Professional Documents
Culture Documents
Surface Water Drainage Design Considerations and Practices PDF
Surface Water Drainage Design Considerations and Practices PDF
Dieter H. Lindner
To cite this article: Dieter H. Lindner (1987) Surface Water Drainage Design Considerations and
Practices , Canadian Water Resources Journal, 12:3, 67-78, DOI: 10.4296/cwrj1203067
Abstract:
Technical considerations and related issues affecting surface water drainage in rural
Alberta are outlined, Such items as appropriate design flow and frequency, ditch and
channel parameters, and grade and erosion control structures are addressed.
Current design philosophy and practice of rural drainage works relative to flood con-
trol are described. This paper focuses on the need to retain technical integrity, and the
desire to achieve ease and economy of construction, in the context of physical con-
straints and the institutional setting, Emphasis is placed on the design process.
Rdsum6.
Ce texte expose les grandes lignes des consid6rations techniques et des questions
connexes en ce quiconcerne le drainage des eaux de surface dans les 169ions rurales
de I'Alberta. ll traite des 6coulements et des fr6quences th6oriques appropri6es, des
paramdtres des foss6s et des canaux, ainsi que des ouvrages de contrOle de l'in-
clinaison et de l'6rosion des terrains.
ll d6crit la philosophie actuelle de la conception et de la pratique des ouvrages de
drainage en milieu rural, en rapport avec Ie contrdle des crues. Ce texte est ax6 sur le
besoin de maintenir l'int6grit6 de la technique et sur le d6sir de r6aliser des travaux de
construction faciles et 6conomiques au niveau des contraintes physiques et du cadre
institutionnel. ll met I'accent plus particulidrement sur le processus de conception.
1 The paper was presented to the Annual Conference of the Canadian Water Resources Association,
Alberta Branch with the Soil Conservation Society of America, Alberta Chapter, Edmonton, October
23-25, 1985.
2 Head, Hydraulics Sectron, Design and Construction Division, Alberta Environment,9820 - 106
Street. Edmonton. Alberta T5K 2J6.
ensure that the basic requirements and fune- This level of investigation is largely an "office
tional objectives are met. study" drawing on readily available information
without a great deal of field work. Problems are
Design Hydrology identified and possible solutions explored,
Most drainage projects are designed to func- largely relying on experience and ludgement in
tion adequately for flows up to a certain return the analysis, The basic purpose of the "concep-
period. When flows of rarer frequency occur, the tual design" is to explore conceptual solutions,
drainage work functions less well and indeed provide order-of-magnitude estimates, and to
may fall as a whole or in part, In dra nage pro- ascertarn whether or not, and what kind of
jects, this design frequency is typically selected follow-up investigation may be indicated, The
on the basis of experience and ludgement with project area is usually visited by the design
5-year to 10-year return periods being common engineer during the course of the investigation
values used in Alberta, to develop an appreciation of the project, gain
Occasionally, a frequency as low as 2.3 familiarity and to note special or unique features.
years, presumably equal to the "dominant dis- Cost estimates target f 35 percent. Concep-
charge,'is used, This results in a very Iow level tual designs, if done at all, are more likely pre-
of develooment and limited effectiveness. The pared on complex large-scaled drainage
entire notion of "dominant discharge" does not prolects, or when quick but cursory evaluation
enjoy universal acceptance and as such its use is desired.
as a drainage criterion is dubious,
On the other hand, the 2)-year return period Feasibiilty Design (Level I)
for design of drainage works is difficult to sus- This type of study is the primary decision-
tain, With intensive development higher expen- making tool to ascertain technical feasibility
ditures usually are a barrier even if greater and associated costs. Once initiated at the local
benefits are achieved. level. appropriate field surveys are conducted
The second hydrologic input is largely gov- and drilling and laboratory testing of soils as
erned by the available data base. Typically, done, A site inspection is normally conducted
Typically the channel cross-sections are taken Design Report is the basic decision-making
every 40 m to 100 m and all structure sites are tool. This report defines the purpose, docu-
drilled and logged. Subsequently preliminary ments the data, investigates alternative solutions,
hydraulic, geotechnical and structural designs establishes and reaches certain conclusions, In
are prepared. The channel, grade control struc- other words, the technical integrity of the solu-
ture and culverts are designed. Alternative tion and cost thereof are established. Informed
solutions for the S-year and 1O-year return decision can then logrcally follow.
penod are conceived, developed, analysed The second step of design, assuming an af-
and costed with appropriate conclusions and firmative decision, is to prepare a frnal design
recommendations made. (Level ll) of the selected alternative for the proj-
Special issues such as land acquisitron, ect in question. The design approach is consis-
safety and environmental impacts are identified tent with the concept of the preliminary design
and also addressed in the Level I design report. :nrl loadq fn 2.^mnlata tan.lar aaa?eaa
Cost estimates are to + 20 percent. This techni- facilitating subsequent construction.
cal report and the merits (benefits) assigned to
the project determine whether implementation Closure
is appropriate. An affirmative decision will also Most surface water drainage prolects in rural
target the preferred alternative for frnal design, Alberta follow these two discrete steps in the
budgeting and cost-sharing. A negative deci- design process. As such it provides for local
sion often leads to a reconsideration of the oroi- input, reasonable project documentation, tech-
ect in light of findings, perhaps a change in nical analysis and feedback, to achieve func-
scope, and probably resurrection at a later tional and cost effective solutions to drainaqe
oate. prooiems.
considered essential with special attention paid of the Namepi-Kennedy Drainage Project,"
to specifrc problem areas. Follow-up inspec-
tions will be done as required to achieve Alberta Environment. l982. "Construction Report
solutions to outstanding issues, Additional sur- No, 1 Namepi-Kennedy Creek Project,1977-
veys, drilling and laboratory analysis will be 78 to 1981-82."
undertaken as required. Typically channel cross Alberta Environment. 1980. "Drainaqe Districts
sections are taken at 20 m intervals and all Act." fr S.A., Chapter D-39
structure sites, and potential material sources
are Investigated. Alberta Environment, 1980. "Water Resources
Detailed hydraulic, geotechnical and structur- Act," R.S.A., Chapter W-5.
al designs are prepared for the channel, grade American lron and Steel Institute. 1984. "Hand-
control structures, culverts and related works. book of Steel Drainage and Highway Construc-
Design drawrngs and written specifications are tion Products." Canadian Edition. W,P. Reymen
prepared and compiled as a formal tender pack- Associates, Inc.. New York.
age. A confrdential "engineers estimate' geared
to be within 1 0 percent of the low bid is prepared Environment Conservation Authority. 1976.
to facilitate evaluation of the bids rece ved, Upon "Erosion of Land in Northwestern Alberta."
implementation "as-built" drawings or "as- Report and Recommendations.
constructed" reports are prepared as illustrated Lindner, D,H. 1983, "Application and Design
by Alberta Environment (1982). Practise of Gabion Structures in Alberta." Cana-
dtan Society for Civil Engineering. Proceedings
Usual Design Approach of 6th Canadian Hydrotechnrcal Conference,
Most drainage projects are prepared by doing Vol. 1. Ottawa. p, 55.
investigations that comply with the preliminary
BALANCE : DEv€LOPMENT
TO ENVIRONMENIAL
PROTECTION
ACTIVITIES
I . MULTI - PURPOSE PROJECTS
LEGISLATION 2. LOUL INITIATIVE l3io5
cosr SHARtNG : Mirt /Yr
WAfER RESOURCES ACT 3. PROTECT PERMANENf WATER
DRAINAGE DISTRIC'S ACT 4. AVOIO INOISCAIMINATE ORAINAGE PROVINCIAL PROJECTS :
TECHNICAL ASSISTANCE
- LICENCING
- COST SHARING
'
- " PnovrNcraL PRoJECTS
- TECHNICAL ASSISTANCE
- REGULATTONS
q
LOCAL INPUT
.L CHANITTL D€SIGN
- BASIC PAPSfTETERS
- CHAi{I{EL HYDRAULICS
- TYPICAL VALIES
- OTI{ER FACTORS
- FUflCTI0{
- HYDflAI}LIC JIJTP
. TYPICAL CO*CRETE STruCTUftTS
- STEEL SIi€ETPILE Dft:OPS
- GABIffi DROPS
- PIPI DROPS
- iltN0vATltr{s
- STflUCTUflT SELECTIOII
E CULVERTS
- ATTRIBUTES
- CULVERT HYDRAULICS
- DESIGI1 AIDS
- I{ATERIALS
- GRADE COI{IROL
- SAFETY
U
OU
FU
<F
zz
HE
ZO
gU ZL
UJ
@
<9@
z
HF
za@a
FI OUOZ q
>-dr '-eO O
F
<OJ U U >- O F c
zut u > E z < U
J - < O A
-El z
=lJvz-z
'--!:ZI U O < a @ U O
J(l) @a) z E
LUHI O d J= =
E
d,u'tt o < u -J (J o a
O-LilI E F F U
Qr =<Jdc)U
z (J z
al
ta<
lttttl UUF
JdO
z MHU
o
(t EH dux
o UF zl
o QZ :i
o oH
F-
o.
c o-u 55
.9 =i q-
Fr
at
o =
U
o <=
OO =i€
ro
OZ
eu
UJ
E
f
g
lr