DEPARTMENT: ELECTRICAL
Total Down
S.No. Date Shift Area Name of the Equipment from to Time in Reasons for Down Time Time in
Min Min.
1 4-Apr-18 A Utilities 51,52 and 53 Mould Cooling Blowers 11:07AM 11:12AM 5 Analog Input Signal Problem So rectified
2 5-Apr-18 B Coldend 56 - Line divider Infeed Conveyor 8:00PM 9:00PM 60 Motor Nde Side Bearing abnormal Sound So replaced
3 9-Apr-18 B Hotend 46 hotend coating M/C 7:00PM 07:30PM 30 Circulation Blower Bearing jammed So replaced
4 18-Apr-18 A Utilities 57 Mould Cooling Blower 1:50PM 2:00PM 10 Tripped due to power fluctuation So resetted
5 24-Apr-18 B ACL Shrink tunnel hood 7:00PM 7:30PM 30 Temperature problem So rectified
6 24-Apr-18 B ACL Shrink tunnel hood 8:20PM 9:20PM 60 Limit Switch Problem So rectified
Production Effected (Min.) 15 Non Production (Min.) 180 195 1.07
External 0
% Down
Time
0.0025
0
DAILY DOWNTIME REPORT FOR M
DEPARTMENT: ELECTRICAL
Total Down
% Down
S.No. Date Shift Area Name of the Equipment from to Time in Reasons for Down Time Time in
Time
Min Min.
11:50 AM 12:00AM
1 7-Jun-18 A Production 41 Control room systems restarted. 20 Cables Insulation failed due to rain Water.
04:35 PM 04:45 PM
3 26-Jun-18 C Coldend 45 packing M/C (L.H.S) 2:40 AM 2:50 AM 10 End Sealer cable cutt off problem So rectified
Total Down
% Down
S.No. Date Shift Area Name of the Equipment from to Time in Reasons for Down Time Time in
Time
Min Min.
1 5-Jul-18 A Cold end 57 packing Machine 6:30 AM 7:00 AM 30 Heaters cable cutt off So rectified
2 15-Jul-18 C Cold end 58 packing Machine 4:50 AM 7:30 AM 160 Auto sensor failed So replaced another sensor
3 22-Jul-18 A Cold end 57 packing Machine 8:30 AM 8:45 AM 15 End sealer Thermo Couple problem So Rectified
Total Down
S.No. Date Shift Area Name of the Equipment from to Time in Reasons for Down Time Time in
Min Min.
F5 process equipments affected due to Un
1 1-Aug-18 B Plant F5 all IS M/C 8:40 PM 9:00 PM 20 authorised Operation of solar panel by solar
team
2 3-Aug-18 B Production 54 I/S Machine 7:30 PM 7:40 PM 10 Due to power Fluctuation So started
3 14-Aug-18 B Coldend 53 packing M/C 9:20 PM 9:35 PM 15 I/C supply Cable cutt off problem So rectified
0.0000
0.1344
DAILY DOWNTIME REPORT FOR SEPTEMBER-2018
DEPARTMENT: ELECTRICAL
Total Down
S.No. Date Shift Area Name of the Equipment from to Time Reasons for Down Time Timein
in Min Min.
1 6-Sep-18 A Coldend 58 packing M/C 8:40 AM 9:00 AM 20 End sealer Sensor failed So replaced.
2 17-Sep-18 A Coldend 57 Packing M/C 8:30 AM 9:00 AM 30 Tunnel Blower Motor bearing problem So replaced.
3 24-Sep-18 A Production 58 Cross Conveyor 6:30 AM 6:35 AM 5 Tripped with Overload fault So resetted.
4 25-Sep-18 A Production 47 MCB (42 IS M/C) 6:15 AM 6:20 AM 5 Tripped with Overload fault So resetted.
132 KV Line conductor snapped Due to thunder
26-Sep-18 B 5:10 PM _
5 Plant Power failure _ storms SO line repair works carried and power
27-Sep-18 A _ 12:50 PM
restored.
6 27-Sep-18 C Lehr 44 Lehr 2:10 AM 2:40 AM 30 Burner Cable shorted So rectified and started.
6:52 PM 6:57 PM 5
7 29-Sep-18 B Pruduction FGB NO -2 (F-V) Star Delta timer problem So FGB No-1 Started.
9:13 PM 9:18 AM 5
8 29-Sep-18 B Coldend 45 Packing M/C 8:50 PM 10:30 PM 100 Pusher sollenoid malfunctioning so rectified
9 29-Sep-18 C Coldend 53 Packing M/C 10:30 PM 11:30 PM 60 I/C Switch failed So replaced
10 30-Sep-18 A Coldend Goods Lift NO-2 10:40 AM 11:20 AM 40 Level adjustment purpose one channel welded
Production Effected (Min.) 20 Non Production (Min.) 280 Total 300 2.38
1200 External 1200
%
Down
Time
0.0055
2.7778
DAILY DOWNTIME REPORT FOR OCTOBER-2018
DEPARTMENT: ELECTRICAL
Total Down
Name of the
S.No. Date Shift Area from to Time in Reasons for Down Time Timein
Equipment
Min Min.
1 1-Oct-18 A Production 45 MCB 10:00 AM 10:05 AM 5 Drive stopped without alaram and fault.
2 2-Oct-18 A Coldend 41 Packing M/C 9:35 AM 9:45 AM 10 SMPS Failed So replaced.
3 2-Oct-18 A Packing Goods Lift NO-4 12:25 PM 1:45 PM 20 Level problem So adjusted.
4 3-Oct-18 B Packing Goods Lift NO-4 8:00 PM 10:00 PM 120 Tripped with Overload fault So resetted.
5 5-Oct-18 B Coldend 56 PLC Conveyor 9:00 PM 9:40 PM 40 56 PLC cable damaged So replaced.
6 8-Oct-18 C Coldend 58 Packing M/C 11:45 PM 12:30 AM 45 Auto Sensor failed So replaced.
7 9-Oct-18 C Plant F4 - PLANT 12:10 AM 1:10 AM 60 10 MVA transformer Tripped.
8 10-Oct-18 A Plant F4 - PLANT 6:30 AM 7:00 AM 30 10 MVA transformer Tripped.
8 12-Oct-18 C Coldend 42 Hotend Coating M/C 12:20 AM 1:20 AM 60 Circulation Blower Failed So replaced
10 13-Oct-18 B Coldend 56 RCP Case Conveyor 4:30 PM 5:15 PM 45 Motor cable got failed So changed.
11 20-Oct-18 B Coldend 41 Wrapping M/C 9:00 PM 9:50 PM 50 41 Wrapping M/C y-phase supply problem, rectified.
12 21-Oct-18 A Coldend 44 Poly pack tunnel 12:45 PM 1:00 PM 15 Blower Motor bearing problem So replaced.
13 23-Oct-18 B Plant All IS M/C 5:50 PM 6:20 PM 30 Compressors tripped due to voltage drop.
14 27-Oct-18 A Production 43 Lehr 12:00 PM 12:10 PM 10 43 Lehr belt drive fan got failed So replaced.
Production Effected (Min.) 105 Non Production (Min.) 435 Total 540 12.32
External 60
%
Down
Time
0.0276
0.1344