Professional Documents
Culture Documents
Aspal Pavement
Aspal Pavement
Aspal Pavement
TABLE OF CONTENTS
I. GENERAL .......................................................................................................................................... 1
I. GENERAL
The flexible bituminous pavement works for Pasteur-Cikapayang-Surapati Project
consisted of construction of new and existing carriageway and shoulder pavement (overlay).
Below flowchart shows the flow of asphalt pavement works:
Quarry/material sources
Aggregate sub grade material was selected from approved sources in accordance with
specification.
Transportation
Sub grade material was transported to site by using dump truck.
Spreading
The sub grade material was placed in uniform layers so that the compacted depth did
not exceed 15cm. Spreading work had been done by excavator and motor grader for
perfection.
Compaction
Immediately followed final spreading and smoothing, each layer was compacted to full
width by compacter. Rolling was gradually progress from the low to the high point of the
cross section, parallel to the center line of the road, and shall continue until the entire
surface has been rolled.
Any irregularities or depressions that was developed, was corrected by loosening the
material until the surface was smooth and uniform. For the places that had no
accessible for the roller, the material was compacted by using hand stamper. The
material was both bladed and rolled until a smooth, even surface had been obtained.
Test
The sub grade layers were test by density and CBR to met required specification.
Degree of compaction
The layers of sub grade, to 20cm depth, below the sub grade layer were compacted to
at least 100% of the maximum dry density as determined according to AASHTO T99.
The minimum CBR that require for sub grade in pavement works was 6%.
Earth cut
The level of sub grade was formed to the correct transverse and longitudinal profiles but
at grade level higher than the final grade in order to allow for the effect of compaction.
Compaction
The soil surface/level was compacted with roller. Prior to compaction, the moisture
content was adjusted by watering with sprinkler trucks or by drying out, as required, in
order that the degree of compaction specified may be attained.
Degree of compaction
The layers of sub grade, to 20cm depth, below the sub grade layer were compacted to
at least 100% of the maximum dry density as determined according to AASHTO T99.
The minimum CBR that require for sub grade in pavement works was 6%.
Quarry/material source
Aggregate sub grade material was selected from approved sources in accordance with
specification.
Mixing
Mixing had been done by using excavator at location of stone crusher. All aggregate
was free from organic matter and lumps of clay or other deleterious matters and the
grading was conformed to the grading requirement as shown on specification.
Transportation
Crushed stone that have been mixed was transported to site by using dump truck.
Spreading
The granular base material A and B was placed in uniform layers so that the compacted
depth was not exceeding 15cm. spreading by using motor grader.
Compaction
Immediately followed final spreading and smoothing, each layer was compacted to full
width by compacter. Rolling was gradually progress from the low to the high point of the
cross section, parallel to the center line of the road, and shall continue until the entire
surface has been rolled.
Any irregularities or depressions that was developed, was corrected by loosening the
material until the surface was smooth and uniform. For the places that had no
accessible for the roller, the material was compacted by using hand stamper. The
material was both bladed and rolled until a smooth, even surface had been obtained.
Degree of compaction
The density of compaction surface/layers were compacted to at least 100% of the
maximum dry density as determined according to AASHTO T180. The finished surface
had been uniform, dense and even.
II.3 Construction of asphalt treated base (ATB) and asphalt concrete (AC) layers
Preparation of surface
Immediately before applying the bituminous material, all loose dirt another objectionable
material was removed from surface with air compressor.
- Transportation
The mixture was transported from the mixing plant to the point of use by dump truck.
No loads were sent out so late in the day as to prevent completion of the spreading
and compaction of the mixture during daylight hours. At the night works, satisfactory
illumination was provided.
Spreading
The mixture was laid upon an approved surface, spread and struck off to the grade and
elevation established. Asphalt paver was used to distribute the mixture either width or
over such partial width as it practical. On areas where irregularities or unavoidable
obstacles made the use of mechanical spread and finishing equipment impracticable.
The mixture was spread, raked, and lute by hand tools. For such area the mixture was
dumped, spread and screed to give required compaction thickness.
Compacting
After the mixture had been spread, struck off and surface irregularities adjustment. It
was throughout and uniform compacted by using rolling. The surface was rolled when
the mixture is in the proper condition and when the rolling did not cause undue
displacement, cracking and shoving.
Roller was moved at slow but uniform speed with the drive roll or wheels nearest the
paver. Rolling began at the sides and proceeds longitudinally parallel to the road center
line. Each trip was overlapping one-half the roller width, and then gradually progressing
to the crown at the road.
The surface level of pavement had been test. The specific gravity of the consolidated
mixture, as determined by AASHTO T230, was not less than 95 percent of the specific
gravity of laboratory compacted specimens that was composed of the same material in
like proportion. Laboratory specimen was consist of the mixture compacted by the
procedure of AASHTO T167.
- Compaction
Immediately followed final spreading and smoothing, each layer was compacted to
full width by compacter. Rolling was gradually progress from the low to the high
point of the cross section, parallel to the center line of the road, and shall continue
until the entire surface has been rolled.
Any irregularities or depressions that was developed, was corrected by loosening
the material until the surface was smooth and uniform. For the places that had no
accessible for the roller, the material was compacted by using hand stamper. The
material was both bladed and rolled until a smooth, even surface had been
obtained.
- Degree of compaction
The density of compaction surface/layers were compacted to at least 100% of the
maximum modified dry density as determined according to AASHTO T180. The
finished surface had been uniform, dense and even.