Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

cb&i 5/5/06 20:17 Page 1

Coke drum design

Issues to consider for extending the turnaround schedule of a delayed coking


unit. Theory behind coke drum failure is discussed, with detailed solutions
centred on drum design and support structures

Coby W Stewart, Aaron M Stryk and Lee Presley


Chicago Bridge & Iron

T
he global supply of crude is 80 years and is used
getting heavier. In response, primarily as a fuel or for
refiners are making their refineries the production of anodes
flexible enough to handle the changing for the aluminum
feedstock. These crudes are cheaper than industry, electrodes for
sweet crudes due to their limited the steel industry,
processing capacity. One of the major graphite or similar carbon-
additions and targets for upgrades are based products. This
delayed coking units, which process the residue is then water
bottom-of-barrel material into valuable, quenched not only to
lighter products such as gasoline and allow for its removal once
distillates. Adding a delayed coker unit the vessel has been
to a refinery flow scheme provides a depressurised, but also to
two-fold financial incentive: cheaper cool it to the point where
feedstock and a higher volume of it will not self-ignite when
light products. exposed to air. As part of
In several parts of the world, North the delayed coking
America being more severe, refining process, coke drums
capacity is struggling to keep up with undergo severe thermal
the demand for products. Refiners are and pressure cycling, as
making strong efforts to improve the the vessel is filled with hot
reliability and availability of process product and subsequently Figure 1 Coke drum shell bulging in early 1960s
units, with the ultimate goal of water quenched after
decreasing the frequency of turnarounds coke formation. In the last decade, the demand for
and making process units safer. Due to the severe heating and delayed coking capacity has been
In an environment where it is very quenching rates of this process, the steadily increasing. Experts attribute this
profitable to keep refinery availability as useful life of coke drums is much shorter trend to refineries having to process
high as possible, efforts are directed than that of other pressure vessels more lower-quality crudes than in the
toward process units and equipment operating in non-cyclic conditions. This past, as previously discussed. Thus, few
that bear the most wear and tear. Also, it is because the severe operational refinery owners have the option of
is financially preferable to run heavier thermal cycling causes the plate and the increasing cycle time, as they must
crudes, especially when a refiner has an weld to be stressed with each cycle and, balance drum distortion with the desire
existing delayed coking unit. But due to their differential strengths, the to meet rising throughput requirements.
nothing is easy: delayed coking units drum may bulge and eventually crack in Instead, refiners must often resort to
require more maintenance than normal the vicinity of the circumferential weld shortening the coking cycle, adding
process units in a refinery, and seams. This leads to coke drums more units or doing both.
increasing the availability of this unit experiencing significant downtime
has a major impact on the long-term throughout their useful life to make Bulging and cracking
profitability of a refiner. needed repairs or partial shell replace- phenomenon
ments. It is a problem that has plagued Weil and Rapasky1 (1958) identified
Delayed coking process refineries for decades. radial bulging as a “re-occurring
Delayed coking is a process in which a Depending on the operating para- difficulty” that existed in essentially all
heavy residual feedstock is superheated meters, type of coke produced, feedstock operating coke drums of the time.
and then introduced into an insulated, and other variables, the cycle time of a Through extensive research carried out
vertically oriented cylindrical pressure given unit can be from as little as 14 on a total of 16 coke drums erected
vessel, commonly known as a coke hours to more than 24 hours. The between 1938 and 1958, they identified
drum. Vapours are then removed to be industry recognises that the shorter and a radial growth varying from almost
further refined into various petroleum more severe the cycle, the sooner and negligible to as much as 0.3in per year.
byproducts, leaving behind a high- more pronounced the bulging and The rate of bulging was found to be
density hydrocarbon residue referred to cracking will appear. To illustrate this, directly attributable to the “quenching
as petroleum coke. Petroleum coke is a Figure 1 is a photo that was taken from portion” of the operating cycle. They
solid coal-like substance that has been a coke drum shell replacement project, also recognised that the girth seams, due
commercially manufactured for nearly illustrating the severity of the distortion. to the higher yield strength of the weld

w w w. e p t q . c o m P T Q Q3 2006 00
cb&i 5/5/06 20:17 Page 2

water injection during the quench cycle


— the slower and more controlled the
quench is, the greater the UQF, which
translates into less bulging. However, as
previously mentioned, fewer owners
have the option of longer cycle times. To
the contrary, the trend is for even
shorter cycles, the result of which is a
higher UQF that will ultimately reduce
the overall lifespan of the vessel.
In recent years, there have been a
number of studies undertaken that
A B C D substantiate the conclusions of Weil and
Stage 1 Stage 2 Stage 3
Normal Onset of Girth seams Advanced Rapasky:
5
shape bulging begin to form bulged shape — Penso et al suggest that low cycle
thermal fatigue is the most common
failure mechanism of a coke drum. The
Figure 2 Coke drums displaying constrained balloon shape due to distortion authors state that thermal shock is the
main mechanism for the initiation of
these cracks. They further propose that
additional analysis of the cooling cycle
is warranted, since the cooling cycle
7/8 thk affects the severity of thermal shock
4
— Livingston and Saunders report that
15/16 thk the coke drums in their survey began to
through-wall crack at roughly 2400
1 thk cycles. The frequency of through-wall
cracking increased
11/16 thk — This evidence of initial and
subsequent cracking is further supported
11/8 thk by an independent 1996 API Survey that
confirms the first through-wall cracks on
13/8 thk
conventional drums typically occur in
the 3000–5000 cycle range
3
Figure 4 Weld profile compounds — Antalffy et al cite at least three
stiffening effect additional examples of recent papers
that reference the bulging phenomena.
2
weld seams, depending on the width of He also cites that Boswell and Ferraro
plate used for each shell course. and others concluded that the high
Figure 3 Coke drum vessel step reduction Through their studies, Weil and relative strength of the circumferential
in thickness Rapasky observed that high quenching weld metal, as compared to the lower
rates produced thermal gradients in strength of the adjacent base metal, was
metal, tended to augment the bulging, excess of 10°F per inch, while lower the cause of the bulging.
causing a “constrained balloon shape”, quenching rates produced smaller As one can see, it is common industry
as illustrated in Figure 2. gradients, thus less bulging. To measure knowledge — supported by several
As a result of the restraint caused by this effect, they developed a “unit thermal and stress analyses of various
the weld seams, the base material tends to quench factor” (UQF, Table 1), which is operating units — that the higher
become thin and ultimately fails via the ratio of water-quenching time in strength of the weld metal in the
through-wall cracking. The bulging is minutes to the coke yield per drum in circumferential seams tends to have a
most severe in the lower cylindrical tons. Utilising the resulting data, they stiffening effect, which increases stress
portion of the vessel, usually 40–50ft theorised that when the UQF is greater and leads to distortion and cracking. It
above the cone section. This section of than 0.5, the bulging is minimal, and should be noted that the longitudinal
the vessel experiences the highest quench when the UQF is greater than 0.8, the weld seams required to make the shell
rates during the quench cycle and bulging is all but non-existent. The UQF courses were reported to be unaffected
typically has four to five circumferential is directly proportional to the rate of by the thermal cycling, except where
these seams intersected the circumfer-
Comparison of quenching methods and growth on various coking ential ones. In the bulge areas near the
circumferential seams, the longitudinal
Unit no. Water quenching Coke capacity, Unit quenching Relative severity of weld seams were also affected by the
time, min tons factor, min bulging distortion thinning effect and would be prone to
9 90 380 0.24 Severe crack given enough thermal cycles.
8 100 370 0.27 Severe
7 90 310 0.29 Severe
1 140 180 0.78 Negligible
Coke drum metallurgy and
5 135 170 0.80 Negligible
shell thickness
2 150 170 0.88 Absent
To extend the useful life and reduce the
6 180 180 1.00 Absent downtime of coke drums, several
modifications have been made to
water – quenching time (minutes) standard coke drum design metallurgy.
UQF = Coke drums that were once constructed
coke capacity (tons)
from mild steel have in recent years
Table 1 been constructed from low-alloy clad

00 P T Q Q3 2006 w w w. e p t q . c o m
cb&i 5/5/06 20:17 Page 3

materials such as Carbon-1/2 Moly and thickness throughout the vessel


11/4 Chrome-1/2 Moly, as well as 21/4 — Specifying materials greater than 2in F. O. F.
Chrome-1 Moly and other higher alloys, in thickness.
typically with 410SS cladding. With the While most of these requirements
exception of 21/4 Chrome-1 Moly and have technical merit, the resulting
other higher alloyed coke drums, those improvement may only be incremental
manufactured with low-Chrome alloy and not necessarily practical. For
materials have all failed in time. example, attempting to narrow the yield
The drums manufactured from 21/4 strength mismatch between the weld
ML
Chrome-1 Moly and other higher alloy metal and base metal is difficult at best
materials have been in service for only a due to the many variables involved. The
few years and have not yet endured actual yield strength of the base metals
enough cycles to demonstrate improved when compared to commercially
reliability. The normal method of available weld metals is typically more
designing the shell courses of coke drums than 10% lower (Table 2). In addition,

1 –511/32

81/16
is to base the thickness of the material on the yield strength of base metals and
the specified design pressure. Typically, weld metals varies with temperature,
the pressure is specified as varying which may make the yield strength
linearly from a minimum value at the differential greater than 10% at elevated
top of the vessel to a maximum at the temperatures. Also, controlling weld
bottom flange. Since overall vessel cost is metal yield strengths to a specific
a function of weight and thickness, the minimum/maximum in relation to the
tendency is to design each shell course as-supplied base metal typically requires
for the design pressure specified at the the use of weld processes that are not
bottom of the course. As a result, there necessarily productive or cost-effective.
are typically step reductions in thickness Blend grinding the weld profiles,
from one shell course to the next, as which reduces the geometric stress raiser
shown in Figure 3. However, the effects near the weld joint, can extend
resulting weld profile compounds the the service life of the weld joint and can
stiffening effect already present due to be cost-effective if properly specified Figure 5 Cylindrical shell sections of up to
the higher yield strength of the weld and managed. However, eventual repairs 46ft help eliminate several circumferential
metal, as shown in Figure 4. to the weld joint are inevitable. weld seams, increasing endurance under
The use of uniform shell thickness the most severe thermal cycles.
Increasing vessel life throughout the critical area of the vessel
Further effort to improving the reliability has an added material and labour cost. alloys translates into increased costs.
and lifespan of coke drums has focused But, as previously mentioned, not Some specifications are requiring
on developing or proposing measures to keeping a uniform thickness will increase increased NDE testing to be performed
mitigate the stiffening effect of the weld the stiffening effect of the metal used for and the acceptable flaw size reduced in
seams. Most of these measures, several of welding the circumferential weld joints. an attempt to get more uniform weld
which have been incorporated into And while the specification of very thick joint properties. This increases costs
numerous procurement specifications, and uniform shells will reduce the peak without having any effect on the basic
were aimed at reducing the discontinuity stresses caused by the thermal cycles problem of the circumferential welds
effect at the circumferential weld seam. somewhat, it will not reduce the effects acting as stiffeners. There is also some
The most common of these specifica- of the circumferential seams acting as evidence that excessive repairs during
tions were as follows: stiffeners during the quench cycle. manufacturing may, in fact, reduce
— Decreasing the weld metal yield Higher alloys such as 21/4 Chrome-1 service life by causing premature failures.
strength to be within a close percentage Moly are thought to be able to resist the
of base metal yield (ie, 0%, +10%) thermal cycling better because of their Elimination of
— Blend grinding the weld profile higher yield and better creep and creep- circumferential weld seams
— Specifying higher alloy materials (ie, fatigue resistance. While these higher When CB&I first approached the girth
21/4 Chrome-1 Moly and higher) alloys may increase the useful life of the weld distortion and cracking problem,
— Requiring more non-destructive vessels and slow down bulging, most of two observations were pivotal in the
examinations (NDE) and using more the newer drums manufactured from analysis. One was the well-known fact
restrictive NDE acceptance criteria than this alloy have not yet seen enough coke that the higher strength of the weld
the construction code requires production cycles to determine if this is metal in the circumferential seams tends
— Maintaining a uniform shell a major improvement. Plus, using these to have a stiffening effect that increases

Typical plate and weld metal properties6

Base metal Type Tensile ksi Yield min. Typical weld Tensile ksi Yield min.
(typ) ksi metal selection (typ) ksi
A516-70 Carbon steel 70–90 38 (46) EM12K 70–95 58 (61 )
A204 C Carbon-1/2 Moly 75–95 43 (52) EA2 70–95 58 (61)
A387-11, CL2 11/4 Cr-1/2 Moly 75–100 45 (58) EB2 80–100 68 (75)
A387-12, CL2 1 Cr-1/2 Moly 65–85 40 (50) EB2 80–100 68 (75)
A387-22, CL2 21/4-1 Moly 75–100 45 (58) EB3 90–110 67 (80)
405 (clad) 13 Cr 60–90 25 (36) ERNiCr-3 80–95 40 (52)
410S (clad) 12 Cr 60–90 30 (36) ERNiCr-3 80–95 40 (52)

All weld metal and base metal in typical PWHT condition for material combinations. All weld metal data is from the SAW (submerged arc welding) process

Table 2

w w w. e p t q . c o m P T Q Q3 2006 00
cb&i 5/5/06 20:17 Page 4

erecting a vertical plate coke system attached to the structure. From


drum. The resulting there, the new vertical plate sections
conclusion was that such a were set in place. The project included
vessel could be economically replacing a large nozzle in the top head
produced, providing a and sections of the skirt support, along
uniform thickness through- with post-weld heat treating and
out the cylindrical portion of hydrostatic testing, all within a span of
the vessel. This method is 28 days. This vertical plate solution was
applicable to new construc- so successful that the refiner subse-
tion (shop-built or field- quently contracted to replace the shells
erected) projects, as well as on an additional four coke drums.
retrofit applications where In 2001, CB&I replaced the shell
the lower cone and top head courses on four coke drums for another
sections of the vessels are refiner that were originally fabricated
Figure 6 Plate-by-plate replacement method in progress reused. and installed by the company in
1968–69. These vessels had reached the
stresses and leads to distortion and Vertical plate coke drums end of their useful life, and the coker
cracking. The other, based on previous Since 2000, CB&I has completed four structure required major modifications
research, was that the longitudinal retrofit projects with the proprietary to meet current building codes. CB&I
welds required to make the shell courses vertical plate coke drum technology, all recommended replacing the existing
were seemingly unaffected by the of which were finished at an equal or can sections on the coke drums with
thermal cycling, except in the areas lower cost to the refiner than traditional vertical plates. Total shell replacement
where those welds intersected the repair methods, and were much less was approximately 65ft 8in in height.
circumferential ones. expensive than a full-vessel replacement. A lower shell course 46ft in height and
After extensive research and analysis, The first successful installation of two an upper shell course 18ft 8in in height
CB&I concluded that the best solution drums took place at a refinery on the US were fabricated. These courses comprised
to the problem of girth seam distortion West Coast in 2000. The refiner had eight shell plates, all of which were
and cracking was to eliminate the originally planned to replace two 20ft- formed in one of CB&I’s fabrication
circumferential weld seams in the area plus sections of distorted and cracked shops and then welded into two-plate
of concern. A method was developed for shell on two of its coke drums, which assemblies. The assemblies were then
successfully fabricating shell plates with would still have left circumferential shipped to the refinery, where the on-
the long side oriented vertically. This seams in the section of the drum where site project team would first erect the
process allows fabrication of cylindrical the bulging and cracking was most lower and upper shell courses and then
shell sections of up to 46ft without a pronounced. However, after reviewing set one on top of the other to complete
circumferential weld seam. The steel the vertical plate concept, the refiner the can section. In addition to replacing
mill manufacturing capability only decided to modify its plan and replaced the shell plates, braces were added to the
limits plate size. Currently, the largest all but the upper 9ft of shell with two stairwell and the drum was insulated.
plates available are in the range of 46ft, vertical plate courses reaching heights of Working on a plant-wide, non-critical
depending on the specified thickness 23.5ft and 40ft respectively. turnaround basis, the can sections on all
and alloy. Depending on plate size For this project, CB&I performed all of four drums were replaced in 37 days.
limitations, up to five circumferential the turnaround activities itself, including The most recent vertical plate project,
weld seams can be eliminated, resulting forming and welding the plates at one of which involved the replacement of a
in a cylindrical shell section that can its fabrication shops, mobilising the 35ft vertical section on a ten-year-old
endure the most severe thermal cycles crane and all of the on-site materials, and coke drum, was completed on a
(Figure 5). erecting the vessels. To execute the actual turnaround basis in 16 days. For this
In late 1997, CB&I launched an shell replacement, CB&I cut the old project, CB&I utilised its can section
extensive investigation into the circumferential sections and then replacement method. This particular
feasibility of designing, fabricating and removed them using a customised rail vessel had experienced excessive
bulging and cracking in 60% of its
circumferential welds. Its shell courses
A
1 –51/2 were replaced with new 35ft-long plates
(Typ) arranged vertically in four sections.
Upper skirt Braces were also added to the vessel
1 –0

10 thk 27.956° R=3 stairwell and the drum was insulated.


SA387-11 CL2
Top plate

81/16
weld slot

Tan line Plate-by-plate replacement


Do not
2 –6

1
1 –0

In many refineries, the area surrounding


Bottom of skirt base

1/2 1/2
1 –11/4
2 –0

the coking unit does not permit the use


of a large-capacity crane to lift out the
8 –0

See note #1
entire can section. To replace the shells
on the four coke drums at the West
A 1 –511/32
Coast refinery, for instance, the damaged
Hot (Typ)
can sections had to be cut into smaller
box
vertical pieces, which were then
Lower skirt 1 removed plate by plate. Likewise, the
1 thk new vertical plates had to be lifted into
SA516–70 place piece by piece, as shown in Figure
Elevation View A–A
6. While not as fast as replacing the
Stretchout of top plate
entire can section, the plate-by-plate
replacement method is still a safe, low-
Figure 7 T-Rex skirt design cost solution.

00 P T Q Q3 2006 w w w. e p t q . c o m
cb&i 5/5/06 20:17 Page 5

Innovations in skirt design elimination of the weld attachment


Another potential area of failure in coke substantially reduces large pre-stresses
drums is the skirt-to-shell weld from weld shrinkage, weld-induced
attachment. Since most coke drums have heat-affected zones and high local
a knuckle transition from their cylinder stresses in the structure, which likewise R1
top to a conical bottom, a skirt assembly improves the overall fatigue resistance Coke drum
is used to support the vessel at its lower of the structure and supporting skirt. shell
tangent line and provide uniformity of Packaging these skirt designs with the R2
support stresses in the structure. Since previously discussed vertical plate
thermal cycling is most severe near the proprietary technology provides a
bottom of the coke drum, where comprehensive vessel solution that not
temperatures can reach up to 1000°F, the only improves the lifespan of a refinery’s
skirt and other attachment welds are just delayed coking vessels, but also saves the
as prone to cracking and premature owner significant repair and replacement
Support
H1
structural failure as the vessel wall. costs. These designs can be used during Coke drum R3
Several alternative skirt designs have retrofit projects such as coke drum repair shell
been developed to counter these or replacement, as well as for
failures. One such design is the T-Rex incorporation into new unit designs. H2
skirt (Figure 7), which is a culmination
of best practices and lessons learned Economics of vertical plate
from years of fabricating and repairing coke drums
coke drums. In service since the 1970s, While the installation of vertical plate
this design has proven to be one of the technology will reduce the capital Figure 8 Wrapper design
most reliable skirts currently around. refinery owners will need for repairing
Recently, a finite element analysis and replacing their vessels, it is too early the 3000–5000 cycle range (Figure 3).
(FEA) was performed on the T-Rex to quantify the actual observed benefit, Based on these findings, no fewer than
design, the results of which were since the existing vertical plate coke 11 cracks per drum may reasonably be
compared to those for the conventional drums in service have not seen enough predicted during the 20-year period.
design configuration. This is a transient coke production cycles. However, the For simplicity, it is assumed that
thermal analysis to establish the model cost and benefits associated with the planned outages deal with 30% of the
temperature profile over the load cycle technology can be demonstrated using a cracks that will appear (three cracks), so
time history. The results of the thermal lifecycle value assessment (LCVA) the remaining eight cracks will
load tests show that the T-Rex methodology, which establishes a true significantly dictate more expensive
configuration has lower stress levels at cost of ownership. This tool, which was unplanned refinery stoppages of the
all locations for the critical charge and developed by the Pembina Institute, is a coke drums, which is where the Opex
quench thermal cycles. This appears to value assessment model that allows cost is greatest. In this example, costs are
be due to the longer hot-box length, owners to combine initial Capex and 20 determined for a planned turnaround,
which results in a more gradual thermal years’ Opex for both conventional and then a 30% uplift is applied for
gradient and also moves the gradient drums and the vertical plate coke unplanned events. It is assumed that
lower on the skirt away from the welded drums. The methodology also considers each stream-to-stream unplanned
connection. As such, the FEA evaluation the direct financial losses arising from outage will last an average of six days.
shows that the T-Rex has substantially unplanned outages of the drums, and Thus, to remedy a through-wall crack, it
reduced stresses as compared to other also applies net present value (NPV) will cost (in 2005 dollars):
skirts currently in operation. Some of principles to further assess the expected — Costs of a single crack repair (20
the features of the T-Rex design include cost savings. A rigorous NPV calculation workers * six days * two 10-hour shifts *
sloped attachment welds that help can demonstrate the excellent value of $85 per hour) + (materials, scaffolding/
reduce stress-related failures and an these innovations. However, for the equipment, insulation, repairs and so
attachment that covers the tangent weld purposes of this discussion, a simplified on) = minimum $225 000
(unless an elongated straight flange is LCVA model is utilised as follows: — Costs of crack repairs over a 20-year
utilised). The T-Rex design reduces period Three planned events * ($225 000)
initial application costs and improves Conventionally designed drums + eight unplanned events * ($225 000 *
long-term reliability over other designs Capex The initial Capex outlays for four 1.3) = $3 million in repair costs for each
that have been evaluated. vertical plate coke drums are assumed to drum, or $12.1 million for all four drums.
Another design recently developed is be $26.1 million. In this example, the Direct financial losses The greatest
the Wrapper skirt (patent pending). This drums come at an initial Capex impact occurs when one considers the
employs a fabricated wrapper-type skirt premium of $2.175 million compared to lost revenues caused by the afore-
that conforms to the geometry of the conventional drum designs. Thus, mentioned cracking events. In addition,
upper cone, knuckle transition and Capex for conventional drums is there are hazardous plant risks that can
lower cylinder to support the drum assumed to be $23.9 million. accompany the cracking. For the eight
primarily by bearing and frictional Opex At an average of 14 hours per unit unplanned refinery stoppages that will
forces rather than load bearing weld cycles, each conventional drum in occur over the 20-year period, if the
attachments (Figure 8). This detail operation will go through 313 cycles per example drum pair has a capacity of
provides a more flexible connection year, which translates into 6260 cycles 25 000bbl/day and the product is valued
between the skirt and vessel than over a 20-year period. As previously at 85% of the WTI value (an average of
traditional methods, which improves mentioned, Livingston and Saunders $50 per bbl):
the fatigue resistance of the structure. In reported that the coke drums in their — Direct financial losses over a 20-year
addition, the extended contact between survey began to through-wall crack at period Eight unplanned events/drum
the drum and skirt lessens thermally roughly 2400 cycles, while an pair * six days for each event * 25 000
induced stresses in both components independent 1996 API Survey confirmed bbl/day * (0.85 * $50) = $51 million in
by ensuring a uniform temperature that the first through-wall cracks on lost revenues for each drum pair, or
gradient between the two. Finally, the conventional drums typically occur in $102 million for all four drums.

w w w. e p t q . c o m P T Q Q3 2006 00
cb&i 5/5/06 20:17 Page 6

Vertical plate coke drums affects the overall throughput of the have coke drums that provide greater
Capex As previously mentioned, the refinery. Also, without a rigorous reliability than traditionally possible.
initial Capex outlays for four vertical inspection and maintenance schedule, Whether it is a retrofit application, a full
plate coke drums is assumed to be $26.1 failures can occur at inopportune times vessel replacement or part of a new
million. such as the summer driving season when process unit, vertical plate coke drums
Opex The vertical plate technology is product values are at their peak. Hence, will be able to endure the most severe
expected to defer cracking substantially. the direct financial losses due to outages thermal cycles and outlast any conven-
Since 75% of the critical circumferential are likely to be greater than described in tionally designed vessel. Implementing
weld seam footage has been eliminated, this discussion, and the corresponding a T-Rex or wrapper design for the
we can assume there will be 75% fewer benefits of vertical plate technology are support is expected to further improve
cracks. Thus, the Opex for shell cracking likely to be that much higher. the life of these vessels.
on a vertical plate coke drum may be 11
* 0.25 = three events over the 20-year Future outlook This article is based on a paper (AM-06-48)
presented at the NPRA Annual Meeting, Salt
period, of which 30%, or one, of the Since 2000, CB&I has completed four Lake City, Utah, 20 March 2006.
events will be planned and the vertical plate projects, bringing its total
remaining two events will be number of vertical plate coke drums in
unplanned. Using the same analysis as service to 11. These projects have References
with the conventionally designed coke included the full circumferential can 1 Weil N A, Rapasky F S, Experience with
vessels of delayed — coking units, API 23rd
drums over the same 20-year period: section replacement of shells ranging Midyear Meeting, 1958.
— Costs of crack repairs over a 20-year from 35–73ft, as well as new lower 2 Boswell R S, Ferraro T, Remaining life
period One planned event * ($225 000) + knuckle and skirt assemblies. As far as evaluation of coke drums, Plant Engineering,
Design and Responsibility Symposium,
two unplanned events * ($225 000 * 1.3) improving the reliability and lifespan of Energy Engineering Conference, 1997.
= $810 000 in repair costs for each drum, coke drums go, as previously mentioned 3 Antalffy L P, Malek D W, Pfeifer J A, Stewart
or $3.2 million for all four drums. none of the vessels have been in service C W, Grimsley B, Shockley R, Innovations
in delayed coking coke drum design, ASME,
Direct financial losses In terms of lost long enough to allow quantification of 1999.
revenues caused by cracking, the same the actual improvement. However, the 4 Livingston B, Saunders K L, Coke drums
assumptions apply from above, but for vertical plate coke drums installed at failure prediction evaluation using
only two unplanned events. Thus: the West Coast refinery in 2000 have probabilistic techniques, ASME, 1998.
5 Penso J A, Lattarulo Y M, Seijas A J, Torres J,
— Direct financial losses over a 20-year seen about six years of service and are Howden D, Tsai C L, Understanding failure
period Two unplanned events/drum pair approaching 2000-plus cycles with no mechanisms to improve reliability of coke
* six days for each event * 25 000bbl/day evidence of any unusual distortion. drums, ASME, 1999.
6 ASME Section II parts A & C, plus Plate and
* (0.85 * $50) = $12.7 million in lost Currently, four more drums are under Electrode Manufacturers brochures and
revenues for each drum pair, or $25.5 contract. The first project is for a CB&I data.
million for all four drums. Canadian refiner and includes two new
Based on the LCVA, it can be seen that drums of slightly larger dimensions to be
the lifecycle Opex and lost revenue costs installed during a turnaround later this Coby W Stewart is business development
over a 20-year period for four year. This project is unique in that the manager, Chicago Bridge & Iron, The
conventionally designed coke drums drums are being fabricated in three Woodlands, Texas, USA.
total about $114 million, compared with segments. The segments are then to be Email: cstewart@cbi.com
about $29 million for coke drums using transported to the site and installed Aaron M Stryk is global marketing
vertical plate technology. Thus, vertical through the side of the structure during manager, Chicago Bridge & Iron, The
plate coke drums can save refinery the outage while seams are being welded Woodlands, Texas, USA.
owners approximately $85 million over in place. The second project is for two Email: astryk@cbi.com
the 20-year period, not to mention the drums being erected on site and installed Lee Presley is product and engineering
added advantages of greater plant safety. on the “table top” for final assembly. manager, pressure vessels and special
Note that these calculations are As feedstocks become heavier and the structures, Chicago Bridge & Iron, The
conservative, as downtime in a delayed need for coking capacity continues to Woodlands, Texas, USA.
coker unit, as in any key processing unit, rise, refiners will need more than ever to Email: lpresley@cbi.com

acs

00 P T Q Q3 2006 w w w. e p t q . c o m

You might also like