Doc. No.

:
Nasa Multiplex Rev. No. : 0
Date :

Sump Pump – Plant Performance Test


M&E Division

Client Project Design Consultant MEP Consultants


EMAAR Properties Burj Dubai – The Residences Woods Bagot Roberts & Partners

1. Pump Consisting of :

2. Pump Details :
MAKE MODEL DUTY SERIAL No. MOTOR CAPACITY

3.
Current Drawn by Motor
Make Overload Setting Fuse Rating
Rated Value Observed Value

4. Level switches operation

a. Pump-1 Start :

b. Pump-2 Start :

c. All pump stop :

d. High level indication :

5. Dry run protection :

6. Flashing / Alarm during high level :


7. Operation of chclic change over :

8. ECMS Controls :

REMARKS

NAME

SIGNATURE

DATE
TESTED & CERTIFIED BY WITNESSED BY WITNESSED BY
(NMX) CONSULTANT
Doc. No. :
Nasa Multiplex Rev. No. : 0
Date :

Test Certificate for Sump Pump


M&E Division

Client Project Design Consultant MEP Consultants


EMAAR Properties Burj Dubai – The Residences Woods Bagot Roberts & Partners

Location / Area :

S. No. Activities / Items to be Inspected

Obtain pump manufacturers test curve prior to


1.
commencement
Check Electrical connections properly made
2. (Terminal covers fitted, level switches connected
properly)
Check overload setting correct and record setting on
3.
test sheets.
Check fuse rating correct and record setting on test
4.
sheets.

5. Check direction and speed of rotation are correct.

Check and record pump and motor name plate details


6.
on test sheets.

7. Check motor current on all phases and record result.

Check valves and non return valves are fitted and area
8.
fully open.

9. Record pump flow and head.

Check auto change over to stand-by pump (if


10.
applicable).
Location / Area :

S. No. Activities / Items to be Inspected

Check float switches located at correct location


11.
proper start-stop-high level indication.
Check pumps can be removed and refixed without
12.
problem.
Check guide bar, lifting chains are fixed properly and
13.
secured.

14. Check for dry run protection.

15. Check for proper operation of pumps.

REMARKS

NAME

SIGNATURE

DATE
TESTED & CERTIFIED BY WITNESSED BY WITNESSED BY
(NMX) CONSULTANT
PUMP SCHEDULE

SL.
Description Model / Make Capacity Location
No.
Podium
Sump Pump set for AP 3 L/s @ 15
1 Basement
Surface water 10.50.12.3/GRUNDFOS Mtr head
Level
Podium
Sump Pump set for AP 3 L/s @ 15
2 Basement
Sewage 51.65.22.3/GRUNDFOS Mtr head
Level
Sump Pump for Podium
AP 1L/s @ 7 Mtr
3 Chilled Water Basement
12.40.04.A1/GRUNDFOS head
Trench Level