Professional Documents
Culture Documents
Productivity Improvement of Rubber Roller Mixing Process Using Cause and Effect Analysis: A Case Study
Productivity Improvement of Rubber Roller Mixing Process Using Cause and Effect Analysis: A Case Study
Productivity Improvement of Rubber Roller Mixing Process Using Cause and Effect Analysis: A Case Study
2, JUL-DEC 2016 24
I. INTRODUCTION
used in paper mill, textile, plastic, rayon and chemical Kneader machine: It is basically a closed chamber
industry. In rubber roll industry for making a rubber roll or mixing machine as shown in Fig. 2. It has two rotor which
rubber lining, formation of rubber compound is an operates at a slight differential speed. Mixing of rubber and
important task. These rubber products are made by mixing ingredients occurs between the rotor and sides of chamber.
of different ingredients which provides specific properties The ingredients are loaded from top opening of chamber.
to the final product. Depending upon the end use of rolls Pressure is applied by the ram which closes the opening
and temperature conditions, the rubber has to be gate of the chamber. Shearing action of ingredient and
compounded with different ingredients. Rubber rubber is done by two rotors and side walls of the chamber.
compounding is carried out to provide desired physical
properties, like hardness, resilience, elasticity and tensile
strength to the final prepared compound.
process is shown in Fig. 3. standard time of the process was established after analyzing
the obtained data and by eliminating unwanted activities.
After successfully implementation of the recommendations
they achieved an overall improvement of 53%.
A. Mariajayaprakash and T. Senthilvelan [5] have
applied principle of cause and effect diagram, Taguchi
method and Failure Mode and Effect Analysis (FMEA) for
identifying the causes and its effects of failure occurring in
a sugar mill industry. They have used the concept of
Ishikawa diagram for listing the reasons of failures such as
human, mechanical, electrical and temperature sensor
failure. They used Failure mode and effect analysis
technique for analyzing the failure occurred in cogeneration
process in sugar mill and found the main parameter which
affects the process. Concept of Taguchi method was used
for reducing the failure in fuel feeding system of
Fig. 3. Process flow chart of rubber roll cogeneration process and for optimizing the process
parameter.
In this paper, mixing process of rubber compounding is A. Gunasekaran and P. Cecille [6] showed how the
studied for making a rubber compound on open mixing mill productivity of a small and medium scale industry can be
and kneader machine. Research paper includes the basic improved. They took three aspects for improving the
process of preparing rubber compound, Cause and effect productivity, first aspect was improvement of tools used in
analysis of mixing process on open mixing mill and the workstation, second aspect was implementation of
kneader machine and remedies to increase the productivity kanban system between hose assembly and hose cutting
of mixing process. [1] Productivity is the ratio of output workstation and last aspect was development of
and input. Higher productivity provides higher standard of autonomous cell. They have also discussed about 5S and
living including larger supplies of consumer goods and control of inventory level in order to have low capital
capital goods at lower cost, higher real earnings, carrying cost and proposed to have a customer oriented
improvement in working and living conditions and assembly line.
strengthening of economic foundation of human well- A. P. Puvanasvaran et al. [7] highlighted the method to
being. improve overall equipment efficiency (OEE) of an
autoclave operating process by using technique of time
II. LITERATURE REVIEW study. They performed two time study techniques, first by
M. Tapiwa1 et.al. [2] used work study technique to using stop watch to validate OEE standards and second
optimize the manufacturing plant maintenance process for a technique was Maynard’s Operating Sequencing Technique
fertilizer manufacturing plant. They have shown the (MOST) which is then revealed in terms of Value added
relationship between the plant maintenance management and Non-Value added activities. They analyzed the data
principle and the ergonomics which imparts better obtained and by eliminating unwanted activity contributed
maintenance workspace for the worker. They have also to reduce in cycle time of process. After evaluating the
developed charts for workforce versus productivity of plant process, standard process sequence was driven and about
and recommended the future scope and possible changes 4.64% increment in efficiency was found without
for engineering, production and the support sections. compromising the quality of product.
Authors have highlighted the main areas of improvement in D. Boothby et al. [8] discussed about the increasing of
fertilizer manufacturing plant maintenance system by companies’ productivity by providing exposure of new
updating the work space for maintenance, improved technology in the field of manufacturing and by providing
efficiency, and product quality and reduced downtime. training to operator to adopt new technique, which will help
I. Bhiradi et al. [3] used work study technique to improve the firms to achieve better productivity and economic
productivity of a heavy machine shop. They studied rear performance. Authors have created awareness about
covering housing line, differential housing line and gear training programs which helps to enhance skill of a person
box housing line of a tractor. They calculated the cycle working on machine and ultimately leads to better
times of each machine in different assembly and performance of a company.
manufacturing lines. They used method study for preparing A. R. Sharma [9] described about the compounding
time study sheet. After critical examination and the techniques used for making a rubber compound, which is
further processed to form a rubber tire. He identified
analyzing the data of time study of exiting method, they
various controllable factors like batch size, rotor speed,
proposed a new method after eliminated all the non-value
sequence of addition, mixing time, ram cylinder pressure,
added activities and improved the productivity by 35% of
temperature of the mixer, finished mix and discharge speed
the system. and subsequently he performed the experiment and found
C. Duran et al. [4] used the technique of time and motion its effect on production. He also discussed about further
study for calculating process time of a tea glass processing of rubber compound to final product tire.
manufacturing process. In this work, micro element study
of tea glass process was carried out and subsequently the
NIRMA UNIVERISTY JOURNAL OF ENGINEERING AND TECHNOLOGY VOL. 5, N0. 2, JUL-DEC 2016 26
D. P. Mishra et al. [10] show how productivity of a coal A. Process description of mixing process on mixing mill
mine industry can be improved. Authors have applied Time
and motion study technique for data collection of mining 1) Set nip roll opening to 2 mm (thinning) and maintain
process. They have identified the factors affecting the cycle roll temperature up to 40-45°C.
time and productivity of coal mine such as cycle time of 2) Add rubber to mill nip and allow it to band as a
operation, manpower allotment and machine efficiency. continuous sheet on front roll.
They analyzed the collected data and then unwanted 3) Make ¾ cut from both side of roll with hand knife and
processes were eliminated for reducing the overall allow rubber to pass through nip till smooth rolling
operation time. They have also highlighted the measures bank is formed on nip.
for reducing breakdown of machine. 4) Set the nip opening to 3 mm (thickening) and add
N. U. I. Hossain et.al. [11] have applied principles of sulphur to masticated rubber then allow it to roll till it
fishbone diagram, total quality management and control get properly mixed with rubber.
charts to improve quality in a pharmaceutical company. 5) Add antioxidant to rolling bank and make cut from
They developed fishbone diagram for weight variation and both side of roll for proper mixing of ingredients.
thickness variation of tablet and analyzed the data of 6) Make cut from one side to other side, remove it and
Cefotil 500 tablet for weight variation and thickness then place the bank in nip at other end of roll for
variation and plotted control charts showing upper control homogenous mixing.
limit and lower control limit and calculated variance of 7) Add filler to rubber bank sequentially in three to four
defects arising in tablet. They discussed about possible times in equal quantity.
changes required in order to lower the waste due to 8) Add processing additives like wax, polymer, blowing
defective tablets. agent and tackifying agent.
M. Hekmatpanah [12] described how the potential causes 9) Make a small cut from both side of the rubber
in an oil company can lead to major problem and how the compound after mixing of all ingredients.
waste in the company can be reduced using technique of 10) Add lubricants like mineral oil, resin blends, fatty acid
fishbone diagram and six sigma. He used fishbone diagram etc. Add reinforcing filler to the compound.
to represent the cause and effect of production line of 11) Add activators like zinc oxide, stearic acid
canning and filling process. He also conducted FMEA of according to the recipe of the compound and then
plate cutting section and developed fishbone diagram and allow the compound to mix properly.
analyzed data of plate cutting process and prepared Pareto 12) Make a small cut from both side of rolling bank
chart. After evaluating the process and eliminating the after adding heat resistive agent to the rubber bank,
causes of potential defect, the generation scrap is reduced remove it and then feed to other side.
from 50000 ppm to 5000 ppm. 13) Allow the compound to mix properly till it get
uniformity.
N. Patel [13] utilized time study technique to monitor the
14) Add accelerator to rubber bank and make a small cut
production in a bearing manufacturing company. He
from both side of rolling bank.
determined the standard time for each process involved in a
15) Cut the compound, reduce the gauge between rolls
bearing manufacturing industry and applied concept of and then cut the sheets from this gauge setting.
OEE tool for each process to measure performance of 16) Cut the sheet from roll, remove it and feed it to roll
equipment per shift. He analyzed and evaluated the nip. Repeat this step for 3 times.
collected data and then by eliminating non value added 17) Cut rubber through one side and remove it from roll,
activity, finishing time and spark out time of the process make nip setting thick. Feed rubber bank to nip and
were reduced. He proposed the use of auto cone checker to make small cuts and mix it properly.
detect the missing roller instead of manual cone check to 18) Cut sheet of required length using knife and place
reduce inspection time per bearing assembly for improving sheet on the table one by one.
the overall productivity. 19) Cut two samples from sheet taken out of mixing mill
and then write the details on sample like date,
III. METHODOLOGY compound number, and batch number on sample.
A Pilot study was carried out to observe and understand Send that sample for Rheometer test.
20) Send Second sample to autoclave for vulcanization
the whole mixing process of rubber compounding. Work
process of 6-7 hrs. Grind the sample on grinding
study of rubber compounding on kneader machine and
wheel for smooth surface finish and check the
open mixing mill was carried out. After work study of
hardness by using Durometer shore A and shore D
mixing process, all the observations regarding mixing for soft rubber compound and hard rubber
process was analyzed in terms of value added, non-value compound, respectively.
added and idle time of man, machine and material. Based
on the work study, a detailed cause and effect diagram was B. Process description of mixing process on kneader
developed. Factors affecting the causes of low production machine
and inconsistent quality were identified and corrective
actions were taken to ensure good quality product and then 1) Raise the ram and insert the elastomer into the
accordingly mixing process on kneader machine and open mixing chamber.
mixing mill was revised. 2) Close the chamber with ram and cover and then
allow the elastomer to disperse up to 1 minute.
NIRMA UNIVERISTY JOURNAL OF ENGINEERING AND TECHNOLOGY VOL. 5, N0. 2, JUL-DEC 2016 27
3) Stop the machine and then raise the ram and Observations identified during the method and time
subsequently tilt the chamber and add filler to the study and corrective actions taken for mixing process on
kneaded rubber. open mixing mill are shown in TABLE I.
4) Tilt the mixing chamber to its original position. Close
the chamber with ram and cover and then start the TABLE I
machine. OBSERVATION AND CORRECTIVE ACTION TAKEN FOR MIXING MILL
5) Lower the ram into mixing chamber by its half stroke Sr. Observation Remark Action Taken
No.
and allow compound to mix for 3 minutes.
6) Lower the ram till its full stroke and allow the 1 Breakdown of Limit switch Limit switch
stock blender plunger jammed changed
ingredients to mix properly. due to impact of
7) Stop the machine and lift the cover and ram. Add oil rubber
to the compound and close the chamber with ram and 2 Temperature of Circulation of Thermocouple
cover. Start the machine. roll increases cooling water fixed at inlet and
blocked outlet unit of
8) Lower the ram up to its half stroke and mix for some water
time. 3 Raw rubber not Cycle time Temporary stock
9) Lower the ram till its full stroke and allow the available at increases as of rubber for two
ingredients to mix properly. workstation waiting time of mixture kept at
rubber is added workstation
10) Stop the machine and lift the ram up to its half stroke, to it
lift the cover and feed the powder spread on top of 4 Variation in Quality gets Sequence
ram to mixing chamber. sequence of affected variation is
11) Lift the ram to its full stroke and feed powder by procedure rectified
5 Variation in use of Cycle time varies Stock blender
cleaning on side of ram face to chamber. stock blender used in each
12) Lower the ram and cover to its full stroke and start the compounding
machine and then wait for 2 minutes. 6 Jamming of Pipe jammed due Filter changed at
13) Place the tray near the discharge door. Lift the cover cooling pipe to rubber particle foot valve of
water pump
and piston to its full stroke. 7 Mixing time is Roll nip kept less Nip setting
14) Tilt the mixing chamber and discharge the compound more while mixing change
in tray. 8 Mixing time is Fatigue of Nip setting
15) Tilt the mixing chamber to its initial position and stop more operator motorized
the machine. 9 Heat built up in Insufficient 5 way valve
bushing of rolls lubrication changed,
16) Wait for the mixing chamber to cool down for next greasing hose
batch. changed
17) Take the compound from tray and take out sheets by 10 Undispersed Improper mixing Proper mixing
adding accelerator in compound and mix it on open chemical cycle
mixing mill.
18) Cut two sample from sheet taken out of mixing mill. Observations identified during the time study and
Write date, compound number, and batch number on corrective actions taken for mixing process on kneader
sample. Send the sample to check quality in machine are shown in TABLE II.
Rheometer.
TABLE II
19) Send the second sample in autoclave for 6-7 hours. OBSERVATION AND CORRECTIVE ACTION TAKEN FOR KNEADER MACHINE
After removing from autoclave the rubber gets hard. Sr.No Observation Remark Action Taken
IV. CAUSE AND EFFECT DIAGRAM 1 Cooling time of Waiting time for Descaling and
machine is more next batch cleaning of
The cause and effect diagram is a tool to display increases mixing chamber
graphically the causes of any problem. It is also called as 2 Mixing chamber Pneumatic 3 way valve
Fishbone diagram or Ishikawa diagram. On the basis of the cover lifting is pressure is not changed at FRL
detailed observation made while carrying out method and slow uniform unit
time study on mixing mill and kneader machine, a detailed 3 Temperature drop Non – uniform Strainer changed
cause and effect diagram is developed. of mixing chamber cooling in cooling tower
is slow
The cause and effect diagram shows all the possible
4 Variation in Quality gets Sequence
modes of causes for the defect and the factors which affects sequence of affected variation is
the quality of the rubber compound. With the help of cause procedure rectified
and effect diagram, problems related with the inferior
quality of the rubber compound can be easily traced and After implementing the suggestions provided for kneader
solved. machine and mixing mill, the results obtained are discussed
As explained in methodology, work study of mixing in the subsequent section ‘result and discussion’.
process on kneader machine and open mixing mill was
carried out for AA75, AH39 compound and same V. RESULT AND DISCUSSION
procedure was followed for different compounds. A The observations of analysis of mixing process and the
detailed cause and effect diagram was developed as shown improvement achieved on kneader machine are as follows:
in Fig. 4 and Fig. 5.
NIRMA UNIVERISTY JOURNAL OF ENGINEERING AND TECHNOLOGY VOL. 5, N0. 2, JUL-DEC 2016 28
Fig. 4. Generic cause and effect (fishbone) diagram for mixing process
Fig. 5. Generic cause and effect (fishbone) diagram for mixing process on kneader machine
29
NIRMA UNIVERISTY JOURNAL OF ENGINEERING AND TECHNOLOGY VOL. 5, N0. 2, JUL-DEC 2016
a) As shown in Fig. 6, average idle time of man is d) Average machine idle time reduced from 188 to 10
reduced from 738 to 345 seconds. seconds as shown in Fig. 9.
1000 200
Time (sec)
800 150
600 100
400 50
200 0
0 1 2 3 Avg.
1 2 3 Avg.
Time (old) 212 117 235 188
Time (old) 809 696 710 738
Time (new) 8 11 12 10
Time (new) 304 328 402 345
b) Average value added time of man reduced from 635 to e) Average machine non - value added time reduced
470 seconds as shown in Fig. 7. from 425 to 314 seconds as shown in Fig. 10.
800
Time (sec)
600 500
400 400
200 300
0 200
1 2 3 Avg. 100
0
Time (old) 475 712 719 635 1 2 3 Avg.
Time (new) 384 483 542 470 Time (old) 346 464 464 425
Time (new) 286 306 349 314
Number of Readings
Number of Readings
Time (old) Time (new)
Time (old) Time (new)
Fig. 7. Comparison of Value added time of man
Fig. 10. Comparison of Value added time of man
c) Average non-value added time of man reduced from
595 to 332 seconds as shown in Fig. 8. Takt Time Calculation (For Kneader Machine)
800
600 rubber compound on kneader machine:
400
200 1. Total available time = 2 shifts per day * 25 working
0 days in a month.
1 2 3 Avg.
2. Demand per day = 36 Mixtures.
Time (old) 602 539 643 595
3. Available working time per shift = 450 minutes
Time (new) 296 339 361 332 (Excluding lunch and tea break) = 27000 seconds
4. Available time per day = 27,000 * 2
Number of Readings = 54,000 seconds
Time (old) Time (new) 5. Takt time = Total available time per demand
=54,000 / 36
Fig. 8. Comparison of Non - value added time of man =1500 seconds (25 minutes) (Can be
achieved)
30
NIRMA UNIVERISTY JOURNAL OF ENGINEERING AND TECHNOLOGY VOL. 5, N0. 2, JUL-DEC 2016
From the past records of June - Nov 2015, the kneader machine from 12 mixtures per shift to 15 mixtures
production of kneader machine was 12 mixtures per shift. per shift and by providing proper training to the operator it
After analyzing the cause and effect diagram of kneader can be increased up to 18 mixtures per shift.
machine, probable solutions were identified and Another study was also carried out on different mixing
implemented which are discussed in TABLE II. After mill and after time study; the problems related with the
implementation of the suggestions, the utilization of breakdown of machine and human error were rectified. A
machine was increased as evident from the production data proposal for attachment for nip setting on mixing mill was
of Dec 2015 – March 2016 as shown in Fig. 11 and it is 15 made, which will reduce the fatigue in operator.
mixtures per shift without compromising the quality in
comparison to the earlier production of 12 mixtures per VI. CONCLUSION
shift. The Takt time calculation shown above shows that In this case study, time study was performed for kneader
the cycle time per mixture which can be achieved without machine and mixing mill. The time study data were
affecting the quality of product and therefore 18 mixtures analyzed in terms of man, machine and material chart and
per shift can be made. non-productive and redundant activities were eliminated.
From the time study of kneader machine it was found that
the machine takes more time between productions of two
Production per month (2015-16) batches due to slower cooling of mixing chamber.
Therefore, a detailed cause and effect diagram for the
Production of rubber
468 445
500 429 422 439 mixing process was prepared and problems related with
379
331 358 equipment and human error were rectified. Mixing process
compound
400
300 on kneader machine and mixing mill was revised.
A proposal for attachment for nip setting on mixing mill
200
was made, which will reduce the fatigue in operator. After
100 implementing necessary changes in machine, production of
0 kneader machine increased from 12 to 15 mixtures per
AUG SEP OCT NOV DEC JAN FEB MAR shift which can be further increased up to 18 mixtures by
Month providing the proper training to the operator. A proposal of
producing one particular compound on one machine per
shift was made which helps in better utilization of the
Fig.11. Production detail of rubber compound on kneader machine (2015- machine with increase in production with less number of
16) days.
[7] A. P. Puvanasvaran, C.Z. Mei and V.A. Alagendran, (2013). G. Patel was a post graduate student
Overall Equipment Efficiency Improvement Using Time Study in an
in the Department of Mechanical
Aerospace Industry. Procedia Engineering, 68(1), pp. 271-277.
Available: Engineering, Institute of
http://www.sciencedirect.com/science/article/pii/S18777058130203 Technology, Nirma University,
3X Ahmedabad. He has obtained M.
[8] D. Boothby, A. Dufour and J. Tang, (2010). Technology adoption,
Tech. Degree in CAD/CAM in
training and productivity performance. Research Policy, [Online].
39(5), pp. 650-661. Available: 2016. His area of interests is
http://www.sciencedirect.com/science/ article/pii/S00487333100005 Industrial Engineering, Design and
[9] A. R. Sharma, (2014). A Review on Rubber Compound Mixing In development, Machine Design and
Banbury Mixer at Tire Industries, International. Journal of
Manufacturing Engineering. He has published 01 research
Engineering Research and Reviews. 2(4), pp. 106-109.
[10] D. P. Mishra, M. Sugla and P. Singha, (2013). Productivity articles in National journals.
Improvement in underground coal mines – A CASE STUDY.
Journal of Sustainable Mining, [Online]. 12 (3), pp. 48–53. Dr. B. K. Mawandiya is presently
Available:http://www.sciencedirect.com/science/article/pii/S23
working as Associate Professor
0039601530014
[11] N. U. I. Hossain, F. Nur and A. Habib, (2013) Achieving with Mechanical Engineering
competitive advantage through practicing TQM tools in Department, Institute of
Pharmaceuticals Company. Journal of Mechanical Engineering, Technology, Nirma University,
[Online]. 43 (2), pp. 103-109. Available:
Ahmedabad, Gujarat, India. He
http://www.banglajol.info/index.php/JME/article/view/
17834/12498 received his B.E. degree in
[12] M. Hekmatpanah, (2011). The application of cause and effect Production Engineering and
diagram in the oil industry in Iran: The case of four liter oil canning Management from National Institute of Technology,
process of Sepahan Oil Company. African Journal of Business Jamshedpur in 1992 and obtained M.Tech. degree in
Management, [Online]. 5 (26), pp. 10900-10907. Available:
http://www. academic journals.org/journal/AJBM/article-full-text-
Industrial Engineering and Management from Indian
pdf/AA1143816550 Institute of Technology Kharagpur, Kharagpur in 1996.
[13] N. Patel, (2015). Reduction in product cycle time in bearing Subsequently, he obtained Ph.D. degree from Indian
manufacturing company. International Journal of Engineering Institute of Technology Kharagpur, Kharagpur in 2016. He
Research and General Science [Online]. 3 (3), pp. 466-471.
Available: http://pnrsolution.org/Datacenter/Vol3/Issue3/62.pdf.
has published 12 research articles in International/National
journals and conferences.