Professional Documents
Culture Documents
MWPP Accss Civ PRD 0004 RG Eddited
MWPP Accss Civ PRD 0004 RG Eddited
MWPP Accss Civ PRD 0004 RG Eddited
Ceylon Electricity Board Vestas Asia Pacific A/S Access Engineering PLC
Page No: Page 2 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Version History
This Version,
Paper size
Main document A4
Contents
Comments Reply Sheet .......................................................................................................................................... 7
1. Introduction ..............................................................................................................................................16
2. Scope of Work .........................................................................................................................................16
2.1. Construction Sequence .................................................................................................................................. 17
1.1.1. Test pile ............................................................................................................................................... 17
3. Resource Requirement ...........................................................................................................................17
3.1. Machinery and equipment list per team ........................................................................................................ 17
3.2. Manpower list per team .................................................................................................................................. 19
4. Construction Methodology ......................................................................................................................19
4.1. Drilling Sequence of Single WTG Foundation .............................................................................................. 20
4.2. Preliminary Survey &Driving temporary steel casing ................................................................................... 20
1.1.2. Ground Preparation and Setting Out ................................................................................................. 20
1.1.3. Pre-Drilling and Driving Temporary Casing....................................................................................... 21
1.1.4. Maximum Permitted Deviation ........................................................................................................... 21
1.1.5. Verticality ............................................................................................................................................. 22
Page No: Page 3 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
1.1.34. Fuel/ Oil split Occurrence Emergency Preparedness and Response plan ..................................... 41
1.1.35. Risk assessment ................................................................................................................................. 43
ANNEX – A: TECHNICAL SPECIFICATIONS OF BG MACHINES .................................................................. 52
ANNEX – B: QA/QC PLAN ................................................................................................................................... 71
1. Introduction ..............................................................................................................................................72
2. Quality Control Hold Points.....................................................................................................................72
3. Material Testing .......................................................................................................................................72
3.1. Bentonite Testing............................................................................................................................................ 72
1.1.36. Bentonite Density Test (According to BS1888 Specifications) ........................................................ 72
1.1.37. Bentonite Viscosity Test (According to BS1888 Specifications.) ..................................................... 73
3.2. Testing For Concrete ..................................................................................................................................... 73
1.1.38. Workability of the Concrete ................................................................................................................ 73
1.1.39. Compressive Strength Test ................................................................................................................ 75
3.3. Steel Testing ................................................................................................................................................... 76
3.4. Pile Testing ..................................................................................................................................................... 76
3.5. Pile Defect Rectification ................................................................................................................................. 77
3.6. QA/QC Formats .............................................................................................................................................. 77
ANNEX – C: SAFETY PLAN ................................................................................................................................95
1. General Safety Work Provisions ............................................................................................................97
1.1. Personal Work Provisions .............................................................................................................................. 97
1.2. Safe Plan According with the Piling Activities .............................................................................................. 97
1.2.1. Pile Driver Assembly ........................................................................................................................... 97
1.2.2. Erection ................................................................................................................................................ 97
1.2.3. Moving the Rig .................................................................................................................................... 98
1.2.4. Driving Piles ......................................................................................................................................... 98
1.2.5. Concreting ........................................................................................................................................... 99
1.2.6. Welding and Cutting............................................................................................................................ 99
1.3. Machine ......................................................................................................................................................... 100
1.4. Fire ................................................................................................................................................................100
1.5. Electrical ........................................................................................................................................................ 100
2. Operators and Maintenance Personnel ...............................................................................................101
3. Equipment Application and Safe Condition .........................................................................................101
4. Danger Zone and Safety Clearance ....................................................................................................102
4.1. Danger Zone ................................................................................................................................................. 102
4.2. Safety Clearance .......................................................................................................................................... 102
5. Personnel Handling ...............................................................................................................................102
6. Tipping and Damage Prevention ..........................................................................................................103
6.1. Operating and Travel Practices ................................................................................................................... 103
6.2. Operation in Vicinity of Unstable Ground ................................................................................................... 103
Page No: Page 5 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
4.2.3 Maximum 13. If the allowable tolerance is exceeded, the 13. At the first, it shall be made a third
permitted deviation alternative technical proposal including party verification for the subjected pile
rectification methodology shall be with the witness of
submitted with justifiable proof by the Engineer/Employer. Situation is same
independent competent professional in as in internal check, we need to
the industry with an agreement of the inform this deviation to the designer
Employer. an then he can show that due to
deviation there is no any impact to the
foundation by calculation.
Third party checking and verification
from consultant side also be better in
this case
4.2.4 Verticality 14. Methods for verify the verticality of the pile 14. Described in section 4.2.4
bore after boring prior installation of the
reinforcement cage to the pile shall be
specified.
4.3.1 Pile boring 15. Boring tools required for actual site 15. Casing tube, core tube, drilling bucket
with bentonite condition shall be specified in MS. and augur drill
slurry
Page No: Page 9 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
3. As per CIDA/SP/101 clause S1.8 (b), Static 3. Our Testing Plan as follows.
load test shall be done 1% of the total One instrumented SLT will be
number of piles and detail description of done as the preliminary test pile.
SLT shall be submitted. Every pile will be tested for
integrity by CSL method.
One PDA scheduled on every
wind tower location. (Nearly 7%
of total number of piles)
1.1.1 Test Pile 4. It is recommended to perform at least 02 4. Please refer the answer for the item
instrumented pile load test including no 03.
compression, tension and lateral load
1.1.2 Ground 9. Overcasting shall not be less than 1.4m as 9. We will take the concrete level up to
preparation and per Employer’s specification (7.6.3.3.5.d). 1.4m from the cut off level or up to
setting out and Thus, temporary platform is essential for the existing ground level. In an event,
4.9 pile head efficient and safe piling work. Revise the the clearance between, cut off level
casing level description accordingly. & existing ground level is lesser than
tolerance 1.4m, pile has flushed with adequate
volume of concrete in order to verify
Page No: Page 13 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
1.1.3 Pre-Drilling 11. The behavior of soil different from 11. It is not recommended to extend
and Driving location to location. So temporary casing the temporary casing over 6.0 m in
Temporary is recommended in the very loose sand. general since during the withdrawal
casing Thus temporary casing at least 10m of process of the casing pile might get
length has to be kept at site prior to damaged. Therefore, in principle we
boring. will maintain the temporary casing
height at 6 m and the balance portion
will be stabilized by bentonite.
1.1.4 Maximum 12. Qualification and experience of the 12. Noted. This will be submitted Commented [M1]: @ Achala
For your necessary action please
permitted surveyor who will do the setting out separately.
Deviation works shall be provided with the MS.
1.1.5 Verticality 13. Method of verticality check shall be 13. BG machine has the facility to check
specified after boring prior to rebar cage the verticality of the borehole, it self.
installation. MS only described verticality
check for temporary casing.
1.1.8 Boring Near 14. Additional test cube shall be made for 14. Noted and will do accordingly.
Recently Cast pile verification of strength in early boring
situation.
1.1.10 Drilling 15. Drilling termination criteria shall be 15. This has been discussed and agreed
Termination revised if pile design depth is more than during the discussion had with CEB on
borehole investigation minus 4D. …………..
1.1.11 17. Number of welding tags shall be 17. We will provide a shop drawing.
Reinforcement specified.
Cages
18. Completely description shall be specified 18. Sonic ducts will be fastened to the
for installation and maintenance of rebar cage in order to maintain its
vertically of the access duct and size of verticality. Detailed shop drawing will
the duct shall be specified. be provided.
Page No: Page 14 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
1.1.13 Placement 19. As specified in contract document 19. Noted and will do accordingly.
of Rebar cage volume 10, chapter 7, clause 7.6.3.3.5 C,
Spacers shall be spaced at interval not
exceeding twice the pile diameter.
1.1.14 Cleaning 20. Methodology shall be provided to ensure 20. Depth of boreholes will be
Pile Toe the bottom sedimentations. And measured in 05 different places
thickness of the sediment to measure including the center and 04 edges to
physically at site. ensure the design depth.
14.12 Inspection 21. Acceptance criteria shall be specified 21. Already submitted as a separate
and Test Plan and clearly. MS.
Annex G, H
22. Check of elevation of pile shall be 22. Top levels of Access ducts will be
Achieving design included. measured prior to the test and that
depth has been included to the CSL check
list.
Alternative plan 24. The PDA or Static Load Test provides the 24. In an uncertain situation as
for extra piling load carrying capacity only and does not specified, we will get opinion from
provides the clear indication for integrity, independent professional/
hence to confirm the integrity of the pile consultant.
PDA or MLT is not accepted. Since all pile
are in the overburden soil layer and no
rock socketing is encountered. Thus pile
integrity is very crucial. Hence integrity
should be verified in addition to the load
carrying capacity of the pile. However,
compensation with the same pile without
additional pile should be confirmed by an
independent consultant.
Annex – B: 25. Defective pile should not be included in 25. Noted.
QA/QC Plan 5% of the PDA test requirement.
Section 3.4 pile
testing
Annex – B: Check 26. Casing levels (top and bottom) and 26. Noted.
list “ Bored pile planned toe level shall be included.
records”
Annex- B: Check 27. Following items shall be included in check 27. Noted.
list “ Bored In list
situ Pile” Planned level of pile top and toe
Length of steel casing
Page No: Page 15 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Annex – B: 31. Calculation sheet for estimate for load 31. Noted. Separately submit for
QA/QC Plan carrying capacity before boring and after approval
boring shall be submitted. So sample
format for calculation sheet shall be
included.
Annex - G 32. Pile testing organization shall be 32. Noted and the company profile of
acceptable to Employer. the testing agent will be submitted.
33. Qualified authorized person and 33. Will be included in the company
acceptable to employer shall be engaged profile.
for recommendation for the test results.
1. Introduction
Ceylon Electricity Board plans to implement 100 MW Mannar Wind Power Project phase 1 in the southern coast of
the Mannar Island which is located in the North province of Sri Lanka 300 km from commercial capital, Colombo.
Vestas Asia Pacific A/S (main contractor) have been awarded to design, supply and install wind farm in Mannar
Island. Access Engineering PLC will be the BoP sub-contractor for civil works.
This method statement is intended as a guideline for CEB (The Employer) Personnel &Vestas Asia Pacific A/S and
Access Engineering PLC site staffs to ensure a safe and efficient piling works of Mannar Wind Power Project. This
should be read in conjunction with the applicable approved drawings, specifications and relevant designs.
BS 8004 and also CIDA/SP/101 will also be applicable for some situations.Execution of bored piles shall be as per
BS EN 1536:2010.
2. Scope of Work
Scope of the project consists of the followings,
Pile setting out
Mobilizing the Boring machinery
Boring machine placement
Pre-boring up to require depth (at least 2/3 rd length of temporary casing)
Temporary casing installation
Rechecking of position and casing verticality
Pile boring up to design depth plus required tolerances
Removal and transferring of soil
Bentonite circulating system for drilling process (density, viscosity, pH, sand content etc.)
De-sanding
Borehole depth reading
Washing the pit and lowering of submersible pump
Pile toe cleaning
Fabricating and bar bending
CSL access tubes installation and attached to rebar cage
Rebar cage installation
Tremie pipe lowering
Check bentonite properties before concreting (density, viscosity, pH, sand content)
Test cube casting
Concreting process
Removal of temporary casing
Waiting for strength gain
Pile head treatment and hacking
Pile testing(CHSL or PIT,PDA)
This method statement covers for providing bored cast-in-situ reinforced concrete pile foundation including boring
work, steel reinforcement, concreting, pile head treatment, pile testing and all other work as required.
Table 1: Scope of Work
Item Description Unit Quantity
1. Bored Piles – 800mm diameter No’s 450
2. Bored Piles – 800mm diameter- Test pile No’s 1, as finalized by design
3. Pile Integrity Test (PIT) ,if pile length <20m No’s All Piles
4. Cross hole sonic logging test, if pile length >20m No’s All Piles
5. PDA test No’s 1 test for each WTG location
Page No: Page 17 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
3. Resource Requirement
3.1. Machinery and equipment list per team
Table 2: Machinery and Equipment list
Item No. Description Unit Quantity
1 Boring rigs Nos 02
2 Mobile crane Nos 01
3 Crawler crane Nos 02
Page No: Page 18 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
4. Construction Methodology
The construction methodology which will be adhered to this project is descriptively illustrated in this chapter. Annex
D consist a summary of this chapter. Typical piling methodology consists following key processes which includes
various sub processes.
i. Preliminary Survey & Driving Temporary steel casing
ii. Pile Boring
iii. Preparation of the R/F Cage
iv. Cleaning and Concreting the Bored Pile
v. Testing of Piles
First four key processes are described in this chapter with various sub processes relevant to them. See the annex
G, H and I for testing details
Page No: Page 20 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
4.2.4 Verticality
During and after installation of the temporary casing also it required to check the position of the boring, in that case
perpendicular offset two points shall be placed 1m (between 1000mm-2000mm) from the center point. After
installation temporary casing, offset distance from each point to casing shall be measured and the values shall be
same or within the allowable limit (±75mm) (Reference BS 8004:1986 clause 7.4.2.5.4). However it is better to
reduce this deviation as much as possible without depending on the tolerances.
During installation verticality shall be checked with 600mm or 1000mm length spirit level from two positions which
locations are perpendicular to each other. If 1m sprit level used to check the verticality, the deviation shall not be
greater than 10mm.
After intermediate checking of the position and verticality temporary casing shall be stay align with the support of
boring machine and drive through the soil.
The maximum permitted deviation of the finished pile from the vertical is 1 in 75
BG machine has the facility to check the verticality of the borehole, itself to check the verticality of bore at the end.
strength results of pile mix design as 18MPa. It is very close to the 50% of day strength which is shown that there
is no unset concrete when it is old 48 hours from the date of casting.
Additional test cube shall be made for verification of strength in early boring situation.
4.3.4 Properties of Bentonite Slurry
Drilling fluid shall be checked for following properties, during the soil boring stage and the flushing stage of a pile.
Table 4: Bentonite Slurry Properties (Reference: BS 8004: 1989 clause 6.5.3.8.2 and clause 7.4.5.4.3)
In order to check the quality of the slurry the following equipment shall be used:
Marsh funnel
Mud balance
Sand Content Kit
Prior to concreting of a pile, Bentonite samples will be taken from the bottom of the pile bore to test the actual
properties of the Bentonite slurry. A Bentonite sampler which allows collecting slurry at any depth will be lowered
to pile bore in order to collect Bentonite samples. It consists of a tube and two balls on top and bottom of the tube.
All the test equipment shall be calibrated and back up testing equipment for this kind of compulsory and urgent test
shall be available at site to use in case of emergency
Page No: Page 24 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Reinforcement cages shall be suspended or supported so as to maintain their correct position during concreting.
Sonic ducts will be fastened to the rebar cage in order to maintain its verticality. Detailed shop drawing will be
provided.
4.4.2 Concrete Spacer blocks Details
75 mm
General Notes:
Y
15 mm
Y
75 mm : Cover
165mm : Outer Diameter of the
75 mm
Spacer Blocks
50 mm : Height
Location of Spacer blocks shall be
decided as per the construction
drawing
165 mm
The reinforcement cage will be hanged by a steel stiffener welded in girder casing to ensure 100mm gap between
the bottom of the reinforcement and the toe of the pile. Grade of spacer block shall not be less than the grade of
pile concrete.
Rebar cage shall be lifted by mechanical means (crawler crane) and lowered into the borehole very carefully without
damaging to the walls. Excess length shall be cut off from the rebar cage after the installation. 100mm gap to be
maintained between pile toe and rebar end which is maintain by using calculation considering the borehole length
from the casing top and total rebar cage length.
The reinforcement shall be installed as soon as possible after the cleaning of the pile bore.
The installation of the reinforcement has to provide for its alignment with the pile axis and maintain the correct
concrete cover over its full length.
However, after lowering the rebar cage the bore-hole will be measured and verified again prior to concreting. If
there is major soil collapse encountered, rebar cage will be lifted up and the bore-hole will be clean again. The
Bentonite slurry properties will satisfy the requirements mentioned in table no 04.
Case 02
Step 01 : If a hard layer is encountered in the pile toe at the termination, flushing operation will take place
Step 02 : Bentonite will be pumped to the borehole through the tremie to remove sludge.
Step 04 : Discharged Bentonite will be collected and sent for de-sanding process
Step 04 After attain the sand content of the pile to satisfactory level, ready the pile for concreting.
4.6.5 De-sanding
Prior to concreting, Bentonite in the bore hole must be sampled and checked to ensure that it satisfies the minimum
criteria for concreting. When this is not the case, Bentonite in the bore hole is circulated through the de-sanding
plant; alternatively it may be partly or completely replaced by fresh Bentonite so that its characteristics satisfy the
contract requirements. The decision on whether to circulate or to replace the slurry is a function of the properties of
the slurry in the bore, the contract specifications that characterize this material, the availability of fresh Bentonite
and time.
Figure 8: De-sander
Page No: Page 30 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Bentonite IN from
the Silo OUTPUT Send to the De-Sander
Concreting shall only commence once a sufficient number of loaded mixer trucks are available on site ready to
discharge the concrete and all other trucks are confirmed for arrival. The slump of the piling concrete shall be
200± 25 mm before the discharge into the pile bore.
At the commencement of concreting, the bottom of the tremie shall be placed between 100-150mm from the
bottom of the borehole. The funnel with appropriate capacity shall then be filled with concrete up to brim level.
The concrete shall be released by removing the lid fixed at the bottom of the funnel and the concrete shall be
discharged without interruption in one operation unit. Then the tremie pipe is raised and the concrete is placed at
the bottom of the pile if needed only. Whilst concreting, the tremie pipe shall be raised in such a manner so that
the embedded Tremie length in to the concrete is at least 3.0 m of fresh concrete.
The concrete may be retarded to ensure that setting does not commence within four (04) hours of arrival at site.
A retardation of 4 hours is recommended to avoid technical problems during concreting. When concrete mix is
supplied to the site, uniformity, temperature (should be less than 32°C) will be checked.
On-site sampling and testing of concrete usually consists of taking:
Sets of cubes - The amount and frequency of sampling and testing are specified in the contract specifications.
(Clause7.6.1.13.2)
Clause 7.2 project quality plan MWPP-ACCSS-QUA-PLN-0001
Cubes to be casted for testing purpose each mix. For each 15 m3 of concrete 3 set of cubes to be casted each
set having 3 no of cubes (total of 09 test cubes). 7 days strength and 28 days strength to be checked compulsory
and other set is to check the strength in any time as the requirement. In 28 days concrete shall be achieved its
full strength and in 7 days 65% of it.If the concrete amount is less than 15m3 for each concrete supply it should
be maintained minimum 9 no of cubes.
Three cubes out of 9 cubes so collected shall be tested at seven (7) days and further three cubes shall be tested
at twenty eight (28) days. The remaining three cubes shall be retained as reserve and tested if and when required
by the Employer.
Slump tests - carried out regularly on site to check consistency in the workability of the concrete.
During the concreting process the actual consumption of concrete is plotted against the theoretical volume and is
included as part of the panel records. This information will enable the identification of zones of necking or over
break
Backup batching plant will be ready for feeding the concrete in an emergency situation. In addition skilled
technician shall be available to settle majority of incident without any delay.
Guide Bars
Steel Tag
Casing
R/F Cage
No Methodology Application
1 Breaking of Piles by Hand Held Pneumatic breakers Reinforced concrete portion
2 Using hand held small chipping Hammers 200mm above Pile cutoff level.
3 Using wedges [A crack will be induced at the cut-off level of the This will be used case-by case
pile head to separate the mass of concrete above, which led to where application of this is
its easy removal in one piece to be lifted away.] appropriate with other parameters
After the level of cutting has been cut by using cutting grinder, continue the pile chipping work using hand
held pneumatic breakers up to cut off level.
Levels: Pile hacking will be carried out from top of casted pile up to sound concrete with conformity to the
cut-off level.
Rebar Protection: Extra care will be adhered for the rebar while hacking to avoid deformation.
Hacking below Cut-off Level: In case sound concrete is encountered below cut-off level, then the pile will
be re-built up to cut-off level.
Engineer’s Confirmation: Joint Inspection with the Engineer’s representative will be performed upon
completion to confirm the levels.
Disposal of Waste Material: Non usable concrete pieces and soil will be removed from the Site premises
immediately.
4.11.5 Safety
All the site staff and workers should wear ear plugs, safety eye glass, safety helmets and shoes (PPE)
All the dangerous areas must be barricaded & demarcated
All the electrical wires and sockets must be covered to safety regulations
All the site staff and workers must be alert when working near heavy machineries
4.11.6 Protection
The excavated area will be demarcated using barricade tapes stretched on support bars, around the
perimeter of excavation.
Page No: Page 36 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
If there will be a first aid case, HSE Manager and/ or first aider will arrange necessary first aids according to the
injury. If the injured person required further medical attention, HSE Manager will contact Mannar General Hospital
or Pesalai Divisional Hospital according to required medical need.
2. Details of contact personal and agencies shall be displayed to inform emergency situation Ex: Hospitals.
3. Lightning arrestor shall be installed at the concrete batching plant, asphalt plant & at height ground.
4. Emergency evacuation path shall be sign posted.
5. Ignitable materials and steel shall be stored separately.
6. Lightning prevent guidance shall be prepared and displayed for all employees and visitors.
7. Welding done workshop and yard shall be stopped during lightning.
8. All lightning prevention equipment shall be checked and tested regularly and failure shall be corrected by
qualified person.
4.13.7 Plan Major Accident (Vehicle and Machinery) Emergency Preparedness and Response plan
1. Instruction to all staff and guest shall be provided on.
a. Protect major accident of vehicle and machinery.
2. Vehicle internal speed control level shall be provided and displayed.
3. Machinery operating manuals and safety manuals shall be provided to the machine operators.
4. Heavy vehicle running and operating areas shall be displayed and prohibited unauthorized entrance
5. All vehicle and machinery shall be maintained and services on time for their safety operation.
6. At the major accident situation first aid and immediately admitted to the hospital.
4.13.8 Fuel/ Oil split Occurrence Emergency Preparedness and Response plan
1. Assign a site emergency response team members and aware & training.
2. Adequate communication facilities shall be established and emergency contact numbers shall be given to the
work force. (Details of contact persons and agencies to inform the emergency situation)
3. Providing oil distribution controlling and collecting facility and equipment needed (PPEs, Oil absorb pads and
alloy wool, Water barriers, compressors and bowsers)
4. Urgent action shall be taken to not blend oil with natural water paths
5. There should be monitoring plan to ensure proper function of all arrangement and equipment shall be checked
and tested periodically
6. Effective of the planned system shall be tested by rehearsal
District General Hospital, Mannar
023-2222261
023-2222349
Divisional Hospital, Pesalai
Page No: Page 42 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
023-3232679
Page No: Page 43 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Value Estimation
1 Injuries or illnesses requiring no treatment or first-aid only
2 Injuries or illnesses requiring medical treatment beyond first-aid
Severity
3 Temporary impairment, causing lost-time or job restriction
4 Permanent/prolonged impairment
5 Fatality
Value Estimation
1 Foreseeable, very low probability , might be seen once during working life
2 May have occurred in past, expects to see several incidents during working life
Probability
3 Occurred in past, expected one per year, would not be surprised by incident
3. Site cleaning and Snakes around the Fatality 5 5 25 Using emergency vehicle to send the victim to hospital 5 2 10
grabbing environment / Snake biting Keep anti- venom stock at site
4. Mobilizing Hit by moving object Crushing injuries 4 5 20 Use speed limits at site area 2 3 6
machinery Un-controlled speed Fatal
Tripping hazard
High volume of vehicle
movement
Un even and muddy ground
condition
10. Removing & Defective and unsafe BG machine or 5 4 20 Take all necessary safety precautions to avoid personal 3 3 9
replace tools of BG equipment inexperience ground instability injury or damage to equipment
Machine operators of mechanical Workers will be made aware of the dangerous working
failures around necessary equipment
Page No: Page 46 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
12. insertion of the toppling injuries 3 4 12 safety precautions to avoid personal injury or damage to 2 2 4
temporary casing damage to the machines and fatality equipment
surround objects Use experienced signalmen
Miscommunication
13. Removal Of Soil Dust emission Injuries to eyes 4 3 12 Use safety glasses and eye protector 2 2 4
14. removal and Soilcontamination Ingestion and 3 3 9 Always educate workers to wear adequate PPEs 2 2 4
transferring of Direct contact with inhalation
soil potentiallycontaminated ofsoils, dusts
soils and vapors
Heavy vehicle movement
15. mixing bentonite Direct contact of site Injuries to eyes 4 3 12 Use safety glasses and eye protector 2 2 4
workers and others Use dust mask when mixing the bentonite
with contaminated
soil
16. Excavations Deep holes at the site Injuries 4 5 20 Hard barricading the deep holes / excavated locations 2 2 4
locations fatal
19. Concrete pouring Falling from height Major injury 3 4 12 Warn safety harness if work at more than 2m height 2 1 2
Protruding reinforcement Hospitalization Make proper access and egress
Foot damage
22. washing the pit Environment hazards Environment 4 4 16 Stop splitting bentonite to the environment 2 2 4
contaminate with bentonite pollutions
26. Pile rectification Hit by machinery falling from Major injury 3 4 12 Use PPE 2 1 2
height falling into pit Fatal Display sign board
Chemical usage Hospitalization Conduct awareness program
Spillages Tool box talk
Keep MSDS on site
27. Bar bending Bar bending and bar cutting Major fracture 3 2 6 Use competent person to operate the machine 2 1 2
machineries Multiple crushing Proper insulation for electrical code
Contract with live wire Cutting injuries Providing inspection for machines
Current due to faulty Foot damage
equipment
Electrocution
28. Welding of Spark & toxic gas from Hospitalization 3 3 9 Wear eye protection. 2 2 4
extension piles. welding works Wear gas mask.
Page No: Page 49 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
30. Power generation Ground contamination with Damage to the 3 3 9 Regular maintenance of machinery & gen set. 1 2 2
oil. environment . Provide drip tray.
Piling machine / generator
set leaks oil onto ground
31. Hand tools Split of wooden handles Impact with body 4 4 16 Renew wooden handles 2 1 2
Sharp edges Cut wound Hammer head tightly wedged on their head keep tools on
Scrap tools Minor injury boxes or racks when not in use
Always use right tool for the job
32. Use of power tools Short circuit Electrical shock 4 3 12 Check foe defective cables, plugs and sockets 2 2 4
Damage sockets Fire Use corned fuse plug, cables
Damage wire codes Burn Switch off before making any adjustment
Personal Injury Ensure that all electrical equipment are periodically
checked and tested
Make sure that the power cable is long enough reach
your working place without straining it
Power tools should be regularly inspected and maintain
by competent person.
33. Sign Board Fixing Cutting injury hit by moving Tetanus crushing 4 3 12 Providing PPE 2 1 2
object manual handing Cutting injury Good supervision
awkward posture.
Law back pain Employ skilled persons
Cut/bruises
Page No: Page 50 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
35. Machinery Contact with lubricant Moderate eye 3 2 6 Use proper PPE 2 1 2
breakdown and Contact with sharp edge irritant Competent Mechanic
repair edges Skin irritant Demarcate working area
Static Postures Deep cut wood Conduct tool box talk
Impact with moving parts Temporary Taking frequently brakes
discomfort on
Good supervision
pain
Major Injury
Minor bruise
36. Manual Handing Lifting unbalanced Major Injury 3 4 12 Frequently change the postures 2 2 4
Risk of back strain from Educate by training
lifting awkward heavy weight
37. During adverse Occupant will be face to Major Injury 4 5 20 Immediately evacuate workers from site as soon as 3 1 3
weather condition thunder- bolt and get Fatal. possible
like Lightning, clammy. Reschedule activity carry out according to weather
thunder showering, Working on rainy conditions condition.
Heavy rain fall and expose to lightning
conditions
38. night work Poor visibility Major Injury 3 5 15 Flash lights and adequate lighting system install to visible 2 1 2
Impact with tools Property Damage working area and traveling route.
Page No: Page 51 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
40. Welding/ gas Fire risk, Electric shock, Major Injury 3 5 15 Use full face welding shield, welding gloves, apron, fire 2 3 6
cutting works Explosion, Welding fumes, Burn extinguishers and fire blankets.
expose to high intensity light,
Eye injury Using flash back arrestors
Create welding sparks, Arc
Fatal
rays, Acetylene leakage
41. Steel element Impact with steel element, Physical injury 3 5 15 Use special PPE relevant to the welding and drilling work 2 5 10
welding, drilling and fire, with burned skin other than the common safety items, especially eye
the other associate eye contact with welding abrasion protection glasses should be warn, sufficient number of
activities. helping person shall be allocated to assist skill workers.
flame directly, Major injury
Entire work will be executed with proper planning.
burning of skin,
electrical shock
Page No: Page 52 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
1. Introduction
This QA/QC plan consists of the criteria of determining the quality standards and methodologies of verifications
of each quality parameter in different stages of project development. The system of routine technical activities, to
assess and maintain the quality of the piling works is documented in the QA/QC plan.
3. Material Testing
3.1. Bentonite Testing
As per the Project Specification, Bentonite slurry should have following properties.
Table 6: Bentonite Slurry Properties – QA/QC Plan
Testing Procedure: -
a. Slump cone
b. Tamping procedure
c. Removing cone
Page No: Page 75 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
d. Height measurement
Testing Procedure:-
A. Testing Equipment
Following equipment will be used from the sample preparation to carry out the compressive test at the site.
Testing machine
150×150 mm cubes
Steel Tamper
Scoop
Auxiliary platens
B. Testing Procedure
Samples are taken from the concrete as it is cast into the pile bore, cured under the standard conditions
which are mentioned in BS 1881-116 and SLS 1144 part II clause 11, crushed to determine the maximum
compressive strength. The first step, sample preparation from the fresh concrete as follows.
Place the mould on a rigid horizontal surface and fill with concrete in such a way as to remove as much
entrapped air as possible (without significantly reducing the amount of entrained air, if present) and to
produce full compaction of the concrete with neither excessive segregation nor laitance. For this purpose,
by means of the scoop, place the concrete in the mould in layers approximately 50 mm deep and compact
each layer by using tamper (compacting bar).
When the compacting each layer with the compacting bar, distribute the strokes of the compacting bar in
a uniform manner over the cross-section of the mould, and ensure that the compacting bar does not
penetrate significantly any previous layer nor forcibly strike the bottom of the mould when compacting the
first layer. The number of strokes per layer required to produce full compaction will depend upon the
workability of the concrete but in no case shall the concrete be subjected to less than 35 strokes per layer
Page No: Page 76 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
for 150 mm cubes. Record the number of strokes. After the top layer has been compacted, smooth it level
with the top of the mould, using the plasterer’s float, and wipe clean the outside of the mould.
Immediately after making specimens store them in a place free from vibration and in conditions which will
prevent loss of moisture. Specimen stored in water shall be tested immediately on removal from the water
and while they are still in the wet condition. Surface water and grit shall be wiped off the specimens and
any projecting find removed specimens when received dry shall be kept in water for sufficient time before
they are taken for the testing.
Demould specimens to be tested at greater ages within the period 16 h to 28 h, just before testing. If the
concrete has not achieved sufficient strength to enable specimens to be demoulded during this period,
demoulding should be delayed for a further 24 h. The dimensions of the specimens to the nearest 0.2mm
and their weight shall be noted before testing. Do not test cubes which have been made in badly
assembled moulds or which are clearly misshapen.
Placing the specimen in the testing machine, the bearing surface of the testing machine shall be wiped
clean and any loose sand or other material removed from the surface of the specimen, which are to be in
contact with the compression platens. Carefully center the cube on the lower platen and ensure that the
load will be applied to two opposite cast faces of the cube. If auxiliary platens are being used, align the
top auxiliary platen with the cube.
Without shock, apply and increase the load continuously at a nominal rate within the range 0.2 N/ (mm2·s)
to 0.4 N/ (mm2·s) until no greater load can be sustained. On manually controlled machines as failure is
approached the loading rate will decrease: at this stage operate the controls to maintain as far as possible
the specified loading rate. Record the maximum load applied to the cube.
Descriptive methodologies of the each test are mentioned in Method Statements which will be submitted
separately for each test if applicable.5% of total amount of pile.
Note: If pile length more than 20m (from cut off level) sonic logging test shall be carried out instead of low strain
Integrity test (PIT), the Contractor shall appropriately install pipes when constructing the piles. Please incorporate
this requirement with testing section.
Page No: Page 77 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Foreword
Safety, occupational health, and environmental protection will not be sacrificed for production at any instant. These
elements are integrated into quality control, cost reduction, and job performance, and are crucial to our success.
The purpose of this safety information is to inform of responsibilities, operating practices and work habits which
will aid in providing safe working conditions.
Page No: Page 97 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
1.2.2 Erection
Before raising leaders, a Technical Officer and operator should ensure that:
TBT has done and persons who engaged in operations ,fully understand the procedures
Carnes have all the documents (third-party certification, valid licenses to the operators)
Steam, jet, and hydraulic hoses have been inspected; if connected to the boom tip, these hoses must
have safety chains secured to the boom
Page No: Page 98 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Lower hose ends and boom safety cables are wired to the boom
Availability of the appropriate check lists.
If operation is doing at night time , should ensure the adequate lighting is available
When erecting, do not attempt to add additional counterweight or tie down the back of the crane. Doing so can
cause gantry and topping lift failure.
After raising the leaders, attach the sliding frame to the spotter and connect the boom safety cables. Once the
hammer is lifted, lower its extensions and cable them off. As hoses are attached, ensure safety chains are
secured.
Lift piles with proper slings or other equipment, with workers properly trained in their use
Clean augers of clods of earth and rocks as they are hoisted out of the ground
Holes made in advance should then be covered or barricaded to prevent a possible fall
Release the core sling on both sides when changing cap blocks or a hammer cushion
Keep workers away from leads when cap blocks or a hammer cushion is being changed
Keep the hammer under control during driving, via slight pressure on the hammer drum brake
Shut off the hammer immediately if the pile should break or start running into the ground
Watch the hammer hose closely when lifting the hammer at the end of driving, ensuring it does not catch
Hold any hose loop below the leaders away from them until the hose is clear
Page No: Page 99 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
If workers are engaging any work near to the borehole unprotected, he should wear a full body harness
which is attached to safe and strong enough anchor point. and also if any worker engaging any height at
work related to pile driving machine , he should have fall protection system
1.2.5 Concreting
Pile driving and concrete operations should be coordinated so that piles are not dragged and the rig is not swung
over an area of concreting in progress.
The principal cause of concreting accidents is associated with the use of narrow or unstable runways. When
runways are more than three feet above ground, duckboards should be used. Because cement can be irritating
to the skin, workers should be fitted with rubber-coated gloves.
Vehicle management plan (Ex: truck mixtures) system should be maintained and vehicle washing inside the site
area is completely prohibited and designated place should be maintain adequate safety precautions should be
applied to prevent environmental hazards and pollution.
Avoid welding in confined spaces without adequate ventilation (if it is a confine space confine space
permit should be maintained.)
Hot objects should not be picked up
Don’t leave the hose unattended, as it could turn into a tripping hazard
Protect the hose from sparks, hot slag, hot objects, and open flames
Ensure that connections between the regulators, adaptors, and cylinder valves are tight
Determine if acetylene is escaping by smelling for odor. Additionally, test with soapy water, but never with
an open flame
Don’t hang a torch with its hose on regulators or cylinder valves
Don’t cut material that would permit sparks, hot metal, or severed sections
Page No: Page 100 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
1.3. Machine
Operator's cab and machine inside must be kept clean and tidy and be free of objects which do not belong
there. Operator's personal belongings shall be stored in such a manner that they do not interfere with
access or operation. Tools, oil cans and other necessary articles shall be stored in the tool box or storage
area of the machine and not lie about in the cab.
All caution and danger signs on the machine must be observed.
All caution and danger signs, decals and nameplates must be maintained legible and installed. If a sign
is defaced or removed, it must be replaced immediately.
Should there be any doubt as to safety of the machine, the work equipment or the operating practice, the
machine shall be shut off immediately and the case be reported to the appropriate authority or appointed
person.
Modifications or additions which could affect the capacity or safe operation of the machine or work
equipment shall not be made without the manufacturer's written approval. The same applies to installation
or readjustment of safety devices or pressure relief valves and welding on load-bearing members.
New parts must conform to the specifications made by the equipment manufacturer; with genuine spare
parts there will be the guarantee that they conform.
No changes may be performed on the programs (software) of programmable control systems in the
machine.
Hydraulic hose assemblies must be replaced in the stated or properly safe intervals and this also when
there is no evidence of a safety impairing defect.
The inspection and maintenance intervals prescribed in the manual must be followed.
To perform maintenance and repair, the appropriate tools and appliances required for the action must be
at hand and be in good working order.
Machine condition should be monitored by marking checklist and it should be practice every shift start.
After any repair or any modification the machine which is under third party inspection process, such
inspection must be done before starting work
Machine repairing should be done at designated place and should use LOTO systems for repairing
1.4. Fire
Personnel shall be informed of the placement of fire extinguishers and be familiar with their use.
Personnel shall be familiar with the fire preventing and suppressing possibilities on the jobsite and also
with the alarming and alerting measures to take in case of fire.
Availability of EPRP and should display emergency contact numbers at site locations
1.5. Electrical
Like other equipment, electrical tools should be inspected regularly for defective or frayed cables. Points
where cables enter tool housings and switch boxes should particularly be checked and repaired
immediately. Under no circumstances should a defective device be utilized by substituting a larger fuse
or bypassing the overcurrent device.
Power tool should be undergone to the monthly color cording system. All power tools should be double
insulated and powered trough GFCI units. Proper and adequate current should be supplied through
industrially accepted cables and sockets.
Page No: Page 101 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
If adjustments or repairs are necessary, the equipment must be shut down and the faults corrected without
delay.
Smoking, sparks and open flame are forbidden during machine refueling and in the proximity of batteries.
The engine must be off during refueling.
Work tools and equipment parts which have been put down on the ground must be safely secured against
movement, to prevent personal accident.
5. Personnel Handling
The operator may pick up passengers with the machine only on seats built-in by the manufacturer.
Equipped seatbelts or slings must be worn.
Passengers may mount the machine only with the operator's permission.
Mounting or dismounting the machine may take place only when the engine is off and the machine is out
of motion.
Persons must never ride on the machine or be transported on the work equipment.
Hoisting equipment must not be used as a personnel lift.
Page No: Page 103 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
o Care must be taken on earth ramps so that the machine remains on the compacted travel path.
Failure to observe the above could result in a crawler sinking, and/or the machine tipping over.
When working in the vicinity of an edge of a slope, bank, pit, etc., the machine must be secured against
shifting, sliding or rolling down.
The contractor or the persons responsible for the job, such as supervisors or foremen, should get
information from any possible owners or users about the existence of lines on the site. Owners or users
would be e. g. states, cities, districts, communities, utility companies, industrial plants, transport
companies.
In case there are underground lines, necessary arrangements must be made with the owner or operator
of the lines to determine the location and courses thereof, to decide upon the safety measures to be taken
and to provide the proper protection of the lines and the employees.
Detailed plans on the location and courses of the lines must be provided by the contractor or his
representatives. The plans must be kept at the construction site and be readily accessible to the
employees.
Supervisors, machine operators and attendants are to be reviewed on the location of the lines and the
required safety measures. Such reviews should be given by authorized representatives of the owner or
operator of the lines as required.
The courses of the lines in the work area are to be clearly identified, under supervision, before the start
of earth-moving operations.
If the courses of the lines are not clear, they have to be traced by means of careful ditching.
Excavation with a machine must not be permitted closer than 50 cm to an underground line!
If other companies are at work simultaneously near the lines, the respective contractors or their
representatives must agree in advance on the coordination of work procedures and safety measures to
be taken. It may be useful to have such agreements put down in writing and kept available at the
construction site.
If a line, or a protection thereof, is encountered unexpectedly, or damaged by accident, the operator must
promptly stop operating and inform his supervisor.
The owner or operator of the line must be notified. It may be required that excavation work be stopped
until a representative of the owner or operator of the line arrives.
Exposed lines are to be fastened, supported or restrained in such a manner that they may not sway, slide
or shift.
To prevent equipment encroaching the above minimum distances, the operator must also take the
following factors into consideration:
Machine conditions such as the position of the boom, rope sway caused by the machine in motion,
dimensions of suspended load or tool, etc.
Page No: Page 108 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Ground conditions; uneven ground can cause the machine to tilt so that the distance to the line will be
reduced.
Wind conditions; wind gusts can cause both the line and the suspended load or tool to sway so that the
distance will be reduced.
In case the above clearances cannot be maintained, the contractor must take other measures, in
agreement with the owner or operator of the line, to protect the equipment and persons from electrical
current.
The adequate measures can be, for example:
o To de-energies the line.
o To string the particular sections of the line safely out of way.
o To place stop-logs or barriers limiting the equipment operating range.
If an electrical charge is induced in the equipment, the operator must raise, lower or swing the respective
part of the equipment out of the energized area, or travel out of the area. If that is not possible, he must
keep the following rules:
o Not leave his position in the cab.
o Warn people around not to touch the equipment.
o Give orders to shut off the power.
Personnel must comply with the safety regulations set forth for the type of job in question. It is the
responsibility of the contractor using the equipment to inform personnel accordingly of accident prevention
and environment protection and to see to that the applicable national safety codes are followed.
Personnel must wear the appropriate personal protection required for the job, such as protective clothing,
safety glasses, gloves, protective shoes etc. Hard hat (protective helmet) is a must with any kind of
assembly, maintenance, inspection and repair! Clothing must fit tightly enough not to catch on protruding
or rotating parts. Long hair must not be worn loose, and rings, bracelets and necklaces must be removed.
The persons carrying out the job must be qualified, familiar with the equipment and have been assigned
by the contractor.
The assigned persons must be briefed on the job and their tasks before they begin, and one person shall
be designated to supervise the job
Equipment control:
The equipment must be shut down while repairs or adjustments are being made unless operation of the equipment
is required in making the repairs or adjustments.
The prescribed maintenance jobs must not be carried out on equipment in operation or machine in travel
unless the manual gives other instructions.
The equipment controls must be applied, set to On, Off or Neutral in compliance with the instructions
given in the manual for the job in question.
Once the equipment has been shut down for maintenance or repair, accidental restarting must be
prevented by
o locking all main controls, such as the engine ignition, and removing the keys
o And/or placing warning tags on main switches.
If operation of the equipment is required in making repairs or adjustments, the following rules must be
adhered to:
o The servicing person shall not be allowed to perform on his own: he must be assisted by the
equipment operator at all times during the job!
o Both the servicing person and the operator must be fully aware of all the hazards involved and
take the proper safety precautions.
o A reliable system of communication between the servicing person and the operator must have
been established before the job is begun.
o The work area must be sufficiently illuminated.
o The operator must keep his position at the equipment controls, watch over the servicing person
and have direct access to the emergency stop button at all times.
Only when the equipment is completely shut down and safely secured against accidental restarting and
movement may a servicing person work on the equipment without the assistance of an operator
positioned at the equipment controls.
Page No: Page 111 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Lifting
If parts or assemblies are to be lifted, the hoisting equipment used must fit the action, have sufficient
capacity and be in safe working order.
Heavy parts or assemblies to be mounted or removed must be safely restrained by hoisting equipment.
Only skilled persons may engage load to hoisting equipment and give hand signals or audible assistance
to control load-handling operations; the assisting person(s) must stay within the operator's sight or
hearing.
Load must be safely secured and shall not be moved over persons; persons must keep out of the load-
handling area. No personnel shall be allowed to work under a suspended load.
Access ways
Where permanent stairways, steps and work platforms are provided on the equipment they must be used;
climbing or standing on equipment parts is forbidden. Where permanent access ways are not provided,
adequate ladders, ramps or platforms meeting the safety requirements must be used to provide safe
access to the elevation required.
Personnel working on an unprotected and high elevation must wear a body belt attached to a lifeline.
Stairways, treads, handrails, ladders, platforms etc. must be maintained free of mud, grease, snow and
ice to permit personnel safe access.
If a hammer or a wire brush is used to chip or scratch office or mud, the person carrying out the job should
wear safety glasses to protect his eyes.
Reinstalling
If screwed connections are loosened or opened up during assembly, maintenance or repair, they must
be properly reconnected and retightened after completion of the job.
If guards or safety devices are removed during assembly, maintenance or repair, they must be promptly
reinstalled and rendered in proper working order as soon as the job is completed.
Page No: Page 112 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Waste materials
It must be ensured that all discarded parts and waste material are properly disposed of, in an environment
protecting way.
waste material must be segregated and need to hand over to authorized person or institute in the area
13.2. Supervision
Assembly, modification or disassembly on this type of equipment may be carried out only under direct supervision
by a person who has been designated by the contractor.
13.3. Stability
Stability of the equipment must be guaranteed at all times of an assembly, maintenance or repair job.
To mount or remove components which could cause changes in the weight distribution on the equipment,
additional adequate support of the equipment must be provided.
Counterweights may be lifted only at the places prescribed by the counterweight manufacturer.
To jack up the equipment, the jacks used must be placed in such a manner that they cannot slide away.
Jacks must stand upright and be applied square to the body of the equipment.
Jacked-up equipment must be underpinned with square timbers laid crosswise, or with steel trestles.
It is prohibited to work underneath hydraulic equipment which is supported by its hydraulics only. After
having lifted such equipment, it must be safely underpinned before assembly, maintenance or repair is
begun; otherwise, the equipment can fall violently in case a lever is touched by accident or if a hydraulic
hose or line disengages.
13.9. Electrics
Only genuine fuses of the prescribed amperage should be used. If there is a fault in the electric power
supply, the machine must be shut down immediately.
Electrical equipment and wiring must be protected against moisture. Cables must be protected against
mechanical damage (vehicular traffic e. g.).
Work on electrical equipment may be carried out by experienced electricians only, or under direct
supervision by an experienced electrician, and in compliance with electrical safety rules.
Machines and equipment to be inspected, maintained or repaired must be switched off where prescribed.
The suspect part must be tested so that it is free of electrical charge and the remaining circuit be bonded
to a "short" and be grounded. Surrounding components for which the power cannot be switched off must
be isolated.
When a cable is unplugged, dust cap must be placed on both the plug and the socket.
All electrical apparatus on the equipment must be regularly inspected/tested. Any defects found such as
loose connections or scorched cables must be corrected without delay.
If it is required to make a repair, adjustment etc. on a component with the power switched on, the servicing
person must be assisted by a second person who may cut off the power at once in case of an emergency.
The work area must be closed off with white and red barrier chain and a warning sign. Tools used must
be insulated.
If it is required to carry out a job on a high-voltage assembly, the power supplying cable must be removed
from the power source and be grounded with a rod. The assembly components (such as capacitates)
must also grounded.
13.10. Noise
All equipped sound insulating covers must remain on the equipment while it is in operation.
Personnel must wear the prescribed hearing protection.
Before changing to an oil or grease of another brand, the compatibility of the two products must be
assured.
14. Travelling
14.1. Towing
The machine must NEVER be towed.
14.2. Transporting
The vehicle (low loader or other suitable vehicle) used to transport the machine and accessories shall not
be loaded beyond rated capacity.
Hoisting equipment used for loading/unloading must have sufficient capacity.
Lifting slings used must be in good order and may be attached only by skilled persons and only to the
lifting-eyes provided for this purpose (see the manual).
Surfaces on which a load will be placed must be free of mud, grease, snow and ice and support the load
safely.
Warning signs must be posted where required.
The operator must be assisted by a skilled signalman who helps control the operations.
Any auxiliary devices used (like ramps, planks, blockings) must be secured against movement.
Equipped (metal) ramp on low loader must be covered with wooden planking before the machine may
travel up or down it.
Machine crawler tracks must be cleaned free of mud, snow and ice to prevent them skidding.
All recommended/supplied devices for securing the machine and work equipment against unintended
movement must be applied during loading/unloading and transportation respectively, so that
o The upper carriage may not rotate
Page No: Page 116 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Reflective Jackets
18.2. Transporting
Prior to transporting power packs, thoroughly close hydraulic couplings and hose ends.
Oil collecting receptacles on power packs must be emptied before transporting.
Lubricated stored material should be protected from rain, as oil can be mixed in to the environment with
the rain water.
Never dispose waste oil into the environment (ground, water, and sewer) and never mix it with other
wastes or have it incinerated in a plant that is not authorized.
Leave coolant antifreeze, brake fluids, oil filters and hydraulic hoses to the appropriate agencies for
recycling or disposal.
Refueling
Refueling from a mobile station or from a tank truck is permissible only when the fuel is dispensed through an
automatic self-closing valve.
Prior to refueling, check how much fuel the tank can accept.
Do not fill up to more than 95 %, to prevent fuel flowing over when there is a temperature rise or when
the equipment is sloping.
The engine and any auxiliary heater fitted to the equipment must be shut down during the refueling.
Have absorbent materials ready!
Keep the refueling procedure under consistent observation.
Recover liquid spills with absorbents.
In water protection areas the regulations may be stricter.
Danger Zone
Persons must keep out of the danger zone of the rig.
o Rig danger zone during drilling
Page No: Page 121 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
At all times, make absolutely sure that the above danger zone (travel path, swing area) is free of persons
before moving the rig.
Only when the rig has been brought to a stop on the site of operations, has been aligned and is stationary (i. e.
when no more travel or swing motions will be carried out), may personnel enter the work area.
Operation:
Adequate outdoor lighting must be provided at all times in all areas where the rig is used.
o Minimum illumination intensities for construction operations can be found in the national or
international safety standards, under "work area lighting intensities" or similar wording. In
addition, consideration must be given to type and proper placement of the lights so that glare,
dark shadows etc. are eliminated and safe operation is provided.
The operator is the only person authorized to stay at the rig while it is in operation.
The mast of the rig must be set to the required angle of inclination before drilling is begun. Once drilling
is in progress, the mast must not be repositioned unless it has been displaced by hard rock, boulders etc.
With a drill string bored into the ground, or with a casing oscillator in operation, the carrier machine must
be kept absolutely stationary (i. e. no travel, no swing).
Page No: Page 122 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
Any hoses (mud and hydraulic) and cables must be safely out of way before travel is started; they must
not be driven over.
Completed, open boreholes which are not under direct and consistent supervision must be protected by
a cover of sufficient bearing capacity.
o To be safe for personnel to tread on, the cover should have at least 100 kp/sq.m bearing capacity
and be secured against movement. Its surface must be slip free and stumble free to permit
personnel safe passage.
o No vehicular traffic whatsoever shall be permitted on a borehole cover.
Wherever a safely supporting cover is not practicable, barricades must be erected around the borehole,
at a safe clearance distance there from.
Heavy material must not be stored or taken into the vicinity of a borehole, to prevent the ground and the
bore hole collapsing.
At all times, make absolutely sure that the above danger zone (travel path, swing area) is free of persons
before making a move with the rig
Only when the rig has been brought to a stop on the site of the operations, has been aligned and is
stationary (i. e. when no more travel or swing motions will be carried out), may personnel enter the work
area.
Operation:
Adequate outdoor lighting must be provided at all times in all areas where the rig is used.
Minimum illumination intensities for construction operations can be found in the national or international
safety standards, under "work area lighting intensities" or similar wording. In addition, consideration must
Page No: Page 124 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
be given to type and proper placement of the lights so that glare, dark shadows etc. are eliminated and
safe operation is provided.
Pile driver and vibrator operations require that the work area be illuminated with at least 100 Lux.
Personnel must wear the appropriate protective equipment. Adequate hearing protection is of great
importance during work with a pile driver or vibrator.
The operator is the only person authorized to stay at the rig while it is in operation.
The mast of the rig must be set to the required angle of inclination before operation is begun. Once
operation is in progress, the mast must not be repositioned unless it has been displaced by hard rock,
boulders etc.
With a pile element suspended to the pile driver/vibrator and driven into the ground, the carrier machine
must be kept absolutely stationary (i. e. no travel, no swing).
A vibrator and its clamps must never be used for load handling.
The rated maximum permissible line pull must never be exceeded; see the specifications given in the
manual.
With dynamic pulling equipment which operates with hydraulic or mechanical-driven holding clamp(s), the
suspended pile element (unless it is cast in situ) must be engaged to the pulling equipment with an
additional tagline, sling or similar device of the same capacity as the clamp(s) holding the load.
Any hoses (mud and hydraulic ones) and cables must be safely out of way before travel is started; they
must not be driven over.
Operation:
Adequate outdoor lighting must be provided in all areas where the equipment is used, at all times:
o Minimum illumination intensities for construction operations can be found in the national or
international safety standards, under "work area lighting intensities" or similar wording. In
addition, consideration must be given to type and proper placement of the lights so that glare,
dark shadows etc. are eliminated and safe operation is provided.
The operator is the only person authorized to stay at the machine while it is in operation.
Wheel chocks must be placed under machine crawlers where the ground is sloping, to prevent motion, in
addition to the hydraulic parking brakes being applied.
20. References
Safety Information Bauer Doc No SIC0030E
Health and Safety control Plan, Access Engineering PLC, January 2008.
Safety, Health and welfare on Construction sites, International labor office, Geneva.
Construction Safety and Environmental management Program by The office of Health and Safety by
Brown University.
Construction Safety Manual by Metropolitan Washington Airports Authority.
Page No: Page 129 of 235
Method Statement for Construction MWPP-ACCSS-CIV-
Date &Revision: 01 August 2019, Rev. G
of Bored Cast In Situ Piles PRD-0004
Prepared By: Access Engineering PLC
After cleaning the pile base, rebar cage for the design
depth is lowered in to the bored hole.