Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 1 of 24

• Home
• Valve
• Piping Components
• Piping layout
◦ PDMS
• Pipe fittings
• How To
• Checklists
• Forum

Column Piping: Study Layout, Nozzle Orientation &


Platforms Requirements
1.0 Sequence of Column Piping Study
1.1 All available information / data from Equipment specification and P&ID shall be written on the elevation view of the
column as illustrated in Fig.1, 2 & 3.

1.2 The designer now starts thinking about the proper orientation of nozzles and provisions for access to the points of operation
and maintenance.

1.3 Considerations of the pipeline leaving the tower area and the adjacent piping shall be visualized.

1.4 The first step is to orient the manholes preferably all in same directions. Normally, manholes shall be oriented towards
dropout area within a 30° segment of column as this facilitates the lowering of tower internals to the main access way. The
manhole segment of platform should not be occupied by any piperack.

1.5 A break in ladder rise (normal 5m, maximum 7m) will occupy another segment of column for platform.

1.6 The levels of platforms are to be decided on the elevation view based on the manholes and access to relief valves,
instrument for viewing.

1.7 All platform levels in the proper segments of the tower with ladder location should be drawn on plan view. The manhole
shall be shown in proper segment with the angle of orientation, and the space for the swing of manhole cover taking davit hinge
as centre.

1.8 Layout should be started from the top of the column with the designer visualizing the layout as a whole. There will be no
difficulty in dropping large overhead line straight down the side of a column, and leaves the column at a high level and crosses
directly to the condenser. This clears a segment at lower elevations for piping or for a ladder from grade level to the first
platform.

1.9 Flexibility and thermal load connected with the large-dia overhead lines to the condenser at grade level or higher level shall
be considered. The relief valve protecting the tower is usually connected to the overhead line. A relief valve discharging to
atmosphere should be located on the highest tower platform.

In a closed relief-line system, the relief-valve should be located on the lowest tower platform above the relief -system header.
This will result in the shortest relief-valve discharge leads to the flare header. The entire relief-line system should be self-
draining.

1.10 From layout point of view, it is preferable to space the platform brackets on the tower equally and to align the brackets
over each other for the entire length of the tower. This will minimize interferences between piping and structural members.

1.11 Nozzles and piping must meet process requirements while platforms must satisfy maintenance and operating needs. Access
for tower piping, valves and instruments influence placement of ladders.

1.12 In routing pipelines, the problem is faced to interconnected tower nozzles with other remote points. The tentative
orientation of a given tower nozzle is on the line between tower centre and the point to which the line is supposed to run.
Segments for piping going to equipment at grade e.g. condenser and reboiler lines are available between ladders and both sides
of manhole.

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 2 of 24

See the Fig.4 / 5 for overall orientation of a distillation column.

Line approaching the yard/piperack can turn left or right depending on the overall arrangement of the plant. The respective
segments of these lines are between the ladders and 180°. The segment at 180° is convenient for lines without valves and
instruments, because this is the point farthest from manhole platforms.

The sequence of lines around the tower is influenced by conditions at grade level. Piping arrangements without lines crossing
over each other give a neat appearance and usually a more convenient installation.

1.13 The correct relationship between process nozzles and tower internals is very important. An angle is usually chosen between
the radial centreline of internals and tower-shell centrelines.

By proper choice of this angle (usually 45° or 90° to the piperack) many hours of work and future inconvenience can be saved.
Tower piping, simplicity of internal piping and manholes access into the tower are affected by this angle. After this, the
information produced by the designer results in selecting the correct orientation of tower nozzles.

1.14 A davit usually handles heavy equipment such as large-size relief valves and large-diameter blinds. If the davit is at the top
of the tower, it can also serve for lifting and lowering tower internals to grade.

Clearance for the lifting tackle to all points from which handling is required, and good access should be provided.

1.15 Very often, interpretation of process requirements inside a tower is more exact than for exterior piping design. The location
of an internal part determines, within strict physical limits, the location of tower nozzles, instruments, piping and the steelwork.
The layout designer has to concentrate on a large-scale drawing of tower-internal details and arrangement of process piping to
finalize the piping study.

1.16 Access, whether internal or external is very important. This includes accessibility of connections from ladders and
platforms and internal accessibility through shell manholes, handholes or removable sections of trays. A manhole opening must
not be obstructed by internal piping.

1.17 Reboiler-line elevations are determined by the draw off and return nozzles and their orientation is influenced by thermal
flexibility considerations. Reboiler lines and the overhead lines should be as simple and direct as possible.

1.18 Fig.6 shows the segments of tower circumference allotted to piping, nozzles, manholes, platform brackets and ladders as
normally recommended to develop a well-designed layout.

2.0 Nozzle Orientation and Level


Nozzles are located at various levels on the tower to meet the process and instrumentation requirements.

2.1 Manholes

Nozzles are to be oriented keeping provision for maintenance and operation needs.

Manholes are usually located at bottom, top and intermediate sections of tower. These access nozzles must not be located at the
downcomer sections of the tower or the seal pot sections of the tower.

Where internal piping is arranged over a tray, manhole shall be provided but it should be ensured that the internals do not block
the maintenance access through the manhole.

Possible location of manhole and handholes within the angular limits of b° are illustrated in detail-2 of Fig.4

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 3 of 24

Fig 1- Sample Piping and Instrumentation Diagram around a Column

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 4 of 24

Fig 2 -Evaluation of the Flow Diagram for a Distillation Column to Visualize an Orderly Arrangement of Piping

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 5 of 24

Fig 3- Typical Nozzle Location and Platform Elevations

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 6 of 24

Fig 4- Details of a Typical Distillation Column

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 7 of 24

Fig 5- Typical Tower Piping Arrangement

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 8 of 24

Fig 6- Typical Tower Area Division for Various Facilities

2.2 Reboiler Connections

Reboiler connections are normally located at the bottom section of the tower. Detail-1 of Fig.4 shows reboiler draw-off
connections for single-flow tray. This connection can be very important for arranging tray orientation. The simplest, most
economical location for reboiler connections with the alternative location within the angular limits of a° is shown. The angle a°
depends on the size of reboiler draw off nozzle and the width of the boot (dimension ‘b’) at the tray down flow.

The return connection from the thermosyphon reboilers is shown in detail-1 of Fig.4.

These lines should be as simple and as direct as possible, consistant with the requirements of thermal flexibility.

For horizontally mounted thermosyphon reboiler, the draw off nozzle is located just below the bottom tray and for vertically
mounted recirculating thermosyphon reboiler, the draw off nozzle is located at the bottom head. For both the systems, the return
nozzles are located just above the liquid level as shown in Fig.7.

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 9 of 24

Fig 7 – Reboiler Connection

2.3 Reflux Connections

Reflux nozzles are provided with internal pipes that discharge the liquid into the sealpot of the tray below. Detail 3 of Fig.4
shows the reflux connections. Care must be taken that the horizontal leg of the internal pipe clears the tops of bubble caps or
weirs. It must be ensured that the internal pipe can be fabricated for easy removal through a manhole or can be fabricated inside
the tower shell.

2.4 Overhead Connections

The vapour outlet nozzle is usually a vertical nozzle on the top head of tower. In addition, the vent and relief valve could be
located on the top head with a typical platform arrangement for access to vent, instrument connections and top manhole. In a
closed relief line system, relief valve should be located on the lowest tower platform above the relief system header. This will
result in the shortest relief valve discharge leads. The entire relief line system should be self draining.

2.5 Bottom Connections

The liquid outlet is located on the bottom head of the tower. If the tower is supported on skirt, the nozzle is routed outside the
skirt as shown in Fig.8. The elevation and orientation of this line is generally dictated by the pump NPSH requirement and the
pump suction line flexibility. (see Fig.9)

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 10 of 24

Fig 8- Details of Tower Skirt

Fig 9 -Net Positive Suction Head (NPSH) of Bottoms Pump

2.6 Temperature & Pressure Instrument Connections / Level Instruments

The temperature and pressure instrument connections are located throughout the tower. The temperature probe must be located
in a liquid space and the pressure connection in a vapour space as shown in Fig.10.

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 11 of 24

Fig 10- Typical Temperature and Pressure Instrument Nozzle Location

The level instruments are located in the liquid section of the tower usually at the bottom. The elevation of the nozzles is decided
by the amount of liquid being controlled or measured and by standard controller and gauge glass lengths. Level controllers must
be operable from grade or platform and level gauges / switches may be from a ladder if no platform is available.

Fig.11, 12, 10, 13 & 14 illustrates a few instrument connections on tower.

Fig 11- Typical Instrument Vessel

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 12 of 24

Fig 12- Typical Arrangement for Level Instrument

Fig 13- Typical Temperature and Pressure Instrument Arrangements

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 13 of 24

Fig 14- Typical Common Bridle-Level Instrument Arrangement

3.0 Access and Maintenance Facility


3.1 Access whether internal or external is very important. This includes accessibility of connections from ladders and platforms
and internal accessibility through shell manholes, handholes or removable sections of trays.

3.2 Tower maintenance is usually limited to removal of exterior items (e.g. relief or control valves) and interior components
(e.g. trays or packing rings) Handling of these items is achieved by fixed devices (e.g. davits or trolley beams) or by mobile
equipment (e.g. cranes). When davits or beams are used, they are located at the top of the tower, accessible from a platform and
designed to lower the heaviest removable item to a specific drop out area at grade level.

When mobile equipment is used, a clear space must be provided at the back (side opposite to

piperack) of the tower that is accessible from plant auxiliary road.

Fig. 15, 16, 17 & 18 illustrates the access and maintenance facilities to be considered in the piping arrangement around a tower.

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 14 of 24

Fig 15- Platform Width Requirements

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 15 of 24

Fig 16- Typical Arrangement of External Piping around Column

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 16 of 24

Fig 17- Typical Operator Access

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 17 of 24

Fig 18- Typical Plan and Elevation View of Tower Area

On free-standing columns, access for major maintenance to insulation or painting will usually require the erection of temporary
scaffolding. Space for scaffolding at grade level and provision of cleats on the shell to facilitate scaffold erection should be
considered.

3.3 Utility stations of two services viz. steam and air are usually provided on maintenance platforms.

Steam and air risers should be located during piping study to keep adequate cleats for support.

(see Fig.19)

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 18 of 24

Fig 19- Typical Platform Arrangement

4.0 Platforms and Ladders


4.1 Platforms on towers are required for access to valves, instruments, blinds and maintenance accesses. Platforms are normally
circular and supported by brackets attached to the side of the tower. Generally, access to platforms is by ladder. Fig.20 illustrates
the platform requirements.

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 19 of 24

Fig 20 – Tower Platform and Ladder Elevation Requirements

4.2 Platform elevations for towers are set by the items that require operation and maintenance.

The maximum ladder run should not exceed 7m.

4.3 Platform widths are dictated by operator access. The clear space on platform width shall be min.900mm.

For platforms with control stations, the width of platform shall be 900mm plus the width of control station.

The platform for manholes and maintenance access, adequate space for swing the cover flange flange must be provided.

4.4 Top-head platforms for access to vents, instruments and relief valves are supported on head by trunions.

4.5 Access between towers may be connected by common platforming.

4.6 It is preferable to space platform brackets on tower equally and to align brackets over each other over the entire length of
shell. This minimizes the structural design and interferences from piping.

4.7 On very wide platforms or those that support heavy piping loads, knee bracing is required in addition to the usual platform
steel. The potential obstruction immediately under the knee brace must be kept in mind during platform design.

4.8 Fig. 3, 15, 21, 22, 20 & 19 illustrates a few platform considerations.

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 20 of 24

Fig 21- Typical Platform Orientation

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014
Column Piping: Study Layout, Nozzle Orientation & Platforms Requirements Page 21 of 24

Fig 22- Details of Circular Platform Bracket Spacings

Related Posts:

• Tower Piping: Center for Equipment Layout Tower Piping: Center for equipment layout A tower is usually a ...
• Distillation Column Piping: Absorption Stripping,… 1.0 Introduction to Column Piping Study for the column piping
should ...
• Nozzle Orientation Drawing The objective of this post is to describe the requirements ...
• Design Guide For Heat Exchanger Piping Table of contents: 1. General 2. Types 3. Definitions a) Shell & Tube
Exchanger b) Plate ...
• Pipe Rack Piping Study Pipe rack piping study: My this post explains the steps required ...

http://www.piping-engineering.com/column-piping-study-layout-nozzle-orientation-pla... 9/22/2014

You might also like