Pile Cap
Pile Cap
Pile Cap
Material constant
tan q = 0.67
sin f = 0.71
cos f = 0.71
Tensile Force in Longitudinal Direction = 524.52 t
Tensile Force in Transverse Direction = 524.52 t
Reinforcement required (Longitudinal Direction) = 11821.4 mm2
Reinforcement required (Transverse Direction) = 11821.4 mm2
Material constant
tan q = 0.67
sin f = 0.71
cos f = 0.71
Tensile Force in Longitudinal Direction = 741.49 t
Tensile Force in Transverse Direction = 741.49 t
Reinforcement required (Longitudinal Direction) = 16711.4 mm2
Reinforcement required (Transverse Direction) = 16711.4 mm2
Provision of Reinforcement:
Nos Dia Nos Dia Area (mm2)
Bottom Steel: Band (a1 & a3) 11 32 + 10 25 13755.5 OK
Bottom Steel: Remaining(a2 & a4) 22 20 + 0 0 6911.5 OK
Top Steel (a5 & a6) 28 16 5629.7 OK
Spacing 177
Transverse Direction Reinf. In band width = 13369.15 mm 2
Provision of Reinforcement:
Nos Dia Nos Dia Area (mm2)
Bottom Steel: Band (b1 & b1a) 11 32 + 10 25 13755.5 OK
Bottom Steel: Remaining (b2 & b2a) 22 20 + 0 0 6911.5 OK
Top Steel (b3) 28 16 5629.7 OK
Spacing 177
Side Reinforcement
= 250 mm2 / m length ( As per clause 707.2.8 IRC:78:2010)
= 1275 mm2 ( Each face )
Provide Dia No Ast Spacing(mm)
12 12 1357.16802635 > 1275 412
Anchorage = 35 d
= 1,128 mm < 1760 mm OK
After allowing cover of 75mm , distance available is 600mm, so the bar will be need to
turn up, Thus the length of bar from centre line of the pile and turning up to distance 1000mm