Professional Documents
Culture Documents
Prefabrication Structural Procedure
Prefabrication Structural Procedure
WSM-PSP-02
PREFABRICATION STRUCTURAL Rev. 0 11/03/19
PROCEDURE Page 1 of 10
PREFABRICATION STRUCTURAL
PROCEDURE
WSM-PSP-02
Revision Summary
INDEX
2 REFERENCE DOCUMENTS
WSM Internal Procedure and Documents
4 RESPONSIBILITIES
4.1 Engineering
Engineering is responsible to verify the completeness and correctness of the shop drawings
which should be used as a reference for the fabrication activity. Engineering also responsible to
issue material take off for material preparation purpose.
4.2 Planner
Planner is responsible for keeping every production process can be run according to the
plan that has been made based on schedule so the production activity can be run on time.
Planner should be able to provide availability of data that support activity like a data of material
that are dimension, material type, material grade, material thickness in order to guarantee the
traceability for each project based on shop drawing.
Doc. No. WSM-PSP-02
PREFABRICATION STRUCTURAL Rev. 0 11/03/19
PROCEDURE Page 5 of 10
4.3 Supervisor
Supervisor should be responsible to execute every fabrication activity based shop drawing
also conducted as per approved procedure, achieve desired quality as per required by
spec/client expectation. Supervisor should give feedback to Engineering and planner if they are
encounter problems during the fabrication process.
5 PREFABRICATION PROCEDURE
5.1 General
The shop drawings (Mark drawing, Welding map, Sub-assembly drawing) should be used
to record all QA/QC requirements (e.g. Material traceability, Mark and Position number) and
accompany the material along the entire fabrication process.
Method for workshop progress tracking and material traceability other than above can be
used, such as using a Work Progress Sheet which shall be in daily bases.
5.6 Welding
Welding process in prefabrication area divided into several sections according to each
requirement. Welding shall be perform manually, welder will be using type of welding SMAW
(Shielded Metal Arc Welding), FCAW (Flux Cored Arc Welding) and GTAW (Gas Tungsten Arc
Gas). The welding work shall be carried out as per approved WPS. Welder has to be certified
Doc. No. WSM-PSP-02
PREFABRICATION STRUCTURAL Rev. 0 11/03/19
PROCEDURE Page 7 of 10
welder in accordance with the tertiary needs. During the welding process, foreman of welder
should constantly monitor the welding process to ensure application of WPS on the welding
process.
Work flow for welding:
1. Welding work should be done in the same preassembly work took place.
2. Welders need to ensure that weld preparation joint are clean and free of all extraneous
matter such as grease, dirt, scale, rust, water etc, that may affect the weld quality.
3. Conducts preheat and interpass temperature as per WPS.
4. Conduct welding work as per WPS.
5. Fill workshop progress sheet.
6. Fill welding follow up sheet.
8. After successful inspection, identify the visual inspection acceptance with marking.
Supervisor should fill workshop progress sheet and welding follow up sheet.
9. QC department record the final obtained result and issued to the supervisor if required.
6 ATTACHMENT
6.1 Flowchart of Fabrication Process
Doc. No. WSM-PSP-02
PREFABRICATION STRUCTURAL Rev. 0 11/03/19
PROCEDURE Page 10 of 10