Qty take off (Footing )

Sl Total
Description Nos Dia Spacing L L D Nos Unit Wt Total wt
No Length

2 Raft
10 x 10 x 400
Longer Span Bottom 1 16 150 10.00 10.00 68 10.64 1.58 1,143.34
Shorter Span Bottom 1 16 150 10.00 10.00 68 10.64 1.58 1,143.34

Longer Span Top 1 16 150 10.00 10.00 68 10.64 1.58 1,143.34


Shorter Span Top 1 16 150 10.00 10.00 68 10.64 1.58 1,143.34
Extra Bar @ Top & Bottom Support - - -

Top 1 16 150 10.00 5.00 68 5.00 1.58 537.28


Bottom 1 16 150 10.00 5.00 68 5.00 1.58 537.28
all Round L 1 16 150 40.00 0.80 268 0.80 1.58 338.80

5,986.73

2 250mm tk Slab
5.00 x 5.00
Longer Span Bottom 1 12 150 5.00 5.00 34 5.00 0.89 151.11
Shorter Span Bottom 1 12 150 5.00 5.00 34 5.00 0.89 151.11

Longer Span Top 1 12 150 5.00 5.00 34 5.00 0.89 151.11


Shorter Span Top 1 12 150 5.00 55.00 34 5.00 0.89 151.11
604.44

2 200mm tk Slab
5.00 x 5.00

Longer Span Bottom 1 12 150 5.00 5.00 34 5.00 0.89 151.11


Shorter Span Bottom 1 12 150 5.00 5.00 34 5.00 0.89 151.11
Longer Span Top 1 12 150 5.00 5.00 34 5.00 0.89 151.11

Shorter Span Top 1 12 150 5.00 55.00 34 5.00 0.89 151.11


604.44
2 150mm tk Slab
5.00 x 5.00

Longer Span Bottom 1 12 150 5.00 5.00 34 5.00 0.89 151.11


Shorter Span Bottom 1 12 150 5.00 5.00 34 5.00 0.89 151.11
Longer Span Top 1 12 150 5.00 5.00 34 5.00 0.89 151.11

Shorter Span Top 1 12 150 5.00 55.00 34 5.00 0.89 151.11


604.44

1 Footing
F1 4 12 150 1.50 1.50 0.40 11 2.10 0.89 82.13
4 12 150 1.50 1.50 0.40 11 2.10 0.89 82.13

4 12 150 1.50 1.50 0.40 11 2.10 0.89 82.13


4 12 150 1.50 1.50 0.40 11 2.10 0.89 82.13
328.53

Earth work excavation (actual) m3 ###

F1 1 2.30 1.20 2.10 5.80

Excavation (Working Space) m3 ###

No A1 A2 V WS
F1 1 7.26 11.60 19.63 13.83
Remarks

40.00 149.67 Kg/m3 say 150 /m3

6.25 96.71 say 105 /m3

5.00 120.89 say 121 /m3

3.75 161.19 say 160 /m3

3.60
3.60 91.26 say 40 95 /m3