Professional Documents
Culture Documents
Key To Continuous Improvement Case Study: Problem Solving
Key To Continuous Improvement Case Study: Problem Solving
Prepare by:
Engr. Khaled M. Al Kolfat
Content List:
1. Researcher Identification.
2. Problem-Solving and Decision Making Steps.
3. Case Study (Marafiq Project) Jubail.
4. What is Cold joint ?
Problem
1. Exists whenever objectives are not being met.
2. What is happening vs. what is wanted to be happen
Problem Solving
1. The process of taking corrective action to meet objectives.
Decision Making
1. The process of selecting an alternative course of action that
will solve a problem.
2. First decision is whether to take corrective action.
Case Study
2 – Gather Information's
3 –Develop Alternatives.
WHY?
Designer report.
process reports.
Fresh concrete
report.
•
• Designer report.
1 2 3 4
Man Method
Concrete not finished
Did not perform properly Sequence of casting
servicing to
vibrators
Concrete not vibrated
Wrongly assemble
properly Cold joint
the pump car
Machine Material
All the ideas are discussed among the group, revised, tossed
out, expanded, etc. based on the group's analysis and awareness of
the validation for each idea, the best ones are selected for closer
review.
a) Examine each cause of the problem. Then for each cause, based
on your direct knowledge and experience, list the solutions that
logically would seem to solve the problem.
b) Check the possible solutions you arrive at with the research you
have compiled on how the problem was solved by others.
Demolish Tools :
1. Coring machine.
4. Allocate resources
7. Training staff
Prepare by:
Engr. Khaled M. Al Kolfat
Building the executing team.
NUMBER OF BLOCKAS
QUANTITY
MARK
UPPER LOWER
G1 28 8
G2 15 6
G3 8 4
G4 6 2
G5 4 2
G6 4 2
G7 6 3
CH1 4
CH2 4
CH3 8
CH4 6
SUB-TOTAL 93 27
TOTAL 120
10/15/2014 Problem Solving (Case Study ) Engr. Khaled M. Al Kolfat 53
Operating Floor Plan
A1100 Insert Diamond Wire Saw Into Drilled Hole And Apply It Upward 2 4-Nov-08 5-Nov-08
A1160 Cut The Column Head By Diamond Wire Saw Horizontally 4 24-Nov-08 27-Nov-08
A1170 Lift Column Head Demolition Block And Transport To Trailer 4 28-Nov-08 1-Dec-08
A1270 Cut The Column Head By Diamond Wire Saw Horizontally 4 27-Nov-08 30-Nov-08
A1280 Lift Column Head Demolition Block And Transport To Trailer 4 1-Dec-08 4-Dec-08
15-Jan-09
STG4 MARAFIQ IWPP (STG#4 REPAIR) 82 25-Oct-08
STG4-3 Re-Construction Phase 36 10-Dec-08 15-Jan-09
STG4-3-
1 Crew1 33 10-Dec-08 12-Jan-09
Connect New Reinforcement To The Existing Reinforcement
A1300 By Mechanical Coupler 4 6-Dec-08 9-Dec-08
A1310 Rebar works Installation for Raft Foundation 7 10-Dec-08 16-Dec-08
A1320 Form work / Shuttering for Raft Foundation 7 17-Dec-08 23-Dec-08
A1330 Casting The Reinforced Concrete for Raft Foundation. 1 24-Dec-08 24-Dec-08
A1340 Casting Treatment 15 25-Dec-08 8-Jan-09
A1350 Removal The Shuttering of Raft Foundation 4 9-Jan-09 12-Jan-09
STG4-3-
2 Crew2 33 13-Dec-08 15-Jan-09
Connect New Reinforcement To The Existing Reinforcement
A1360 By Mechanical Coupler 4 9-Dec-08 12-Dec-08
A1370 Rebar works Installation for Raft Foundation 7 13-Dec-08 19-Dec-08
A1380 Form work / Shuttering for Raft Foundation 7 20-Dec-08 26-Dec-08
A1390 Casting The Reinforced Concrete for Raft Foundation. 1 27-Dec-08 27-Dec-08
A1400 Casting Treatment 15 28-Dec-08 11-Jan-09
A1410 Removal The Shuttering of Raft Foundation 4 12-Jan-09 15-Jan-09