Proposed Program of Work

No. Activity Names Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 7 Month 8 Month 9 Month10

1 Design and Drawings

1.1 Design/ drawings

1.2 Design finalization

2 Manufacturing

2.1 Material procurement

2.2 Manufacturing for turbo-generator units

2.3 Manufacturing for other equipments

2.4 Assembling, testing, inspection, dis-assembling &


packing
3 Transportation

3.1 Shipment from manufacturer's works in China to


Pakistan(Sust Dry Port)
3.2 Transportation from Sust to site

4 E&M Installation

4.1 Installation for turbo-generator unit

4.2 Installation for other equipments

5 Test Running, training and Handing Over

5.1 Test Running and Commissioning

5.2 Training of Staff & handing over


Month 11 Month 12