450 Layiing & termination of HT & LT cables inclusing cable termination 150 d
451 DC System 46 d
452 Readiness of Battery Room 0d
453 Installation of Battery Stand / Rack 10 d
454 Installation of Batteries in Sequential Polarity 10 d
455 Installation of Battery Chargers 5d
456 Installation of DCDB with float cum Boost Charger 5d
457 Testing & Precommissioning Activities 10 d
458 Commissioning 3d
459 Aux Power Transformers 318 d
460 Station Aux. Transfomer -2 Nos 272 d
461 Readiness of Founadtion for SAT 0d
462 Installation of Main Tank on Foundation for SAT 6d
463 Alignment & Roller Blocking 4d
464 Installation of Conservator Tank 8d
465 Installation of Radiator,accessories and Fan Supports 8d
466 Installation of Marshalling Box and RTCC Panel 7d
467 Installation of Radiators, Bushings, Piping & Protective Devices etc 5d
468 Oil Top up and Filteration 20 d
469 Testing & Precommissioning Activities of SAT 20 d
470 Commissioning Activities of SAT 5d
471 NGR for SAT 17 d
472 Installation of NGR 7d
473 Testing & Precommissioning Activities 10 d
474 CHP Aux. Transformer -2 Nos 216 d
475 Readiness of foundation 0d
476 Installation of Main Tank on Foundation 10 d
477 Alignment & Roller Blocking 8d
478 Installation of Conservator Tank 12 d
479 Installation of Radiator,accessories and Fan Supports 8d
480 Installation of Marshalling Box and RTCC Panel 7d
481 Installation of Radiators, Bushings, Piping & Protective Devices etc 5d
482 Oil Top up and Filteration 25 d
483 Testing & Precommissioning Activities 25 d
484 Commissioning Activities of CHP Aux.Transformer 5d
485 NGR for CHP Aux Transformer 17 d
486 Installation of NGR 7d
487 Testing & Precommissioning Activities 10 d
488 Service Transformers 380 d
489 Station Service Transformer - 4 Nos 153 d
490 Readiness of 12m floor 0d
491 Installation of SST -4 Nos 25 d
492 Testing & Precommissioning Activities of SST 30 d
493 Commissioning Activities of SST 5d
494 Water Treatment Service Transformer - 2 Nos 199 d
495 Readiness of transformer foundation 0d
496 Installation of Main Tank on Foundation 10 d
497 Alignment & Roller Blocking 8d
498 Installation of Conservator Tank 10 d
499 Installation of Radiator & accessories 8d
500 Installation of Marshalling Box and RTCC Panel 5d
501 Oil Top up and Filteration 20 d
502 Testing & Precommissioning Activities 20 d
503 Commissioning Activities 5d
504 Ash Water pump House Service Transfomer - 2 Nos 269 d
505 Readiness of foundation 0d
506 Installation of Main Tank on Foundation 10 d
507 Alignment & Roller Blocking 8d
508 Installation of Conservator Tank 10 d
509 Installation of Radiator & accessories 8d
510 Installation of Marshalling Box and RTCC Panel 5d
511 Oil Top up and Filteration 10 d
512 Testing & Precommissioning Activities 10 d
513 Commissioning Activities 5d
514 Ash Extraction Service Transformer - 2 Nos 251 d
515 Readiness of foundation 0d
516 Installation of Main Tank on Foundation 10 d
517 Alignment & Roller Blocking 8d
518 Installation of Conservator Tank 10 d
519 Installation of Radiator & accessories 8d
520 Installation of Marshalling Box and RTCC Panel 5d
521 Oil Top up and Filteration 10 d
522 Testing & Precommissioning Activities 10 d
523 Commissioning Activities 5d
524 Electro Chlorination Plant Service Transformer - 2 Nos 169 d
525 readiness of Foundation 0d
526 Installation of Main Tank on Foundation 10 d
527 Alignment & Roller Blocking 8d
528 Installation of Conservator Tank 10 d
529 Installation of Radiator & accessories 8d
530 Installation of Marshalling Box and RTCC Panel 5d
531 Oil Top up and Filteration 10 d
532 Testing & Precommissioning Activities 10 d
533 Commissioning Activities of ECP 5d
534 Ash Silo Service Transformer-2 Nos 223 d
535 Readiness of foundation 0d
536 Installation of Main Tank on Foundation 10 d
537 Alignment & Roller Blocking 8d
538 Installation of Conservator Tank 10 d
539 Installation of Radiator & accessories 8d
540 Installation of Marshalling Box and RTCC Panel 5d
541 Oil Top up and Filteration 10 d
542 Testing & Precommissioning Activities 10 d
543 Commissioning Activities 5d
544 Fire water Service Transformer - 2 Nos 160 d
545 Foundation readiness 0d
546 Installation of Main Tank on Foundation 10 d
547 Alignment & Roller Blocking 8d
548 Installation of Conservator Tank 10 d
549 Installation of Radiator & accessories 8d
550 Installation of Marshalling Box and RTCC Panel 5d
551 Oil Top up and Filteration 10 d
552 Testing & Precommissioning Activities 10 d
553 Commissioning Activities 5d
554 Ash water Recovery Service Transformer - 2 Nos 188 d
555 Radiness of foundation 0d
556 Installation of Main Tank on Foundation 10 d
557 Alignment & Roller Blocking 8d
558 Installation of Conservator Tank 10 d
559 Installation of Radiator & accessories 8d
560 Installation of Marshalling Box and RTCC Panel 5d
561 Oil Top up and Filteration 10 d
562 Testing & Precommissioning Activities 10 d
563 Commissioning Activities 5d
564 Admin Service Transfomer- 2 Nos 177 d
565 Installation of Main Tank on Foundation 0d
566 Alignment & Roller Blocking 10 d
567 Installation of Conservator Tank 8d
568 Installation of Radiator & accessories 10 d
569 Installation of Marshalling Box and RTCC Panel 8d
570 Oil Top up and Filteration 5d
571 Testing & Precommissioning Activities 10 d
572 Commissioning Activities 5d
573 ESP Service Transformers- 16 Nos 161 d
574 Foundation readiness of ESP area 0d
575 Installation of Main Tank on Foundation 25 d
576 Alignment & Roller Blocking 20 d
577 Installation of Conservator Tank 16 d
578 Installation of Radiator & accessories 25 d
579 Installation of Marshalling Box and RTCC Panel 5d
580 Oil Top up and Filteration 30 d
581 Testing & Precommissioning Activities 30 d
582 Commissioning of ESP transformers 10 d
583 UST- 8 Nos 158 d
584 Readiness of floor 0d
585 Installation of UST -8 Nos 56 d
586 Testing & Precommissioning Activities 40 d
587 Commissioning Activities of UST 5d
588 CHP - 6 Nos 154 d
589 Readiness of foundation 0d
590 Installation of Main Tank on Foundation 12 d
591 Alignment & Roller Blocking 20 d
592 Installation of Conservator Tank 15 d
593 Installation of Radiator & accessories 15 d
594 Installation of Marshalling Box and RTCC Panel 15 d
595 Oil Top up and Filteration 20 d
596 Testing & Precommissioning Activities 25 d
597 Commissioning of CHP 5d
598 UPS 52 d
599 Readiness of UPS Room 0d
600 Installation of Base Frame 7d
601 Alignment and Welding/Anchoiring 8d
602 Installation and coupling of Panels 20 d
603 Earthing of Panel 7d
604 Testing & Precommissioning Activities 5d
605 Commissioning Activites for UPS 5d
606 NSPBD 60 d
607 Erection of NSPBD 60 d
608 LT Switchgear Station 140 d
609 Readiness of 13.5 mtr panel room ( completion of 17 m Mtr floor) 0d
610 Installation of Base Frame 15 d
611 Alignment and Welding/Anchoiring 10 d
612 Installation and coupling of Panels 15 d
613 Earthing of MCC Panel 15 d
614 Testing & Precommissioning Activities 25 d
615 Commissioning Activities 10 d
616 LT Switchgear Unit 145 d
617 Installation of Base Frame 15 d
618 Alignment and Welding/Anchoiring 10 d
619 Installation and coupling of Panels 15 d
620 Earthing of MCC Panel 15 d
621 Testing & Precommissioning Activities 25 d
622 Commissioning Activities 10 d
623 415V Swgr (AHP,CHP,ESP) 320 d
624 Installation of Base Frame 15 d
625 Alignment and Welding/Anchoiring 10 d
626 Installation and coupling of Panels 15 d
627 Earthing of MCC Panel 15 d
628 Testing & Precommissioning Activities 25 d