ISSN 1751-
API 1 7D. Specification for Subsea Wellhead and Christmas tree equipment.
18471.
API 14E RP. Offshore piping design section 2.5, version 1991.
NORSOK Standard M001. (August 2004). Materials selection, rev 4.
API 2RD RP. Design of risers for floating production systems, and tension leg
NTSB Carlsbad pipeline failure report # PAR 03/01.
platforms.
Nyborg, R. (2002). Overview CO2 corrosion models. Paper 02233. NACE.
API 580. (May 2002). Risk based inspection (1st ed).
Nyborg, R. N., & Dugstad, A. (2007). TOL corrosion NACE paper #07555. NACE.
Baker, J. A. (January 2007). Report e the BP US Refineries Independent Safety
Ohio University. (2007/8). Corrosion modeling JIP. Chair: professor S. Nesjic.
Review Panel.
Poblete, B. R., Singh, B., & Dalzell, G. The inherent safe design of an offshore
BBC web pages. Various articles regarding the Piper Alpha disaster.
installation. In Texas A&M process safety conference, MKOPS, 23e24 Oct 2007.
BP Booklet. (2004). Integrity management e learning from past major industrial
Private correspondences with Messrs Ben Poblete (LR/Cameron), Graeme Dalzell
incidents booklet 14. Sunbury, UK.
(TBS3), Trevor Kletz (Author), Chris Robbins (UK HSE). (2000e2008).
BP report no. S/EPT/096/04 e erosion guidelines (rev 3). (2004).
Prodger, M. (Dec 1997). LR private correspondences 1997e1999, & LRIM corrosion
Coastal Training Technology Corporation. (2007). DVD Piper Alpha spiral to disaster.
management ppt.
Dalziell, G. (2004). Inherently safe design. Paper # 86598. SPE.
Ramachandra, S. (2007/8). Baker Petrolite, private communications.
Deepwater Corrosion Services Inc. Houston, web pages www.stoprust.com. (2008/9).
SCOTA/UKOOA. (ca 1995). Materials and corrosion course modules, by Singh/
DNV. (Jan 2000). Offshore standard. Submarine pipeline systems OS-F 101.
Bradley, Aberdeen, UK.
DNV RP 0501. (2002). Erosive wear in piping systems 1999.
Shreir, L. L. (1994). Corrosion control handbook (3rd ed.). Butterworth Heinemann.
DOT Regulations. CFR 49 parts 192/195 per gas and liquid pipelines.
Singh, B. (Feb 2007). Materials selection and inherently safe design. ASM presen-
Edison, E. (MayeJune 2008). The team development life cycle e a new look. Defense
tation, Houston.
AT&L.
Singh, B., Britton, J. N., & Flannery, D. (2003). Offshore corrosion failure analyses:
EEMUA. (2004). 194 Guidelines for materials selection & corrosion control for
series of case histories, # 03114. NACE.
subsea oil/gas production equipment.
Singh, B., Britton, J. N., Poblete, B. R., & Smith, G. (2005). The 3 R’s e risk, rust and
Fontana, M. G. (ca. 1984). Corrosion engineering. Van Wylen Press.
reliability. Paper # 05553 NACE.
Hahn. J. (ca 2008). Ph.D. thesis, Ohio University, Athens, OH (advance findings).
Singh, B., Folk, T., Jukes, P., Garcia, J., & Perich, W. (2006). From the North Sea to the
Hibbert, L. (June 2008). Averting disaster, professional engineering. IMechE Journal,
Gulf of Mexico e making the link between corrosion research and best practice.
21(11).
RIP # 06R206, NACE.
International Association of Oil & Gas Producers (OGP). (Dec 2008). Asset integrity
Singh, B., Folk, T., Jukes, P., Garcia, J., Perich, W., & Van Oostendorp, D. (2007).
e the key to managing major incident risks. Report #415.
Engineering pragmatic solutions for CO2 corrosion problems. NACE Corrosion.
IONIK JIP. (Nov 2008). Business case report (77447.03), rev B.
Singh, B., Jukes, P., Wittkower, R., & Poblete, B. R. Annual OTC, offshore integrity
Jepson, P., & Research Workers (1999e2002). The effects of multiphase flow on
management e 20 years on: overview of lessons learnt post Piper Alpha. Paper
sweet corrosion in oil and gas pipelines-vars early work presentations from
# OTC 20051-PP, Houston, TX, 4e7th May 2009.
Ohio University.
Singh, B., & Krishnathasan, K. Pipeline pigging & integrity management conference:
JP Kenny. HSE alerts and safety notices 2005e2008.
Making the link between inherently safe design, integrity management and
JP Kenny. (Dec. 2008). T4B series e arctic pipelines, materials, FFS, and corrosion
pigging, Houston, 12e15th Feb 2008.
studies. C-In-C.
Singh, B., Krishnathasan, K., & Ahmed, T. (Oct 2008). Predicting pipeline corrosion.
JPKenny/Ionik. Internal experience basis, corrosion reports, in-house spreadsheets
Pipeline and Gas Technology Journal.
& toolboxes.
Smart, J. (1990). A review of erosion corrosion in oil and gas production. In Flow
JPKenny/University of Houston. (2008/9). Pipeline engineering course modules, by
induced corrosion symposium: Fundamental studies and industry experience.
AEG/IONIK.
NACE Corrosion.
JPKeIonik. Corrosion and integrity management literature, experience basis e
Thamala, K. (ca 2008). M.S. thesis, Tulsa University (advance findings).
various projects 2005e2008.
UK HSE. (2001). Contract research report 363/2001, best practices for risk based
Jukes, P., Singh, B., Garcia, J., & Delille, F. Critical thermal, corrosion, & material issues
inspection (TWI/Sun Alliance).
related to flowline pipe-in-pipe (PIP) systems. Paper # ISOPE-2008-TPC-297.
UK HSE/TUV-NEL. (2003). Erosion research report #115.
Kletz, T. (1998). What went wrong e Case histories of process plant disasters (4th ed.).
UMIST/University of Manchester Corrosion Center (J. L. Dawson/G. E. Thompson, W.
Butterworth Heinemann.
Cox, et al.). (1983e1995)..
Lee, J. (ca 2004/5). Ph.D. thesis, Ohio University, Athens, OH (research data).
University of Tulsa. (2007/8). Erosion and corrosion JIP. Chair: professor E. Rybicki.
Lees, F. P. (1980). Loss prevention in the process industries. Butterworths.
US DOI-MMS. (Feb 2007). Offshore & pipeline regulations e PINC listings.
Lord Cullen Report. (1990)Public inquiry into the Piper Alpha disaster, Vols. 1 and 2.
US DOI-MMS Federal Register, Vol. 72, No. 191 Oct 3 2007/Proposed Rules 30CFR
HMSO. (Reprinted 1993).
parts 250,253,254,256.
Marsh, J. (2007). T.Teh, conflicting views CO2 corrosion. SPE paper #109209.
Vars operator standardization documents for subsea materials 2006e2008.
Massey, B. S. (1970). Mechanics of fluids. Van Nostrand Reinhold Co.
WGIM internal training modules. (2000e2008). A. Denny/G. Strong et al. Includes
McLaury, B., Rybicki, E., Shirazi, S. (1997). Tulsa Univ. SPE # 38842 SPE Tech. Conf,
support literature from Alberta Energy & Utilities Board (Canada), Roxar (USA),
San Antonio, TX.
Cormon (USA).
Mueller, R. A. (March 2006). Corrosion allowance e not always a simple concept,
Wood Group HSE Matters. Company report 2008 e article, the lessons of Piper Alpha.
materials performance.

You might also like