Work Breakdown Structures (WBS) : Geographical Process Area Within A Project
Work Breakdown Structures (WBS) : Geographical Process Area Within A Project
Work breakdown
structures (WBS)
Before any meaningful programme can be pro-
duced, it is essential that careful thought is given
to the number and size of networks required. Not
only is it desirable to limit the size of network,
but each ‘block’ of networks should be con-
sidered in relation to the following aspects:
choosing the correct blocks, i.e. drawing the demarcation lines in the most
advantageous way, cannot be overemphasized. This decision has an effect not
only on the number and size of planning networks but also on the organization
of the design teams and, in the case of large projects, on the organizational
structure of the site management set-up.
Because of its importance, a guide is given below which indicates the type
of block distribution which may be sensibly selected for various projects. The
list is obviously limited, but it should not be too difficult to abstract some firm
guidelines to suit the project under consideration.
1 Pharmaceutical factory
Block A Administration block (offices and laboratories)
Block B Incoming goods area, raw material store
Block C Manufacturing area 1 (pills)
Block D Manufacturing area 2 (capsules)
Block E Manufacturing area 3 (creams)
Block F Boiler house and water treatment
Block G Air-conditioning plant room and electrical distribution control
room
Block H Finished goods store and dispatch
For planning purposes, general site services such as roads, sewers, fencing and
guard houses can be incorporated into Block A or, if extensive, can form a
block of their own.
Obviously, the number of housing areas or high-rise blocks can vary with the
size of the development. Roads and sewers and statutory services are part of
their respective housing blocks unless they are constructed earlier as a separate
contract, in which case they would form their own block or blocks.
26
Work breakdown structures (WBS)
Here again, the road and sewage system could form a block on its own
incorporating the lorry park.
4 Oil terminal
Block A Crude reception and storage
Block B Stabilization and desalting
Block C Stabilized crude storage
Block D NGL separation plant
Block E NGL storage
Block F Boiler and water treatment
Block G Effluent and ballast treatment
Block H Jetty loading
Block J Administration block and laboratory
Block K Jetty 1
Block L Jetty 2
Block M Control room 1
Block N Control room 2
Block P Control room 3
Here roads, sewers and underground services are divided into the various
operational blocks.
27
Project Planning and Control
7 Bitumen refinery
Block A Crude line and tankage
Block B Process unit
Block C Effluent treatment and oil/water separator
Block D Finished product tankage
Block E Road loading facility, transport garage and lorry park
Block F Rail loading facility and sidings
Block G Boiler house and water treatment
Block H Fired heater area
28
Work breakdown structures (WBS)
Depending on size, the process unit may have to be subdivided into more
blocks but it may be possible to combine K and L. Again, roads and sewers
may be separate or part of each block.
29
Project Planning and Control
30
Work breakdown structures (WBS)
31
Project Planning and Control
Table 5.1
Project risks
32
Work breakdown structures (WBS)
Car
Assembly
0.0
Assemble
Car
0.0
Assemble Assemble Weld Side Forge Cross Press Roof Fit out
Engine Transmission Members Members & Sides Interior
1.1 1.2 2.1 2.2 3.1 3.2
Figure 5.2 WBS
33
Project Planning and Control
Figure 5.3
34
Work breakdown structures (WBS)
35
Project Planning and Control
Bodywork Superintendent
Chassis Superintendent
Chassis Shop Manager
Engine Superintendent
Power Plant Manager
QA Manager
Director
Car Assembly A B A B
Power Unit A B A B C
Chassis A B A B C
Body Shell A B A B C
Engine B A B C C
Transmission B A B C C
Side Members B A B C C
Cross Members B A B C C
Roof & Floor B A B C C
Interior & Trim B A B C C
Figure 5.6
36
Work breakdown structures (WBS)
Responsibility matrix
By combining the WBS with the OBS it is possible to create a Responsibility
Matrix. Using the car assembly example given in Figures 5.1 and 5.5, the
matrix is drawn by writing the WBS work areas vertically and the OBS
personnel horizontally as shown in Figure 5.6.
By placing a suitable designatory letter into the intersecting boxes, the level
of responsibility for any work area can be recorded on the matrix.
37