Professional Documents
Culture Documents
Final Report Gen-3 Stator Bar
Final Report Gen-3 Stator Bar
Final Report Gen-3 Stator Bar
Page 1 of 55
INDEX
11 Chapter-11 – Conclusion 31
Page 2 of 55
CHAPTER-1
A. Generator Transformer
a. Insulation Resistance and Polarization Index measurement
b. Tan Delta and capacitance Measurement.
c. Moisture content in insulation by Recovery Voltage
measurement analysis.
d. Short circuit Impedance.
e. Winding Resistance Measurement
f. Magnetizing current measurement
g. Sweep frequency response analysis
h. Transformer Turn Ratio
B. Generator
a. Stator
i. Insulation Resistance and Polarization Index
Measurement
ii. Tan delta and Capacitance measurement
Page 3 of 55
iii. Winding Resistance Measurement
iv. Partial Discharge Measurement
v. DC Leakage current measurement
vi. Surge Comparison Test
b. Rotor
i. Insulation Resistance and Polarization Index
Measurement
ii. Field impedance Measurement
iii. Pole Voltage Drop Measurement
iv. Recurrent Surge oscilograph (RSO)
v. Conductor Resistance Measurement.
IR AND PI VALUE
Unit-3 IR VALUE (Mega Ohm) TEMP- 38 Deg. Cel.
Configuration (Applied 15 sec. 60 sec. 600 sec. P.I. (600 SEC./60 SEC)
voltage 2500 V)
Generator Over all 10.63 11.40 11.74 1.03
(Capacitance in Circuit)
R+Y+B-E 105 272 984 3.61
R-Y+B+E 237 676 2220 3.28
Y-R+B+E 242 699 2240 3.20
B-R+Y+E 295 908 2480 2.73
R-Y (B+E) 545 1680 5350 3.18
Y-B (R+E) 451 1236 4860 3.93
B-R (Y+E) 450 1180 4710 3.99
ROTOR (250 v) 101.3 101.4
Page 4 of 55
CHAPTER-2
IR AND PI VALUE
Unit-3 IR VALUE (Mega Ohm) Testing equip.
Make Megger, Model S1 5010
Configuration (Applied 15 sec. 60 sec. 600 sec. P.I. (600 SEC./60 SEC)
voltage 500 V)
ROTOR (500 v) 224 229 241 1.06
Recurrent Surge was also measured and graph plot in oscilograph was
satisfactory.
IR AND PI VALUE
Unit-3 IR VALUE (Mega Ohm) Testing equip.
Make Megger, Model S1 5010
Configuration (Applied 15 sec. 60 sec. 600 sec. P.I. (600 SEC./60 SEC)
voltage 2500 V)
R-Y+B+E 274 745 2430 3.26
Y-R+B+E 316 935 2350 2.51
B-R+Y+E 531 1140 2500 2.20
Winding resistance of stator winding was measured and the results are
as tabled below:
Page 7 of 55
CHAPTER-3
Concoction: The OEM I.e. M/s. GE Power India Limited (GEPIL) was
recommended for localization of fault and replacement of faulty stator
bar. The preparation for the same in line with the recommendation of
OEM was started and in the first step 02 nos. Work order no.
NH/DG/E&M/WO/2019/300 and 301 dt. 15.03.2019 were issued to M/s.
Purvanchal for providing service support for replacement of faulty
stator bars and to M/s.GEPIL for deputation of Generator expert
respectively. A list of insulating items and other required tools and
tackles were provided by the OEM for replacement of stator bar.
6 FILLERS 20 NOS
10 WEDGE 20 NOS
13 FELT 20 PIECE
Page 8 of 55
15 WHITE SPRIT FOR CLEANING 5 LTS
CONSUMABLE
7 PAINT DK 222 2 KG
The Induction Brazing Machine which was required for Brazing and De-
Brazing of bar connections available with Chamera-III Power Station
was collected and transported to Dhauliganga Power Station for the
rectification work.
The service support team from M/s. Purvanchal were reached at site on
20.03.2019 to 23.03.2019. The team started the work for removal of
Rotor pole to make access to Stator slots. The rotor pole no. 9 & 10
were removed and cleaning of stator was started. After completion of
stator cleaning a visual inspection was made for any mark of damage,
which was not observed at any portion of stator.
Page 9 of 55
REMOVAL OF ROTOR POLE
Page 10 of 55
CHAPTER-4
Page 11 of 55
TOP BAR of STATOR SLOT 151
Page 12 of 55
END CAPS REMOVED
Page 13 of 55
CHAPTER-5
ABNORMAL PARAMETER
Page 14 of 55
SUSPECTED MOTHER BOARD AND ITS OCNNECTIONS
Page 15 of 55
ELECTRICAL MAINTENANCE PERSONAL CHECKING THE PARAMETERS AS PER
SUGGESTIONS OF SERVICE ENGINEER
Page 16 of 55
AFTER RECTIFICATION
NORMAL PARAMETER
The second induction brazing machine which was brought from Chamera-
III Power Station, in view of faulty of first machine, also found
faulty with the fault ‘Tr-1. Over current’ which was also rectified by
service engineer and made ready for operation.
Page 17 of 55
CHAPTER-6
R- Phase winding
Y- Phase winding
B- Phase winding
Page 18 of 55
There were 03 types of stator bars, 01 no. Bottom bar marked as R-01,
11 nos. Of Top Bar marked as R-02 and 03 nos. Of Top connection bars
marked as R-04, in total 15 nos. Of stator bar which was required to
be replace.
All above said identified bars were brought out from store. The
cleaning of new stator bar was made for further electrical testing.
There are two electrical tests, insulation resistance test at 2500 VDC
and high voltage test (Hipot test)at 40 kV DC, were performed on each
stator bars,
Page 19 of 55
STATOR BAR TESTING VALUES
HIPOT
IR MEASUREMENT (IN OHM) TEST @ 40 IR MEASUREMENT (IN OHM)
BEFORE HIPOT TEST KV DC AFTER HIPOT TEST
APPLIED VOLTGE 2500 VOLT (APPLIED APPLIED VOLTGE 2500 VOLT
FOR 1
MIN) REMARKS
DESCRIPTI MEASURM
ON ENT OF
(IDENTIFIC LEAKAGE
SL. ATION OF 600 CURRENT 15 600
NO. BAR) 15 SEC. 60 SEC SEC PI IN mA SEC. 60 SEC SEC PI
BOTTOM
1 BAR (R1- 11.94 24.00 26.70 1.11 0.080 40.10 70.80 59.80 0.84 STATOR SLOT 151
128)
TOP BAR
2 3.12 4.18 5.80 1.39 0.150 19.70 30.70 31.20 1.02 STATOR SLOT 138
(R2-22)
TOP BAR
3 22.40 46.30 50.50 1.09 0.130 15.03 27.90 29.20 1.05 STATOR SLOT 139
(R2-24)
TOP BAR
4 21.20 28.20 30.10 1.07 0.110 14.40 25.50 26.60 1.04 STATOR SLOT 146
(R2-16)
TOP BAR
5 18.80 40.60 37.40 0.92 0.130 28.20 37.40 34.80 0.93 STATOR SLOT 141
(R2-08)
TOP BAR
6 4.86 6.26 7.79 1.24 0.040 13.84 22.10 22.80 1.03 STATOR SLOT 149
(R2-01)
Page 20 of 55
TOP BAR
7 3.96 4.49 5.14 1.14 0.040 19.68 35.30 33.20 0.94 STATOR SLOT 147
(R2-07)
TOP BAR
8 1.89 2.26 2.87 1.27 0.100 35.60 41.20 35.10 0.85 STATOR SLOT 148
(R2-21)
TOP BAR
9 16.69 29.40 30.50 1.04 0.110 15.96 26.50 27.20 1.03 STATOR SLOT 142
(R2-18)
TOP BAR
10 19.47 34.30 35.30 1.03 0.120 15.90 29.30 30.90 1.05 STATOR SLOT 151
(R2-10)
TOP BAR
11 20.99 32.89 34.00 1.03 0.170 15.33 25.00 26.10 1.04 STATOR SLOT 143
(R2-13)
TOP BAR
12 14.17 23.40 24.40 1.04 0.220 12.68 21.90 17.92 0.82 HIGH LEAKAGE CURRENT
(R2-15)
TOP BAR
13 12.36 17.23 18.01 1.05 0.320 11.09 16.49 17.67 1.07 HIGH LEAKAGE CURRENT
(R2-12)
TOP BAR
14 20.00 40.00 42.30 1.06 0.100 20.60 34.70 36.80 1.06 STATOR SLOT 144
(R2-11)
Page 21 of 55
TOP
CONNECTI
15 12.85 21.20 22.10 1.04 0.160 14.00 24.20 25.00 1.03 STATOR SLOT 150
ON BAR
(R4-01)
TOP
CONNECTI
16 7.13 12.37 12.82 1.04 0.200 7.86 12.49 12.97 1.04 HIGH LEAKAGE CURRENT
ON BAR
(R4-02)
TOP
CONNECTI
17 12.17 18.95 20.10 1.06 0.600 10.87 17.75 18.76 1.06 HIGH LEAKAGE CURRENT
ON BAR
(R4-03)
TOP
CONNECTI
18 15.05 27.30 30.40 1.11 0.140 15.66 27.50 29.60 1.08 STATOR SLOT 140
ON BAR
(R4-04)
TOP
CONNECTI
19 12.35 20.50 21.60 1.05 0.180 13.31 22.60 23.07 1.02 STATOR SLOT 145
ON BAR
(R4-05)
On the basis of test results 02 nos stator top bars (R-02) and 02
stator top connection bars (R-04) which had high leakage current were
decided not to use. Other 15 nos. Stator bars were cleaned and heating
was started to avoid moisture absorption.
Page 22 of 55
CHAPTER-7
SEMICONDUCTING TAPE
Page 23 of 55
CHAPTER-8
Page 24 of 55
FLASH OVER MARK AT
TOP BAR
STATOR SPACER WITH RTD SLOT (SPARE RTD AT STATOR SLOT 151)
Page 25 of 55
Another 13 nos. Stator Bars from stator slot no. 138 to 150 were
dismantled on 05.04.2019. dismantling of these bars was carried out by
great manoeuvre. These bars damaged completely due to lot of rust &
silt, which was due to total submergence of units during flood in June
2013. Cleaning of stator slot was started.
Page 26 of 55
CHAPTER-9
Page 27 of 55
BRAZING OF STATOR BAR CONNECTION
Rotor pole no. 9 & 10 were fixed at their locations. Assembly of unit
I.e. dome cover fixing, assembly of top and bottom Air baffles,
electrical connections of rotor and stator, water pipe connections for
the coolers of Thrust and Generator guide bearings etc completed.
The machine started and voltage was buildup in manual mode and voltage
was increased upto 11 kV. The inspection was made at Transformer and
Generator barrel for any abnormal sound. After assurance for normal
behaviour of unit the synchronization process was started in auto mode
and unit synchronized on 14.04.2019 at 12:22 hrs.
Page 28 of 55
CHAPTER-10
Page 29 of 55
3. The fault in Induction Brazing Machine: The Induction brazing
machine from Chamera-III Power Station was arrived at Dhauliganga
Power Station on 27.03.2019. The water connection to chiller
plant and electrical connection to both chiller and Control Panel
was made on same day. The service Engineer from OEM I.e. M/s.
GEPIL reached on 28.03.2019 and fault was localized and stator
bottom bar at Stator slot 151 was identified. The De-Brazing of
winding connection was required but the machine failed to
maintain the required heat. The OEM of equipment I.e. M/s. EFD
induction Pvt. Ltd. Was contacted with the problem. The OEM
service engineer suggested some electrical tests on Electronic
cards. Based upon the values and test results OEM concluded for
deputation of engineer for replacement of faulty Electronic card
(VCPM card. The Power Station issued a Letter of Intent for
deputation of service engineer alongwith the faulty electronic
cards. The service Engineer reached at Power Station on
04.04.2019 and rectified the Induction Brazing Machine. The
Stator winding connection were debrazed on 04.04.2019 and again
brazed on 09.04.2019.
Page 30 of 55
CHAPTER-11
Page 31 of 55
CHAPTER-12
TEST RESULTS
Page 32 of 55
Page 33 of 55
Page 34 of 55
Page 35 of 55
Page 36 of 55
Page 37 of 55
Page 38 of 55
Page 39 of 55
Page 40 of 55
Page 41 of 55
Page 42 of 55
Page 43 of 55
Page 44 of 55
Page 45 of 55
Page 46 of 55
Page 47 of 55
Page 48 of 55
Page 49 of 55
CHAPTER-13
Page 50 of 55
Page 51 of 55
MINUTES OF MEETINGS WITH M/S. PURVANCHAL
Page 52 of 55
Page 53 of 55
MINUTES OF MEETINGS WITH M/S. EFD INDUCTION PVT LTD.
Page 54 of 55
CHAPTER-14
THE TEAM
NHPC Management:
NHPC Officers:
Electrical Maintenance:-
O&M,CO Representative:-
Page 55 of 55