SUMMARY M.T.

O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

A ANCHOR BLOCK FOUNDATION (2 UNIT)


Foundation size: (1.9W x 2.2 L) m, Reinforced Concrete (2 unit)
A.1 Civil works
A.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

A.1.2 Earthworks & Sandbedding,


A.1.2.a - Soil excavation for: pilecap fdt, and etc.
A.1.2.b - Soil backfill and compaction (from soil excavation mat'l)
A.1.2.c - Sand bedding 50 mm thk & well compacted

A.1.3 Pile Foundation

Comp. strength 28 days (min.) f'c = 40Mpa (cylinder spece.test) or K-500 kg/cm2 (cubical space

- Pre-cast PC pile square 200 x 200 (mm) solid

A.1.4 Concrete
A.1.4.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
A.1.4.1.a - Concrete, total volume
A.1.4.1.b - Reinforcing bar, total weight

A.1.4.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
A.1.4.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

B PUMP SHELTER FOUNDATION


Shelter size: (10W x 30L) m, Steel Structure
B.1 Civil works
B.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

B.1.2 Earthworks, Sandbedding, Base course fill and stone masonry foundation
B.1.2.a - Soil excavation for: pilecap fdt, and etc.

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 1 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

B.1.2.b - Soil backfill and compaction (from soil excavation mat'l)


B.1.2.c - Sand bedding 50 mm thk & well compacted

B.1.3 Pile Foundation

Comp. strength 28 days (min.) f'c = 40Mpa (cylinder spece.test) or K-500 kg/cm2 (cubical space

- Pre-cast PC pile square 200 x 200 (mm) solid

B.1.4 Concrete
B.1.4.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
B.1.4.1.a - Concrete, total volume
B.1.4.1.b - Reinforcing bar, total weight

B.1.4.2 Reinforced Concrete (R.C) structure K-225


Cable trench & cable duct bank encasement concrete, compressive strength 28 days (min.) f'c =
Mpa (cylinder specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 G
SII-0136, BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
B.1.4.2.a - Concrete, total volume
B.1.4.2.b - Reinforcing bar, total weight

B.1.4.3 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
B.1.4.3.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

B.1.5 Accossoris Works


B.1.5.1 Cable trench steel plate cover

B.1.5.1.a - Steel frame L50x50x5 for cover plate & embedded plate, Structural steel shape and plate: A
JIS G3101 SS, Alkyd paint finish surface.
B.1.5.1.b - Checker plate floor cover 3mm th'k (min.) ASTM A786 and hotdip galvanized finish surface

B.1.5.2 Cable Duct bank PVC conduit


- PVC pipe slevee Dia.6" AW

B.2.2 Floor, wall and Ceiling Finishes


B.2.2.1 Floor finishes
B.2.2.1.a - Concrete steel trowel finish with floor hardener
B.2.2.1.b - Concrete steel trowel finish (without floor hardener)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 2 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

C DENSITO METER SHELTER FOUNDATION (2 UNIT)


Shelter size: 2 x(2.75W x 3L) m, Steel Structure
C.1 Civil works
C.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

C.1.2 Earthworks, Sandbedding, Base course fill and stone masonry foundation
C.1.2.a - Soil excavation for: pilecap fdt, and etc.
C.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
C.1.2.c - Sand bedding 50 mm thk & well compacted

C.1.3 Concrete
C.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
C.1.3.1.a - Concrete, total volume
C.1.3.1.b - Reinforcing bar, total weight

C.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
C.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

C.1.4 Floor, wall and Ceiling Finishes


C.1.4.1 Floor finishes
C.1.4.1.a - Concrete steel trowel finish with floor hardener
C.1.4.1.b - Concrete steel trowel finish (without floor hardener)

D METERING SHELTER FOUNDATION TBBM LOMANIS


Shelter size: (6W x 17L) m, Steel Structure
Civil works
D.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

D.1.2 Earthworks & Sandbedding


D.1.2.a - Soil excavation for: pilecap fdt., and etc.
D.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
D.1.2.c - Sand bedding 50 mm thk & well compacted

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 3 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

D.1.3 Concrete
D.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
D.1.3.1.a - Concrete, total volume
D.1.3.1.b - Reinforcing bar, total weight

D.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
D.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

D.2 Architecture & Finishing work

D.2.1 Floor, Wall and Ceiling Finishes


D.2.1.1 Interior & Exterior floor finishes
D.2.1.1.a - Concrete steel trowel finish with floor hardener
D.2.1.1.b - Concrete steel trowel finish (without floor hardener)

E METERING SHELTER FOUNDATION TBBM TASIKMALAYA


Shelter size: (6W x 17L) m, Steel Structure
Civil works
E.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

E.1.2 Earthworks & Sandbedding


E.1.2.a - Soil excavation for: pilecap fdt., and etc.
E.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
E.1.2.c - Sand bedding 50 mm thk & well compacted

E.1.3 Concrete
E.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
E.1.3.1.a - Concrete, total volume
E.1.3.1.b - Reinforcing bar, total weight

E.1.3.2 Non structural concrete and lean concrete K-150

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 4 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
E.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

E.2 Architecture & Finishing work


E.2.1 Floor, Wall and Ceiling Finishes
E.2.1.1 Interior & Exterior floor finishes
E.2.1.1.a - Concrete steel trowel finish with floor hardener
E.2.1.1.b - Concrete steel trowel finish (without floor hardener)

F BOX VALVE SHELTER FOUNDATION CILACAP (KP 0+009)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
F.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

F.1.2 Earthworks & Sandbedding


F.1.2.a - Soil excavation for: pilecap fdt., and etc.
F.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
F.1.2.c - Sand bedding 50 mm thk & well compacted

F.1.3 Concrete
F.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
F.1.3.1.a - Concrete, total volume
F.1.3.1.b - Reinforcing bar, total weight

F.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
F.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

F.2 Architecture & Finishing work

F.2.1 Floor, Wall and Ceiling Finishes


F.2.1.1 Interior & Exterior floor finishes
F.2.1.1.a - Box Valve floor area, gravel 100 mm thk
F.2.1.1.b - Gravel 100 mm thk

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 5 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

G BOX VALVE SHELTER FOUNDATION SITINGIL-1 (KP 35+140)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
G.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

G.1.2 Earthworks & Sandbedding


G.1.2.a - Soil excavation for: pilecap fdt., and etc.
G.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
G.1.2.c - Sand bedding 50 mm thk & well compacted

G.1.3 Concrete
G.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
G.1.3.1.a - Concrete, total volume
G.1.3.1.b - Reinforcing bar, total weight

G.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
G.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

G.2 Architecture & Finishing work

G.2.1 Floor, Wall and Ceiling Finishes


G.2.1.1 Interior & Exterior floor finishes
G.2.1.1.a - Box Valve floor area, gravel 100 mm thk
G.2.1.1.b - Gravel 100 mm thk

H BOX VALVE SHELTER FOUNDATION SITINGIL-2 (KP 35+290)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
H.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

H.1.2 Earthworks & Sandbedding


H.1.2.a - Soil excavation for: pilecap fdt., and etc.

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 6 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

H.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
H.1.2.c - Sand bedding 50 mm thk & well compacted

H.1.3 Concrete
H.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
H.1.3.1.a - Concrete, total volume
H.1.3.1.b - Reinforcing bar, total weight

H.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
H.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

H.2 Architecture & Finishing work

H.2.1 Floor, Wall and Ceiling Finishes


H.2.1.1 Interior & Exterior floor finishes
H.2.1.1.a - Box Valve floor area, gravel 100 mm thk
H.2.1.1.b - Gravel 100 mm thk

I BOX VALVE SHELTER FOUNDATION TARISI (KP 69+563)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
I.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

I.1.2 Earthworks & Sandbedding


I.1.2.a - Soil excavation for: pilecap fdt., and etc.
I.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
I.1.2.c - Sand bedding 50 mm thk & well compacted

I.1.3 Concrete
I.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
I.1.3.1.a - Concrete, total volume
I.1.3.1.b - Reinforcing bar, total weight

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 7 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

I.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
I.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

I.2 Architecture & Finishing work

I.2.1 Floor, Wall and Ceiling Finishes


I.2.1.1 Interior & Exterior floor finishes
I.2.1.1.a - Box Valve floor area, gravel 100 mm thk
I.2.1.1.b - Gravel 100 mm thk

J BOX VALVE SHELTER FOUNDATION CINTARATU(KP 69+888)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
J.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

J.1.2 Earthworks & Sandbedding


J.1.2.a - Soil excavation for: pilecap fdt., and etc.
J.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
J.1.2.c - Sand bedding 50 mm thk & well compacted

J.1.3 Concrete
J.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
J.1.3.1.a - Concrete, total volume
J.1.3.1.b - Reinforcing bar, total weight

J.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
J.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

J.2 Architecture & Finishing work

J.2.1 Floor, Wall and Ceiling Finishes

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 8 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

J.2.1.1 Interior & Exterior floor finishes


J.2.1.1.a - Box Valve floor area, gravel 100 mm thk
J.2.1.1.b - Gravel 100 mm thk

K BOX VALVE SHELTER FOUNDATION DESA REJA SARI I(KP 77+752)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
K.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

K.1.2 Earthworks & Sandbedding


K.1.2.a - Soil excavation for: pilecap fdt., and etc.
K.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
K.1.2.c - Sand bedding 50 mm thk & well compacted

K.1.3 Concrete
K.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
K.1.3.1.a - Concrete, total volume
K.1.3.1.b - Reinforcing bar, total weight

K.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
K.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

K.2 Architecture & Finishing work

K.2.1 Floor, Wall and Ceiling Finishes


K.2.1.1 Interior & Exterior floor finishes
K.2.1.1.a - Box Valve floor area, gravel 100 mm thk
K.2.1.1.b - Gravel 100 mm thk

L BOX VALVE SHELTER FOUNDATION DESA REJA SARI II(KP 77+800)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
L.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 9 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

L.1.2 Earthworks & Sandbedding


L.1.2.a - Soil excavation for: pilecap fdt., and etc.
L.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
L.1.2.c - Sand bedding 50 mm thk & well compacted

L.1.3 Concrete
L.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
L.1.3.1.a - Concrete, total volume
L.1.3.1.b - Reinforcing bar, total weight

L.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
L.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

L.2 Architecture & Finishing work

L.2.1 Floor, Wall and Ceiling Finishes


L.2.1.1 Interior & Exterior floor finishes
L.2.1.1.a - Box Valve floor area, gravel 100 mm thk
L.2.1.1.b - Gravel 100 mm thk

M BOX VALVE SHELTER FOUNDATION BRIDGE LANGKAP LANCAR I (KP 79+326)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
M.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

M.1.2 Earthworks & Sandbedding


M.1.2.a - Soil excavation for: pilecap fdt., and etc.
M.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
M.1.2.c - Sand bedding 50 mm thk & well compacted

M.1.3 Concrete
M.1.3.1 Reinforced Concrete (R.C) structure K-275

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 10 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
M.1.3.1.a - Concrete, total volume
M.1.3.1.b - Reinforcing bar, total weight

M.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
M.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

M.2 Architecture & Finishing work

M.2.1 Floor, Wall and Ceiling Finishes


M.2.1.1 Interior & Exterior floor finishes
M.2.1.1.a - Box Valve floor area, gravel 100 mm thk
M.2.1.1.b - Gravel 100 mm thk

N BOX VALVE SHELTER FOUNDATION BRIDGE LANGKAP LANCAR II (KP 79+419)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
N.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

N.1.2 Earthworks & Sandbedding


N.1.2.a - Soil excavation for: pilecap fdt., and etc.
N.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
N.1.2.c - Sand bedding 50 mm thk & well compacted

N.1.3 Concrete
N.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
N.1.3.1.a - Concrete, total volume
N.1.3.1.b - Reinforcing bar, total weight

N.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 11 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

N.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

N.2 Architecture & Finishing work

N.2.1 Floor, Wall and Ceiling Finishes


N.2.1.1 Interior & Exterior floor finishes
N.2.1.1.a - Box Valve floor area, gravel 100 mm thk
N.2.1.1.b - Gravel 100 mm thk

O BOX VALVE SHELTER FOUNDATION BEBER (KP 102+200)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
O.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

O.1.2 Earthworks & Sandbedding


O.1.2.a - Soil excavation for: pilecap fdt., and etc.
O.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
O.1.2.c - Sand bedding 50 mm thk & well compacted

O.1.3 Concrete
O.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
O.1.3.1.a - Concrete, total volume
O.1.3.1.b - Reinforcing bar, total weight

O.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
O.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

O.2 Architecture & Finishing work

O.2.1 Floor, Wall and Ceiling Finishes


O.2.1.1 Interior & Exterior floor finishes
O.2.1.1.a - Box Valve floor area, gravel 100 mm thk
O.2.1.1.b - Gravel 100 mm thk

P BOX VALVE SHELTER FOUNDATION TASIK I (KP 126+853)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 12 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

Shelter size: (5W x 12L) m, Steel Structure


Civil works
P.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

P.1.2 Earthworks & Sandbedding


P.1.2.a - Soil excavation for: pilecap fdt., and etc.
P.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
P.1.2.c - Sand bedding 50 mm thk & well compacted

P.1.3 Concrete
P.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
P.1.3.1.a - Concrete, total volume
P.1.3.1.b - Reinforcing bar, total weight

P.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
P.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

P.2 Architecture & Finishing work

P.2.1 Floor, Wall and Ceiling Finishes


P.2.1.1 Interior & Exterior floor finishes
P.2.1.1.a - Box Valve floor area, gravel 100 mm thk
P.2.1.1.b - Gravel 100 mm thk

Q BOX VALVE SHELTER FOUNDATION TASIK II (KP 126+944)


Shelter size: (5W x 12L) m, Steel Structure
Civil works
Q.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

Q.1.2 Earthworks & Sandbedding


Q.1.2.a - Soil excavation for: pilecap fdt., and etc.
Q.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Q.1.2.c - Sand bedding 50 mm thk & well compacted

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 13 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

Q.1.3 Concrete
Q.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Q.1.3.1.a - Concrete, total volume
Q.1.3.1.b - Reinforcing bar, total weight

Q.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Q.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

Q.2 Architecture & Finishing work

Q.2.1 Floor, Wall and Ceiling Finishes


Q.2.1.1 Interior & Exterior floor finishes
Q.2.1.1.a - Box Valve floor area, gravel 100 mm thk
Q.2.1.1.b - Gravel 100 mm thk

R PIG LAUNCHER FOUNDATION TBBM LOMANIS


Foundation size: (2.4W x 9.67L) m, Reinforced Concrete
Civil works
R.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

R.1.2 Earthworks & Sandbedding


R.1.2.a - Soil excavation for: pilecap fdt., and etc.
R.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
R.1.2.c - Sand bedding 50 mm thk & well compacted

R.1.3 Concrete
R.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
R.1.3.1.a - Concrete, total volume
R.1.3.1.b - Reinforcing bar, total weight

R.1.3.2 Non structural concrete and lean concrete K-150

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 14 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
R.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

R.2 Architecture & Finishing work

R.2.1 Floor, Wall and Ceiling Finishes


R.2.1.1 Interior & Exterior floor finishes
R.2.1.1.a - Floor area, Concrete steel trowel finish with floor hardener
R.2.1.1.b - Concrete steel trowel finish (without floor hardener)

S PIG RECEIVER FOUNDATION TBBM TASIKMALAYA


Foundation size: (2.4W x 13L) m, Reinforced Concrete
Civil works
S.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

S.1.2 Earthworks & Sandbedding


S.1.2.a - Soil excavation for: pilecap fdt., and etc.
S.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
S.1.2.c - Sand bedding 50 mm thk & well compacted

S.1.3 Concrete
S.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
S.1.3.1.a - Concrete, total volume
S.1.3.1.b - Reinforcing bar, total weight

S.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
S.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

S.2 Architecture & Finishing work

S.2.1 Floor, Wall and Ceiling Finishes


S.2.1.1 Interior & Exterior floor finishes
S.2.1.1.a - Floor area, Concrete steel trowel finish with floor hardener

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 15 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

S.2.1.1.b - Concrete steel trowel finish (without floor hardener)

T PERIMETER DRAINAGE FOR NEW FACILITY TBBM LOMANIS

T.1 Open ditch type-U ditch size: (0.3W x 0.3~0.6 Depth avrg.) m, L = 355 m

T.1.1 Site preperation


- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area
T.1.2 Earthworks and Sandbedding
- Soil excavation
- Soil backfill and compaction
- Sandbedding 50 mm th'k & compaction
T.1.3 Brickwall, plaster & hollow concrete 1/2 Ø 300 mm
- Brickwall (include wet area) and thin bed mortar 1PC:2 Sand
- Wall plaster 15mm th'k and mortar 1PC : 2 Sand & Smooth surface

T.2 Concrete
T.2.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
T.2.1.1 - Concrete, total volume
T.2.1.2 - Reinforcing bar, total weight

T.2.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
T.2.2.1 - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

U FENCING AND GATE


Fencing and gates shall be meet the following requirements LK3 Pertaminawith a minimum height of
with an additional 0.3 meters (min.) overhang consisting of four stands of barbed wire placed at a 45
angle facing outward from the area to be secured Appurtenances: Braced bands, tension bars and te
bands shall be fabricated of 1/8-inch (3.175 mm) by 7/8-inch (22.22 mm) hot dip galvanized steel with
bolts and nuts (galvanized) in accordance with ASTM A123. Tension bars shall be 1/4 -inch (6.35 mm
(19.05 mm) galvanized steel bar in accordance with ASTM A153. Fabric ties shall be class I galvanize
no less than 9-gage.The total length of fence approximately = 2627 meters (minus opening gate span

U.1 CHAIN LINK FENCE


U.1.1 Main materials of fence:

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 16 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

Fence fabric 2.5 meters minimum high, heavy galvanized chain link fence, conforming to ASTM
U.1.1.a - Class 2, of 2-inches mesh 9-gage wire (0.148-inches) in diameter, with the top and bottom selve
twisted and barbed.
End corner and pull posts shall be 2½ -inches NPs (2.875" O.D) standard weight hot dip galvani
U.1.1.b - steel (Schedule 40) ASTM A120 and pull post shall be installed at interval not exceed 15-meters
fence installing and shall be reinforced inward brace with equal material and size.
Line posts 2-inches NPs (2.375" O.D) standard weight hot dip galvanized tubular steel (Schedul
U.1.1.c - A120.Line posts shall be spaced not more than 3-meters apart in the line of the fence.

Top rails shall conform to 1 ¼ -inches NPs (1.625" O.D) standard weight hot dip galvanized tubu
U.1.1.d - (Schedule 40) ASTM A120. ASTM A120.

4-strands of barbed wire shall consist of double stranded, 12 ½ -gage wire galvanized, ASTM A1
U.1.1.e - III, with 4-point barbs spaced 5-inches part.

Tension wire shall be 7-gage U.S. steel wire galvanized in accordance with ASTM A116 coatings
U.1.1.f - The tension wire shall be stretched near the bottom of the fence and attached at 700 mm maxim
intervals.
Appurtenances : Braced bands, tension bars and tension bands shall be fabricated of 1/8-inch (3
U.1.1.g - by 7/8-inch (22.22 mm) hot dip galvanized steel with carriage bolts and nuts (galvanized) in acco
with ASTM A123. Tension bars shall be 1/4 -inch (6.35 mm) by ¾-inch (19.05 mm) galvanized st
accordance with ASTM A153. Fabric ties shall be class I galvanized steel wire no less than 9-ga
U.1.2 Fencing Foundation:
U.1.2.1.a - Reinforced concrete K-225
U.1.2.1.b - Reinforcing bar
U.1.2.1.c - Lean concrete K-150

U.2 GATE
Gate material such as fabric, bolts, nuts, tension bars, and barbed wire shall be consistent with fenc
materials.Gate frame materials and size of the post as shown on the drawings welded at all corners
equipped 1 ¼ -inches NPs schedule 40 galvanized steel pipe cross or truss bracing and fitted with f
similar to that of the fence. Personnel gates shall be provided and 1.20 meters approximately clear
opening.Gates shall be hung on gate fittings as required. Hardware shall be thoroughly secured, pr
adjusted, and in good working order. Rollers, hinges, and cross bracing shall be adjusted so that ga
or roll level and are properly aligned to permit locking. Gate and plunger rod catches shall be install

U.2.1 1-unit Swing Gate, width opening: 5 meters


Fence fabric 2.5 meters minimum high, heavy galvanized chain link fence, conforming to ASTM
- Class 2, of 2-inches mesh 9-gage wire (0.148-inches) in diameter, with the top and bottom selve
twisted and barbed.
Swing gate frame and gate posts shall be 3½ -inches NPs (4" O.D) standard weight hot dip galv
- tubular steel (Schedule 40) ASTM A120

Horizontal brace1¼ -inches NPs (1.625" O.D) standard weight hot dip galvanized tubular steel (
- 40) ASTM A120. ASTM A120.

- Rollers, slide gates shall be furnished with heavy duty rollers 6" diameter (min.).

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 17 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

Rails, round bar ASTM A-36, include steel support 3x L-50x50x5 (min.), size diameter of rail as p
- manufacturer recommended.

U.2.2 CONCRETE PANEL FENCE


Concrete panel fence, compressive strength 28 days (min.) f'c = 18.675 Mpa (cylinder specement t
225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136, BjTD40 or equivale
stress) = 400 Mpa (min.)
Concrete panel fence 2.5m Hight, include columns & foundation with an additional 0.3 meters (m
- overhang consisting of four stands of barbed wire placed at a 45 degree angle facing outward fr
to be secured The panel size and thichkness shall refer to manufacturer recommended

V PIPE SUPPORT TYPE 1 (PS-001~PS-003, PS-010 ~PS-014)


Foundation size: (1W x 1L) m, Reinforced Concrete
V.1 Civil works
V.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

V.1.2 Earthworks & Sandbedding


V.1.2.a - Soil excavation for: pilecap fdt., and etc.
V.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
V.1.2.c - Sand bedding 50 mm thk & well compacted

V.1.3 Concrete
V.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
V.1.3.1.a - Concrete, total volume
V.1.3.1.b - Reinforcing bar, total weight

V.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
V.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

W PIPE SUPPORT TYPE 2 (PS-004, PS-007 ~PS-009)


Foundation size: (1W x 1.5L) m, Reinforced Concrete
W.1 Civil works
W.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 18 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

W.1.2 Earthworks & Sandbedding


W.1.2.a - Soil excavation for: pilecap fdt., and etc.
W.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
W.1.2.c - Sand bedding 50 mm thk & well compacted

W.1.3 Concrete
W.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
W.1.3.1.a - Concrete, total volume
W.1.3.1.b - Reinforcing bar, total weight

W.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
W.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

X PIPE SUPPORT TYPE 3 (PS-005 ~PS-006)


Foundation size: (1W x 2.4L) m, Reinforced Concrete
X.1 Civil works
X.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

X.1.2 Earthworks & Sandbedding


X.1.2.a - Soil excavation for: pilecap fdt., and etc.
X.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
X.1.2.c - Sand bedding 50 mm thk & well compacted

X.1.3 Concrete
X.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
X.1.3.1.a - Concrete, total volume
X.1.3.1.b - Reinforcing bar, total weight

X.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 19 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

X.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

Y PIPE SUPPORT TYPE 4 (PS-015, PS-017~PS-023, PS-025, PS-027, PS-033~PS-036)


Foundation size: (1.2W x 1.2L) m, Reinforced Concrete
Y.1 Civil works
Y.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

Y.1.2 Earthworks & Sandbedding


Y.1.2.a - Soil excavation for: pilecap fdt., and etc.
Y.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Y.1.2.c - Sand bedding 50 mm thk & well compacted

Y.1.3 Concrete
Y.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Y.1.3.1.a - Concrete, total volume
Y.1.3.1.b - Reinforcing bar, total weight

Y.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Y.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

Z PIPE SUPPORT TYPE 5 (PS-016, PS-024, PS-026, PS-028)


Foundation size: (1W x 1.4L) m, Reinforced Concrete
Z.1 Civil works
Z.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

Z.1.2 Earthworks & Sandbedding


Z.1.2.a - Soil excavation for: pilecap fdt., and etc.
Z.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Z.1.2.c - Sand bedding 50 mm thk & well compacted

Z.1.3 Concrete
Z.1.3.1 Reinforced Concrete (R.C) structure K-275

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 20 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Z.1.3.1.a - Concrete, total volume
Z.1.3.1.b - Reinforcing bar, total weight

Z.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Z.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

AA PIPE SUPPORT TYPE 6 (PS-029, PS-031, PS-032)


Foundation size: (1.2W x 1.2L) m, Reinforced Concrete
AA.1 Civil works
AA.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

AA.1.2 Earthworks & Sandbedding


AA.1.2.a - Soil excavation for: pilecap fdt., and etc.
AA.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
AA.1.2.c - Sand bedding 50 mm thk & well compacted

AA.1.3 Concrete
AA.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
AA.1.3.1.a - Concrete, total volume
AA.1.3.1.b - Reinforcing bar, total weight

AA.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
AA.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

AB PIPE SUPPORT TYPE 7 (PS-030)


Foundation size: (1.2W x 2.5L) m, Reinforced Concrete
AB.1 Civil works
AB.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 21 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

AB.1.2 Earthworks & Sandbedding


AB.1.2.a - Soil excavation for: pilecap fdt., and etc.
AB.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
AB.1.2.c - Sand bedding 50 mm thk & well compacted

AB.1.3 Concrete
AB.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
AB.1.3.1.a - Concrete, total volume
AB.1.3.1.b - Reinforcing bar, total weight

AB.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
AB.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

AC PIPE BRIDGE (LANGKAP LANCAR BRIDGE KP 79+326)


Foundation size: 2x(2.6W x 3.1L) m, Reinforced Concrete
AC.1 Civil works
AC.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

AC.1.2 Earthworks & Sandbedding


AC.1.2.a - Soil excavation for: pilecap fdt., and etc.
AC.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
AC.1.2.c - Sand bedding 50 mm thk & well compacted

AC.1.3 Pile Foundation

Comp. strength 28 days (min.) f'c = 50Mpa (cylinder spece.test) or K-600 kg/cm2 (cubical space

- Pre-cast PC pile dia 350 (mm)

AC.1.4 Concrete
AC.1.4.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
AC.1.4.1.a - Concrete, total volume

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 22 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

AC.1.4.1.b - Reinforcing bar, total weight

AC.1.4.2 Non
Lean/structural concretenon
leveling concrete, and lean concrete
structural K-150
concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mm
AC.1.4.2.a 40, SII-0136,
- Lean/ BjTP36
leveling or equivalent
concrete, Fy (Yield
50mm th'k understress) = 240 Mpa
& to achieve (min.)
levelling bottom R.C structure, total v

AC.2 Architecture & Finishing work

AC.2.1. Exterior floor finishes


AC.2.1.1 - Concrete steel trowel finish (without floor hardener)

AD PIPE BRIDGE (AWIPARI BRIDGE KP 121+600)


Foundation size: 2x(2.6W x 3.1L) m, Reinforced Concrete
AD.1 Civil works
AD.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

AD.1.2 Earthworks & Sandbedding


AD.1.2.a - Soil excavation for: pilecap fdt., and etc.
AD.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
AD.1.2.c - Sand bedding 50 mm thk & well compacted

AD.1.3 Pile Foundation

Comp. strength 28 days (min.) f'c = 50Mpa (cylinder spece.test) or K-600 kg/cm2 (cubical space

- Pre-cast PC pile dia 350 (mm)

AD.1.4 Concrete
AD.1.4.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
AD.1.4.1.a - Concrete, total volume
AD.1.4.1.b - Reinforcing bar, total weight

AD.1.4.2 Non
Lean/structural concretenon
leveling concrete, and lean concrete
structural K-150
concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mm
AD.1.4.2.a 40, SII-0136,
- Lean/ BjTP36
leveling or equivalent
concrete, Fy (Yield
50mm th'k understress) = 240 Mpa
& to achieve (min.)
levelling bottom R.C structure, total v

AD.2 Architecture & Finishing work

AD.2.1. Exterior floor finishes

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 23 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

AD.2.1.1 - Concrete steel trowel finish (without floor hardener)

AE PIPE BRIDGE (CONDONG BRIDGE KP 124+000)


Foundation size: 2x(2.6W x 3.1L) m, Reinforced Concrete
AE.1 Civil works
AE.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

AE.1.2 Earthworks & Sandbedding


AE.1.2.a - Soil excavation for: pilecap fdt., and etc.
AE.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
AE.1.2.c - Sand bedding 50 mm thk & well compacted

AE.1.3 Pile Foundation

Comp. strength 28 days (min.) f'c = 50Mpa (cylinder spece.test) or K-600 kg/cm2 (cubical space

- Pre-cast PC pile dia 350 (mm)

AE.1.4 Concrete
AE.1.4.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
AE.1.4.1.a - Concrete, total volume
AE.1.4.1.b - Reinforcing bar, total weight

AE.1.4.2 Non
Lean/structural concretenon
leveling concrete, and lean concrete
structural K-150
concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mm
AE.1.4.2.a 40, SII-0136,
- Lean/ BjTP36
leveling or equivalent
concrete, Fy (Yield
50mm th'k understress) = 240 Mpa
& to achieve (min.)
levelling bottom R.C structure, total v

AE.2 Architecture & Finishing work

AE.2.1. Exterior floor finishes


AE.2.1.1 - Concrete steel trowel finish (without floor hardener)

AF PIPE BRIDGE (CINTAPADA BRIDGE KP 125+440)


Foundation size: 2x(2.6W x 3.6L) m, Reinforced Concrete
AF.1 Civil works
AF.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

AF.1.2 Earthworks & Sandbedding

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 24 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

AF.1.2.a - Soil excavation for: pilecap fdt., and etc.


AF.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
AF.1.2.c - Sand bedding 50 mm thk & well compacted

AF.1.3 Pile Foundation

Comp. strength 28 days (min.) f'c = 50Mpa (cylinder spece.test) or K-600 kg/cm2 (cubical space

- Pre-cast PC pile dia 350 (mm)

AF.1.4 Concrete
AF.1.4.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
AF.1.4.1.a - Concrete, total volume
AF.1.4.1.b - Reinforcing bar, total weight

AF.1.4.2 Non
Lean/structural concretenon
leveling concrete, and lean concrete
structural K-150
concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mm
AF.1.4.2.a 40, SII-0136,
- Lean/ BjTP36
leveling or equivalent
concrete, Fy (Yield
50mm th'k understress) = 240 Mpa
& to achieve (min.)
levelling bottom R.C structure, total v

AF.2 Architecture & Finishing work

AF.2.1. Exterior floor finishes


AF.2.1.1 - Concrete steel trowel finish (without floor hardener)

AG WALKWAY PLATFORM FOUNDATION


Foundation size: 2x(0.8W x 1.6L) m, Reinforced Concrete
AG.1 Civil works
AG.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

AG.1.2 Earthworks & Sandbedding


AG.1.2.a - Soil excavation for: pilecap fdt., and etc.
AG.1.2.b - Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
AG.1.2.c - Sand bedding 50 mm thk & well compacted

AG.1.3 Concrete
AG.1.3.1 Reinforced Concrete (R.C) structure K-275
Structural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (c
specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0
BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 25 of 358
SUMMARY M.T.O
CIVIL, ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS

NO ITEM DESCRIPTION WORKS

AG.1.3.1.a - Concrete, total volume


AG.1.3.1.b - Reinforcing bar, total weight

AG.1.3.2 Non structural concrete and lean concrete K-150


Lean/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cy
specement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-6
40, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
AG.1.3.2.a - Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total v

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 26 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

HOR BLOCK FOUNDATION (2 UNIT)


dation size: (1.9W x 2.2 L) m, Reinforced Concrete (2 unit)

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding,


Soil excavation for: pilecap fdt, and etc.
Soil backfill and compaction (from soil excavation mat'l)
Sand bedding 50 mm thk & well compacted

e Foundation

mp. strength 28 days (min.) f'c = 40Mpa (cylinder spece.test) or K-500 kg/cm2 (cubical spacement test)

Pre-cast PC pile square 200 x 200 (mm) solid

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

P SHELTER FOUNDATION
er size: (10W x 30L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks, Sandbedding, Base course fill and stone masonry foundation


Soil excavation for: pilecap fdt, and etc.

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 27 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Soil backfill and compaction (from soil excavation mat'l)


Sand bedding 50 mm thk & well compacted

e Foundation

mp. strength 28 days (min.) f'c = 40Mpa (cylinder spece.test) or K-500 kg/cm2 (cubical spacement test)

Pre-cast PC pile square 200 x 200 (mm) solid

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

inforced Concrete (R.C) structure K-225


ble trench & cable duct bank encasement concrete, compressive strength 28 days (min.) f'c = 18.675
pa (cylinder specement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60,
-0136, BjTD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

cossoris Works
ble trench steel plate cover
Steel frame L50x50x5 for cover plate & embedded plate, Structural steel shape and plate: ASTM-A36 or
JIS G3101 SS, Alkyd paint finish surface.
Checker plate floor cover 3mm th'k (min.) ASTM A786 and hotdip galvanized finish surface

ble Duct bank PVC conduit


PVC pipe slevee Dia.6" AW

oor, wall and Ceiling Finishes


oor finishes
Concrete steel trowel finish with floor hardener
Concrete steel trowel finish (without floor hardener)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 28 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

ITO METER SHELTER FOUNDATION (2 UNIT)


er size: 2 x(2.75W x 3L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks, Sandbedding, Base course fill and stone masonry foundation


Soil excavation for: pilecap fdt, and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

oor, wall and Ceiling Finishes


oor finishes
Concrete steel trowel finish with floor hardener
Concrete steel trowel finish (without floor hardener)

ERING SHELTER FOUNDATION TBBM LOMANIS


er size: (6W x 17L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 29 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Concrete steel trowel finish with floor hardener
Concrete steel trowel finish (without floor hardener)

ERING SHELTER FOUNDATION TBBM TASIKMALAYA


er size: (6W x 17L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 30 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work


oor, Wall and Ceiling Finishes
erior & Exterior floor finishes
Concrete steel trowel finish with floor hardener
Concrete steel trowel finish (without floor hardener)

VALVE SHELTER FOUNDATION CILACAP (KP 0+009)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 31 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

VALVE SHELTER FOUNDATION SITINGIL-1 (KP 35+140)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION SITINGIL-2 (KP 35+290)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 32 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION TARISI (KP 69+563)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 33 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION CINTARATU(KP 69+888)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 34 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

erior & Exterior floor finishes


Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION DESA REJA SARI I(KP 77+752)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION DESA REJA SARI II(KP 77+800)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 35 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION BRIDGE LANGKAP LANCAR I (KP 79+326)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 36 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION BRIDGE LANGKAP LANCAR II (KP 79+419)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 37 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION BEBER (KP 102+200)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION TASIK I (KP 126+853)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 38 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

VALVE SHELTER FOUNDATION TASIK II (KP 126+944)


er size: (5W x 12L) m, Steel Structure

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 39 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Box Valve floor area, gravel 100 mm thk
Gravel 100 mm thk

AUNCHER FOUNDATION TBBM LOMANIS


dation size: (2.4W x 9.67L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 40 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Floor area, Concrete steel trowel finish with floor hardener
Concrete steel trowel finish (without floor hardener)

ECEIVER FOUNDATION TBBM TASIKMALAYA


dation size: (2.4W x 13L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

tecture & Finishing work

oor, Wall and Ceiling Finishes


erior & Exterior floor finishes
Floor area, Concrete steel trowel finish with floor hardener

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 41 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Concrete steel trowel finish (without floor hardener)

METER DRAINAGE FOR NEW FACILITY TBBM LOMANIS

ditch type-U ditch size: (0.3W x 0.3~0.6 Depth avrg.) m, L = 355 m

reperation
tallation of bowplank, wood stiffener, points building coordinat and leveling survey area
works and Sandbedding
il excavation
il backfill and compaction
ndbedding 50 mm th'k & compaction
wall, plaster & hollow concrete 1/2 Ø 300 mm
ckwall (include wet area) and thin bed mortar 1PC:2 Sand
all plaster 15mm th'k and mortar 1PC : 2 Sand & Smooth surface

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

ING AND GATE


and gates shall be meet the following requirements LK3 Pertaminawith a minimum height of 2.5 meters
additional 0.3 meters (min.) overhang consisting of four stands of barbed wire placed at a 45 degree
cing outward from the area to be secured Appurtenances: Braced bands, tension bars and tension
hall be fabricated of 1/8-inch (3.175 mm) by 7/8-inch (22.22 mm) hot dip galvanized steel with carriage
d nuts (galvanized) in accordance with ASTM A123. Tension bars shall be 1/4 -inch (6.35 mm) by ¾-inch
mm) galvanized steel bar in accordance with ASTM A153. Fabric ties shall be class I galvanized steel wire
han 9-gage.The total length of fence approximately = 2627 meters (minus opening gate span).

N LINK FENCE
materials of fence:

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 42 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

nce fabric 2.5 meters minimum high, heavy galvanized chain link fence, conforming to ASTM A392,
ass 2, of 2-inches mesh 9-gage wire (0.148-inches) in diameter, with the top and bottom selvedges
sted and barbed.
d corner and pull posts shall be 2½ -inches NPs (2.875" O.D) standard weight hot dip galvanized tubular
el (Schedule 40) ASTM A120 and pull post shall be installed at interval not exceed 15-meters as long
nce installing and shall be reinforced inward brace with equal material and size.
e posts 2-inches NPs (2.375" O.D) standard weight hot dip galvanized tubular steel (Schedule 40) ASTM
20.Line posts shall be spaced not more than 3-meters apart in the line of the fence.
p rails shall conform to 1 ¼ -inches NPs (1.625" O.D) standard weight hot dip galvanized tubular steel
chedule 40) ASTM A120. ASTM A120.
strands of barbed wire shall consist of double stranded, 12 ½ -gage wire galvanized, ASTM A121, Class
with 4-point barbs spaced 5-inches part.
nsion wire shall be 7-gage U.S. steel wire galvanized in accordance with ASTM A116 coatings class III.
e tension wire shall be stretched near the bottom of the fence and attached at 700 mm maximal of
ervals.
purtenances : Braced bands, tension bars and tension bands shall be fabricated of 1/8-inch (3.175 mm)
7/8-inch (22.22 mm) hot dip galvanized steel with carriage bolts and nuts (galvanized) in accordance
h ASTM A123. Tension bars shall be 1/4 -inch (6.35 mm) by ¾-inch (19.05 mm) galvanized steel bar in
cordance with ASTM A153. Fabric ties shall be class I galvanized steel wire no less than 9-gage.
ng Foundation:
inforced concrete K-225
inforcing bar
an concrete K-150

material such as fabric, bolts, nuts, tension bars, and barbed wire shall be consistent with fence
ials.Gate frame materials and size of the post as shown on the drawings welded at all corners with
ped 1 ¼ -inches NPs schedule 40 galvanized steel pipe cross or truss bracing and fitted with fabric
r to that of the fence. Personnel gates shall be provided and 1.20 meters approximately clear
ng.Gates shall be hung on gate fittings as required. Hardware shall be thoroughly secured, properly
ed, and in good working order. Rollers, hinges, and cross bracing shall be adjusted so that gates swing
level and are properly aligned to permit locking. Gate and plunger rod catches shall be installed.

Swing Gate, width opening: 5 meters


nce fabric 2.5 meters minimum high, heavy galvanized chain link fence, conforming to ASTM A392,
ass 2, of 2-inches mesh 9-gage wire (0.148-inches) in diameter, with the top and bottom selvedges
sted and barbed.
wing gate frame and gate posts shall be 3½ -inches NPs (4" O.D) standard weight hot dip galvanized
bular steel (Schedule 40) ASTM A120
rizontal brace1¼ -inches NPs (1.625" O.D) standard weight hot dip galvanized tubular steel (Schedule
) ASTM A120. ASTM A120.
llers, slide gates shall be furnished with heavy duty rollers 6" diameter (min.).

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 43 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

ils, round bar ASTM A-36, include steel support 3x L-50x50x5 (min.), size diameter of rail as per
anufacturer recommended.

CRETE PANEL FENCE


ete panel fence, compressive strength 28 days (min.) f'c = 18.675 Mpa (cylinder specement test) or K-
g/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136, BjTD40 or equivalent Fy (Yield
) = 400 Mpa (min.)
ncrete panel fence 2.5m Hight, include columns & foundation with an additional 0.3 meters (min.)
erhang consisting of four stands of barbed wire placed at a 45 degree angle facing outward from the area
be secured The panel size and thichkness shall refer to manufacturer recommended

SUPPORT TYPE 1 (PS-001~PS-003, PS-010 ~PS-014)


dation size: (1W x 1L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

SUPPORT TYPE 2 (PS-004, PS-007 ~PS-009)


dation size: (1W x 1.5L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 44 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

SUPPORT TYPE 3 (PS-005 ~PS-006)


dation size: (1W x 2.4L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 45 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

SUPPORT TYPE 4 (PS-015, PS-017~PS-023, PS-025, PS-027, PS-033~PS-036)


dation size: (1.2W x 1.2L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

SUPPORT TYPE 5 (PS-016, PS-024, PS-026, PS-028)


dation size: (1W x 1.4L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 46 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

SUPPORT TYPE 6 (PS-029, PS-031, PS-032)


dation size: (1.2W x 1.2L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

SUPPORT TYPE 7 (PS-030)


dation size: (1.2W x 2.5L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 47 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

BRIDGE (LANGKAP LANCAR BRIDGE KP 79+326)


dation size: 2x(2.6W x 3.1L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

e Foundation

mp. strength 28 days (min.) f'c = 50Mpa (cylinder spece.test) or K-600 kg/cm2 (cubical spacement test)

Pre-cast PC pile dia 350 (mm)

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 48 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Reinforcing bar, total weight

n structural
an/ concretenon
leveling concrete, and lean concrete
structural K-150
concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, Lean/
SII-0136, BjTP36
leveling or equivalent
concrete, Fy (Yield
50mm th'k understress) = 240 Mpa
& to achieve (min.)
levelling bottom R.C structure, total volume

tecture & Finishing work

terior floor finishes


Concrete steel trowel finish (without floor hardener)

BRIDGE (AWIPARI BRIDGE KP 121+600)


dation size: 2x(2.6W x 3.1L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

e Foundation

mp. strength 28 days (min.) f'c = 50Mpa (cylinder spece.test) or K-600 kg/cm2 (cubical spacement test)

Pre-cast PC pile dia 350 (mm)

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural
an/ concretenon
leveling concrete, and lean concrete
structural K-150
concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, Lean/
SII-0136, BjTP36
leveling or equivalent
concrete, Fy (Yield
50mm th'k understress) = 240 Mpa
& to achieve (min.)
levelling bottom R.C structure, total volume

tecture & Finishing work

terior floor finishes

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 49 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Concrete steel trowel finish (without floor hardener)

BRIDGE (CONDONG BRIDGE KP 124+000)


dation size: 2x(2.6W x 3.1L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

e Foundation

mp. strength 28 days (min.) f'c = 50Mpa (cylinder spece.test) or K-600 kg/cm2 (cubical spacement test)

Pre-cast PC pile dia 350 (mm)

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural
an/ concretenon
leveling concrete, and lean concrete
structural K-150
concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, Lean/
SII-0136, BjTP36
leveling or equivalent
concrete, Fy (Yield
50mm th'k understress) = 240 Mpa
& to achieve (min.)
levelling bottom R.C structure, total volume

tecture & Finishing work

terior floor finishes


Concrete steel trowel finish (without floor hardener)

BRIDGE (CINTAPADA BRIDGE KP 125+440)


dation size: 2x(2.6W x 3.6L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 50 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Soil excavation for: pilecap fdt., and etc.


Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

e Foundation

mp. strength 28 days (min.) f'c = 50Mpa (cylinder spece.test) or K-600 kg/cm2 (cubical spacement test)

Pre-cast PC pile dia 350 (mm)

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-275 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)
Concrete, total volume
Reinforcing bar, total weight

n structural
an/ concretenon
leveling concrete, and lean concrete
structural K-150
concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, Lean/
SII-0136, BjTP36
leveling or equivalent
concrete, Fy (Yield
50mm th'k understress) = 240 Mpa
& to achieve (min.)
levelling bottom R.C structure, total volume

tecture & Finishing work

terior floor finishes


Concrete steel trowel finish (without floor hardener)

KWAY PLATFORM FOUNDATION


dation size: 2x(0.8W x 1.6L) m, Reinforced Concrete

e preperation
Installation of bowplank, wood stiffener, points building coordinat and leveling survey area

rthworks & Sandbedding


Soil excavation for: pilecap fdt., and etc.
Soil backfill and compaction (from soil excavation mat'l) and achieve to floor elevation
Sand bedding 50 mm thk & well compacted

inforced Concrete (R.C) structure K-275


uctural Concrete building & foundation, compressive strength 28 days (min.) f'c = 22.8 Mpa (cylinder
ecement test) or K-225 kg/cm2 (cub.spac.test), Reinforcing-bar , ASTM A-615 Grade 60, SII-0136,
TD40 or equivalent Fy (Yield stress) = 400 Mpa (min.)

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 51 of 358
SUMMARY M.T.O
ARCHITECHTURE AND PLUMBING FOR PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

ITEM DESCRIPTION WORKS

Concrete, total volume


Reinforcing bar, total weight

n structural concrete and lean concrete K-150


an/ leveling concrete, non structural concrete, comp. strength 28 days (min.) f'c = 12 Mpa (cylinder
ecement test) or K-150 kg/cm2 (cub.spac.test), Reinforcing-bar less than 13 mmØ, ASTM A-615 Grade
, SII-0136, BjTP36 or equivalent Fy (Yield stress) = 240 Mpa (min.)
Lean/ leveling concrete, 50mm th'k under & to achieve levelling bottom R.C structure, total volume

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 52 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

40.40 m'

110.05 m3
98.68 m3
0.50 m3

96.00 m

25.08 m3
1,956.24 kg

0.92 m3

192.80 m'

416.91 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 53 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
298.63 m3
23.13 m3

144.00 m

128.44 m3
11,468.75 kg

16.51 m3
1,815.50 kg

25.43 m3

1,343.85 kg

31.28 m2

2.43 m

193.04 m2
121.20 m2

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 54 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

55.60 m'

28.03 m3
24.09 m3
3.83 m3

11.84 m3
1,123.24 kg

3.43 m3

18.88 m2
45.60 m2

120.80 m'

70.13 m3
37.84 m3
9.66 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 55 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

42.64 m3
4,472.99 kg

9.89 m3

74.21 m2
72.60 m2

120.80 m'

70.13 m3
37.84 m3
9.66 m3

42.64 m3
4,472.99 kg

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 56 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

9.89 m3

74.21 m2
72.60 m2

131.80 m'

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 57 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

131.80 m'

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

131.80 m'

75.50 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 58 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

131.80 m'

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 59 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

1.72 m3

60.00 m2
78.60 m2

131.80 m'

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

1.72 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 60 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

60.00 m2
78.60 m2

131.80 m'

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

131.80 m'

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 61 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

131.80 m'

75.50 m3
57.33 m3
1.97 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 62 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

131.80 m'

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 63 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
1.72 m3

60.00 m2
78.60 m2

131.80 m'

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 64 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

131.80 m'

75.50 m3
57.33 m3
1.97 m3

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

131.80 m'

75.50 m3
57.33 m3
1.97 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 65 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

14.13 m3
2,178.84 kg

1.72 m3

60.00 m2
78.60 m2

73.48 m'

11.70 m3
8.67 m3
1.50 m3

7.92 m3
707.77 kg

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 66 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

0.81 m3

10.80 m2
41.96 m2

86.80 m'

11.70 m3
8.29 m3
1.91 m3

7.20 m3
695.48 kg

1.05 m3

15.60 m2

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 67 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
51.43 m2

355.00 m'

113.60 m3
42.60 m3
10.65 m3

639.00 m2
958.50 m2

12.54 m3
150.48 kg

12.43 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 68 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

365 m2

32 m

117 m

146 m

584 m

584 m

1 Lot

4.06 m3
865.20 kg
0.84 m3

14.00 m2

30.20 m

13.59 m

2.00 Ea

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 69 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

2.00 Set

90.00 m

254.40 m'

18.86 m3
14.59 m3
1.16 m3

3.84 m3
579.84 kg

0.48 m3

131.20 m'

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 70 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

12.91 m3
9.76 m3
0.30 m3

2.88 m3
382.32 kg

0.35 m3

69.20 m'

9.59 m3
7.09 m3
0.24 m3

2.30 m3
275.33 kg

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 71 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
0.28 m3

470.40 m'

43.48 m3
34.18 m3
1.01 m3

7.08 m3
1,063.61 kg

1.18 m3

134.40 m'

12.22 m3
9.45 m3
0.28 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 72 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

2.32 m3
264.50 kg

0.33 m3

100.80 m'

9.32 m3
7.32 m3
0.22 m3

1.77 m3
267.18 kg

0.25 m3

36.20 m'

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 73 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT

5.71 m3
4.35 m3
0.15 m3

1.05 m3
124.94 kg

0.17 m3

80.40 m'

32.48 m3
22.97 m3
4.28 m3

40.00 m

18.09 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 74 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
1,920.00 kg

4.27 m3

69.56 m2

80.40 m'

32.48 m3
22.97 m3
4.28 m3

40.00 m

18.09 m3
1,920.00 kg

4.27 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 75 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
69.56 m2

80.40 m'

32.48 m3
22.99 m3
4.07 m3

40.00 m

18.09 m3
1,920.00 kg

4.27 m3

69.56 m2

82.40 m'

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 76 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
37.12 m3
26.31 m3
4.41 m3

72.00 m

19.64 m3
2,040.46 kg

4.61 m3

69.56 m2

67.20 m'

4.66 m3
3.58 m3
4.41 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 77 of 358
TASIKMALAYA)

TOTAL QUANTITY

QTY UNIT
1.42 m3
140.82 kg

0.32 m3

__________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 ________________________________________ Rev. 1
Att. A Page 78 of 358
DETAIL MTO PILE FOUNDATION
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

Typ.pilecap or Nos. point pile per Total points of Embedded pile (m)
Found.Qt'y pilecap or pile from FGL PC pile Sqr.200
No Description of pile foundation foundation Total length pile
Nos. unit (m)

ANCHOR BLOCK FOUNDATION (2


A UNIT)
A.1.3 Pile Foundation for:
Pilecap-4pile 4 Ea 4 16 6.00 96.00

PUMP AND BOOSTER FOUNDATION


B

B.1.3 Pile Foundation for:


Pilecap-6pile 4 Ea 6 24 6.00 144.00

PIPE BRIDGE (LANGKAP LANCAR


C BRIDGE KP. 79+326 ) FOUNDATION

C.1.3 Pile Foundation for:


Pilecap-4pile 2 Ea 4 8 5.00 -

PIPE BRIDGE (AWIPARI BRIDGE KP.


D 121+600 ) FOUNDATION

D.1.3 Pile Foundation for:


Pilecap-4pile 2 Ea 4 8 5.00 -

PIPE BRIDGE (CONDONG BRIDGE KP.


E 124+000 ) FOUNDATION

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
__________________________________
Att. B Page 79 of 358
DETAIL MTO PILE FOUNDATION
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

Typ.pilecap or Nos. point pile per Total points of Embedded pile (m)
Found.Qt'y pilecap or pile from FGL PC pile Sqr.200
No Description of pile foundation foundation Total length pile
Nos. unit (m)
E.1.3 Pile Foundation for:
Pilecap-4pile 2 Ea 4 8 5.00 -

PIPE BRIDGE (CINTAPADA BRIDGE KP.


F 125+440 ) FOUNDATION

F.1.3 Pile Foundation for:


Pilecap-4pile 2 Ea 4 8 9.00 -
SUB TOTAL 240.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
__________________________________
Att. B Page 80 of 358
PC pile Dia.350

Total length pile


(m)

40.00

40.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
__________________________________
Att. B Page 81 of 358
PC pile Dia.350

Total length pile


(m)

40.00

72.00
192.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
__________________________________
Att. B Page 82 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
A ANCHOR BLOCK FOUNDATION
Foundation size: (1.9W x 2.2 L) m, Reinforced Concrete (2 unit)
A.1 Civil works
A.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 2 Lot 20.20
A.1.2 Earthworks
A.1.2.a - Soil excavation for:
- Pilecap foundation, size of pilecap: (1.9Wx2.2Lx1.5Thk.) m, depth=2.2m under FGL 2 Ea 3.65
- Sandbeding & lean conc. Depth = 2.3m under FGL 2 Ea 3.65

Volume structure & foundation under FGL


- Anchor Block Foundation, size 1.9Wx2.2Lx1.3Thk 2 Ea 2.20
Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 2 Ea 2.40

A.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

A.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50mm Thk. Under footing fdn. 2 Ea 2.40

B PUMP SHELTER FOUNDATION


Shelter size: (10W x 30L) m, Steel Structure

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 83 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
B.1 Civil works
B.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 192.80
B.1.2 Earthworks
B.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (2.5Wx2.5Lx0.3Thk.) m, depth=1.8 m under FGL 12 Ea 3.60
- Cable trench, inside size: (0.65W x 0.8D) m, depth= 0.6 m under FGL 4 Ea 5.60
- Cable trench, inside size: (1.12W x 1.14D)m, depth= 1 m under FGL 4 Ea 6.00
- Duct bank, size: as per dwg 1 Ea 2.70
- Grade beam (300Wx500D) mm, depth= 0.3 m under FGL 2 Ea 30.00
- ditto- 4 Ea 10.00
- Sandbeding & lean conc.under pump fdn Type-1 size:(9.35Lx2.6W)m , depth= 0.1 m under FGL 1 Ea 9.55

- Sandbeding & lean conc.under pump fdn Type-2 size:(6.6Lx2.2W)m , depth=0.1 m under FGL 3 Ea 6.80

- Sandbeding & lean conc.under pump fdn Type-3 size:(1.5Lx1.5W)m , depth=0.1 m under FGL 3 Ea 1.70

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (2.5Wx2.5Lx0.3Thk.) m, depth=1.8 m under FGL 12 Ea 2.50
- Grade beam (300Wx500D) mm, depth=1m under FGL 2 Ea 30.00
- ditto- 4 Ea 10.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 84 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Pedestal (0.4Wx0.4D) m, depth=1.5 m under FGL 12 Ea 0.40
- Cable trench, inside size: (0.65W x 0.8D) m, depth= 0.6 m under FGL 4 Ea 5.60
- Cable trench, inside size: (1.12W x 1.14D)m, depth= 1 m under FGL 4 Ea 6.00
- Duct bank, size: as per dwg 1 Ea 2.70
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 12 Ea 2.70
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 30.00
- ditto- 4 Ea 10.00
- Sand bedding & lean conc. Total thk 100mm u/ cable trench, inside size: (0.65W x 0.8D)m 4 Ea 5.60
- Sand bedding & lean conc. Total thk 100mm u/ cable trench, inside size: (1.12W x 1.14D)m 4 Ea 6.00
- Sand bedding & lean conc. Total thk. 100 mm under Duct bank 1 Ea 2.70
- Sandbeding & lean conc.100mm total thk. under pump fdn Type-1 size:(9.35Lx2.6W)m 1 Ea 9.45
- Sandbeding & lean conc.100mm total thk. under pump fdn Type-2 size:(6.6Lx2.2W)m 3 Ea 6.70
- Sandbeding & lean conc.100mm total thk. under pump fdn Type-3 size:(1.5Lx1.5W)m 3 Ea 1.60

B.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

B.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 12 Ea 2.70
- ditto-, under concrete floor incl'd under pump fdn. (minus u/ cable trench & duct bank) 1 Ea Area (m2) =
- ditto-, under concrete floor footpath/ terrace (minus Ramp) 2 Ea 32.40
ditto- 2 Ea 13.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 85 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
B.2 Architecture & Finishing work
B.2.1 FloorPump
Finishes
room floor area (minus pump fdn & cable trench), Concrete steel trowel finish with floor
B.2.1.a - hardener 1 Set Area (m2) =

B.2.1.b - Concrete steel trowel finish


terrace/ footpath 2 Set 32.40
- ditto- 2 Set 10.00

C DENSITO METER SHELTER FOUNDATION (2 UNIT)


Shelter size: 2 x(2.75W x 3L) m, Steel Structure
C.1 Civil works
C.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 2 Lot 27.80
C.1.2 Earthworks
C.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (0.7Wx0.7Lx0.25Thk.) m, depth=0.7 m under FGL 8 Ea 1.25
- Grade beam (200Wx300D) mm, depth= 0.2 m under FGL 4 Ea 3.00
- ditto- 4 Ea 2.75
- Sandbeding & lean conc.under footing , depth= 0.1 m under FGL 8 Ea 0.90

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 86 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume structure & foundation under FGL
- Footing foundation, size of foundation: (0.7Wx0.7Lx0.25Thk.) m, depth=0.7 m under FGL 8 Ea 0.70
- Grade beam (200Wx300D) mm, depth= 0.2 m under FGL 4 Ea 3.00
- ditto- 4 Ea 2.75
- Pedestal (0.225Wx0.3D) m, depth=0.45 m under FGL 8 Ea 0.23
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 0.90
- Sand bedding & lean conc. Total thk 100mm under grade beam 4 Ea 3.00
- ditto- 4 Ea 2.75

C.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

C.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 0.90
- ditto-, under concrete floor 2 Ea Area (m2) =
- ditto-, under concrete floor footpath/ terrace 4 Ea 5.40
ditto- 4 Ea 5.75

C.2 Architecture & Finishing work


C.2.1 Floor Finishes
C.2.1.a - Floor area 2 Set Area (m2) =

C.2.1.b - Concrete steel trowel finish

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 87 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
terrace/ footpath 4 Set 5.40
- ditto- 4 Set 2.75

D METERING SHELTER FOUNDATION TBBM LOMANIS


Shelter size: (6W x 17L) m, Steel Structure
D.1 Civil works
D.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 120.80
D.1.2 Earthworks
D.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.5Wx1.5Lx0.3Thk.) m, depth=1.2 m under FGL 8 Ea 2.30
- Grade beam (250Wx400D) mm, depth= 0.4 m under FGL 2 Ea 17.00
- ditto- 2 Ea 6.00
- Sandbeding & lean conc.under metering fdn size:(14Lx2.4W)m , depth= 0.1 m under FGL 1 Ea 14.20

- Sandbeding & lean conc.under footing , depth= 0.1 m under FGL 8 Ea 1.70

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.5Wx1.5Lx0.3Thk.) m, depth=1.2 m under FGL 8 Ea 1.50
- Grade beam (250Wx400D) mm, depth= 0.4 m under FGL 2 Ea 17.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 88 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- ditto- 2 Ea 6.00
- Pedestal (0.3Wx0.3D) m, depth=0.9m under FGL 8 Ea 0.30
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.70
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 17.00
- ditto- 2 Ea 6.00
- Sandbeding & lean conc.under metering fdn size:(14Lx2.4W)m , depth= 0.1 m under FGL 1 Ea 14.10

D.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

D.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.70
- ditto-, under concrete floor incl'd under metering fdn. 1 Ea Area (m2) =
- ditto-, under concrete floor footpath/ terrace (minus Ramp) 2 Ea 19.40
ditto- 2 Ea 9.00

D.2 Architecture & Finishing work


D.2.1 Floor Finishes
D.2.1.a - Metering room floor area (minus metering fdn), Concrete steel trowel finish with floor hardener 1 Set Area (m2) =

D.2.1.b - Concrete steel trowel finish


terrace/ footpath 2 Set 19.40
- ditto- 2 Set 6.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 89 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

E METERING SHELTER FOUNDATION TBBM TASIKMALAYA


Shelter size: (6W x 17L) m, Steel Structure
E.1 Civil works
E.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 120.80
E.1.2 Earthworks
E.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.5Wx1.5Lx0.3Thk.) m, depth=1.2 m under FGL 8 Ea 2.30
- Grade beam (250Wx400D) mm, depth= 0.4 m under FGL 2 Ea 17.00
- ditto- 2 Ea 6.00
- Sandbeding & lean conc.under metering fdn size:(14Lx2.4W)m , depth= 0.1 m under FGL 1 Ea 14.20

- Sandbeding & lean conc.under footing , depth= 0.1 m under FGL 8 Ea 1.70

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.5Wx1.5Lx0.3Thk.) m, depth=1.2 m under FGL 8 Ea 1.50
- Grade beam (250Wx400D) mm, depth= 0.4 m under FGL 2 Ea 17.00
- ditto- 2 Ea 6.00
- Pedestal (0.3Wx0.3D) m, depth=0.9m under FGL 8 Ea 0.30

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 90 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.70
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 17.00
- ditto- 2 Ea 6.00
- Sandbeding & lean conc.under metering fdn size:(14Lx2.4W)m , depth= 0.1 m under FGL 1 Ea 14.10

E.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

E.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.70
- ditto-, under concrete floor incl'd under metering fdn. 1 Ea Area (m2) =
- ditto-, under concrete floor footpath/ terrace (minus Ramp) 2 Ea 19.40
ditto- 2 Ea 9.00

E.2 Architecture & Finishing work


E.2.1 Floor Finishes
E.2.1.a - Metering room floor area (minus metering fdn), Concrete steel trowel finish with floor hardener 1 Set Area (m2) =

E.2.1.b - Concrete steel trowel finish


terrace/ footpath 2 Set 19.40
- ditto- 2 Set 6.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 91 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
F BOX VALVE SHELTER FOUNDATION CILACAP (KP 0+009)
Shelter size: (5W x 12L) m, Steel Structure
F.1 Civil works
F.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
F.1.2 Earthworks
F.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 92 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

F.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

F.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 93 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
F.2 Architecture & Finishing work
F.2.1 Floor Finishes
F.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

F.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

G BOX VALVE SHELTER FOUNDATION SITINGIL-1 (KP 35+140)


Shelter size: (5W x 12L) m, Steel Structure
G.1 Civil works
G.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
G.1.2 Earthworks
G.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 94 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 95 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

G.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

G.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

G.2 Architecture & Finishing work


G.2.1 Floor Finishes
G.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

G.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

H BOX VALVE SHELTER FOUNDATION SITINGIL-2 (KP 35+290)


Shelter size: (5W x 12L) m, Steel Structure
H.1 Civil works
H.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
H.1.2 Earthworks
H.1.2.a - Soil excavation for:

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 96 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 97 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

H.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

H.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

H.2 Architecture & Finishing work


H.2.1 Floor Finishes
H.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

H.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 98 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

I BOX VALVE SHELTER FOUNDATION TARISI (KP 69+563)


Shelter size: (5W x 12L) m, Steel Structure
I.1 Civil works
I.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
I.1.2 Earthworks
I.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 99 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

I.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

I.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 100 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

I.2 Architecture & Finishing work


I.2.1 Floor Finishes
I.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

I.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

J BOX VALVE SHELTER FOUNDATION CINTARATU(KP 69+888)


Shelter size: (5W x 12L) m, Steel Structure
J.1 Civil works
J.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
J.1.2 Earthworks
J.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 101 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 102 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- ditto- 2 Ea 9.00

J.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

J.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

J.2 Architecture & Finishing work


J.2.1 Floor Finishes
J.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

J.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

K BOX VALVE SHELTER FOUNDATION DESA REJA SARI I(KP 77+752)


Shelter size: (5W x 12L) m, Steel Structure
K.1 Civil works
K.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
K.1.2 Earthworks

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 103 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
K.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 104 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

K.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

K.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

K.2 Architecture & Finishing work


K.2.1 Floor Finishes
K.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

K.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 105 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- ditto- 2 Set 9.00

L BOX VALVE SHELTER FOUNDATION DESA REJA SARI II(KP 77+800)


Shelter size: (5W x 12L) m, Steel Structure
L.1 Civil works
L.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
L.1.2 Earthworks
L.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 106 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

L.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

L.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 107 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

L.2 Architecture & Finishing work


L.2.1 Floor Finishes
L.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

L.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

M BOX VALVE SHELTER FOUNDATION BRIDGE LANGKAP LANCAR I (KP 79+326)


Shelter size: (5W x 12L) m, Steel Structure
M.1 Civil works
M.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
M.1.2 Earthworks
M.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 108 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 109 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

M.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

M.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

M.2 Architecture & Finishing work


M.2.1 Floor Finishes
M.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

M.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

N BOX VALVE SHELTER FOUNDATION BRIDGE LANGKAP LANCAR II (KP 79+419)


Shelter size: (5W x 12L) m, Steel Structure
N.1 Civil works
N.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 110 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
N.1.2 Earthworks
N.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 111 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

N.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

N.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

N.2 Architecture & Finishing work


N.2.1 Floor Finishes
N.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

N.2.1.b - Gravel 100 mm thk

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 112 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

O BOX VALVE SHELTER FOUNDATION BEBER (KP 102+200)


Shelter size: (5W x 12L) m, Steel Structure
O.1 Civil works
O.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
O.1.2 Earthworks
O.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 113 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume structure & foundation under FGL
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

O.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

O.1.2.c Sand bedding 50 mm thk & well compacted

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 114 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

O.2 Architecture & Finishing work


O.2.1 Floor Finishes
N.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

N.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

P BOX VALVE SHELTER FOUNDATION TASIK I (KP 126+853)


Shelter size: (5W x 12L) m, Steel Structure
P.1 Civil works
P.1.1 Site preperation
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
P.1.2 Earthworks
P.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 115 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 116 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

P.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

P.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

P.2 Architecture & Finishing work


P.2.1 Floor Finishes
P.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

P.2.1.b - Gravel 100 mm thk


terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

Q BOX VALVE SHELTER FOUNDATION TASIK II (KP 126+944)


Shelter size: (5W x 12L) m, Steel Structure
Q.1 Civil works
Q.1.1 Site preperation

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 117 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Installation of bowplank, wood stiffener, points building coordinat and leveling survey area 1 Lot 131.80
Q.1.2 Earthworks
Q.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 2.15
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 8 Ea 1.80

Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 1.15
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Sandbeding & lean conc.under footing , depth= 0.875 m under FGL 21 Ea 0.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.6Wx1.6Lx0.3Thk.) m, depth=0.7 m under FGL 8 Ea 1.60
- Grade beam (250Wx350D) mm, depth= 0.2 m under FGL 2 Ea 12.00
- ditto- 2 Ea 5.00
- Pedestal (0.2Wx0.4D) m, depth=0.575m under FGL 8 Ea 0.20
Fence Foundation
- Footing foundation, size of foundation: (0.6Wx0.6Lx0.2Thk.) m, depth=0.7 m under FGL 21 Ea 0.60

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 118 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Grade beam (20Wx250D) mm, depth= 0.2 m under FGL 2 Ea 16.00
- ditto- 2 Ea 9.00
- Pedestal (0.25Wx0.25D) m, depth=0.5 m under FGL 21 Ea 0.25

Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 12.00
- ditto- 2 Ea 5.00
Fence Foundation
Volume sand bedding 50 mm Thk.& lean conc. 50 mm thk, Under footing fdn 21 Ea 0.80
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 16.00
- ditto- 2 Ea 9.00

Q.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

Q.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.80
Volume sand bedding 50 mm Thk. Under footing fence fdn. 21 Ea 0.80

Q.2 Architecture & Finishing work


Q.2.1 Floor Finishes
Q.2.1.a - Box Valve floor area, gravel 100 mm thk 1 Set Area (m2) =

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 119 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Q.2.1.b - Gravel 100 mm thk
terrace/ footpath 2 Set 19.00
- ditto- 2 Set 9.00

R PIG LAUNCHER FOUNDATION TBBM LOMANIS


Foundation size: (2.4W x 9.67L) m, Reinforced Concrete
R.1 Civil works
R.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 1 Lot 73.48
R.1.2 Earthworks
R.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.5Wx1.5Lx0.35Thk.) m, depth= 1m under FGL 2 Ea 2.20
- Grade beam (250Wx500D) mm, depth= 0.6 m under FGL 1 Ea 4.27
- Sandbeding & lean conc. Under footing depth = 1 m under FGL 1 Ea 1.70

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.5Wx1.5Lx0.35Thk.) m, depth= 1m under FGL 2 Ea 1.50
- Grade beam (250Wx500D) mm, depth= 0.6 m under FGL 1 Ea 4.27
- Pedestal (0.4Wx0.8D) m, depth=0.65 m under FGL 2 Ea 0.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 120 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 1 Ea 1.70
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 4.27

R.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

R.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 2 Ea 1.70
Volume sand bedding 50 mm Thk. Under grade beam. 1 Ea 4.27
Volume sand bedding 50 mm Thk. Concrete slab. 1 Ea 9.67

R.2 Architecture & Finishing work


R.2.1 Floor Finishes
R.2.1.a - Floor area, Concrete steel trowel finish with floor hardener 1 Set Area (m2) =

B.2.1.b - Concrete steel trowel finish


terrace/ footpath 2 Set 12.07
- ditto- 2 Set 2.40

S PIG RECEIVER FOUNDATION TBBM TASIKMALAYA


Foundation size: (2.4W x 13L) m, Reinforced Concrete

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 121 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
S.1 Civil works
S.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 1 Lot 86.80
S.1.2 Earthworks
S.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.5Wx1.5Lx0.35Thk.) m, depth= 1m under FGL 2 Ea 2.20
- Grade beam (250Wx500D) mm, depth= 0.6 m under FGL 1 Ea 4.27
- Sandbeding & lean conc. Under footing depth = 1 m under FGL 1 Ea 1.70

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.5Wx1.5Lx0.35Thk.) m, depth= 1m under FGL 2 Ea 1.50
- Grade beam (250Wx500D) mm, depth= 0.6 m under FGL 1 Ea 6.42
- Pedestal (0.4Wx0.8D) m, depth=0.65 m under FGL 2 Ea 0.80

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 1 Ea 1.70
- Sand bedding & lean conc. Total thk 100mm under grade beam 2 Ea 6.42

S.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

S.1.2.c Sand bedding 50 mm thk & well compacted

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 122 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume sand bedding 50 mm Thk. Under footing fdn. 2 Ea 1.70
Volume sand bedding 50 mm Thk. Under grade beam. 1 Ea 6.42
Volume sand bedding 50 mm Thk. Concrete slab. 1 Ea 12.82

S.2 Architecture & Finishing work


S.2.1 Floor Finishes
S.2.1.a - Floor area, Concrete steel trowel finish with floor hardener 1 Set Area (m2) =

S.2.1.b - Concrete steel trowel finish


terrace/ footpath 2 Set 15.22
- ditto- 2 Set 2.40

T PERIMETER DRAINAGE FOR NEW FACILITY TBBM LOMANIS


T.1 Open ditch type-U ditch size: (0.3W x 0.3~0.6 Depth avrg.) m, L = 355 m
T.2.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 1 Lot 355.00
T.2.2 Earthworks
T.2.2.a - Soil excavation for:
- Open ditch, size: (0.3W x 0.3~0.6 Depth) m, depth=0.4 m u/ FGL 1 Ea 355.00

Volume ditch & sand & lean concrete under FGL


- Open ditch volume 1 Ea 355.00

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 123 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Sandbeding 50mm total thk. Under ditch 1 Ea 355.00

T.2.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of ditch under FGL)

T.2.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50mm Thk. Under concrete ditch. 1 Ea 355.00

T.2.3 Brickwall, plaster & hollow concrete 1/2 Ø 300 mm


T.2.3.a - Brickwall (include wet area) and thin bed mortar 1PC:2 Sand 1 Set 355.00
T.2.3.b - Wall plaster 15mm th'k and mortar 1PC : 2 Sand & Smooth surface 1 Set 355.00

U FENCE FOUNDATION
U.1 Chain Link Fence ( Length = 146 m)
Fencing and gates shall be meet the following requirements LK3 Pertamina with a minimum height of 2.5
meters with an additional 0.3 meters (min.) overhang consisting of four stands of barbed wire placed at a 45 1 Set 146
degree angle facing outward from the area to be secured. The main materials:
Fence fabric 2.5 meters minimum high, heavy galvanized chain link fence, conforming to ASTM A392,
- Class 2, of 2-inches mesh 9-gage wire (0.148-inches) in diameter, with the top and bottom selvedges 1 Set 146
twisted and barbed.

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 124 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
End corner and pull posts shall be 2½ -inches NPs (2.875" O.D) standard weight hot dip galvanized tubular
- steel (Schedule 40) ASTM A120 and pull post shall be installed at interval not exceed 15-meters as long 11 Ea 3
fence installing and shall be reinforced inward brace with equal material and size.
Line posts 2-inches NPs (2.375" O.D) standard weight hot dip galvanized tubular steel (Schedule 40)
- ASTM A120.Line posts shall be spaced not more than 3-meters apart in the line of the fence. 39 Ea 3

Top rails shall conform to 1 ¼ -inches NPs (1.625" O.D) standard weight hot dip galvanized tubular steel
- (Schedule 40) ASTM A120. ASTM A120. 1 Set 146

4-strands of barbed wire shall consist of double stranded, 12 ½ -gage wire galvanized, ASTM A121, Class
- III, with 4-point barbs spaced 5-inches part. 4 Set 146

Tension wire shall be 7-gage U.S. steel wire galvanized in accordance with ASTM A116 coatings class III.
- The tension wire shall be stretched near the bottom of the fence and attached at 700 mm maximal of 4 Set 146
intervals.
Appurtenances : Braced bands, tension bars and tension bands shall be fabricated of 1/8-inch (3.175 mm)
by 7/8-inch (22.22 mm) hot dip galvanized steel with carriage bolts and nuts (galvanized) in accordance
with ASTM A123. Tension bars shall be 1/4 -inch (6.35 mm) by ¾-inch (19.05 mm) galvanized steel bar in
- 1 Lot
accordance with ASTM A153. Fabric ties shall be class I galvanized steel wire no less than 9-gage.

U.2 Concrete Panel Fence (Length = 90 m)


Precast Concrete Panel, height = 2.5 m 1 Set 90.00

V PIPE SUPPORT TYPE 1 (PS-001~PS-003, PS-010 ~PS-014)


Foundation size: (1W x 1L) m, Reinforced Concrete

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 125 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
V.1 Civil works
V.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 8 Lot 31.80
V.1.2 Earthworks
V.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1Wx1Lx0.3Thk.) m, depth= 0.6 m under FGL 8 Ea 1.50
- Sandbeding & lean conc. Under footing depth = 0.7 m under FGL 8 Ea 1.20

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1Wx1Lx0.3Thk.) m, depth= 0.6 m under FGL 8 Ea 1.00
- Pedestal (0.3Wx1D) m, depth=0.3m under FGL 8 Ea 1.00

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 8 Ea 1.20

V.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

V.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 8 Ea 1.70

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 126 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
W PIPE SUPPORT TYPE 2 (PS-004, PS-007 ~PS-009)
Foundation size: (1W x 1.5L) m, Reinforced Concrete
W.1 Civil works
W.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 4 Lot 32.80
W.1.2 Earthworks
W.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1Wx1.5Lx0.3Thk.) m, depth= 0.6 m under FGL 4 Ea 2.00
- Sandbeding & lean conc. Under footing depth = 0.7 m under FGL 4 Ea 1.70

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1Wx1.5Lx0.3Thk.) m, depth= 0.6 m under FGL 4 Ea 1.50
- Pedestal (0.3Wx1.5D) m, depth=0.3m under FGL 4 Ea 0.30

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 4 Ea 1.70

W.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

W.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 4 Ea 1.50

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 127 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

X PIPE SUPPORT TYPE 3 (PS-005 ~PS-006)


Foundation size: (1W x 2.4L) m, Reinforced Concrete
X.1 Civil works
X.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 2 Lot 34.60
X.1.2 Earthworks
X.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1Wx2.4Lx0.3Thk.) m, depth= 0.6 m under FGL 2 Ea 2.90
- Sandbeding & lean conc. Under footing depth = 0.7 m under FGL 2 Ea 2.60

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1Wx2.4Lx0.3Thk.) m, depth= 0.6 m under FGL 2 Ea 2.40
- Pedestal (0.3Wx2.4D) m, depth=0.3m under FGL 2 Ea 2.40

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 2 Ea 2.60

X.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 128 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
X.1.2.c Sand bedding 50 mm thk & well compacted
Volume sand bedding 50 mm Thk. Under footing fdn. 2 Ea 2.40

Y PIPE SUPPORT TYPE 4 (PS-015, PS-017~PS-023, PS-025, PS-027, PS-033~PS-036)


Foundation size: (1.2W x 1.2L) m, Reinforced Concrete
Y.1 Civil works
Y.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 14 Lot 33.60
Y.1.2 Earthworks
Y.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.2Wx1.2Lx0.3Thk.) m, depth= 0.6 m under FGL 14 Ea 1.70
- Sandbeding & lean conc. Under footing depth = 0.7 m under FGL 14 Ea 1.40

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.2Wx1.2Lx0.3Thk.) m, depth= 0.6 m under FGL 14 Ea 1.20
- Pedestal (0.35Wx0.35D) m, depth=0.3m under FGL 14 Ea 0.35

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 14 Ea 1.40

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 129 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Y.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

Y.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 14 Ea 1.20

Z PIPE SUPPORT TYPE 5 (PS-016, PS-024, PS-026, PS-028)


Foundation size: (1W x 1.4L) m, Reinforced Concrete
Z.1 Civil works
Z.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 4 Lot 33.60
Z.1.2 Earthworks
Z.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1Wx1.4Lx0.3Thk.) m, depth= 0.6 m under FGL 4 Ea 1.90
- Sandbeding & lean conc. Under footing depth = 0.7 m under FGL 4 Ea 1.60

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1Wx1.4Lx0.3Thk.) m, depth= 0.6 m under FGL 4 Ea 1.00
- Pedestal (0.35Wx0.76D) m, depth=0.3m under FGL 4 Ea 0.76

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 4 Ea 1.60

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 130 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

Z.1.2.b Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

Z.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 4 Ea 1.00

AA PIPE SUPPORT TYPE 6 (PS-029, PS-031, PS-032)


Foundation size: (1.2W x 1.2L) m, Reinforced Concrete
AA.1 Civil works
AA.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 3 Lot 33.60
AA.1.2 Earthworks
AA.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.2Wx1.2Lx0.3Thk.) m, depth= 0.6 m under FGL 3 Ea 1.70
- Sandbeding & lean conc. Under footing depth = 0.7 m under FGL 3 Ea 1.40

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (1.2Wx1.2Lx0.3Thk.) m, depth= 0.6 m under FGL 3 Ea 1.20
- Pedestal (0.35Wx0.35D) m, depth=0.3m under FGL 3 Ea 0.35

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 131 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 3 Ea 1.40

Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

AA.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 3 Ea 1.20

AB PIPE SUPPORT TYPE 7 (PS-030)


Foundation size: (1.2W x 2.5L) m, Reinforced Concrete
AB.1 Civil works
AB.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 1 Lot 36.20
AB.1.2 Earthworks
AB.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (1.2Wx2.5Lx0.3Thk.) m, depth= 0.6 m under FGL 1 Ea 3.00
- Sandbeding & lean conc. Under footing depth = 0.7 m under FGL 1 Ea 2.70

Volume structure & foundation under FGL

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 132 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Footing foundation, size of foundation: (1.2Wx2.5Lx0.3Thk.) m, depth= 0.6 m under FGL 1 Ea 2.50
- Pedestal (0.35Wx0.35D) m, depth=0.3m under FGL 2 Ea 0.35

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 1 Ea 2.70

Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

AB.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 1 Ea 2.50

AC PIPE BRIDGE (LANGKAP LANCAR BRIDGE KP 79+326)


Foundation size: 2x(2.6W x 3.1L) m, Reinforced Concrete
AC.1 Civil works
AC.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 2 Lot 40.20
AC.1.2 Earthworks
AC.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (2.6Wx3.1Lx0.4Thk.) m, depth= 1 m under FGL 2 Ea 3.10
- Sandbeding & lean conc. Under footing depth = 1.1 m under FGL 1 Ea 2.80

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 133 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
Volume structure & foundation under FGL
- Footing foundation, size of foundation: (2.6Wx3.1Lx0.4Thk.) m, depth= 1 m under FGL 2 Ea 2.60
- Pedestal (0.5Wx0.5D) m, depth=0.6m under FGL 8 Ea 0.50

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 2 Ea 2.82

Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

AC.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 2 Ea 2.60
- ditto-, under concrete floor 2 Ea Area (m2) =

AC.2 Architecture & Finishing work


AC.2.1 Floor Finishes
AC.2.1.a - Floor area, Concrete steel trowel finish with floor hardener 2 Set Area (m2) =

AD PIPE BRIDGE (AWIPARI BRIDGE KP 121+600)


Foundation size: 2x(2.6W x 3.1L) m, Reinforced Concrete
AD.1 Civil works
AD.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 2 Lot 40.20

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 134 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
AD.1.2 Earthworks
AD.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (2.6Wx3.1Lx0.4Thk.) m, depth= 1 m under FGL 2 Ea 3.10
- Sandbeding & lean conc. Under footing depth = 1.1 m under FGL 1 Ea 2.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (2.6Wx3.1Lx0.4Thk.) m, depth= 1 m under FGL 2 Ea 2.60
- Pedestal (0.5Wx0.5D) m, depth=0.6m under FGL 8 Ea 0.50

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 2 Ea 2.82

Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

AD.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 2 Ea 2.60
- ditto-, under concrete floor 2 Ea Area (m2) =

AD.2 Architecture & Finishing work


AD.2.1 Floor Finishes
AD.2.1.a - Floor area, Concrete steel trowel finish with floor hardener 2 Set Area (m2) =

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 135 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)

AE PIPE BRIDGE (CONDONG BRIDGE KP 124+000)


Foundation size: 2x(2.6W x 3.1L) m, Reinforced Concrete
AE.1 Civil works
AE.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 2 Lot 40.20
AE.1.2 Earthworks
AE.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (2.6Wx3.1Lx0.4Thk.) m, depth= 1 m under FGL 2 Ea 3.10
- Sandbeding & lean conc. Under footing depth = 1.1 m under FGL 1 Ea 2.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (2.6Wx3.1Lx0.4Thk.) m, depth= 1 m under FGL 2 Ea 2.60
- Pedestal (0.5Wx0.5D) m, depth=0.6m under FGL 8 Ea 0.50

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 2 Ea 2.80

Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 136 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
AE.1.2.c Sand bedding 50 mm thk & well compacted
Volume sand bedding 50 mm Thk. Under footing fdn. 2 Ea 2.60
- ditto-, under concrete floor 2 Ea Area (m2) =

AE.2 Architecture & Finishing work


AE.2.1 Floor Finishes
AE.2.1.a - Floor area, Concrete steel trowel finish with floor hardener 2 Set Area (m2) =

AF PIPE BRIDGE (CINTAPADA BRIDGE KP 125+440)


Foundation size: 2x(2.6W x 3.6L) m, Reinforced Concrete
AF.1 Civil works
AF.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 2 Lot 41.20
AF.1.2 Earthworks
AF.1.2.a - Soil excavation for:
- Footing foundation, size of foundation: (2.6Wx3.6Lx0.4Thk.) m, depth= 1 m under FGL 2 Ea 3.10
- Sandbeding & lean conc. Under footing depth = 1.1 m under FGL 1 Ea 2.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (2.6Wx3.6Lx0.4Thk.) m, depth= 1 m under FGL 2 Ea 2.60

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 137 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Pedestal (0.5Wx0.5D) m, depth=0.6m under FGL 8 Ea 0.50

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 2 Ea 2.80

Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

AF.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 2 Ea 2.60
- ditto-, under concrete floor 2 Ea Area (m2) =

AF.2 Architecture & Finishing work


AF.2.1 Floor Finishes
AF.2.1.a - Floor area, Concrete steel trowel finish with floor hardener 2 Set Area (m2) =

AG WALKWAY PLATFORM FOUNDATION


Foundation size: 2x(0.8W x 1.6L) m, Reinforced Concrete
AG.1 Civil works
AG.1.1 Site preperation
- Installation of bowplank, wood stiffener and leveling & survey area 2 Lot 33.60
AG.1.2 Earthworks
AG.1.2.a - Soil excavation for:

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 138 of 358
DETAIL MTO CIVIL WORK AND FINISHES ARCHITECHTURE

QUANTITY OF
SIZES OF M
MEMBERS
NO DESCRIPTION OF BUILDING/ SHELTER AND ITEM WORKS
Nos of Length
Unit
m'bers
(m)
- Footing foundation, size of foundation: (0.8Wx1.6Lx0.25Thk.) m, depth= 0.475 m under FGL 2 Ea 1.30
- Sandbeding & lean conc. Under footing depth = 0.575 m under FGL 2 Ea 1.80

Volume structure & foundation under FGL


- Footing foundation, size of foundation: (0.8Wx1.6Lx0.25Thk.) m, depth= 0.475 m under FGL 2 Ea 1.60
- Pedestal (0.25Wx0.35D) m, depth=0.225m under FGL 4 Ea 0.35

Volume sand bedding 50mm Thk.& lean conc. 50 mm thk, Under footing fdn 2 Ea 1.80

Soil back fill and compaction = (Vol.of soil excavation - Vol. Of Struc.fdn under FGL)

AG.1.2.c Sand bedding 50 mm thk & well compacted


Volume sand bedding 50 mm Thk. Under footing fdn. 2 Ea 2.60
- ditto-, under concrete floor 2 Ea Area (m2) =

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 139 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

40.40 m

3.35 2.20 53.80 m3

3.35 2.30 56.25 m3

Sub-total = 110.05 m3

1.90 1.30 10.87 m3


2.10 0.05 0.50 m3
Sub-total = 11.37 m3

98.68 m3
sub-total = 98.68 m3

2.10 0.05 0.50 m3


Sub-total = 0.50 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 140 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

192.80 m

3.60 1.80 279.94 m3


1.20 0.60 16.13 m3
1.73 1.00 41.52 m3
1.75 1.50 7.09 m3
1.10 0.30 19.80 m3
1.10 1.00 44.00 m3

2.80 0.10 2.67 m3

2.40 0.10 4.90 m3

1.70 0.10 0.87 m3

Sub-total = 416.91 m3

2.50 0.30 22.50 m3


0.30 0.50 9.00 m3
0.30 0.50 6.00 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 141 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.40 1.50 2.88 m3
0.65 0.80 11.65 m3
1.12 1.14 30.64 m3
0.80 0.80 1.73 m3
2.70 0.10 8.75 m3
0.30 0.10 1.80 m3
0.30 0.10 1.20 m3
0.84 0.10 1.88 m3
1.14 0.10 2.74 m3
0.80 0.10 0.22 m3
12.60 0.10 11.91 m3
2.30 0.10 4.62 m3
1.60 0.10 0.77 m3
Sub-total = 118.28 m3

298.63 m3
sub-total = 298.63 m3

2.70 0.05 4.37 m3


266.10 0.05 13.31 m3
1.20 0.05 3.89 m3
1.20 0.05 1.56 m3
Sub-total = 23.13 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 142 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

193.04 193.04 m2
sub-total = 193.04 m2

1.50 97.20 m2
1.20 24.00 m2
sub-total = 121.20 m2

55.60 m

3.05 0.70 21.35 m3


0.45 0.20 1.08 m3
0.45 1.00 4.95 m3

0.90 0.10 0.65 m3

Sub-total = 28.03 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 143 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

0.70 0.25 0.98 m3


0.20 0.30 0.72 m3
0.20 0.30 0.66 m3
0.30 0.45 0.24 m3
0.90 0.10 0.65 m3
0.30 0.10 0.36 m3
0.30 0.10 0.33 m3
Sub-total = 3.94 m3

24.09 m3
sub-total = 24.09 m3

0.90 0.05 0.32 m3


8.25 0.05 0.83 m3
1.20 0.05 1.30 m3
1.20 0.05 1.38 m3
Sub-total = 3.83 m3

9.44 18.88 m2
sub-total = 18.88 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 144 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.50 32.40 m2
1.20 13.20 m2
sub-total = 45.60 m2

120.80 m

2.30 1.20 50.78 m3


0.73 0.40 9.86 m3
0.73 0.40 3.48 m3

2.60 0.10 3.69 m3

1.70 0.10 2.31 m3

Sub-total = 70.13 m3

1.50 0.30 5.40 m3


0.25 0.40 3.40 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 145 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.25 0.40 1.20 m3
0.30 0.90 0.65 m3
1.70 0.10 2.31 m3
0.40 0.10 1.36 m3
0.40 0.10 0.48 m3
12.40 0.10 17.48 m3
Sub-total = 32.28 m3

37.84 m3
sub-total = 37.84 m3

1.70 0.05 1.16 m3


102.00 0.05 5.10 m3
1.20 0.05 2.33 m3
1.20 0.05 1.08 m3
Sub-total = 9.66 m3

74.21 74.21 m2
sub-total = 74.21 m2

1.50 58.20 m2
1.20 14.40 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 146 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
sub-total = 72.60 m2

120.80 m

2.30 1.20 50.78 m3


0.73 0.40 9.86 m3
0.73 0.40 3.48 m3

2.60 0.10 3.69 m3

1.70 0.10 2.31 m3

Sub-total = 70.13 m3

1.50 0.30 5.40 m3


0.25 0.40 3.40 m3
0.25 0.40 1.20 m3
0.30 0.90 0.65 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 147 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.70 0.10 2.31 m3
0.40 0.10 1.36 m3
0.40 0.10 0.48 m3
12.40 0.10 17.48 m3
Sub-total = 32.28 m3

37.84 m3
sub-total = 37.84 m3

1.70 0.05 1.16 m3


102.00 0.05 5.10 m3
1.20 0.05 2.33 m3
1.20 0.05 1.08 m3
Sub-total = 9.66 m3

74.21 74.21 m2
sub-total = 74.21 m2

1.50 58.20 m2
1.20 14.40 m2
sub-total = 72.60 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 148 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 149 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 150 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 151 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 152 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 153 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
2.15 0.70 25.89 m3
0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 154 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 155 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
sub-total = 78.60 m2

131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 156 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 157 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 158 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 159 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 160 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 161 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 162 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 163 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.60 0.30 6.14 m3
0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 164 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 165 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
2.15 0.70 36.35 m3
0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 166 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 167 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 168 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 169 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 170 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 171 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.80 0.05 1.30 m3
0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 172 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3


0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 173 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.80 0.10 1.34 m3
0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 174 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
131.80 m

2.15 0.70 25.89 m3


0.60 0.20 2.88 m3
0.60 0.20 1.20 m3

1.80 0.10 2.59 m3

2.15 0.70 36.35 m3


0.53 0.20 3.36 m3
0.53 0.20 1.89 m3

0.80 0.10 1.34 m3

Sub-total = 75.50 m3

1.60 0.30 6.14 m3


0.25 0.20 1.20 m3
0.25 0.20 0.50 m3
0.40 0.58 0.37 m3

0.60 0.20 1.51 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 175 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.20 0.20 1.28 m3
0.20 0.20 0.72 m3
0.25 0.50 0.66 m3

1.80 0.10 2.59 m3


0.25 0.10 0.60 m3
0.25 0.10 0.25 m3

0.80 0.10 1.34 m3


0.20 0.10 0.64 m3
0.20 0.10 0.36 m3
Sub-total = 18.17 m3

57.33 m3
sub-total = 57.33 m3

1.80 0.05 1.30 m3


0.80 0.05 0.67 m3
Sub-total = 1.97 m3

60.00 60.00 m2
sub-total = 60.00 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 176 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

1.50 57.00 m2
1.20 21.60 m2
sub-total = 78.60 m2

73.48 m'

2.20 1.00 9.68 m3


0.68 0.60 1.73 m3

1.70 0.10 0.29 m3

Sub-total = 11.70 m3

1.50 0.35 1.58 m3


0.25 0.50 0.53 m3
0.40 0.65 0.42 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 177 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.70 0.10 0.29 m3
0.25 0.10 0.21 m3
Sub-total = 3.03 m3

8.67 m3
sub-total = 8.67 m3

1.70 0.05 0.29 m3


0.25 0.05 0.05 m3
2.40 0.05 1.16 m3
Sub-total = 1.50 m3

10.80 10.80 m2
sub-total = 10.80 m2

1.50 36.20 m2
1.20 5.76 m2
sub-total = 41.96 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 178 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

86.80 m'

2.20 1.00 9.68 m3


0.68 0.60 1.73 m3

1.70 0.10 0.29 m3

Sub-total = 11.70 m3

1.50 0.35 1.58 m3


0.25 0.50 0.80 m3
0.40 0.65 0.42 m3

1.70 0.10 0.29 m3


0.25 0.10 0.32 m3
Sub-total = 3.40 m3

8.29 m3
sub-total = 8.29 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 179 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.70 0.05 0.29 m3
0.25 0.05 0.08 m3
2.40 0.05 1.54 m3
Sub-total = 1.91 m3

15.60 15.60 m2
sub-total = 15.60 m2

1.50 45.67 m2
1.20 5.76 m2
sub-total = 51.43 m2

355.00 m'

0.80 0.40 113.60 m3

0.30 0.60 63.90 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 180 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.40 0.05 7.10 m3
sub-total = 71.00 m3

42.60 m3

0.60 0.05 10.65 m3

1.80 639.00 m2
2.70 958.50 m2

2.5 365 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 181 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

32 m

117 m

146 m

584 m

584 m

1 Lot

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 182 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

254.40 m'

1.50 0.60 10.80 m3

1.20 0.70 8.06 m3

Sub-total = 18.86 m3

1.00 0.30 2.40 m3


0.30 0.30 0.72 m3

1.20 0.10 1.15 m3


Sub-total = 4.27 m3

14.59 m3
sub-total = 14.59 m3

1.70 0.05 1.16 m3


Sub-total = 1.16 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 183 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

131.20 m'

1.50 0.60 7.20 m3

1.20 0.70 5.71 m3

Sub-total = 12.91 m3

1.00 0.30 1.80 m3


1.50 0.30 0.54 m3

1.20 0.10 0.82 m3


Sub-total = 3.16 m3

9.76 m3
sub-total = 9.76 m3

1.00 0.05 0.30 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 184 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
Sub-total = 0.30 m3

69.20 m'

1.50 0.60 5.22 m3

1.20 0.70 4.37 m3

Sub-total = 9.59 m3

1.00 0.30 1.44 m3


0.30 0.30 0.43 m3

1.20 0.10 0.62 m3


Sub-total = 2.50 m3

7.09 m3
sub-total = 7.09 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 185 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

1.00 0.05 0.24 m3


Sub-total = 0.24 m3

470.40 m'

1.70 0.60 24.28 m3

1.40 0.70 19.21 m3

Sub-total = 43.48 m3

1.20 0.30 6.05 m3


0.35 0.30 0.51 m3

1.40 0.10 2.74 m3


Sub-total = 9.31 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 186 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
34.18 m3
sub-total = 34.18 m3

1.20 0.05 1.01 m3


Sub-total = 1.01 m3

134.40 m'

1.50 0.60 6.84 m3

1.20 0.70 5.38 m3

Sub-total = 12.22 m3

1.40 0.30 1.68 m3


0.35 0.30 0.32 m3

1.20 0.10 0.77 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 187 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
Sub-total = 2.77 m3

9.45 m3
sub-total = 9.45 m3

1.40 0.05 0.28 m3


Sub-total = 0.28 m3

100.80 m'

1.70 0.60 5.20 m3

1.40 0.70 4.12 m3

Sub-total = 9.32 m3

1.20 0.30 1.30 m3


0.35 0.30 0.11 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 188 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

1.40 0.10 0.59 m3


Sub-total = 1.99 m3

7.32 m3
sub-total = 7.32 m3

1.20 0.05 0.22 m3


Sub-total = 0.22 m3

36.20 m'

1.70 0.60 3.06 m3

1.40 0.70 2.65 m3

Sub-total = 5.71 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 189 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
1.20 0.30 0.90 m3
0.35 0.30 0.07 m3

1.40 0.10 0.38 m3


Sub-total = 1.35 m3

4.35 m3
sub-total = 4.35 m3

1.20 0.05 0.15 m3


Sub-total = 0.15 m3

80.40 m'

3.60 1.00 22.32 m3

3.30 1.10 10.16 m3

Sub-total = 32.48 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 190 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

3.10 0.40 6.45 m3


0.50 0.60 1.20 m3

3.30 0.10 1.86 m3


Sub-total = 9.51 m3

22.97 m3
sub-total = 22.97 m3

3.10 0.05 0.81 m3


34.78 0.05 3.48 m3
Sub-total = 4.28 m3

34.78 69.56 m2
sub-total = 69.56 m2

80.40 m'

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 191 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

3.60 1.00 22.32 m3

3.30 1.10 10.16 m3

Sub-total = 32.48 m3

3.10 0.40 6.45 m3


0.50 0.60 1.20 m3

3.30 0.10 1.86 m3


Sub-total = 9.51 m3

22.97 m3
sub-total = 22.97 m3

3.10 0.05 0.81 m3


34.78 0.05 3.48 m3
Sub-total = 4.28 m3

34.78 69.56 m2

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 192 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
sub-total = 69.56 m2

80.40 m'

3.60 1.00 22.32 m3

3.30 1.10 10.16 m3

Sub-total = 32.48 m3

3.10 0.40 6.45 m3


0.50 0.60 1.20 m3

3.30 0.10 1.85 m3


Sub-total = 9.50 m3

22.99 m3
sub-total = 22.99 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 193 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)

3.10 0.05 0.81 m3


32.68 0.05 3.27 m3
Sub-total = 4.07 m3

34.78 69.56 m2
sub-total = 69.56 m2

82.40 m'

4.10 1.00 25.42 m3

3.80 1.10 11.70 m3

Sub-total = 37.12 m3

3.60 0.40 7.49 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 194 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
0.50 0.60 1.20 m3

3.80 0.10 2.13 m3


Sub-total = 10.82 m3

26.31 m3
sub-total = 26.31 m3

3.60 0.05 0.94 m3


34.78 0.05 3.48 m3
Sub-total = 4.41 m3

34.78 69.56 m2
sub-total = 69.56 m2

67.20 m'

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 195 of 358
SIZES OF MEMBERS TOTAL QUANTITY

Width/ High Depth/ Thick


QTY UNIT
(m) (m)
2.10 0.48 2.59 m3

1.00 0.58 2.07 m3

Sub-total = 4.66 m3

0.80 0.25 0.64 m3


0.25 0.23 0.08 m3

1.00 0.10 0.36 m3


Sub-total = 1.08 m3

3.58 m3
sub-total = 3.58 m3

3.60 0.05 0.94 m3


34.78 0.05 3.48 m3
Sub-total = 4.41 m3

_______________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 __________________________________ Rev. 1
Att. C Page 196 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)

A ANCHOR BLOCK FOUNDATION


Concrete structure K-275 (2 UNIT)
- Pilecap-4PC pile Sqr. 200 mm, sizes: (1.9Wx2.2Lx1.5Thk) m, 4 Ea 2.20 1.90 1.50 6.27
for Anchor Block fdn
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ pilecap 4 Ea 2.30 2.00 0.05 0.23
Sub-total =

B PUMP SHELTER FOUNDATION


Size: (10W x 30L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (2.5Wx2.5Lx0.3Thk) m 12 Ea 2.50 2.50 0.30 1.88

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 199 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =
PEDESTAL
- Pedestal: (0.4W x 0.4D x 2.1H) m 12 Ea 2.10 0.40 0.40 0.34
Sub-total =
GRADE BEAM AND CONC. FLOOR (TOC.EL. +0.300)
- Gr.-beam (300Wx500D) mm 2 Ea 30.00 0.30 0.50 4.50
- - ditto - 6 Ea 10.00 0.30 0.50 1.50
Sub-total =
CONCRETE FLOOR 120mm Thk.( 1-layer rebar Ø10-200)
- 1 Set Area (m2)= 193.04 0.12 23.16
Area of concrete floor (minus pump fdn & cable trench)
- Conc. floor terrace 120 mm Thk (1-layers wiremesh M8) 2 Ea 32.40 1.50 0.12 5.83
- ditto - 2 Ea 10.00 1.20 0.12 1.44
- Reinf. beam terrace floor, (0.15W x 0.2D)m 2 Ea 32.40 0.15 0.20 0.97
- ditto - 2 Ea 13.00 0.15 0.20 0.39
Sub-total =
Pump Foundation
- 1-Units Pump Foundation type-1 1 Ea 9.35 2.60 0.50 12.16
- 3-Units Pump Foundation type-2 3 Ea 6.60 2.00 0.45 5.94
- 3-Units Pump Foundation type-3 3 Ea 1.50 1.50 2.00 4.50
Sub-total =
CONCRETE CABLE TRENCH
- Cable trench (0.65W x 0.8D x 0.12Thk ) m 4 Ea 1.31

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 200 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- ditto - size: (1.120Wx1.140Dx0.12Thk.) m 4 Ea 2.50
Sub-total =
DUCT BANK CABLE
- Duct bank cables access 1 Ea 2.75 0.80 0.58 1.27
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 12 Ea 2.70 2.70 0.05 0.36
- Under conc. floor (incl'd pump fdn & cable trench) 1 Ea 30.00 10.00 0.05 15.00
under concrete floor footpath/ terrace 2 Ea 32.40 1.50 0.05 2.43
- ditto - 2 Ea 10.00 1.20 0.05 0.60
Sub-total =

C DENSITO METER SHELTER FOUNDATION (2 UNIT)


Size: 2 x(2.75W x 3L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (0.7Wx0.7Lx0.25Thk) m 8 Ea 0.70 0.70 0.25 0.12
Sub-total =
PEDESTAL
- Pedestal: (0.225W x 0.3D x 0.75H) m 8 Ea 0.75 0.23 0.30 0.05
Sub-total =
GRADE BEAM AND CONC. FLOOR (TOC.EL. +0.300)
- Gr.-beam (200Wx300D) mm 4 Ea 3.00 0.20 0.30 0.18
- - ditto - 4 Ea 2.75 0.20 0.30 0.17

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 201 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =
CONCRETE FLOOR 120mm Thk.( 1-layer rebar Ø10-200)
- Area of concrete floor 2 Set Area (m2)= 9.44 0.12 1.13
- Conc. floor terrace 120 mm Thk (1-layers wiremesh M8) 4 Ea 5.40 1.50 0.12 0.97
- ditto - 4 Ea 2.75 1.20 0.12 0.40
- Reinf. beam terrace floor, (0.15W x 0.2D)m 4 Ea 5.40 0.15 0.20 0.16
- ditto - 4 Ea 5.75 0.15 0.20 0.17
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 0.90 0.90 0.05 0.04
- Under conc. floor 2 Ea 3.00 2.75 0.05 0.41
under concrete floor footpath/ terrace 4 Ea 5.40 1.50 0.05 0.41
- ditto - 4 Ea 2.75 1.20 0.05 0.17
Sub-total =

D METERING SHELTER FOUNDATION TBBM LOMANIS


Size: (6W x 17L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.5Wx1.5Lx0.3Thk) m 8 Ea 1.50 1.50 0.30 0.68
Sub-total =
PEDESTAL
- Pedestal: (0.3W x 0.3D x 1.4H) m 8 Ea 1.40 0.30 0.30 0.13

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 202 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =
GRADE BEAM AND CONC. FLOOR (TOC.EL. +0.300)
- Gr.-beam (250Wx400D) mm 2 Ea 17.00 0.25 0.40 1.70
- - ditto - 2 Ea 6.00 0.25 0.40 0.60
Sub-total =
CONCRETE FLOOR 150mm Thk.( 2-layer rebar Ø10-200)
- Area of concrete floor (minus metering fdn) 1 Set Area (m2)= 74.21 0.15 11.13
- Conc. floor terrace 120 mm Thk (1-layers wiremesh M8) 2 Ea 19.40 1.50 0.12 3.49
- ditto - 2 Ea 6.00 1.20 0.12 0.86
- Reinf. beam terrace floor, (0.15W x 0.2D)m 2 Ea 19.40 0.15 0.20 0.58
- ditto - 2 Ea 9.00 0.15 0.20 0.27
Sub-total =
Metering Foundation
- 1-Units Metering Foundation 1 Ea 14.00 2.40 0.30 10.08
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.70 1.70 0.05 0.14
- Under conc. floor (incl'd metering fdn) 1 Ea 17.00 6.00 0.05 5.10
under concrete floor footpath/ terrace 2 Ea 19.40 1.50 0.05 1.46
- ditto - 2 Ea 6.00 1.20 0.05 0.36
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 203 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
E METERING SHELTER FOUNDATION TBBM TASIKMALAYA
Size: (6W x 17L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.5Wx1.5Lx0.3Thk) m 8 Ea 1.50 1.50 0.30 0.68
Sub-total =
PEDESTAL
- Pedestal: (0.3W x 0.3D x 1.4H) m 8 Ea 1.40 0.30 0.30 0.13
Sub-total =
GRADE BEAM AND CONC. FLOOR (TOC.EL. +0.300)
- Gr.-beam (250Wx400D) mm 2 Ea 17.00 0.25 0.40 1.70
- - ditto - 2 Ea 6.00 0.25 0.40 0.60
Sub-total =
CONCRETE FLOOR 150mm Thk.( 2-layer rebar Ø10-200)
- Area of concrete floor (minus metering fdn) 1 Set Area (m2)= 74.21 0.15 11.13
- Conc. floor terrace 120 mm Thk (1-layers wiremesh M8) 2 Ea 19.40 1.50 0.12 3.49
- ditto - 2 Ea 6.00 1.20 0.12 0.86
- Reinf. beam terrace floor, (0.15W x 0.2D)m 2 Ea 19.40 0.15 0.20 0.58
- ditto - 2 Ea 9.00 0.15 0.20 0.27
Sub-total =
Metering Foundation
- 1-Units Metering Foundation 1 Ea 14.00 2.40 0.30 10.08
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 204 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.70 1.70 0.05 0.14
- Under conc. floor (incl'd metering fdn) 1 Ea 17.00 6.00 0.05 5.10
under concrete floor footpath/ terrace 2 Ea 19.40 1.50 0.05 1.46
- ditto - 2 Ea 6.00 1.20 0.05 0.36
Sub-total =

F BOX VALVE SHELTER FOUNDATION CILACAP (KP 0+009)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 205 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =

G BOX VALVE SHELTER FOUNDATION SITINGIL-1 (KP 35+140)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 206 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =
H BOX VALVE SHELTER FOUNDATION SITINGIL-2 (KP 35+290)
Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 207 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 208 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =

I BOX VALVE SHELTER FOUNDATION TARISI (KP 69+563)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 209 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =

J BOX VALVE SHELTER FOUNDATION CINTARATU(KP 69+888)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 210 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =

K BOX VALVE SHELTER FOUNDATION DESA REJA SARI I(KP 77+752)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 211 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 212 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =

L BOX VALVE SHELTER FOUNDATION DESA REJA SARI II(KP 77+800)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 213 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =

M BOX VALVE SHELTER FOUNDATION BRIDGE LANGKAP LANCAR I (KP 79+326)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 214 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =

N BOX VALVE SHELTER FOUNDATION BRIDGE LANGKAP LANCAR II (KP 79+419)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 215 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 216 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
O BOX VALVE SHELTER FOUNDATION BEBER (KP 102+200)
Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 217 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =

P BOX VALVE SHELTER FOUNDATION TASIK I (KP 126+853)


Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM AND CONC. FLOOR (TOC.EL. +0.300)
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 218 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =
Q BOX VALVE SHELTER FOUNDATION TASIK II (KP 126+944)
Size: (5W x 12L) M, SHELTER
FOOTING FOUNDATION
- Footing foundation, size: (1.6Wx1.6Lx0.3Thk) m 8 Ea 1.60 1.60 0.30 0.77
Sub-total =
PEDESTAL
- Pedestal: (0.2W x 0.4D x 0.775H) m 8 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM AND CONC. FLOOR (TOC.EL. +0.300)
- Gr.-beam (250Wx350D) mm 2 Ea 12.00 0.25 0.35 1.05

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 219 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- - ditto - 2 Ea 5.00 0.25 0.35 0.44
Sub-total =
Volume lean concrete 50 mm thk
- Under footing foundation 8 Ea 1.80 1.80 0.05 0.16
- Under grade beam 2 Ea 12.00 0.25 0.05 0.15
- ditto - 2 Ea 5.00 0.25 0.05 0.06
Sub-total =

FENCE FOUNDATION BOX VALVE SHELTER


FOOTING FOUNDATION
- Footing foundation, size: (0.6Wx0.6Lx0.2Thk) m 21 Ea 0.60 0.60 0.20 0.07
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.25D x 0.6H) m 21 Ea 0.78 0.20 0.40 0.06
Sub-total =
GRADE BEAM
- Gr.-beam (200Wx250D) mm 2 Ea 12.00 0.20 0.25 0.60
- - ditto - 2 Ea 5.00 0.20 0.25 0.25
Sub-total =
R PIG LAUNCHER FOUNDATION TBBM LOMANIS
FOOTING FOUNDATION
- Footing foundation, size: (1.5Wx1.5Lx0.35Thk) m 2 Ea 1.50 1.50 0.35 0.79
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 220 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
PEDESTAL
- Pedestal: (0.4W x 0.8D x 0.9H) m 2 Ea 0.80 0.40 0.90 0.29
Sub-total =
GRADE BEAM AND CONC. FLOOR (TOC.EL. +0.100)
- Gr.-beam (250Wx500D) mm 1 Ea 4.50 0.25 0.50 0.56
Sub-total =
CONCRETE FLOOR 120mm Thk.( 1-layer rebar Ø10-200)
- Area of concrete floor 1 Set Area (m2)= 10.80 0.12 1.30
- Conc. floor terrace 120 mm Thk (1-layers wiremesh M8) 2 Ea 6.90 1.50 0.12 1.24
- ditto - 2 Ea 2.40 1.20 0.12 0.35
- Reinf. beam terrace floor, (0.15W x 0.2D)m 2 Ea 6.90 0.15 0.20 0.21
- ditto - 2 Ea 5.40 0.15 0.20 0.16
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 2 Ea 1.60 1.60 0.05 0.13
- Lean conc. 50mm thk u/ grade beam 1 Ea 0.60 0.35 0.05 0.01
- Lean conc. 50mm thk u/ concrete floor 1 Ea 4.50 2.40 0.05 0.54
Sub-total =
S PIG RECEIVER FOUNDATION TBBM TASIKMALAYA
FOOTING FOUNDATION
- Footing foundation, size: (1.5Wx1.5Lx0.35Thk) m 2 Ea 1.50 1.50 0.35 0.79
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 221 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
PEDESTAL
- Pedestal: (0.4W x 0.8D x 0.9H) m 2 Ea 0.40 0.80 0.90 0.29
Sub-total =
GRADE BEAM AND CONC. FLOOR (TOC.EL. +0.100)
- Gr.-beam (250Wx500D) mm 1 Ea 4.50 0.25 0.50 0.56
Sub-total =
CONCRETE FLOOR 120mm Thk.( 1-layer rebar Ø10-200)
- Area of concrete floor 1 Set Area (m2)= 15.60 0.12 1.87
- Conc. floor terrace 120 mm Thk (1-layers wiremesh M8) 2 Ea 3.90 1.50 0.12 0.70
- ditto - 2 Ea 1.50 1.20 0.12 0.22
- Reinf. beam terrace floor, (0.15W x 0.2D)m 2 Ea 3.90 0.15 0.20 0.12
- ditto - 2 Ea 9.00 0.15 0.20 0.27
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 2 Ea 1.60 1.60 0.05 0.13
- Lean conc. 50mm thk u/ grade beam 1 Ea 0.60 0.35 0.05 0.01
- Lean conc. 50mm thk u/ concrete floor 1 Ea 6.50 2.40 0.05 0.78
Sub-total =
T PERIMETER DRAINAGE FOR NEW FACILITY TBBM LOMANIS
Concrete structure K-225
- 1/2 Ø Hollow Concrete Precast 1 m 355.00 0.60 0.50 12.54

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 222 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =
Non structure concrete K-150
- Lean concrete 50 mm thickness 1 m 355.00 0.70 0.05 12.43
Sub-total =

U FENCE FOUNDATION
Chain Link Fence ( Length = 146 m)
FOOTING FOUNDATION
- Footing foundation Pull Post, size: (0.8Wx0.8Lx0.25Thk.) m 13 Ea 0.80 0.80 0.25 0.16
Sub-total =
PEDESTAL
- Pedestal Pull Post : (0.3W x 0.3D x 0.45H) m 13 Ea 0.30 0.30 0.45 0.04
- Pedestal Line Post : (0.3W x 0.3D x 0.73H) m 36 Ea 0.30 0.30 0.45 0.04
Sub-total =
Non structure concrete K-150
- Lean concrete K-150 13 Ea 0.90 0.95 0.05 0.04
- Lean concrete K-150 36 Ea 0.40 0.40 0.05 0.01
Sub-total =

V PIPE SUPPORT TYPE 1 (PS-001~PS-003, PS-010 ~PS-014)


Concrete structure K-225
FOOTING FOUNDATION
- Footing foundation, size: (1Wx1Lx0.3Thk) m 8 Ea 1.00 1.00 0.30 0.30

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 223 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Sub-total =
PEDESTAL
- Pedestal: (0.3W x 1D x 0.6H) m 8 Ea 0.30 1.00 0.60 0.18
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 8 Ea 1.10 1.10 0.05 0.06
Sub-total =

W PIPE SUPPORT TYPE 2 (PS-004, PS-007 ~PS-009)


Concrete structure K-225
FOOTING FOUNDATION
- Footing foundation, size: (1Wx1.5Lx0.3Thk) m 4 Ea 1.50 1.00 0.30 0.45
Sub-total =
PEDESTAL
- Pedestal: (0.3W x 1.5D x 0.6H) m 4 Ea 0.30 1.50 0.60 0.27
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 4 Ea 1.60 1.10 0.05 0.09
Sub-total =

X PIPE SUPPORT TYPE 3 (PS-005 ~PS-006)


Concrete structure K-225
FOOTING FOUNDATION

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 224 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- Footing foundation, size: (1Wx2.4Lx0.3Thk) m 2 Ea 2.40 1.00 0.30 0.72
Sub-total =
PEDESTAL
- Pedestal: (0.3W x 2.4D x 0.6H) m 2 Ea 0.30 2.40 0.60 0.43
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 2 Ea 2.50 1.10 0.05 0.14
Sub-total =

Y PIPE SUPPORT TYPE 4 (PS-015, PS-017~PS-023, PS-025, PS-027, PS-033~PS-036)


Concrete structure K-225
FOOTING FOUNDATION
- Footing foundation, size: (1.2Wx1.2Lx0.3Thk) m 14 Ea 1.20 1.20 0.30 0.43
Sub-total =
PEDESTAL
- Pedestal: (0.35W x 0.35D x 0.6H) m 14 Ea 0.35 0.35 0.60 0.07
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 14 Ea 1.30 1.30 0.05 0.08
Sub-total =

Z PIPE SUPPORT TYPE 5 (PS-016, PS-024, PS-026, PS-028)


Concrete structure K-225

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 225 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
FOOTING FOUNDATION
- Footing foundation, size: (1Wx1.4Lx0.3Thk) m 4 Ea 1.00 1.40 0.30 0.42
Sub-total =
PEDESTAL
- Pedestal: (0.35W x 0.76D x 0.6H) m 4 Ea 0.76 0.35 0.60 0.16
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 4 Ea 1.50 1.10 0.05 0.08
Sub-total =
AA PIPE SUPPORT TYPE 6 (PS-029, PS-031, PS-032)
Concrete structure K-225
FOOTING FOUNDATION
- Footing foundation, size: (1.2Wx1.2Lx0.3Thk) m 3 Ea 1.20 1.20 0.30 0.43
Sub-total =
PEDESTAL
- Pedestal: (0.35W x 0.35D x 0.6H) m 3 Ea 0.76 0.35 0.60 0.16
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 3 Ea 1.30 1.30 0.05 0.08
Sub-total =
AB PIPE SUPPORT TYPE 7 (PS-030)
Concrete structure K-225
FOOTING FOUNDATION

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 226 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- Footing foundation, size: (1.2Wx2.5Lx0.3Thk) m 1 Ea 2.50 1.20 0.30 0.90
Sub-total =
PEDESTAL
- Pedestal: (0.35W x 0.35D x 0.6H) m 2 Ea 0.35 0.35 0.60 0.07
Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 1 Ea 2.60 1.30 0.05 0.17
Sub-total =

AC PIPE BRIDGE (LANGKAP LANCAR BRIDGE KP 79+326)


Concrete structure K-275
- Pilecap-4PC pile dia 350, sizes: (2.6Wx3.1Lx0.4Thk) m, for 2 Ea 3.10 2.60 0.40 3.22
Pipe Bridge fdn
Sub-total =

PEDESTAL
- Pedestal: (0.5W x 0.5D x 1.8H) m 8 Ea 0.50 0.50 1.80 0.45
Sub-total =
CONCRETE FLOOR 120mm Thk.( 1-layer rebar Ø10-200)
- Area of concrete floor 2 Set Area (m2)= 33.52 0.12 4.02

Sub-total =
Non structure concrete K-150

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 227 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
- Lean conc. 50mm thk u/ footing 2 Ea 3.20 2.70 0.05 0.43
- Lean conc. 50mm thk u/ concrete floor 2 Ea 8.10 4.20 0.05 1.70
Sub-total =

AD PIPE BRIDGE (AWIPARI BRIDGE KP 121+600)


Concrete structure K-275
- Pilecap-4PC pile dia 350, sizes: (2.6Wx3.1Lx0.4Thk) m, for 2 Ea 3.10 2.60 0.40 3.22
Pipe Bridge fdn
Sub-total =

PEDESTAL
- Pedestal: (0.5W x 0.5D x 1.8H) m 8 Ea 0.50 0.50 1.80 0.45
Sub-total =
CONCRETE FLOOR 120mm Thk.( 1-layer rebar Ø10-200)
- Area of concrete floor 2 Set Area (m2)= 33.52 0.12 4.02

Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 2 Ea 3.20 2.70 0.05 0.43
- Lean conc. 50mm thk u/ concrete floor 2 Ea 8.10 4.20 0.05 1.70
Sub-total =

AE PIPE BRIDGE (CONDONG BRIDGE KP 124+000)

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 228 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Concrete structure K-275
- Pilecap-4PC pile dia 350, sizes: (2.6Wx3.1Lx0.4Thk) m, for 2 Ea 3.10 2.60 0.40 3.22
Pipe Bridge fdn
Sub-total =

PEDESTAL
- Pedestal: (0.5W x 0.5D x 1.8H) m 8 Ea 0.50 0.50 1.80 0.45
Sub-total =
CONCRETE FLOOR 120mm Thk.( 1-layer rebar Ø10-200)
- Area of concrete floor 2 Set Area (m2)= 33.52 0.12 4.02

Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 2 Ea 3.20 2.70 0.05 0.43
- Lean conc. 50mm thk u/ concrete floor 2 Ea 8.10 4.20 0.05 1.70
Sub-total =

AF PIPE BRIDGE (CINTAPADA BRIDGE KP 125+440)


Concrete structure K-275
- Pilecap-4PC pile dia 350, sizes: (2.6Wx3.1Lx0.4Thk) m, for 2 Ea 3.60 2.60 0.40 3.74
Pipe Bridge fdn
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 229 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
PEDESTAL
- Pedestal: (0.5W x 0.5D x 1.8H) m 8 Ea 0.50 0.50 1.80 0.45
Sub-total =
CONCRETE FLOOR 120mm Thk.( 1-layer rebar Ø10-200)
- Area of concrete floor 2 Set Area (m2)= 35.62 0.12 4.27

Sub-total =
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 2 Ea 3.70 2.70 0.05 0.50
- Lean conc. 50mm thk u/ concrete floor 2 Ea 8.60 4.20 0.05 1.81
Sub-total =

AG WALKWAY PLATFORM FOUNDATION


Concrete structure K-225
- Footing foundation, size: (0.8Wx1.6Lx0.25Thk) m 2 Ea 1.60 0.80 0.25 0.32
Sub-total =
PEDESTAL
- Pedestal: (0.25W x 0.35D x 0.425H) m 4 Ea 0.35 0.25 0.43 0.04
Sub-total =
CONCRETE LANDING
- Concrete Landing (1.0Wx1.4Lx0.225Thk) m 2 Ea 1.00 1.40 0.23 0.32
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 230 of 358
MTO DETAIL REINFORCED CONCRETE
FOR BUILDING, SHELTER FOUNDATION, EQUIPMENT FOUNDATION, ROAD & PAVEMENT, DRAINAGE, ETC REINFORCED CO
PIPANISASI CB-III (LOMANIS - TASIKMALAYA)

QUANTITY OF
SIZE (m) OF MEMBERS PER UNIT CONCRETE VOLUME
M'BERS
DESCRIPTION OF REINFORCED CONCRETE STRUCTURE AND L / High /
NO. Nos.of Depth or
MEMBERS CONCRETE STRUCTURE Permtr.lengt Width W Vol./Nos m'ber
m'bers Unit thickness
h
(a) (b) (c) (d) (e) = (b)x(c)x(d)
Non structure concrete K-150
- Lean conc. 50mm thk u/ footing 2 Ea 1.70 0.90 0.05 0.08
- Lean conc. 50mm thk u/ concrete landing 2 Ea 1.50 1.10 0.05 0.08
Sub-total =

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 231 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

25.08 78.00 1,956.24

25.08 1,956.24

0.92
0.92

22.50 140.00 3,150.00

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 232 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
22.50 3,150.00

4.03 138.00 556.42


4.03 556.42

9.00 114.00 1,026.00


9.00 114.00 1,026.00
18.00 2,052.00

23.16 58.00 1,343.56

11.66 47.00 548.21


2.88 47.00 135.36
1.94 191.00 371.30
0.78 191.00 148.98
40.43 2,547.41

12.16 83.00 1,008.87


17.82 58.00 1,033.56
13.50 83.00 1,120.50
43.48 3,162.93

5.24 129.00 676.17

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 233 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
10.00 109.00 1,090.00
15.24 1,766.17

1.27 39.00 49.34


1.27 49.34

4.37
15.00
4.86
1.20
25.43

0.98 171.00 167.58


0.98 167.58

0.41 263.00 106.52


0.41 106.52

0.72 119.00 85.68


0.66 119.00 78.54

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 234 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.38 164.22

2.27 76.00 172.19

3.89 47.00 182.74


1.58 47.00 74.45
0.65 191.00 123.77
0.69 191.00 131.79
9.08 684.93

0.32
0.83
1.62
0.66
3.43

5.40 140.00 756.00


5.40 756.00

1.01 284.00 286.27

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 235 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.01 286.27

3.40 103.00 350.20


1.20 103.00 123.60
4.60 473.80

11.13 100.00 1,113.19

6.98 47.00 328.25


1.73 47.00 81.22
1.16 191.00 222.32
0.54 191.00 103.14
21.55 1,848.12

10.08 110.00 1,108.80


10.08 1,108.80

1.16
5.10
2.91
0.72
9.89

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 236 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

5.40 140.00 756.00


5.40 756.00

1.01 284.00 286.27


1.01 286.27

3.40 103.00 350.20


1.20 103.00 123.60
4.60 473.80

11.13 100.00 1,113.19

6.98 47.00 328.25


1.73 47.00 81.22
1.16 191.00 222.32
0.54 191.00 103.14
21.55 1,848.12

10.08 110.00 1,108.80


10.08 1,108.80

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 237 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

1.16
5.10
2.91
0.72
9.89

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 238 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 239 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
2.10 154.00 323.40
0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 240 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
6.14 138.00 847.87
6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 241 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.20 136.00 163.20
0.50 136.00 68.00
1.70 231.20

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13
1.72

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 242 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 243 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

1.30
0.30
0.13
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

6.14 138.00 847.87


6.14 847.87

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 244 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 245 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.70 231.20

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13
1.72

1.51 193.00 291.82

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 246 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 247 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
0.30
0.13
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 248 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 249 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13
1.72

1.51 193.00 291.82


1.51 291.82

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 250 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.30 202.00 263.00
1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40


0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 251 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

6.14 138.00 847.87


6.14 847.87

0.50 175.00 86.80


0.50 86.80

2.10 154.00 323.40

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 252 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
0.88 154.00 134.75
2.98 458.15

1.30
0.30
0.13
1.72

1.51 193.00 291.82


1.51 291.82

1.30 202.00 263.00


1.30 263.00

1.20 136.00 163.20


0.50 136.00 68.00
1.70 231.20

1.58 123.00 193.73


1.58 193.73

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 253 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

0.58 119.00 68.54


0.58 68.54

0.56 101.00 56.81


0.56 56.81

1.30 76.00 98.50

2.48 47.00 116.75


0.69 47.00 32.49
0.41 191.00 79.07
0.32 191.00 61.88
5.21 388.69

0.26
0.01
0.54
0.81

1.58 123.00 193.73


1.58 193.73

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 254 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

0.58 119.00 68.54


0.58 68.54

0.56 101.00 56.81


0.56 56.81

1.87 76.00 142.27

1.40 47.00 65.99


0.43 47.00 20.30
0.23 191.00 44.69
0.54 191.00 103.14
4.48 376.40

0.26
0.01
0.78
1.05

12.54 12.00 150.48

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 255 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
12.54 150.48

12.43
12.43

2.08 145.00 301.60


2.08 301.60

0.53 284.00 149.53


1.46 284.00 414.07
1.98 563.60

0.56
0.29
0.84

2.40 130.00 312.00

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 256 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
2.40 312.00

1.44 186.00 267.84


1.44 267.84

0.48 `
0.48

1.80 123.00 221.40


1.80 221.40

1.08 149.00 160.92


1.08 160.92

0.35
0.35

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 257 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
1.44 118.00 169.92
1.44 169.92

0.86 122.00 105.41


0.86 105.41

0.28
0.28

6.05 150.00 907.20


6.05 907.20

1.03 152.00 156.41


1.03 156.41

1.18
1.18

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 258 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

1.68 124.00 208.32


1.68 208.32

0.64 88.00 56.18


0.64 56.18

0.33
0.33

1.30 150.00 194.40


1.30 194.40

0.48 152.00 72.78


0.48 72.78

0.25
0.25

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 259 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
0.90 114.00 102.60
0.90 102.60

0.15 152.00 22.34


0.15 22.34

0.17
0.17

6.45 79.00 509.39

6.45 509.39

3.60 222.00 799.20


3.60 799.20

8.04 76.00 611.40

8.04 611.40

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 260 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)
0.86
3.40
4.27

6.45 79.00 509.39

6.45 509.39

3.60 222.00 799.20


3.60 799.20

8.04 76.00 611.40

8.04 611.40

0.86
3.40
4.27

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 261 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

6.45 79.00 509.39

6.45 509.39

3.60 222.00 799.20


3.60 799.20

8.04 76.00 611.40

8.04 611.40

0.86
3.40
4.27

7.49 79.00 591.55

7.49 591.55

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 262 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

3.60 222.00 799.20


3.60 799.20

8.55 76.00 649.71

8.55 649.71

1.00
3.61
4.61

0.64 128.00 81.92


0.64 81.92

0.15 163.00 24.25


0.15 24.25

0.63 55.00 34.65


0.63 34.65

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 263 of 358
NFORCED CONCRETE STRUCTURE

RETE VOLUME (m3) WEIGHT OF RE-BAR

Unit conc.vol &


Tot. Vol.Nos
area : (kg/m3) Total weight (kg)
m'ber
or (kg/m2)*
(f) = (a)x(e) (g) (h) = (f)x(g)

0.15
0.17
0.32

___________________________________________________________________________________________________________________________________________
Doc. No. CB3-EC-50-MT-001-A4 Rev. 1
Att. D Page 264 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
PILECAP

1 1-Unit Pilecap Sqr- for 1PC Pile D250-Dia.(mm) = 0.25

Sizes: W width = 0.75 0.28


L length or Prmtr length = 0.75
D depth, H hight or Th'k = 0.50
Reinforcing-Bar D16 (Top & Bott.)
- Lat.Bar D16-200 (top&bot.) 5 Ea
- Transv. Bar D16-200 (top&bot.) 5 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar

2 1-Unit Pilecap Sqr- for 1PC Pile D300-Dia.(mm) = 0.30

Sizes: W width = 0.90 0.49


L length or Prmtr length = 0.90
D depth, H hight or Th'k = 0.60
Reinforcing-Bar D16 (Top & Bott.)
- Lat.Bar D16-200 (top&bot.) 6 Ea
- Transv. Bar D16-200 (top&bot.) 6 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar

3 1-Unit Pilecap Sqr- for 1PC Pile D400-Dia.(mm) = 0.40

Sizes: W width = 1.20 0.86


L length or Prmtr length = 1.20
D depth, H hight or Th'k = 0.60
Reinforcing-Bar D16 (Top & Bott.)
- Lat.Bar D16-200 (top&bot.) 7 Ea
- Transv. Bar D16-200 (top&bot.) 7 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar

3 1-Unit Pilecap Sqr- for 1PC Pile D400-Dia.(mm) = 0.40

Sizes: W width = 1.20 0.86


UNIT-WEIGHT REBAR TBBM TGL BR Page 265 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
L length or Prmtr length = 1.20
D depth, H hight or Th'k = 0.60
Reinforcing-Bar D16 (Top & Bott.)
- Lat.Bar D16-150 (top&bot.) 9 Ea
- Transv. Bar D16-150 (top&bot.) 9 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar

1-Unit Pilecap Rect- for 2PC Pile@D250-Dia.(mm)


4 0.25
=
Sizes: W width = 0.75 0.56
L length or Prmtr length = 1.50
D depth, H hight or Th'k = 0.50
Reinforcing-Bar D16 (Top & Bott.)
- Lat-Main-Bar D16-150 (top&bot.) 6 Ea
- Ties-Transv.Bar D13-150 (top&bot) 9 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar

1-Unit Pilecap Rect- for 2PC Pile@D300-Dia.(mm)


5 0.30
=
Sizes: W width = 0.90 0.97
L length or Prmtr length = 1.80
D depth, H hight or Th'k = 0.60
Reinforcing-Bar D16 (Top & Bott.)
- Lat-Main-Bar D16-150 (top&bot.) 7 Ea
- Ties-Transv.Bar D13-150 (top&bot) 10 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar

1-Unit Pilecap Rect- for 3-PC Pile @ D350-Dia.


6 0.35
(mm) =
Sizes: W width = 1.20 2.66
L length or Prmtr length = 3.70
D depth, H hight or Th'k = 0.60
Reinforcing-Bar
- Lat-Main-Bar D19-200 (top&bot.) 7 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 266 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Ties-Transv.Bar D16-200 (top&bot) 20 Ea
- Side Bar 1-D13 1 Ea

1-Unit Pilecap Rect- for 2PC Pile@D400-Dia.(mm)


7 0.40
=
Sizes: W width = 1.20 1.73
L length or Prmtr length = 2.40
D depth, H hight or Th'k = 0.60
Reinforcing-Bar:
- Lat-Main-Bar D16-150 (top&bot.) 9 Ea
- Ties-Transv.Bar D13-150 (top&bot) 17 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar -

1-Unit Pilecap Rectangular (normal) - for 4PC


8 0.40
Pile@D400-Dia.(mm) =
Sizes: W width = 2.40 3.46
L length or Prmtr length = 2.40
D depth, H hight or Th'k = 0.60
Reinforcing-Bar:
- Lat-Main-Bar D16-150 (top&bot.) 17 Ea
- Ties-Transv.Bar D13-150 (top&bot) 17 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar

1-Unit Pilecap Rectangular (extended) - for 4PC


9 0.40
Pile@ D400-Dia.(mm) =
Sizes: W width = 2.40 4.61
L length or Prmtr length = 3.20
D depth, H hight or Th'k = 0.60
Reinforcing-Bar:
- Lat-Main-Bar D16-150 (top&bot.) 17 Ea
- Ties-Transv.Bar D13-150 (top&bot) 22 Ea
- Side Bar 1-D13 1 Ea
- Vertical supp./ Cross bar -

UNIT-WEIGHT REBAR TBBM TGL BR Page 267 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

10 1-Unit Pilecap Sqr- for 1PC Pile D200-Dia.(mm) = 0.20

Sizes: W width = 0.60 0.16


L length or Prmtr length = 0.60
D depth, H hight or Th'k = 0.45
Reinforcing-Bar D13 (Top & Bott.)
- Lat.Bar D13-200 (top&bot.) 4 Ea
- Transv. Bar D13-200 (top&bot.) 4 Ea
- Side Bar 1-D13 Ea
- Vertical supp./ Cross bar

11 1-Unit Pilecap Sqr- for 4PC Pile 200-.(mm) = 0.20

Sizes: W width = 1.90 1.88


L length or Prmtr length = 2.20
D depth, H hight or Th'k = 0.45
Reinforcing-Bar D13 (Top & Bott.)
- Lat.Bar D16-200 (top&bot.) 11 Ea
- Transv. Bar D13-200 (top&bot.) 12 Ea
- Side Bar 1-D13
- Vertical supp./ Cross bar

11 1-Unit Pilecap Sqr- for 4PC Pile dia350-.(mm) = 0.35

Sizes: W width = 2.60 3.22


L length or Prmtr length = 3.10
D depth, H hight or Th'k = 0.40
Reinforcing-Bar D13 (Top & Bott.)
- Lat.Bar D16-200 (top&bot.) 14 Ea
- Transv. Bar D13-200 (top&bot.) 17 Ea
- Side Bar 1-D13
- Vertical supp./ Cross bar

UNIT-WEIGHT REBAR TBBM TGL BR Page 268 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

12 1-Unit Pilecap Sqr- for 2PC Pile D200-Dia.(mm) = 0.20


Sizes: W width = 0.60 0.32
L length or Prmtr length = 1.20
D depth, H hight or Th'k = 0.45
Reinforcing-Bar D13 (Top & Bott.)
- Lat.Bar D16-150 (top&bot.) 5 Ea
- Transv. Bar D13-150 (top&bot.) 9 Ea
- Side Bar 1-D13
- Vertical supp./ Cross bar

PEDESTAL
1 1M3 Pedestal 300x300
Sizes: W width = 0.30 1.00
D Thick. = 0.30
H High = 11.11
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
- Main bar diameter D = 16.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-150 = 75 Ea

2 1M3 Pedestal 250x250


Sizes: W width = 0.25 1.00
D Thick. = 0.25
H High = 16.00
Thickness of pilecap or footing fdn, Th'k = 0.25
Reinforcing-Bar
- Main bar diameter D = 13.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-200 = 81 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 269 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

3 1M3 Pedestal 250x250


Sizes: W width = 0.25 1.00
D Thick. = 0.25
H High = 16.00
Thickness of pilecap or footing fdn, Th'k = 0.30
Reinforcing-Bar
- Main bar diameter D = 13.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-150 = 108 Ea

3 1M3 Pedestal 300x300


Sizes: W width = 0.30 1.00
D Thick. = 0.30
H High = 11.11
Thickness of pilecap, Th'k = 0.30
Reinforcing-Bar
- Main bar diameter D = 16.00 mm
- Nos of main-Bar = 12 Ea
- Nos of Ties Ø10-150 = 75 Ea

4 1M3 Pedestal 350x350


Sizes: W width = 0.35 1.00
D Thick. = 0.35
H High = 8.16
Thickness of pilecap, Th'k = 0.30
Reinforcing-Bar
- Main bar diameter D = 16.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-200 = 42 Ea

4 1M3 Pedestal 350x760


Sizes: W width = 0.35 1.00
UNIT-WEIGHT REBAR TBBM TGL BR Page 270 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
D Thick. = 0.76
H High = 3.76
Thickness of pilecap, Th'k = 0.30
Reinforcing-Bar
- Main bar diameter D = 16.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-200 = 20 Ea

5 1M3 Pedestal 225x300


Sizes: W width = 0.23 1.00
D Thick. = 0.30
H High = 14.81
Thickness of pilecap, Th'k = 0.25
Reinforcing-Bar
- Main bar diameter D = 16.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-150 = 100 Ea

6 1M3 Pedestal 400x400


Sizes : W width = 0.40 1.00
D Thick. = 0.40
H High = 6.25
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
- Main bar diameter D = 16.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-150 = 43 Ea

7 1M3 Pedestal 400x400


Sizes : W width = 0.40 1.00
D Thick. = 0.40
H High = 6.25
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
- Main bar diameter D = 16.00 mm
- Nos of main-Bar = 12 Ea
- Nos of Ties Ø10-150 = 43 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 271 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

8 1M3 Pedestal 450x450


Sizes : W width = 0.45 1.00
D Thick. = 0.45
H High = 4.94
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 12 Ea
- Nos of Ties Ø10-150 = 34 Ea

8 1M3 Pedestal 500x500


Sizes : W width = 0.50 1.80
D Thick. = 0.50
H High = 7.20
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 12 Ea
- Nos of Ties Ø10-150 = 49 Ea

9 1M3 Pedestal 250 X 350


Sizes : W width = 0.25 1.00
D Thick. = 0.35
H High = 11.43
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 6 Ea
- Nos of Ties Ø10-200 = 58 Ea

9 1M3 Pedestal 200 X 400


Sizes : W width = 0.20 1.00
D Thick. = 0.40
H High = 12.50
UNIT-WEIGHT REBAR TBBM TGL BR Page 272 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Thickness of pilecap, Th'k = 0.30
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 6 Ea
- Nos of Ties Ø10-200 = 64 Ea

9 1M3 Pedestal 400 X 800


Sizes : W width = 0.40 1.00
D Thick. = 0.80
H High = 3.13
Thickness of pilecap, Th'k = 0.35
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 14 Ea
- Nos of Ties Ø10-200 = 17 Ea

10 1M3 Pedestal 500x1200


Sizes : W width = 0.50 1.00
D Thick. = 1.20
H High = 1.67
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 20 Ea
- Nos of Ties Ø10-150 = 12 Ea

10 1M3 Pedestal 300x1000


Sizes : W width = 0.30 1.00
D Thick. = 1.00
H High = 3.33
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 20 Ea
- Nos of Ties Ø10-150 = 23 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 273 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

10 1M3 Pedestal 300x1500


Sizes : W width = 0.30 1.00
D Thick. = 1.50
H High = 2.22
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 20 Ea
- Nos of Ties Ø10-150 = 16 Ea

10 1M3 Pedestal 300x2400


Sizes : W width = 0.30 1.00
D Thick. = 2.40
H High = 1.39
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 20 Ea
- Nos of Ties Ø10-150 = 10 Ea

11 1M3 Pedestal 500x3300


Sizes : W width = 0.50 2.31
D Thick. = 3.30
H High = 1.40
Thickness of pilecap, Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 78 Ea
- Nos of Ties Ø10-200 = 7 Ea

COLUMN
1 1-M3 second./ Non structural Column 120x120
Sizes : W width = 0.12 1.00
D Thick. = 0.12
UNIT-WEIGHT REBAR TBBM TGL BR Page 274 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
H High = 69.44
Reinforcing-Bar
Main bar diameter Ø = 12.00 mm
- Nos of main-Bar = 4 Ea
- Nos of Ties Ø10-200- = 347 Ea

2 1-M3 Column 200x200, main bar 4-D13


Sizes : W width = 0.20 1.00
D Thick. = 0.20
H High = 25.00
Reinforcing-Bar
Main bar diameter D = 13.00 mm
- Nos of main-Bar = 4 Ea
- Nos of Ties Ø10-150 = 167 Ea

3 1-M3 Column 250x250, main bar 8-D13


Sizes : W width = 0.25 1.00
D Thick. = 0.25
H High = 16.00
Reinforcing-Bar
Main bar diameter D = 13.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-150 = 107 Ea

4 1-M3 Column 250x250, main bar 8-D13


Sizes : W width = 0.25 1.00
D Thick. = 0.25
H High = 16.00
Reinforcing-Bar
Main bar diameter D = 13.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-200 = 80 Ea

5 1-M3 Column 300x300, main bar 8-D13


Sizes : W width = 0.30 1.00
UNIT-WEIGHT REBAR TBBM TGL BR Page 275 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
D Thick. = 0.30
H High = 11.11
Reinforcing-Bar
Main bar diameter D = 13.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-150 = 74 Ea

6 1-M3 Column 300x300, main bar 12-D13


Sizes : W width = 0.30 1.00
D Thick. = 0.30
H High = 11.11
Reinforcing-Bar
Main bar diameter D = 13.00 mm
- Nos of main-Bar = 12 Ea
- Nos of Ties Ø10-150 = 74 Ea

7 1-M3 Column 350x350, main bar 8-D16, ties: Ø10-150


Sizes : W width = 0.35 1.00
D Thick. = 0.35
H High = 8.16
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 8 Ea
- Nos of Ties Ø10-150 = 54 Ea

8 1-M3 Column 400x400 Mian bar 12-D16


Sizes : W width = 0.40 1.00
D Thick. = 0.40
H High = 6.25

Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 12 Ea
- Nos of Ties Ø10-150 = 42 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 276 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
9 1-M3 Column 300x700 Mian bar 16-D16 (Control room & office Bdg)
Sizes : W width = 0.70 1.00
D Thick. = 0.30
H High = 4.76

Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Nos of main-Bar = 16 Ea
- Nos of Ties Ø12-150 = 32 Ea

GRADE BEAM
1 1-M3 beam: (150Wx200D) mm, main bar 4-Ø12
Sizes : W width (m) = 0.15 1.00
D depth, H hight or Th'k (m) = 0.20
L length or Prmtr length (m) = 33.33
Reinforcing-Bar
Main-bar size dia.= 12.00 mm
- Main-Bar 4-Ø12 (2-Top & 2-bott) 4 Ea
- Ties Ø10-200 168 Ea

2 1-M3 beam: (200Wx300D) mm, main bar 4-Ø12


Sizes : W width (m) = 0.20 1.00
D depth, H hight or Th'k (m) = 0.30
L length or Prmtr length (m) = 16.67
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 4-Ø13 (2-Top & 2-bott) 4 Ea
- Ties Ø10-200 84 Ea

2 1-M3 beam: (200Wx250D) mm, main bar 4-Ø12


Sizes : W width (m) = 0.20 1.00
D depth, H hight or Th'k (m) = 0.25
L length or Prmtr length (m) = 20.00
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 4-Ø13 (2-Top & 2-bott) 4 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 277 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Ties Ø10-200 101 Ea

3 1-M3 beam: (250Wx300D) mm, main bar 6-D13


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.30
L length or Prmtr length (m) = 13.33
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (2-Top & 2-bott) 6 Ea
- Ties Ø10-100 134 Ea

3 1-M3 beam: (250Wx350D) mm, main bar 6-D13


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.35
L length or Prmtr length (m) = 11.43
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (2-Top & 2-bott) 6 Ea
- Ties Ø10-100 115 Ea

4 1-M3 Grade Beam: (250Wx450D) mm, main bar 6-D16


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.45
L length or Prmtr length (m) = 8.89
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 6-D16 (3-Top & 3-bott) 6 Ea
- Ties Ø10-200 44 Ea

5 1-M3 Grade Beam: (250Wx400D) mm, main bar 6-D13


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.40
L length or Prmtr length (m) = 10.00
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
UNIT-WEIGHT REBAR TBBM TGL BR Page 278 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Main-Bar 6-D13 (3-Top & 3-bott) 6 Ea
- Ties Ø10-200 50 Ea

6 1-M3 Grade Beam: (250Wx400D) mm, main bar 6-D13


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.40
L length or Prmtr length (m) = 10.00
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (3-Top & 3-bott) 6 Ea
- Ties Ø10-150 67 Ea

6 1-M3 Grade Beam: (250Wx500D) mm, main bar 6-D13


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.50
L length or Prmtr length (m) = 8.00
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (3-Top & 3-bott) 6 Ea
- Ties Ø10-150 53 Ea

7 1-M3 Grade Beam: (300Wx400D) mm, main bar 10-D16


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.40
L length or Prmtr length (m) = 10.00
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 10-D16 (5-Top & 5-bott) 10 Ea
- Ties Ø10-200 50 Ea

8 1-M3 Grade beam: (300Wx500D) mm, main bar 7-D16


Sizes : W width (m) = 0.30 1.00
D depth, H hight or Th'k (m) = 0.50
L length or Prmtr length (m) = 6.67
UNIT-WEIGHT REBAR TBBM TGL BR Page 279 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 7-D16 7 Ea
- Side bar 2-Ø10 2 Ea
- Ties Ø10-200 33 Ea

9 1-M3 Grade beam: (300Wx500D) mm, main bar 6-D16


Sizes : W width (m) = 0.30 1.00
D depth, H hight or Th'k (m) = 0.50
L length or Prmtr length (m) = 6.67
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 6-D16 6 Ea
- Side bar 2-Ø10 2 Ea
- Ties Ø10-200 33 Ea

10 1-M3 Separator beam: (250Wx800D) mm, main bar 10-D13


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.80
L length or Prmtr length (m) = 5.00
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 10-Ø12 10 Ea
- Ties Ø10-200 26 Ea

1-St FLOOR BEAM


1 1-M3 Beam: (200Wx300D) mm, main bar 4-D16 Ties: Ø10-100
Sizes : W width (m) = 0.20 1.00
D depth, H hight or Th'k (m) = 0.30
L length or Prmtr length (m) = 16.67
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 4-D16 (3-Top & 3-bott) 4 Ea
- Ties Ø10-100 167 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 280 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

2 1-M3 Beam: (250Wx350D) mm, main bar 6-D16, Ties Ø10-100


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.35
L length or Prmtr length (m) = 11.43
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 6-D16 (3-Top & 3-bott) 6 Ea
- Ties Ø10-100 114 Ea

3 1-M3 Beam: (250Wx450D) mm. Main bar 6-D16, Ties Ø10-125


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.45
L length or Prmtr length (m) = 8.89
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 6-D16 (3-Top & 3-bott) 6 Ea
- Ties Ø10-125 71 Ea

4 1-M3 Beam: (300Wx400D) mm, main bar 7-D16, Ties Ø100-150


Sizes : W width (m) = 0.30 1.00
D depth, H hight or Th'k (m) = 0.40
L length or Prmtr length (m) = 8.33
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 7-D16 7 Ea
- Ties Ø10-150 56 Ea

5 1-M3 Beam: (300Wx450D) mm, main bar 7-D16, Ties Ø10-150


Sizes : W width (m) = 0.30 1.00
D depth, H hight or Th'k (m) = 0.45
L length or Prmtr length (m) = 7.41
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 7-D16 7 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 281 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Ties Ø10-150 49 Ea

6 1-M3 beam: (300Wx500D) mm, main bar 8-D16, Ties Ø10-125


Sizes : W width (m) = 0.30 1.00
D depth, H hight or Th'k (m) = 0.50
L length or Prmtr length (m) = 6.67
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 8-D16 8 Ea
- Side bar 2-Ø10 2 Ea
- Ties Ø10-125 53 Ea

7 1-M3 beam: (300Wx1050D) mm, main bar 10-D16, Ties Ø10-125


Sizes : W width (m) = 0.30 1.00
D depth, H hight or Th'k (m) = 1.05
L length or Prmtr length (m) = 3.17
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 10-D16 10 Ea
- Side bar 4-D16 4 Ea
- Ties Ø10-125 25 Ea

ROOF BEAM

1 1-M3 Beam: (150Wx200D) mm, main bar 6-D13, Ties: Ø10-200


Sizes : W width (m) = 0.15 1.00
D depth, H hight or Th'k (m) = 0.20
L length or Prmtr length (m) = 33.33
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 4-D13 (3Top & 3bott) 4 Ea
- Ties Ø10-200 167 Ea

2 1-M3 Beam: (200Wx300D) mm, main bar 6-D13, Ties: Ø10-200


UNIT-WEIGHT REBAR TBBM TGL BR Page 282 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Sizes : W width (m) = 0.20 1.00
D depth, H hight or Th'k (m) = 0.30
L length or Prmtr length (m) = 16.67
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (3-Top & 3-bott) 6 Ea
- Ties Ø10-200 83 Ea

3 1-M3 Beam: (200Wx300D) mm, main bar 6-D13, Ties: Ø10-100


Sizes : W width (m) = 0.20 1.00
D depth, H hight or Th'k (m) = 0.30
L length or Prmtr length (m) = 16.67
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (3-Top & 3-bott) 6 Ea
- Ties Ø10-100 167 Ea

4 1-M3 Beam: (250Wx300D) mm


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.30
L length or Prmtr length (m) = 13.33
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (2-Top & 2-bott) 6 Ea
- Ties Ø10-100 133 Ea

5 1-M3 Beam: (250Wx350D) mm


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.35
L length or Prmtr length (m) = 11.43
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (2-Top & 2-bott) 6 Ea
- Ties Ø10-200 57 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 283 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
6 1-M3 Beam: (250Wx350D) mm
Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.35
L length or Prmtr length (m) = 11.43
Reinforcing-Bar
Main-bar size dia.= 13.00 mm
- Main-Bar 6-D13 (2-Top & 2-bott) 6 Ea
- Ties Ø10-100 114 Ea

7 1-M3 Beam: (250Wx400D) mm


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.40
L length or Prmtr length (m) = 10.00
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 4-D16 4 Ea
- Ties Ø10-150 67 Ea

8 1-M3 Beam: (250Wx400D) mm, main bar 6-D16, Ties: Ø10-200


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.40
L length or Prmtr length (m) = 10.00
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 6-D16 (3-Top & 3-bott) 6 Ea
- Ties Ø10-200 50 Ea

9 1-M3 Beam: (250Wx400D) mm, main bar 6-D16, Ties: Ø10-100


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.40
L length or Prmtr length (m) = 10.00
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 6-D16 (3-Top & 3-bott) 6 Ea
- Ties Ø10-100 100 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 284 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

10 1-M3 Beam: (250Wx450D) mm, main bar 7-D16, Ties: Ø10-175


Sizes : W width (m) = 0.25 1.00
D depth, H hight or Th'k (m) = 0.45
L length or Prmtr length (m) = 8.89
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 7-D16 7 Ea
- Ties Ø10-175 51 Ea

11 1-M3 Beam: (300Wx400D) mm


Sizes : W width (m) = 0.30 1.00
D depth, H hight or Th'k (m) = 0.40
L length or Prmtr length (m) = 8.33
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 6-D16 (3-Top & 3-bott) 6 Ea
- Ties Ø10-150 56 Ea

12 1-M3 Beam: (300Wx450D) mm


Sizes : W width (m) = 0.30 1.00
D depth, H hight or Th'k (m) = 0.45
L length or Prmtr length (m) = 7.41
Reinforcing-Bar
Main-bar size dia.= 16.00 mm
- Main-Bar 6-D16 (3-Top & 3-bott) 6 Ea
- Ties Ø10-125 59 Ea

CONCRETE SLAB (FOR FLOOR & ROOF)


1-M3 Conc.Floor 200 mm th'k
Sizes : W width = 2.24 1.00
L length or Prmtr length = 2.24
D depth, H hight or Th'k = 0.20
Reinf-bar (2-layers, wiremesh M-8 c/c 150)
Main bar diameter = 8.00 mm
- Top layer Wiremesh M8-150 5.00 m2
UNIT-WEIGHT REBAR TBBM TGL BR Page 285 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Top layer Wiremesh M8-150 5.00 m2
- Support bar Ø10 31 Ea

1-M3 Conc.Floor 225 mm th'k


Sizes : W width = 2.11 1.00
L length or Prmtr length = 2.11
D depth, H hight or Th'k = 0.23
Reinf-bar (2-layers, wiremesh M-8 c/c 150)
Main bar diameter = 8.00 mm
- Top layer Wiremesh M8-150 4.44 m2
- Top layer Wiremesh M8-150 4.44 m2
- Support bar Ø10 28 Ea

1 1-M3 Conc.Floor 150 mm th'k


Sizes : W width = 2.58 1.00
L length or Prmtr length = 2.58
D depth, H hight or Th'k = 0.15
Reinforcing-Bar (2-layers)
Main bar diameter = 10.00 mm
- Lateral..Bar Ø10-200 (top&bot.) 28 Ea
- Transv..Bar Ø10-200 (top&bot.) 28 Ea
- Support bar Ø10 42 Ea

2 1-M3 Conc.floor 135 mm th'k


Sizes : W width = 2.72 1.00
L length or Prmtr length = 2.72
D depth, H hight or Th'k = 0.14
Reinforcing-Bar (2-layers)
Main bar diameter = 10.00 mm
- Lateral..Bar Ø10-200 (top&bot.) 29 Ea
- Transv..Bar Ø10-200 (top&bot.) 29 Ea
- Support bar Ø10 46 Ea

3 1-M3 Conc.floor 130 mm th'k


UNIT-WEIGHT REBAR TBBM TGL BR Page 286 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Sizes : W width = 2.77 1.00
L length or Prmtr length = 2.77
D depth, H hight or Th'k = 0.13
Reinforcing-Bar (2-layers)
Main bar diameter = 10.00 mm
- Lateral..Bar Ø10-200 (top&bot.) 30 Ea
- Transv..Bar Ø10-200 (top&bot.) 30 Ea
- Support bar Ø10 48 Ea

4 1-M3 Conc.roof 120 mm th'k


Sizes : W width = 2.89 1.00
L length or Prmtr length = 2.89
D depth, H hight or Th'k = 0.12
Reinforcing-Bar (2-layers)
Main bar diameter = 10.00 mm
- Lateral..Bar Ø10-200 (top&bot.) 31 Ea
- Transv..Bar Ø10-200 (top&bot.) 31 Ea
- Support bar Ø10 52 Ea

5 1-M3 Conc.roof 120 mm th'k


Sizes : W width = 2.89 1.00
L length or Prmtr length = 2.89
D depth, H hight or Th'k = 0.12
Reinforcing-Bar (1-layers)
Main bar diameter = 10.00 mm
- Lateral..Bar Ø10-200 15 Ea
- Transv..Bar Ø10-200 15 Ea
- Support bar Ø10 - Ea

6 1-M3 Conc.roof 120 mm th'k


Sizes : W width = 2.89 1.00
L length or Prmtr length = 2.89
D depth, H hight or Th'k = 0.12
Reinforcing-Bar (1-layers)
Main bar diameter = 10.00 mm
- Lateral..Bar Ø10-150 20 Ea
- Transv..Bar Ø10-150 20 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 287 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Support bar Ø10 - Ea

7 1-M3 Conc.floor 120 mm th'k


Sizes : W width = 2.89 1.00
L length or Prmtr length = 2.89
D depth, H hight or Th'k = 0.12
Reinf-Bar-1 layer wire mesh M8@150 8.33 m2
Overlap and splacing (5%)

8 1-M3 Conc.floor 100 mm th'k


Sizes : W width = 3.16 1.00
L length or Prmtr length = 3.16
D depth, H hight or Th'k = 0.10
Reinf-Bar-1 layer wire mesh M6@150 10.00 m2
Overlap and splacing (5%)

9 1-M3 Conc.floor 100 mm th'k


Sizes : W width = 3.16 1.00
L length or Prmtr length = 3.16
D depth, H hight or Th'k = 0.10
Reinf-Bar-1 layer wire mesh M8@150 10.00 m2
Overlap and splacing (5%)

10 1-M3 Conc.floor 100 mm th'k


Sizes : W width = 3.16 1.00
L length or Prmtr length = 3.16
D depth, H hight or Th'k = 0.10
Reinf-Bar-1 layer wire mesh M10@150 10.00 m2
Overlap and splacing (5%)

CONCRETE PARAPET
1 1-M3 For 800 mm high
UNIT-WEIGHT REBAR TBBM TGL BR Page 288 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Sizes : H high = 0.80 1.00
L length or Prmtr length = 12.50
Thickness = 0.10
Reinforcing-Bar
- Vert. bar Ø10-200 64 Ea
- Horz. Bar 5-Ø10 5 Ea

CONCRETE CANOPY
1 Conc. Canopy, size: (0.6W x 0.1Thick.) m
Sizes : W width = 0.60 0.06
L length or Prmtr length = 1.00 Vol.tot.=
D depth, H hight or Th'k = 0.10 0.08
Beam stiffener
Sizes : W width = 0.12 0.02
L length or Prmtr length = 1.00
D depth, H hight or Th'k = 0.20
Reinforcing-Bar
For conc. Canopy
- Main-Bar Ø12-100 (1-layer) 11 Ea
- lateral bar Ø10-150 5 Ea
- Main beam bar 4Ø12 4 Ea
- Ties Ø10-100 11 Ea

2 Conc. Canopy, size: (1.75W x 0.12Thick.) m


Sizes : W width = 1.75 0.21
L length or Prmtr length = 1.00 Vol.tot.=
D depth, H hight or Th'k = 0.12 0.23
Beam stiffener
Sizes : W width = 0.12 0.02
L length or Prmtr length = 1.00
D depth, H hight or Th'k = 0.20
Reinforcing-Bar
For conc. Canopy
- Main-Bar D13-100 (1-layer) 11 Ea
- lateral bar Ø10-150 13 Ea
- Main beam bar 4D13 4 Ea
- Ties Ø10-100 11 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 289 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

CONCRETE STAIRCASE
1-M3 CONCRETE STAIRCASE-1.50 M WIDTH
Floor staircase
Sizes : W-width stair = 1.50 0.23
1-m' length of stair = 1.00
D Th'k of stair = 0.15
3Ea- Tread un-tread (for 1-M' length stair) 0.36
W-width = 1.50 0.14
L length of tread = 0.28
D Th'k riser = 0.220
3xSection tread riser Area = 0.092
Reinforcing-Bar
150mm thk staircase floor
- Lat.bar Ø12-100 (Top&bott.) 32 Ea
- Transv. bar Ø10-200 (Top&bott.) 12 Ea
3Ea- Tread un-tread
- lat. bar Ø10 11 Ea
- Riser-tread bar Ø10-200 26 Ea

1-M3 Sub-Conc.floor 150 mm th'k "BORDES" stair


Sizes : W width = 1.35 0.82
L length or Prmtr length = 4.06
D depth, H hight or Th'k = 0.15
Reinforcing-Bar-2 layers
- Lateral..Bar Ø10-200 (Top&bot.) 16 Ea
- Transv..Bar Ø10-200 (Top&bot.) 43 Ea

Weight re-bar per 1M2 "BORD

FOOTING FOUNDATION
1 1M3 FOOTING FOUNDATION (0.6W x 0.6L) M
Sizes : W width = 0.60 0.07
L length or Prmtr length = 0.60
D depth, H hight or Th'k = 0.20
Reinforcing-Bar
- Lat.Bar Ø12-150 (top&bot.) 9 Ea
- Transv. Bar Ø12-150 (top&bot.) 9 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 290 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

2 1M3 FOOTING FOUNDATION (0.75W x 0.75L) M


Sizes : W width = 0.75 0.11
L length or Prmtr length = 0.75
D depth, H hight or Th'k = 0.20
Reinforcing-Bar
- Lat.Bar Ø12-150 (top&bot.) 11 Ea
- Transv. Bar Ø12-150 (top&bot.) 11 Ea

3 1M3 FOOTING FOUNDATION (0.8W x 0.8L) M


Sizes : W width = 0.80 0.16
L length or Prmtr length = 0.80
D depth, H hight or Th'k = 0.25
Reinforcing-Bar
- Lat.Bar Ø12-150 (top&bot.) 11 Ea
- Transv. Bar Ø12-150 (top&bot.) 11 Ea

3 1M3 FOOTING FOUNDATION (0.9W x 0.9L) M


Sizes : W width = 0.90 0.20
L length or Prmtr length = 0.90
D depth, H hight or Th'k = 0.25
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 13 Ea
- Transv. Bar D13-150 (top&bot.) 13 Ea

4 1M3 FOOTING FOUNDATION (1.2W x 1.2L) M


Sizes : W width = 1.20 0.36
L length or Prmtr length = 1.20
D depth, H hight or Th'k = 0.25
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 18 Ea
- Transv. Bar D13-150 (top&bot.) 18 Ea
- vert. supp.Cross bar D13 8 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 291 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

5 1M3 FOOTING FOUNDATION (1.2W x 1.2L) M


Sizes : W width = 1.20 0.43
L length or Prmtr length = 1.20
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D16-200 (top&bot.) 13 Ea
- Transv. Bar D16-200 (top&bot.) 13 Ea
- Side Bar 2-D13 2 Ea
- vert. supp.Cross bar D16 8 Ea

6 1M3 FOOTING FOUNDATION (1.2W x 1.5L) M


Sizes : W width = 1.20 0.54
L length or Prmtr length = 1.50
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D16-200 (top&bot.) 13 Ea
- Transv. Bar D16-200 (top&bot.) 16 Ea
- Side Bar 2-D13 2 Ea
- vert. supp.Cross bar D16 10 Ea

7 1M3 FOOTING FOUNDATION (0.7W x 0.7L) M


Sizes : W width = 0.70 0.12
L length or Prmtr length = 0.70
D depth, H hight or Th'k = 0.25
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 10 Ea
- Transv. Bar D13-150 (top&bot.) 10 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D13 4 Ea

7 1M3 FOOTING FOUNDATION (1W x 1L) M


Sizes : W width = 1.00 0.30
L length or Prmtr length = 1.00
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 14 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 292 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Transv. Bar D13-150 (top&bot.) 14 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D13 9 Ea

7 1M3 FOOTING FOUNDATION (1W x 1.5L) M


Sizes : W width = 1.00 0.45
L length or Prmtr length = 1.50
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 14 Ea
- Transv. Bar D13-150 (top&bot.) 21 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D13 14 Ea

7 1M3 FOOTING FOUNDATION (0.8W x 1.6L) M


Sizes : W width = 0.80 0.38
L length or Prmtr length = 1.60
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 11 Ea
- Transv. Bar D13-150 (top&bot.) 22 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D13 12 Ea

7 1M3 FOOTING FOUNDATION (1W x 1.4L) M


Sizes : W width = 1.00 0.42
L length or Prmtr length = 1.40
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 14 Ea
- Transv. Bar D13-150 (top&bot.) 19 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D13 13 Ea

7 1M3 FOOTING FOUNDATION (1W x 2.4L) M


UNIT-WEIGHT REBAR TBBM TGL BR Page 293 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Sizes : W width = 1.00 0.72
L length or Prmtr length = 2.40
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 14 Ea
- Transv. Bar D13-150 (top&bot.) 33 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D13 23 Ea

7 1M3 FOOTING FOUNDATION (1.2W x 2.5L) M


Sizes : W width = 1.20 0.90
L length or Prmtr length = 2.50
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D13-150 (top&bot.) 17 Ea
- Transv. Bar D13-150 (top&bot.) 34 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D13 29 Ea

8 1M3 FOOTING FOUNDATION (1.5W x 1.5L) M


Sizes : W width = 1.50 0.68
L length or Prmtr length = 1.50
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D16-200 (top&bot.) 16 Ea
- Transv. Bar D16-200 (top&bot.) 16 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D16 12 Ea

8 1M3 FOOTING FOUNDATION (1.5W x 1.5L) M


Sizes : W width = 1.50 0.79
L length or Prmtr length = 1.50
D depth, H hight or Th'k = 0.35
Reinforcing-Bar
- Lat.Bar D16-200 (top&bot.) 16 Ea
- Transv. Bar D16-200 (top&bot.) 16 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 294 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D16 12 Ea

8 1M3 FOOTING FOUNDATION (1.6W x 1.6L) M


Sizes : W width = 1.60 0.77
L length or Prmtr length = 1.60
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D16-200 (top&bot.) 17 Ea
- Transv. Bar D16-200 (top&bot.) 17 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D16 14 Ea

9 1M3 FOOTING FOUNDATION (1.75W x 1.75L) M


Sizes : W width = 1.75 0.92
L length or Prmtr length = 1.75
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
- Lat.Bar D16-200 (top&bot.) 19 Ea
- Transv. Bar D16-200 (top&bot.) 19 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D16 17 Ea

10 1M3 FOOTING FOUNDATION (2.25W x 2.25L) M


Sizes : W width = 2.25 2.03
L length or Prmtr length = 2.25
D depth, H hight or Th'k = 0.40
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Lat.Bar D16-200 (top&bot.) 24 Ea
- Transv. Bar D16-200 (top&bot.) 24 Ea
- Side Bar 3-D13 2 Ea
- vert. supp.Cross bar D16 29 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 295 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

10 1M3 FOOTING FOUNDATION (2.5W x 2.5L) M


Sizes : W width = 2.50 1.88
L length or Prmtr length = 2.50
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Lat.Bar D16-200 (top&bot.) 24 Ea
- Transv. Bar D16-200 (top&bot.) 24 Ea
- Side Bar 3-D13 2 Ea
- vert. supp.Cross bar D16 36 Ea

BLOCK FOUNDATION/ EQUIPMENT FDN


DEG FOUNDATION (2.25W x 6L x 0.6D) m
Sizes : W width = 2.25 8.10
L length or Prmtr length = 6.00
D depth, H hight or Th'k = 0.60
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Lat.Bar D16-150 (top&bot.) 32 Ea
- Transv. Bar D13-150 (top&bot.) 82 Ea
- Side Bar 3-D13 3 Ea
- vert. supp.Cross bar D16 51 Ea

BLOCK FOUNDATION/ EQUIPMENT FDN


METERING FOUNDATION (2.4W x 17L x 0.3D) m
Sizes : W width = 2.40 12.24
L length or Prmtr length = 17.00
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Lat.Bar D16-150 (top&bot.) 32 Ea
- Transv. Bar D13-150 (top&bot.) 82 Ea
- Side Bar 3-D13 3 Ea
- vert. supp.Cross bar D16 155 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 296 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

FIREWATER PUMP FOUNDATION (4Wx10Lx0.3D) m


Sizes : W width = 4.00 12.00
L length or Prmtr length = 10.00
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
Main bar diameter D = 16.00 mm
- Lat.Bar D16-200 (top&bot.) 42 Ea
- Transv. Bar D13-200 (top&bot.) 102 Ea
- Side Bar 1-D13 1 Ea
- vert. supp.Cross bar D16 154 Ea

PUMP BOOSTER FOUNDATION TYPE-1


Conc. Slab Sizes :
W width = 4.00 7.80
L length or Prmtr length = 6.50
D depth, H hight or Th'k = 0.30
Lat.Bar D13-200 (top&bot.) - Ea
Transv. Bar D13-200 (top&bot.) 65 Ea

Block/ pedestal pump foundation-a


W width = 2.00 5.85
L length or Prmtr length = 6.50
D depth, H hight or Th'k = 0.45
Lat.Bar D16-200 (top&bot.) 20 Ea
Transv. Bar D13-200 (top&bot.) 65 Ea

Block/ pedestal pump foundation-b


W width = 2.00 5.85
L length or Prmtr length = 6.50
D depth, H hight or Th'k = 0.45
- Lat.Bar D16-200 (top&bot.) 20 Ea
- Transv. Bar D13-200 (top&bot.) 65 Ea

Total Concrete volume = 19.50

UNIT-WEIGHT REBAR TBBM TGL BR Page 297 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
PUMP BOOSTER FOUNDATIONTYPE-2
Conc. Slab Sizes :
W width = 3.70 3.11
L length or Prmtr length = 2.80
D depth, H hight or Th'k = 0.30
Lat.Bar D13-200 (top&bot.) 7 Ea
Transv. Bar D13-200 (top&bot.) 28 Ea

Block/ pedestal pump foundation-a


W width = 1.50 0.34
L length or Prmtr length = 1.50
D depth, H hight or Th'k = 0.15
Lat.Bar D16-200 (top&bot.) 15 Ea
Transv. Bar D13-200 (top&bot.) 15 Ea

Block/ pedestal pump foundation-b


W width = 1.50 0.34
L length or Prmtr length = 1.50
D depth, H hight or Th'k = 0.15
- Lat.Bar D16-200 (top&bot.) 15 Ea
- Transv. Bar D13-200 (top&bot.) 15 Ea

Total Concrete volume = 3.78

PUMP BOOSTER FOUNDATION TYPE-3


Conc. Slab Sizes :
W width = 6.00 28.05
L length or Prmtr length = 9.35
D depth, H hight or Th'k = 0.50
Lat.Bar D13-200 (top&bot.) 8 Ea
Transv. Bar D13-200 (top&bot.) 94 Ea

Block/ pedestal pump foundation-a


W width = 2.60 12.16
L length or Prmtr length = 9.35
D depth, H hight or Th'k = 0.50
Lat.Bar D16-200 (top&bot.) 26 Ea
Transv. Bar D13-200 (top&bot.) 94 Ea

Block/ pedestal pump foundation-b


W width = 2.60 12.16
UNIT-WEIGHT REBAR TBBM TGL BR Page 298 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
L length or Prmtr length = 9.35
D depth, H hight or Th'k = 0.50
- Lat.Bar D16-200 (top&bot.) 26 Ea
- Transv. Bar D13-200 (top&bot.) 94 Ea

Total Concrete volume = 52.36

LOADING- UNLOADING PUMP FOUNDATION TYPE-4


Conc. Slab Sizes :
W width = 3.63 3.05
L length or Prmtr length = 2.80
D depth, H hight or Th'k = 0.30
Lat.Bar D13-200 (top&bot.) 10 Ea
Transv. Bar D13-200 (top&bot.) 28 Ea

Block/ pedestal pump foundation-a


W width = 1.40 0.78
L length or Prmtr length = 2.80
D depth, H hight or Th'k = 0.20
Lat.Bar D16-200 (top&bot.) 14 Ea
Transv. Bar D13-200 (top&bot.) 28 Ea

Block/ pedestal pump foundation-b


W width = 1.25 0.61
L length or Prmtr length = 2.45
D depth, H hight or Th'k = 0.20
- Lat.Bar D16-200 (top&bot.) 13 Ea
- Transv. Bar D13-200 (top&bot.) 25 Ea

Total Concrete volume = 4.44

LOADING- UNLOADING PUMP FOUNDATION TYPE-5


Conc. Slab Sizes :
W width = 3.55 2.66
L length or Prmtr length = 2.50
D depth, H hight or Th'k = 0.30
Lat.Bar D13-200 (top&bot.) 11 Ea
Transv. Bar D13-200 (top&bot.) 25 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 299 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Block/ pedestal pump foundation-a
W width = 1.25 0.63
L length or Prmtr length = 2.50
D depth, H hight or Th'k = 0.20
Lat.Bar D16-200 (top&bot.) 13 Ea
Transv. Bar D13-200 (top&bot.) 25 Ea

Block/ pedestal pump foundation-b


W width = 1.25 0.63
L length or Prmtr length = 2.50
D depth, H hight or Th'k = 0.20
- Lat.Bar D16-200 (top&bot.) 13 Ea
- Transv. Bar D13-200 (top&bot.) 25 Ea

Total Concrete volume = 3.91

LOADING- UNLOADING PUMP FOUNDATION TYPE-6


Conc. Slab Sizes :
W width = 3.15 1.70
L length or Prmtr length = 1.80
D depth, H hight or Th'k = 0.30
Lat.Bar D13-200 (top&bot.) 15 Ea
Transv. Bar D13-200 (top&bot.) 18 Ea

Block/ pedestal pump foundation-a


W width = 0.85 0.31
L length or Prmtr length = 1.80
D depth, H hight or Th'k = 0.20
Lat.Bar D16-200 (top&bot.) 9 Ea
Transv. Bar D13-200 (top&bot.) 18 Ea

Block/ pedestal pump foundation-b


W width = 0.85 0.31
L length or Prmtr length = 1.80
D depth, H hight or Th'k = 0.20
- Lat.Bar D16-200 (top&bot.) 9 Ea
- Transv. Bar D13-200 (top&bot.) 18 Ea

Total Concrete volume = 2.31

UNIT-WEIGHT REBAR TBBM TGL BR Page 300 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

LOADING- UNLOADING PUMP FOUNDATION TYPE-7


Conc. Slab Sizes :
W width = 3.13 1.69
L length or Prmtr length = 1.80
D depth, H hight or Th'k = 0.30
Lat.Bar D13-200 (top&bot.) 14 Ea
Transv. Bar D13-200 (top&bot.) 18 Ea

Block/ pedestal pump foundation-a


W width = 0.85 0.31
L length or Prmtr length = 1.80
D depth, H hight or Th'k = 0.20
Lat.Bar D16-200 (top&bot.) 9 Ea
Transv. Bar D13-200 (top&bot.) 18 Ea

Block/ pedestal pump foundation-b


W width = 0.85 0.27
L length or Prmtr length = 1.60
D depth, H hight or Th'k = 0.20
- Lat.Bar D16-200 (top&bot.) 9 Ea
- Transv. Bar D13-200 (top&bot.) 16 Ea

Total Concrete volume = 2.27

LOADING- UNLOADING PUMP FOUNDATION TYPE-8


Conc. Slab Sizes :
W width = 3.10 1.44
L length or Prmtr length = 1.55
D depth, H hight or Th'k = 0.30
Lat.Bar D13-200 (top&bot.) 15 Ea
Transv. Bar D13-200 (top&bot.) 16 Ea

Block/ pedestal pump foundation-a


W width = 0.80 0.25
L length or Prmtr length = 1.55
D depth, H hight or Th'k = 0.20
Lat.Bar D16-200 (top&bot.) 8 Ea
Transv. Bar D13-200 (top&bot.) 16 Ea

Block/ pedestal pump foundation-b


UNIT-WEIGHT REBAR TBBM TGL BR Page 301 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
W width = 0.80 0.25
L length or Prmtr length = 1.55
D depth, H hight or Th'k = 0.20
- Lat.Bar D16-200 (top&bot.) 8 Ea
- Transv. Bar D13-200 (top&bot.) 16 Ea

Total Concrete volume = 1.94

CABLE TRENCH
1 1-M3 Concrete Cable trench (1500Wx1000Dx150Th'k) mm
Sizes : W prmtr width = 3.80 1.00
L length = 1.75
Wall & floor thickness = 0.15
Reinforcing-Bar 2- layers
- Lateral..Bar Ø12-200 40 Ea
- Vert.Bar D13-200 20 Ea

2 1-M3 Concrete Cable trench (600Wx800 D x 120Th'k) mm


Sizes : W prmtr width = 2.44 1.00
L length = 3.42
Thichkness wall & floor = 0.12
Reinforcing-Bar 1- layer
- Lateral..Bar Ø12-200 13 Ea
- Vert.Bar D13-200 18 Ea

3 1-M3 Concrete Cable trench (800Wx800 D x 120Th'k) mm


Sizes : W prmtr width = 2.64 1.00
L length = 3.16
Thichkness wall & floor = 0.12
Reinforcing-Bar 1- layer
- Lateral..Bar Ø12-200 14 Ea
- Vert.Bar D13-200 17 Ea

4 1-M3 Concrete Cable trench (600Wx600 D x 120Th'k) mm


UNIT-WEIGHT REBAR TBBM TGL BR Page 302 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Sizes : W prmtr width = 2.04 1.00
L length = 4.08
Thichkness wall & floor = 0.12
Reinforcing-Bar 1- layer
- Lateral..Bar Ø12-200 11 Ea
- Vert.Bar D13-200 21 Ea

5 1-M3 Concrete Cable trench (500Wx800 D x 120Th'k) mm


Sizes : W prmtr width = 0.65 0.06
L length = 0.80
Thichkness wall & floor = 0.12
Reinforcing-Bar 1- layer
- Lateral..Bar Ø12-200 4 Ea
- Vert.Bar D13-200 5 Ea

6 1-M3 Concrete Cable trench (300Wx400 D x 120Th'k) mm


Sizes : W prmtr width = 1.14 0.15
L length = 1.12
Thichkness wall & floor = 0.12
Reinforcing-Bar 1- layer
- Lateral..Bar Ø12-200 7 Ea
- Vert.Bar D13-200 7 Ea

7 DUCT BANK FOR I/O CABLES ACCESS


Sizes : W prmtr width = 0.80 1.76
L length = 2.75
Thichkness wall & floor = 0.80
Re-Bar
- Ties Bar Ø10-200 15 Ea
- Horz.Bar Ø10-200 30 Ea
- Vert.Bar Ø10-200 30 Ea

TRANSFORMER FOUNDATION
UNIT-WEIGHT REBAR TBBM TGL BR Page 303 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Floor foundation, size: (2W x 3L x 0.3Thick)
m
Sizes : W width = 2.00 1.80
L length or Prmtr length = 3.00
D depth, H hight or Th'k = 0.30
Wing (around fdn) 400 mm 2.50
W width = 0.40 0.70
L length or Prmtr length = 10.00
D depth, H hight or Th'k = 0.18
Reinforcing-Bar (2-layers)
Main bar diameter = 13.00 mm
- Lateral..Bar D13-150 (top) 14 Ea
- Lateral..Bar D13-150 (bot.) 14 Ea
- Transv..Bar D13-150 (top) 21 Ea
- Transv..Bar D13-150 (bot.) 21 Ea
- Support bar D13 38 Ea
- Side bar 3Ø12 3 Ea

1-M3 Conc.wall 150 mm th'k


Sizes : W width = 4.70 14.81
L length or Prmtr length = 21.00
D depth, H hight or Th'k = 0.15
Main bar diameter = 12.00 mm
Reinforcing-Bar (2-layers)
- Lateral..Bar Ø12-200 (2-sides) 49 Ea
- Vert.- Bar Ø12-200 (2-sides) 211 Ea

1-EA SHALLOW FOUNDATION


Footing foundation (900W x 900L x 300Th.) mm
W-width = 0.90 0.24
L length or Prmtr length = 0.90
D depth, H hight or Th'k = 0.30
Reinforcing-Bar
For footing
- Lat.Bar D13-200 (Top&bott.) 10 Ea
- Transv. Bar D13-200 (Top&bott.) 10 Ea
- Cross bar D13 9 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 304 of 358


UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

Foundation for fence


Footing foundation (600W x 600L x 200Th.) mm
W-width = 0.60 0.07
L length or Prmtr length = 0.60
D depth, H hight or Th'k = 0.20

Reinforcing-Bar
For footing
- Lat.Bar Ø12-150 (Top&bott.) 9 Ea
- Transv. Bar Ø12-150 (Top&bott.) 9 Ea
- Cross bar Ø12 4 Ea
Pedestal (200W x 200L)
W-width = 0.20 0.03
L length or Prmtr length = 0.20
D depth, H hight or Th'k = 0.80

1 EA CONC. BOX CONTROL


Sizes : W width = 0.60 0.15
L length or Prmtr length = 2.00
D depth, H hight or Th'k = 0.10
Floor 100 mm thick. = 0.025
- Vert.-Bar Ø12-100 (1-layer) 12 Ea
- lateral bar Ø10-100 (1-layer) 7 Ea

FOUNDATION FOR STORAGE TANK


1-UNIT CIRCLE FOUNDATION Dia.= 21M, & CONCRETE M'BERS REINF
300mm Thk. Conc.Slab (Conus-center) for SOLAR Size
Conc.Vol. Quantity-Bar
STORAGE TANK and Typical foundation for m'bers
PREMIUM STORAGE TANK (m) (m3) Nos. unit

Concrete slab foundation: Weight of 1-layer reinforcing b


Diameter Conc. Slab, D (m) = 21.00 Transverse Re-bar: D16-200
Radian, r (m) = 10.50 20 Ea
Conc.slab thick, T (m) = 0.30 20 Ea
phi (∏) = 3.14 40 Ea
Area: 𝐴=𝜋𝑟^2 (m2) =
UNIT-WEIGHT REBAR TBBM TGL BR Page 305 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Area: 𝐴=𝜋𝑟^2 (m2) = 346.50 84 Ea
L Prmtr = (∏xD) = 66.00 164 Ea
Sub total- concrete slab volume = 103.95 Circle re-bar: D16-200
4 Ea
4 Ea
4 Ea
4 Ea

sub-total weight of re-bar

1-Unit Pilecap Sqr- for 1PC Pile D400-Dia.(mm) = 0.40 Reinforcing-Bar D16 (Top & Bott.)
Sizes: W width = 1.20 0.43 Lat.Bar D16-150 (top&bot.)
L length or Prmtr length = 1.20 9 Ea
D depth, H hight or Th'k = 0.60 Transv. Bar D16-150 (top&bot.)
Pilecap effec. Thick. = D-Thickness of slab = 0.30 9 Ea
Side Bar 1-D13
63 Ea pilecap per 1-unit foundation 1 Ea
Sub total-concrete pilecap volume = 27.22

Concrete Ringbeam Dia. 21 mtr


Main re-bar dia. (mm): 16.00 Main bar 6D16 (3top&3 bot), inclu
Dia. Conc. Ringbeam, D (m) : 21.00 splicind 2x 40 (Dia. Bar)
Ringbeam width, W (m) : 0.30 6 Ea
Ringbeam thick, T (m) : 0.50 Side re-bar 2D13
phi (∏) = 3.14 2 Ea
Section Area: 𝐴=𝑊 𝑥 � (m2) : 0.15 Ties bar Ø10-200
L Prmtr (∏xD) = 66.00 331 Ea
Sub total- concrete ring beam volume = 9.90

CONCRETE M'BERS REINF


1-UNIT CIRCLE FOUNDATION Dia.= 9M, &
300mm Thk. Conc.Slab (Conus-center) for FAME Size
Conc.Vol. Quantity-Bar
STORAGE TANK and Typical foundation for m'bers
PERTAMAX STORAGE TANK and PERTAMINA
DEX STORAGE TANK (m) (m3) Nos. unit

Concrete slab foundation: Weight of 1-layer reinforcing b


UNIT-WEIGHT REBAR TBBM TGL BR Page 306 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Diameter Conc. Slab, D (m) = 9.00 Transverse Re-bar: D16-200
Radian, r (m) = 4.50 20 Ea
Conc.slab thick, T (m) = 0.30 20 Ea
phi (∏) = 3.14 40 Ea
Area: 𝐴=𝜋𝑟^2 (m2) = 63.64 80 Ea
L Prmtr = (∏xD) = 28.29
Sub total-concrete slab volume = 19.09 Circle re-bar: D16-200
4 Ea
4 Ea
4 Ea
4 Ea

sub-total weight rebar for 2-layer

1-Unit Pilecap Sqr- for 1PC Pile D350-Dia.(mm) = 0.35 0.33 Reinforcing-Bar D16 (Top & Bott.)
Sizes: W width = 1.05 Lat.Bar D16-150 (top&bot.)
L length or Prmtr length = 1.05 8 Ea
D depth, H hight or Th'k = 0.60 Transv. Bar D16-150 (top&bot.)
Pilecap effec. Thick. = D-Thickness of slab = 0.30 8 Ea
Side Bar 1-D13
27 Ea pilecap per 1-unit foundation 1 Ea
Sub total-concrete pilecap volume = 8.93

Concrete Ringbeam Dia.9 mtr


Main re-bar dia. (mm): 16.00 Main bar 6D16 (3top&3 bot), inclu
Dia. Conc. Ringbeam, D (m) : 9.00 splicind 2x 40 (Dia. Bar)
Ringbeam width, W (m) : 0.30 6 Ea
Ringbeam thick, T (m) : 0.50 Side re-bar 2D13
phi (∏) = 3.14 2 Ea
Section Area: 𝐴=𝑊 𝑥 � (m2) : 0.15 Ties bar Ø10-200
L Prmtr (∏xD) = 28.29 142 Ea
Sub total- concrete ring beam volume = 4.24 Sub total weig

1-UNIT CIRCLE FOUNDATION Dia.= 22.93M, & 300mm Thk.


Conc.Slab (Flat surface) for FIRE WATER STORAGE TANK
Concrete slab foundation: For 2-layer (Top & Bott.) re-bar D
UNIT-WEIGHT REBAR TBBM TGL BR Page 307 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
Diameter Conc. Slab, D (m) : 22.93 Longitudinal Re-bar:
Radian, r (m) : 11.47 4 Ea
Conc.slab thick, T (m) : 0.30 8 Ea
phi ( ∏ ): 3.14 8 Ea
Area: 𝐴=𝜋𝑟^2 (m2) : 413.12 8 Ea
L Prmtr ( ∏ X D) : 72.07 8 Ea
Sub total-concrete slab volume = 123.94 8 Ea
8 Ea
8 Ea
8 Ea

1-Unit Pilecap Sqr- for 1PC Pile D400-Dia.(mm) = 0.40 Reinforcing-Bar D16 (Top & Bott.)
Sizes: W width = 1.20 0.43 Lat.Bar D16-150 (top&bot.)
L length or Prmtr length = 1.20 9 Ea
D depth, H hight or Th'k = 0.60 Transv. Bar D16-150 (top&bot.)
Pilecap effec. Thick. = D-Thickness of slab = 0.30 9 Ea
Side Bar 1-D13
101 Ea pilecap per 1-unit foundation 1 Ea
Sub total-concrete pilecap volume = 43.63

Concrete Ringbeam
Dia. Conc. Ringbeam, D (m) : 22.93 Main bar 6D16 (3top&3 bot)
Ringbeam width, W (m) : 0.30 6 Ea
Ringbeam thick, T (m) : 0.50 Side re-bar 2D13
phi ( ∏ ): 3.14 2 Ea
Section Area: 𝐴=𝑊 𝑥 � (m2) : 0.15 Ties bar Ø10-200
Ringbeam length prmtr ( ∏ X D) : 72.07 361 Ea
Sub total- concrete ring beam volume = 10.81 Sub total weig

1M' Length BUNDWALL (reinforced concrete structure)


Raft foundation (1.2W x 1.0L x 0.3Thk.) m
W-width = 1.20 0.24
L length or Prmtr length = 1.00
D depth, H hight or Th'k = 0.20
Reinforcing-Bar
UNIT-WEIGHT REBAR TBBM TGL BR Page 308 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit
- Lat.Bar Ø10-200 (Top&bott.) 7 Ea
- Transv. Bar Ø12-200 (Top&bott.) 5 Ea

Bundwall 200mm thick. & 1.5m High.


Sizes: W width = 1.00 2.10 Nos of Vertcal-Bar (Ø12-200) =
D Thick. = 0.20 5 Ea
H High = 1.90 Nos of Ties Ø10-200 =
Thickness of raft fdn, Th'k = 0.20 21 Ea
Reinforcing-Bar
Main bar diameter D = 12.00 mm

CONCRETE ROAD AND PAVEMENT


1-M3 Heavy duty Concrete pavement 220 mm th'k
Sizes : W width = 1.00 0.22
L length or Prmtr length = 1.00
D depth, H hight or Th'k = 0.22
Reinforcing-Bar-2 layers
- Top layer bar wire mesh M-8 @150 1 M2
- Bott. layer bar wire mesh M-8 @150 1 M2
- Cross bar support- Ø10 5 Ea

1-M3 Light duty Concrete pavement 200 mm th'k


Sizes : W width = 1.00 0.20
L length or Prmtr length = 1.00
D depth, H hight or Th'k = 0.20
Reinforcing-Bar-1 layers
- 1-layer bar wire mesh M-8 @150 1 M2
- Cross bar support- Ø10 5 Ea

Dowel re-bar weight per 1-M2 Conc.Pavement


Sizes : W width = 4.50 20.25
L length or Prmtr length = 4.50

Reinf-bar (2-layers, wiremesh M-8 c/c 150)


- Longitudinal dowel D19-1000 10 Ea
- Transverse dowel D16-600 16 Ea
UNIT-WEIGHT REBAR TBBM TGL BR Page 309 of 358
UNIT WEIGHT OF REINFORCING BAR
PER M3 CONCRETE VOLUME

CONC. M'BERS REINF


DESCRIPTION OF REINFORCED CONCRETE Size
NO Conc.Vol. Quantity-Bar
STRUCTURE m'bers
(m) (m3) Nos. unit

1m Length U-DITC (600W x 900D x 100 Thk ) mm


Sizes : Width of ditch = 0.60 1.60
Depth avarage of ditch = 0.40
Thickness of wall = 0.10
Perimeter width of section ditch, W = 1.60
1m-length of ditch, L = 1.00

Reinforcing-Bar 1- layers
- Longitudinal bar Ø10-200 9 Ea
- Vertical bar Ø12-200 5 Ea
- Angle bar Ø12-200 10 Ea

1-M' U-DITCH TYPE-1 (250W x 500D avrage x 60 Thk ) mm


Perimeter ditch of building
Sizes : W width = 1.25 0.10
L length or Prmtr length = 1.00
D depth, H hight or Th'k = 0.08
Reinforcing-Bar:
- 1-layer Wire mesh-M6@150 1 M'
- Cross bar support- Ø8 6 Ea

1-M' U-DITCH TYPE-2 (400W x 750D avrage x 80 Thk ) mm


Both sides acees road
Sizes : W width = 2.20 0.18
L length or Prmtr length = 1.00
D depth, H hight or Th'k = 0.08
Reinforcing-Bar:
- 1-layer Wire mesh-M6@150 1 M'
- Cross bar support- Ø10 10 Ea

UNIT-WEIGHT REBAR TBBM TGL BR Page 310 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

2.60 12.35 1.552 19.17


2.60 12.35 1.552 19.17
3.20 3.20 0.994 3.18

SUMM.= 41.52
Weight rebar per m3 concrete = 147.61
ROUND-UP = 148.00

3.10 17.05 1.552 26.46


3.10 17.05 1.552 26.46
3.40 3.40 0.994 3.38

SUMM.= 56.30
Weight rebar per m3 concrete = 115.85
ROUND-UP = 116.00

3.70 25.90 1.552 40.20


3.70 25.90 1.552 40.20
4.60 4.60 0.994 4.57

SUMM.= 84.97
Weight rebar per m3 concrete = 98.34
ROUND-UP = 99.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 311 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

3.70 33.30 1.552 51.68


3.70 33.30 1.552 51.68
4.60 4.60 0.994 4.57

SUMM.= 107.94
Weight rebar per m3 concrete = 124.93
ROUND-UP = 125.00

4.10 24.60 1.552 38.18


2.60 22.10 0.994 21.97
4.30 4.30 0.994 4.27

SUMM.= 64.42
Weight rebar per m3 concrete = 114.53
ROUND-UP = 115.00

4.90 34.30 1.552 53.23


3.10 31.00 0.994 30.81
5.20 5.20 0.994 5.17

SUMM.= 89.22
Weight rebar per m3 concrete = 91.79
ROUND-UP = 92.00

8.70 60.90 2.235 136.11


UNIT-WEIGHT REBAR TBBM TGL BR Page 312 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


3.70 72.15 1.552 111.98
9.60 9.60 0.994 9.54
SUMM.= 257.63
Weight rebar per m3 concrete = 96.71
ROUND-UP = 97.00

6.10 54.90 1.552 85.20


3.70 62.90 0.994 62.52
7.40 7.40 0.994 7.36
- - -
SUMM.= 155.08
Weight rebar per m3 concrete = 89.75
ROUND-UP = 90.00

6.10 103.70 1.552 160.94


6.10 103.70 0.994 103.08
9.80 9.80 0.994 9.74
- -
SUMM.= 273.76
Weight rebar per m3 concrete = 79.21
ROUND-UP = 80.00

7.70 130.90 1.552 203.16


6.10 136.23 0.994 135.42
11.40 11.40 0.994 11.33
- -
SUMM.= 349.90
UNIT-WEIGHT REBAR TBBM TGL BR Page 313 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


Weight rebar per m3 concrete = 75.93
ROUND-UP = 76.00

2.20 8.80 0.994 8.75


2.20 8.80 0.994 8.75
2.60 - 0.994 -

SUMM.= 17.49
Weight rebar per m3 concrete = 107.99
ROUND-UP = 108.00

5.40 56.70 1.552 88.00


4.80 57.60 0.994 57.25
- -

SUMM.= 145.25
Weight rebar per m3 concrete = 77.22
ROUND-UP = 78.00

7.10 99.40 1.552 154.27


6.10 100.65 0.994 100.05
- -

SUMM.= 254.31
Weight rebar per m3 concrete = 78.88
ROUND-UP = 79.00
UNIT-WEIGHT REBAR TBBM TGL BR Page 314 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

3.40 17.00 1.552 26.38


2.20 19.80 0.994 19.68
- -

SUMM.= 46.07
Weight rebar per m3 concrete = 142.18
ROUND-UP = 143.00

SPLICE=40 XD

12.55 100.41 1.552 155.83


1.20 90.09 0.617 55.58
SUMM.= 211.42
Weight rebar per m3 concrete = 211.42
ROUND-UP = 212.00

16.97 135.76 0.994 134.95


1.00 81.00 0.617 49.98
UNIT-WEIGHT REBAR TBBM TGL BR Page 315 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


SUMM.= 184.92
Weight rebar per m3 concrete = 184.92
ROUND-UP = 185.00

17.02 136.16 0.994 135.34


1.00 107.67 0.617 66.43
SUMM.= 201.77
Weight rebar per m3 concrete = 201.77
ROUND-UP = 202.00

12.25 147.01 1.552 228.16


1.20 90.09 0.617 55.58
SUMM.= 283.75
Weight rebar per m3 concrete = 283.75
ROUND-UP = 284.00

9.30 74.43 1.552 115.51


1.40 58.54 0.617 36.12
SUMM.= 151.63
Weight rebar per m3 concrete = 151.63
ROUND-UP = 152.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 316 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

4.90 39.20 1.552 60.83


2.22 43.95 0.617 27.12
SUMM.= 87.95
Weight rebar per m3 concrete = 87.95
ROUND-UP = 88.00

15.90 127.24 1.552 197.47


1.05 104.75 0.617 64.63
SUMM.= 262.11
Weight rebar per m3 concrete = 262.11
ROUND-UP = 263.00

7.69 61.52 1.552 95.48


1.60 68.27 0.617 42.12
SUMM.= 137.60
Weight rebar per m3 concrete = 137.60
ROUND-UP = 138.00

7.69 92.28 1.552 143.22


1.60 68.27 0.617 42.12
UNIT-WEIGHT REBAR TBBM TGL BR Page 317 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


SUMM.= 185.34
Weight rebar per m3 concrete = 185.34
ROUND-UP = 186.00

6.38 76.54 1.552 118.79


1.80 61.06 0.617 37.67
SUMM.= 156.46
Weight rebar per m3 concrete = 156.46
ROUND-UP = 157.00

8.64 103.68 1.552 160.91


2.00 98.00 0.617 60.47
SUMM.= 221.38
Weight rebar per m3 concrete = 221.38
ROUND-UP = 222.00

12.87 77.21 1.552 119.83


1.20 69.77 0.617 43.05
SUMM.= 162.88
Weight rebar per m3 concrete = 162.88
ROUND-UP = 163.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 318 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

13.64 81.84 1.552 127.02


1.20 76.20 0.617 47.02
SUMM.= 174.03
Weight rebar per m3 concrete = 174.03
ROUND-UP = 175.00

4.32 60.41 1.552 93.76


2.40 39.90 0.617 24.62
SUMM.= 118.37
Weight rebar per m3 concrete = 118.37
ROUND-UP = 119.00

3.11 62.13 1.552 96.43


3.40 41.18 0.617 25.41
SUMM.= 121.84
Weight rebar per m3 concrete = 121.84
ROUND-UP = 122.00

4.77 95.47 1.552 148.16


2.60 60.38 0.617 37.25
SUMM.= 185.42
Weight rebar per m3 concrete = 185.42
UNIT-WEIGHT REBAR TBBM TGL BR Page 319 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


ROUND-UP = 186.00

3.66 73.24 1.552 113.68


3.60 56.93 0.617 35.13
SUMM.= 148.80
Weight rebar per m3 concrete = 148.80
ROUND-UP = 149.00

2.83 56.58 1.552 87.81


5.40 55.40 0.617 34.18
SUMM.= 121.99
Weight rebar per m3 concrete = 121.99
ROUND-UP = 122.00

2.57 200.46 1.552 311.11


7.60 53.20 0.617 32.82
SUMM.= 343.94
Weight rebar per m3 concrete = 148.89
ROUND-UP = 149.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 320 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

69.44 277.78 0.888 246.67


0.48 166.67 0.617 102.83
SUMM.= 349.50
Weight rebar per m3 concrete = 349.50
ROUND-UP = 350.00

25.52 102.08 0.994 101.47


0.80 133.33 0.617 82.27
SUMM.= 183.73
Weight rebar per m3 concrete = 183.73
ROUND-UP = 184.00

16.52 132.16 0.994 131.37


1.00 106.67 0.617 65.81
SUMM.= 197.18
Weight rebar per m3 concrete = 197.18
ROUND-UP = 198.00

16.52 132.16 0.994 131.37


1.00 80.00 0.617 49.36
SUMM.= 180.73
Weight rebar per m3 concrete = 180.73
ROUND-UP = 181.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 321 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

11.63 93.05 0.994 92.49


1.20 88.89 0.617 54.84
SUMM.= 147.34
Weight rebar per m3 concrete = 147.34
ROUND-UP = 148.00

11.63 139.57 0.994 138.74


1.20 88.89 0.617 54.84
SUMM.= 193.58
Weight rebar per m3 concrete = 193.58
ROUND-UP = 194.00

8.80 70.43 1.552 109.30


1.40 76.19 0.617 47.01
SUMM.= 156.31
Weight rebar per m3 concrete = 156.31
ROUND-UP = 157.00

6.89 82.68 1.552 128.32


1.60 66.67 0.617 41.13
SUMM.= 169.45
Weight rebar per m3 concrete = 169.45
ROUND-UP = 170.00
UNIT-WEIGHT REBAR TBBM TGL BR Page 322 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

5.40 86.43 1.552 134.14


2.00 63.49 0.888 56.38
SUMM.= 190.52
Weight rebar per m3 concrete = 190.52
ROUND-UP = 191.00

33.33 133.33 0.888 118.40


0.70 117.37 0.617 72.42
SUMM.= 190.82
Weight rebar per m3 concrete = 190.82
ROUND-UP = 191.00

16.67 66.67 0.994 66.27


1.00 84.33 0.617 52.03
SUMM.= 118.30
Weight rebar per m3 concrete = 118.30
ROUND-UP = 119.00

20.00 80.00 0.994 79.52


UNIT-WEIGHT REBAR TBBM TGL BR Page 323 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


0.90 90.90 0.617 56.09
SUMM.= 135.61
Weight rebar per m3 concrete = 135.61
ROUND-UP = 136.00

13.33 80.00 0.994 79.52


1.10 147.77 0.617 91.17
SUMM.= 170.69
Weight rebar per m3 concrete = 170.69
ROUND-UP = 171.00

11.43 68.57 0.994 68.16


1.20 138.34 0.617 85.36
SUMM.= 153.52
Weight rebar per m3 concrete = 153.52
ROUND-UP = 154.00

9.53 57.17 1.552 88.73


1.40 62.22 0.617 38.39
SUMM.= 127.12
Weight rebar per m3 concrete = 127.12
ROUND-UP = 128.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 324 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


10.52 63.12 0.994 62.74
1.30 65.00 0.617 40.11
SUMM.= 102.85
Weight rebar per m3 concrete = 102.85
ROUND-UP = 103.00

10.52 63.12 0.994 62.74


1.30 86.67 0.617 53.47
SUMM.= 116.21
Weight rebar per m3 concrete = 116.21
ROUND-UP = 117.00

8.52 51.12 0.994 50.81


1.50 80.00 0.617 49.36
SUMM.= 100.17
Weight rebar per m3 concrete = 100.17
ROUND-UP = 101.00

10.64 106.40 1.552 165.13


1.30 65.00 0.617 40.11
SUMM.= 205.24
Weight rebar per m3 concrete = 205.24
ROUND-UP = 206.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 325 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

6.67 46.67 1.552 72.43


6.67 13.33 0.617 8.23
1.60 53.33 0.617 32.91
SUMM.= 113.56
Weight rebar per m3 concrete = 113.56
ROUND-UP = 114.00

6.67 40.00 1.552 62.08


6.67 13.33 0.617 8.23
1.60 53.33 0.617 32.91
SUMM.= 103.21
Weight rebar per m3 concrete = 103.21
ROUND-UP = 104.00

5.00 50.00 0.888 44.40


2.10 54.60 0.617 33.69
SUMM.= 78.09
Weight rebar per m3 concrete = 78.09
ROUND-UP = 79.00

17.31 69.23 1.552 107.44


1.00 166.67 0.617 102.83
UNIT-WEIGHT REBAR TBBM TGL BR Page 326 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


SUMM.= 210.27
Weight rebar per m3 concrete = 210.27
ROUND-UP = 211.00

12.07 72.41 1.552 112.38


1.20 137.14 0.617 84.62
SUMM.= 197.00
Weight rebar per m3 concrete = 197.00
ROUND-UP = 197.00

9.53 57.17 1.552 88.73


1.40 99.56 0.617 61.43
SUMM.= 150.16
Weight rebar per m3 concrete = 150.16
ROUND-UP = 151.00

8.97 62.81 1.552 97.49


1.40 77.78 0.617 47.99
SUMM.= 145.48
Weight rebar per m3 concrete = 145.48
ROUND-UP = 146.00

8.05 56.33 1.552 87.43


UNIT-WEIGHT REBAR TBBM TGL BR Page 327 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


1.50 74.07 0.617 45.70
SUMM.= 133.13
Weight rebar per m3 concrete = 133.13
ROUND-UP = 134.00

7.31 58.45 1.552 90.72


7.31 14.61 0.617 9.02
1.60 85.33 0.617 52.65
SUMM.= 152.39
Weight rebar per m3 concrete = 152.39
ROUND-UP = 153.00

3.81 38.15 1.552 59.20


3.17 12.70 1.552 19.71
2.70 68.57 0.617 42.31
SUMM.= 121.22
Weight rebar per m3 concrete = 121.22
ROUND-UP = 122.00

33.33 133.33 0.994 132.53


0.70 116.67 0.617 71.98
SUMM.= 204.52
Weight rebar per m3 concrete = 204.52
ROUND-UP = 205.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 328 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

16.67 100.00 0.994 99.40


1.00 83.33 0.617 51.42
SUMM.= 150.82
Weight rebar per m3 concrete = 150.82
ROUND-UP = 151.00

16.67 100.00 0.994 99.40


1.00 166.67 0.617 102.83
SUMM.= 202.23
Weight rebar per m3 concrete = 202.23
ROUND-UP = 203.00

13.33 80.00 0.994 79.52


1.10 146.67 0.617 90.49
SUMM.= 170.01
Weight rebar per m3 concrete = 170.01
ROUND-UP = 171.00

11.43 68.57 0.994 68.16


1.20 68.57 0.617 42.31
SUMM.= 110.47
Weight rebar per m3 concrete = 110.47
ROUND-UP = 111.00
UNIT-WEIGHT REBAR TBBM TGL BR Page 329 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

11.43 68.57 0.994 68.16


1.20 137.14 0.617 84.62
SUMM.= 152.78
Weight rebar per m3 concrete = 152.78
ROUND-UP = 153.00

10.00 40.00 1.552 62.08


1.30 86.67 0.617 53.47
SUMM.= 115.55
Weight rebar per m3 concrete = 115.55
ROUND-UP = 116.00

10.00 60.00 1.552 93.12


1.30 65.00 0.617 40.11
SUMM.= 133.23
Weight rebar per m3 concrete = 133.23
ROUND-UP = 134.00

10.00 60.00 1.552 93.12


1.30 130.00 0.617 80.21
SUMM.= 173.33
Weight rebar per m3 concrete = 173.33
UNIT-WEIGHT REBAR TBBM TGL BR Page 330 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


ROUND-UP = 174.00

8.89 62.22 1.552 96.57


1.40 71.11 0.617 43.88
SUMM.= 140.44
Weight rebar per m3 concrete = 140.44
ROUND-UP = 141.00

8.97 53.84 1.552 83.56


1.40 77.78 0.617 47.99
SUMM.= 131.55
Weight rebar per m3 concrete = 131.55
ROUND-UP = 132.00

8.05 48.28 1.552 74.94


1.95 115.56 0.888 102.61
SUMM.= 177.55
Weight rebar per m3 concrete = 177.55
ROUND-UP = 178.00

5.50 27.50
UNIT-WEIGHT REBAR TBBM TGL BR Page 331 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


5.50 27.50
0.30 9.38 0.617 5.78
SUMM.= 60.78
Weight rebar per m3 concrete = 60.78
ROUND-UP = 61.00

5.50 24.44
5.50 24.44
0.33 9.03 0.617 5.57
SUMM.= 54.46
Weight rebar per m3 concrete = 54.46
ROUND-UP = 55.00

2.71 75.45 0.617 46.55


2.71 75.45 0.617 46.55
0.25 10.42 0.617 6.43
SUMM.= 99.53
Weight rebar per m3 concrete = 99.53
ROUND-UP = 100.00

2.85 83.32 0.617 51.41


2.85 83.32 0.617 51.41
0.24 10.88 0.617 6.71
SUMM.= 109.52
Weight rebar per m3 concrete = 109.52
ROUND-UP = 110.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 332 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

2.90 86.34 0.617 53.27


2.90 86.34 0.617 53.27
0.23 11.06 0.617 6.82
SUMM.= 113.36
Weight rebar per m3 concrete = 113.36
ROUND-UP = 114.00

3.02 93.12 0.617 57.45


3.02 93.12 0.617 57.45
0.22 11.46 0.617 7.07
SUMM.= 121.98
Weight rebar per m3 concrete = 121.98
ROUND-UP = 122.00

3.02 46.56 0.617 28.73


3.02 46.56 0.617 28.73
- - - -
SUMM.= 57.45
Weight rebar per m3 concrete = 57.45
ROUND-UP = 58.00

3.02 61.07 0.617 37.68


3.02 61.07 0.617 37.68
UNIT-WEIGHT REBAR TBBM TGL BR Page 333 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


- - - -
SUMM.= 75.37
Weight rebar per m3 concrete = 75.37
ROUND-UP = 76.00

5.50 45.83
0.28
SUMM.= 46.11
Weight rebar per m3 concrete = 46.11
ROUND-UP = 47.00

2.96 29.60
0.15
SUMM.= 29.75
Weight rebar per m3 concrete = 29.75
ROUND-UP = 30.00

5.50 55.00
0.28
SUMM.= 55.28
Weight rebar per m3 concrete = 55.28
ROUND-UP = 56.00

8.50 85.00
0.43
SUMM.= 85.43
Weight rebar per m3 concrete = 85.43
ROUND-UP = 86.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 334 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

0.90 57.15 0.617 35.26


12.60 63.00 0.617 38.87
SUMM.= 74.13
Weight rebar per m3 concrete = 74.13
ROUND-UP = 75.00

0.90 9.90 0.888 8.79


1.10 5.50 0.617 3.39
1.20 4.80 0.888 4.26
0.74 8.14 0.617 5.02
SUMM.= 21.47
Weight rebar per m3 concrete = 255.59
ROUND-UP = 256.00

2.05 22.55 0.994 22.41


1.10 13.93 0.617 8.60
1.20 4.80 0.994 4.77
0.74 8.14 0.617 5.02
SUMM.= 40.81
UNIT-WEIGHT REBAR TBBM TGL BR Page 335 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


Weight rebar per m3 concrete = 174.38
ROUND-UP = 175.00

1.30 41.60 0.888 36.94


1.80 21.60 0.617 13.33

1.80 18.90 0.617 11.66


1.10 28.05 0.617 17.31
SUMM.= 79.24
Weight rebar per m3 concrete = 217.92
ROUND-UP = 218.00

4.31 66.81 0.617 41.22


1.60 68.16 0.617 42.05
SUMM.= 83.27
Weight rebar per m3 concrete = 101.29
e-bar per 1M2 "BORDES" floor = ROUND-UP = 102.00

0.90 7.80 0.888 6.93


0.90 7.80 0.888 6.93
UNIT-WEIGHT REBAR TBBM TGL BR Page 336 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


SUMM.= 13.85
Weight rebar per m3 concrete = 192.40
ROUND-UP = 193.00

1.05 11.20 0.888 9.95


1.05 11.20 0.888 9.95
SUMM.= 19.89
Weight rebar per m3 concrete = 176.81
ROUND-UP = 177.00

1.15 13.03 0.888 11.57


1.15 13.03 0.888 11.57
SUMM.= 23.15
Weight rebar per m3 concrete = 144.67
ROUND-UP = 145.00

1.25 15.83 0.994 15.74


1.25 15.83 0.994 15.74
SUMM.= 31.48
Weight rebar per m3 concrete = 155.44
ROUND-UP = 156.00

1.55 27.90 0.994 27.73


1.55 27.90 0.994 27.73
0.55 4.16 0.994 4.13
SUMM.= 55.47
Weight rebar per m3 concrete = 154.07
UNIT-WEIGHT REBAR TBBM TGL BR Page 337 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


ROUND-UP = 155.00

1.60 20.80 1.552 32.28


1.60 20.80 1.552 32.28
4.60 9.20 0.994 9.14
0.60 4.54 1.552 7.04
SUMM.= 64.56
Weight rebar per m3 concrete = 149.45
ROUND-UP = 150.00

1.90 24.70 1.552 38.33


1.60 25.60 1.552 39.73
5.20 10.40 0.994 10.34
0.60 5.78 1.552 8.96
SUMM.= 78.07
Weight rebar per m3 concrete = 144.57
ROUND-UP = 145.00

1.05 10.50 0.994 10.44


1.05 10.50 0.994 10.44
2.60 2.60 0.994 2.58
0.55 2.20 0.994 2.19
SUMM.= 20.87
Weight rebar per m3 concrete = 170.40
ROUND-UP = 171.00

1.40 19.60 0.994 19.48


UNIT-WEIGHT REBAR TBBM TGL BR Page 338 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


1.40 19.60 0.994 19.48
3.80 3.80 0.994 3.78
0.60 5.40 0.994 5.37
SUMM.= 38.96
Weight rebar per m3 concrete = 129.88
ROUND-UP = 130.00

1.90 26.60 0.994 26.44


1.40 28.93 0.994 28.76
4.80 4.80 0.994 4.77
0.60 8.40 0.994 8.35
SUMM.= 55.20
Weight rebar per m3 concrete = 122.67
ROUND-UP = 123.00

2.00 22.67 0.994 22.53


1.20 26.40 0.994 26.24
4.60 4.60 0.994 4.57
0.60 7.00 0.994 6.96
SUMM.= 48.77
Weight rebar per m3 concrete = 127.01
ROUND-UP = 128.00

1.80 25.20 0.994 25.05


1.40 27.07 0.994 26.90
4.60 4.60 0.994 4.57
0.60 7.80 0.994 7.75
SUMM.= 51.95
Weight rebar per m3 concrete = 123.70
ROUND-UP = 124.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 339 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

2.80 39.20 0.994 38.96


1.40 45.73 0.994 45.46
6.60 6.60 0.994 6.56
0.60 13.80 0.994 13.72
SUMM.= 84.42
Weight rebar per m3 concrete = 117.26
ROUND-UP = 118.00

2.90 48.33 0.994 48.04


1.60 54.40 0.994 54.07
7.20 7.20 0.994 7.16
0.60 17.60 0.994 17.49
SUMM.= 102.12
Weight rebar per m3 concrete = 113.46
ROUND-UP = 114.00

1.90 30.40 1.552 47.18


1.90 30.40 1.552 47.18
5.80 5.80 0.994 5.77
0.60 7.35 1.552 11.41
SUMM.= 94.36
Weight rebar per m3 concrete = 139.79
ROUND-UP = 140.00

1.95 31.20 1.552 48.42


1.95 31.20 1.552 48.42
UNIT-WEIGHT REBAR TBBM TGL BR Page 340 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


5.80 5.80 0.994 5.77
0.65 7.96 1.552 12.36
SUMM.= 96.84
Weight rebar per m3 concrete = 122.98
ROUND-UP = 123.00

2.00 34.00 1.552 52.77


2.00 34.00 1.552 52.77
6.20 6.20 0.994 6.16
0.60 8.44 1.552 13.10
SUMM.= 105.54
Weight rebar per m3 concrete = 137.42
ROUND-UP = 138.00

2.15 39.78 1.552 61.73


2.15 39.78 1.552 61.73
6.80 6.80 0.994 6.76
0.60 10.21 1.552 15.84
SUMM.= 123.46
Weight rebar per m3 concrete = 134.38
ROUND-UP = 135.00

2.85 66.98 1.552 103.95


2.85 66.98 1.552 103.95
9.20 18.40 0.994 18.29
0.70 20.22 1.552 31.39
SUMM.= 257.57
Weight rebar per m3 concrete = 127.19
UNIT-WEIGHT REBAR TBBM TGL BR Page 341 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


ROUND-UP = 128.00

2.85 66.98 1.552 103.95


2.85 66.98 1.552 103.95
10.20 20.40 0.994 20.28
0.60 21.60 1.552 33.52
SUMM.= 261.69
Weight rebar per m3 concrete = 139.57
ROUND-UP = 140.00

6.80 217.60 1.552 337.72


3.05 250.10 0.994 248.60
16.70 50.10 0.994 49.80
0.80 40.59 1.552 63.00
SUMM.= 699.11
Weight rebar per m3 concrete = 86.31
ROUND-UP = 87.00

17.50 560.00 1.552 869.12


2.90 237.80 0.994 236.37
39.00 117.00 0.994 116.30
0.50 77.74 1.552 120.65
SUMM.= 1,342.44
UNIT-WEIGHT REBAR TBBM TGL BR Page 342 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


Weight rebar per m3 concrete = 109.68
ROUND-UP = 110.00

10.40 436.80 1.552 677.91


4.40 448.80 0.994 446.11
28.20 28.20 0.994 28.03
0.50 77.22 1.552 119.85
SUMM.= 1,271.90
Weight rebar per m3 concrete = 105.99
ROUND-UP = 106.00

6.90 - 0.994 -
4.40 286.00 0.994 284.28

7.45 149.00 1.552 231.25


2.95 191.75 0.994 190.60

7.45 149.00 1.552 231.25


2.95 191.75 0.994 190.60
SUMM.= 1,127.98

Weight rebar per m3 concrete = 57.85


ROUND-UP = 58.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 343 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

3.20 22.40 0.994 22.27


4.10 114.80 0.994 114.11

2.15 32.25 1.552 50.05


2.15 32.25 0.994 32.06

2.15 32.25 1.552 50.05


2.95 44.25 0.994 43.98
SUMM.= 312.52

Weight rebar per m3 concrete = 82.61


ROUND-UP = 83.00

3.20 25.60 0.994 25.45


4.10 383.35 0.994 381.05

2.15 55.90 1.552 86.76


2.15 201.03 0.994 199.82

UNIT-WEIGHT REBAR TBBM TGL BR Page 344 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

2.15 55.90 1.552 86.76


2.95 275.83 0.994 274.17
SUMM.= 1,054.00

Weight rebar per m3 concrete = 20.13


ROUND-UP = 21.00

3.20 31.20 0.994 31.01


4.10 114.80 0.994 114.11

2.15 30.10 1.552 46.72


2.15 60.20 0.994 59.84

2.15 26.88 1.552 41.71


2.95 72.28 0.994 71.84
SUMM.= 365.23

Weight rebar per m3 concrete = 82.23


ROUND-UP = 83.00

3.20 33.60 0.994 33.40


4.10 102.50 0.994 101.89

UNIT-WEIGHT REBAR TBBM TGL BR Page 345 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

2.15 26.88 1.552 41.71


2.15 53.75 0.994 53.43

2.15 26.88 1.552 41.71


2.95 73.75 0.994 73.31
SUMM.= 345.44

Weight rebar per m3 concrete = 88.29


ROUND-UP = 89.00

3.20 46.40 0.994 46.12


4.10 73.80 0.994 73.36

2.15 18.28 1.552 28.36


2.15 38.70 0.994 38.47

2.15 18.28 1.552 28.36


2.95 53.10 0.994 52.78
SUMM.= 267.45

Weight rebar per m3 concrete = 115.63


ROUND-UP = 116.00
UNIT-WEIGHT REBAR TBBM TGL BR Page 346 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

3.20 45.60 0.994 45.33


4.10 73.80 0.994 73.36

2.15 18.28 1.552 28.36


2.15 38.70 0.994 38.47

2.15 18.28 1.552 28.36


2.95 47.20 0.994 46.92
SUMM.= 260.79

Weight rebar per m3 concrete = 115.12


ROUND-UP = 116.00

3.20 48.00 0.994 47.71


4.10 63.55 0.994 63.17

2.15 17.20 1.552 26.69


2.15 33.33 0.994 33.13

UNIT-WEIGHT REBAR TBBM TGL BR Page 347 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

2.15 17.20 1.552 26.69


2.95 45.73 0.994 45.45
SUMM.= 242.85

Weight rebar per m3 concrete = 125.34


ROUND-UP = 126.00

1.95 78.18 0.888 69.42


3.90 76.22 0.994 75.76
SUMM.= 145.18
Weight rebar per m3 concrete = 145.18
ROUND-UP = 146.00

3.62 47.72 0.888 42.38


2.64 47.72 0.994 47.44
SUMM.= 89.81
Weight rebar per m3 concrete = 89.81
ROUND-UP = 90.00

3.36 47.66 0.888 42.32


2.84 47.66 0.994 47.38
SUMM.= 89.70
Weight rebar per m3 concrete = 89.70
ROUND-UP = 90.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 348 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

4.28 47.99 0.888 42.62


2.24 47.99 0.994 47.70
SUMM.= 90.32
Weight rebar per m3 concrete = 90.32
ROUND-UP = 91.00

1.00 4.25 0.888 3.77


0.85 4.25 0.994 4.22
SUMM.= 8.00
Weight rebar per m3 concrete = 128.18
ROUND-UP = 129.00

1.32 8.84 0.888 7.85


1.34 8.84 0.994 8.79
SUMM.= 16.64
Weight rebar per m3 concrete = 108.63
ROUND-UP = 109.00

3.40 50.15 0.617 30.94


1.00 29.50 0.617 18.20
1.00 29.50 0.617 18.20
SUMM.= 67.35
Weight rebar per m3 concrete = 38.26
ROUND-UP = 39.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 349 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

wing

5.40 77.40 0.994 76.94


3.70 53.03 0.994 52.72
4.40 92.40 0.994 91.85
2.70 56.70 0.994 56.36
0.40 15.00 0.994 14.91
10.10 30.30 0.888 26.91
SUMM.= 319.67
Weight rebar per m3 concrete = 127.87
ROUND-UP = 128.00

21.46 1,051.54 0.888 933.77


4.85 1,023.35 0.888 908.73
SUMM.= 1,842.50
Weight rebar per m3 concrete = 124.45
ROUND-UP = 125.00

1.50 15.00 0.994 14.91


1.50 15.00 0.994 14.91
0.40 3.60 0.994 3.58
SUMM.= 33.40
Weight rebar per m3 concrete = 137.44
UNIT-WEIGHT REBAR TBBM TGL BR Page 350 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


ROUND-UP = 138.00

1.00 9.00 0.888 7.99


1.00 9.00 0.888 7.99
0.30 1.20 0.888 1.07

weight re-bar per m3 = 184.00 5.888

SUMM.= 22.94
Weight rebar per m3 concrete = 220.55
ROUND-UP = 221.00

1.70 20.40 0.888 18.12


2.10 14.70 0.617 9.07
SUMM.= 27.19
Weight rebar per m3 concrete = 187.48
ROUND-UP = 188.00

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight


per Nos. Total length Bar- (kg/m) Bar- (kg)

1-layer reinforcing b
Re-bar: D16-200
10.65 213.00 1.552 330.58
10.00 200.00 1.552 310.40
9.33 373.20 1.552 579.21

UNIT-WEIGHT REBAR TBBM TGL BR Page 351 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


8.00 672.00 1.552 1,042.94
5.35 877.40 1.552 1,361.72
r: D16-200
217.9 871.60 1.552 1,352.72
246.90 987.60 1.552 1,532.76
64.00 256.00 1.552 397.31
24.20 96.80 1.552 150.23
Summ.= 7,057.88
b-total weight of re-bar for 2-layer (Top & Bott.) = 14,115.75
Weight rebar per m3 concrete = 135.79
ROUND-UP = 136.00

-Bar D16 (Top & Bott.)


6-150 (top&bot.)
3.70 33.30 1.552 51.68
D16-150 (top&bot.)
3.70 33.30 1.552 51.68
D13
4.90 4.90 0.994 4.87
Summ.= 108.23
Sub total- pilecap rebar weight = 6,818.73
Weight rebar per m3 concrete = 250.54
ROUND-UP = 251.00

D16 (3top&3 bot), include re-bar


40 (Dia. Bar)
67.28 403.68 1.552 626.51
2D13
67.28 134.56 0.994 133.75

1.60 529.60 0.617 326.76


Sub total- pilecap rebar weight = 1,087.03
Weight rebar per m3 concrete = 109.80
ROUND-UP = 110.00

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)

1-layer reinforcing b
UNIT-WEIGHT REBAR TBBM TGL BR Page 352 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


Re-bar: D16-200
4.65 93.00 1.552 144.34
4.00 80.04 1.552 124.22
3.33 133.20 1.552 206.73
2.01 161.12 1.552 250.06

r: D16-200
44.50 178.00 1.552 276.26
32.05 128.20 1.552 198.97
8.45 33.80 1.552 52.46
3.40 13.60 1.552 21.11
Summ.= 1,274.13
eight rebar for 2-layer (Top&Bott.) conc. slab = 2,548.26
Weight rebar per m3 concrete = 133.47
ROUND-UP = 134.00

-Bar D16 (Top & Bott.)


6-150 (top&bot.)
3.40 27.20 1.552 42.21
D16-150 (top&bot.)
3.40 27.20 1.552 42.21
D13
4.30 4.30 0.994 4.27
Summ.= 88.70
Sub total- weight rebar 27 Ea pilecap = 2,394.98
Weight rebar per m3 concrete = 268.19
ROUND-UP = 269.00

D16 (3top&3 bot), include re-bar


40 (Dia. Bar)
29.57 177.39 1.552 275.32
2D13
29.57 59.13 0.994 58.78

1.60 227.89 0.617 140.61


Sub total weight rebar conc.Ring beam = 474.70
Weight rebar per m3 concrete = 111.88
ROUND-UP = 112.00

(Top & Bott.) re-bar D16-200


UNIT-WEIGHT REBAR TBBM TGL BR Page 353 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


l Re-bar:
23.23 92.92 1.552 144.21
185.04 1,480.32 1.552 2,297.46
225.59 1,804.72 1.552 2,800.93
129.37 1,034.96 1.552 1,606.26
102.77 822.16 1.552 1,275.99
78.02 624.16 1.552 968.70
173.21 1,385.66 1.552 2,150.54
95.02 760.18 1.552 1,179.79
57.47 459.74 1.552 713.51
SUMM.= 13,137.38
Weight rebar per m3 concrete = 106.00
ROUND-UP = 107.00

-Bar D16 (Top & Bott.)


6-150 (top&bot.)
3.70 33.30 1.552 51.68
D16-150 (top&bot.)
3.70 33.30 1.552 51.68
D13
4.90 4.90 0.994 4.87
Summ.= 108.23
Sub total- pilecap rebar weight = 10,931.61
Weight rebar per m3 concrete = 250.54
ROUND-UP = 251.00

D16 (3top&3 bot)


73.35 440.07 1.552 683.00
2D13
73.35 146.69 0.994 145.81

1.60 578.13 0.617 356.70


Sub total weight rebar conc.Ring beam = 1,185.51
Weight rebar per m3 concrete = 109.67
ROUND-UP = 110.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 354 of 358


G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


1.00 7.00 0.617 4.32
2.40 12.00 0.888 10.66
SUMM.= 14.98
Weight rebar per m3 concrete = 62.40
ROUND-UP = 63.00

cal-Bar (Ø12-200) =
4.88 24.40 0.888 21.67
Ø10-200 =
1.00 21.00 0.617 12.96
SUMM.= 34.62
Weight rebar per m3 concrete = 16.49
ROUND-UP = 17.00

5.500 5.50
5.500 5.50
0.22 1.10 0.617 0.68
SUMM.= 11.68
Weight rebar per m3 concrete = 53.09
ROUND-UP = 54.00

5.500 5.50
0.10 0.50 0.617 0.31
SUMM.= 5.81
Weight rebar per m3 concrete = 29.04
ROUND-UP = 30.00

0.20 2.00 2.24 4.47


0.20 3.20 1.55 4.97
UNIT-WEIGHT REBAR TBBM TGL BR Page 355 of 358
G BAR
ME

REINFORCING-BAR

Length of Bar (m) Unit Weight Total weight

per Nos. Total length Bar- (kg/m) Bar- (kg)


SUMM.= 9.44
Weight rebar per m2 concrete = 0.47
ROUND-UP = 0.50

1.10 9.90 0.617 6.11


1.70 8.50 0.890 7.57
0.60 6.00 0.890 5.34
SUMM.= 19.01
Weight rebar per m3 concrete = 11.88
ROUND-UP = 12.00

3.700 3.70
0.08 0.48 0.500 0.24
SUMM.= 3.94
ROUND-UP = 4.00

6.512 6.51
0.08 0.78 0.617 0.48
SUMM.= 7.00
ROUND-UP = 7.00

UNIT-WEIGHT REBAR TBBM TGL BR Page 356 of 358


DETAIL MTO STEEL STRUCTURE (CIVIL AND BUILDING ACCESSORIES ITEM WORKS)
TBBM TEGAL BARU

Number of QTY per NOS m'bers Total QTY of m'bers


NO DESCRIPTION OF STEEL STRUCTURE AND MEMBERS members
Length Width Area Total length Total area
NOS Unit (m) (m) (m2) (m) (m2)

1 PUMP SHELTER FOUNDATION


Cable trench steel plate cover and frame include
1.1 embedded plate
1.1.a - Embedded plate L-50X50X5 with anchor bar Ø10 2 Set 25.00 50.00
- ditto - 8 Set 6.00 48.00
- Anchor bar Ø10 x 150m L (C/C 300mm) 326.667 Ea 0.15 49.00

1.1.b - Checker plate 3mm thk.cover & frame


for cable trench (0.5Wx0.8Dx36L) m
- Cheker plate cover 3mm thk. 1 Set 25.00 0.56 14.00 14.00
- Steel frame cover L50x50x5, longitudinal 2 Ea 25.00 50.00
- Steel frame cover L50x50x5, intermediate 1 Ea 25.00 25.00
- ditto- , transverse frame 75 Ea 0.56 42.00
for cable trench (0.3Wx0.4Dx3.6L) m
- Cheker plate cover 3mm thk. 8 Set 6.00 0.36 2.16 17.28
- Steel frame cover L50x50x5, longitudinal 16 Ea 6.00 96.00
- ditto- , transverse frame 104 Ea 0.36 37.44
sub-total= 31.28

Page 357 of 358


Unit weight Total weight

Weight Unit (kg)

3.77 kg/m' 188.50


3.77 kg/m' 180.96
0.617 kg/m' 30.23
sub-total = 399.69

3.77 kg/m' 188.50


3.77 kg/m' 94.25
3.77 kg/m' 158.34

3.77 kg/m' 361.92


3.77 kg/m' 141.15
sub-total = 944.16

Page 358 of 358