Project Details: Activities Undertaken Under The Project
Project Details: Activities Undertaken Under The Project
ROAD WORK
After preparation and signing of agreement between Third Party Agency and Client, WAPCOS initiate
site visits for the projects where tenders have been invited or where construction has commenced
Examination of project documents, designs and drawings w.r.t. the sanctioned convenants.
Analyzing various material used in road construction such as good earth, coarse aggregates, fine
Conducting field tests at various stages such as measurement of road width and thickness, sieve
analysis, field density of GSB, WMM, BC etc., %age Compaction, Bitumen Content test, Core Cutting,
Plate Test for Tack Coat, Determining Compressive Strength of Pavers (if used) etc. and all other
Checking whether the Design Mix of Bitumen being used in road work is as per approved Grade and
Specifications or not.
To keep an eye on smooth ongoing of the project and simultaneously rectifying the defects or errors,
if any.
Compiling of data and preparation of joint inspection reports including status of work as per
agreement and actual status of work executed at site with test reports for the tests conducted at
site, deficiencies observed in execution of work, corrective measures and overall comments in the
After preparation and signing of agreement between Third Party Agency and Client, WAPCOS initiate
site visits for the projects where tenders have been invited or where construction has commenced
Examination of project documents, designs and drawings w.r.t. the sanctioned convenants.
Analyzing various material used in laying of sewerage and water supply lines such as coarse
aggregates, fine aggregates, cement, quality of water etc. quantitatively and qualitatively.
Analyzing various parameters such as length of sewer/ water supply line, whether type of sewer
being laid is as per agreement or not, quality and type of pipes being used, concrete being used in
laying of sewer/ water supply, slope, steps of manholes, haunching etc. and all other necessary tests
To keep an eye on smooth ongoing of the project and simultaneously rectifying the defects or errors,
if any.
Compiling of data and preparation of joint inspection reports including status of work as per
agreement and actual status of work executed at site with test reports for the tests conducted at
site, deficiencies observed in execution of work, corrective measures and overall comments in the
CIVIL WORKS
After preparation and signing of agreement between Third Party Agency and Client, WAPCOS initiate
site visits for the projects where tenders have been invited or where construction has commenced
Examination of project documents, designs and drawings w.r.t. the sanctioned convenants.
Analyzing various material used in construction of civil works such as Community Centres, Sewerage
Treatment Plants, Police Station, Old Age Home and other Departmental Buildings such as coarse
aggregates, fine aggregates, cement, bricks, reinforcement, quality of water etc. quantitatively and
qualitatively.
Conducting field tests at various stages such as slump cone test, casting of cubes for determination
of Comressive Strength of concrete being used, whether steel reinforcement being used is as per
approved make of DNIT or not, Rebound Hammer test for determination of Compressive Concrete
already casted concrete structure, whether curing of brick work and concrete work is adequate or
not, shuttering, bending and binding of steel, and all other necessary tests pertaining to road
construction.
To keep an eye on smooth ongoing of the project and simultaneously rectifying the defects or errors,
if any.
Compiling of data and preparation of joint inspection reports including status of work as per
agreement and actual status of work executed at site with test reports for the tests conducted at
site, deficiencies observed in execution of work, corrective measures and overall comments in the