Overview of Admin Bathroom Partitions Cistern Roof Framing

Cloud Framing in VC East View of Visitors Center Granite Stone on 1st Floor.

• Site work grading, concrete and seat wall are ongoing.


• Masonry is 100% complete at the buck hoist area.
• Ceiling grid installation began on the 5th floor with ceiling tile being laid on the 1st floor.
• Glass is being installed in the transoms.
• Bathroom partitions are installed on all 1st and 2nd floor bathrooms..
• Granite stone flooring is 50% laid on the 1st floor of the HQ.
• Metal panel installation of the VC fascia/soffit is 75% complete.
• Framing for the clouds in the VC exhibit area is ongoing.
• Admin Building crawl space walls are being poured.
• Mow strip around VC has been poured along with the sidewalk on the
northwest side of the HQ.
• Pile caps are being poured, column cages are being set, and grade beams
are being excavated for the Admin.