5KW Solar PV Quotation

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

Rooftop Solar

PV System
Under Net
Metering
Arrangement
Address: -PURANADHAR POWER VISION, PUNE
Purandhar niwas sainagar sr no 58, Pune 411048
Mobile No:- 9850123182
Mail Id:puranadhar@gmail.com

Purandhar Power Vision


Proposal for
***************************
5 KW ON Grid tie Inverter
***************************

Roof top Solar Power Generating System


Under
Net Metering Arrangement
********************************
Reference: - MERC GR of Dt. 10 Sept 2016 and MSEDCL commercial circular dt. 25
Jan2016

*****************************
From, To,
Mr. RAHUL PATAVEKAR
Mr. Dhanesh Gaikwad
S.NO.23/1A,23/1B,24/2,26/1 PLOT NO.90, RAJAS
SOCIETY, 411046
Contact No: 9850123182

Proposal for Rooftop Solar Power Generating System (On-grid).

Purandhar Power Vision


Dear Sir,

We are introducing you with Rooftop Solar Power Generation under Net Metering System and MERC GR of Dt.
10 Sept 2016 and MSEDCL commercial circular dt.25 Jan2016.

What is Rooftop Solar Power Generation under Net Metering

This system generates electricity, reduces our electricity bill and if generates more it feeds to Grid and Gives us benefit
for the same.

We request you to install this system in your premises on various buildings and save your electricity bill up to 100%
and contribute to Green Energy Generation ultimately to Nation Building.

We are an ISO 9001:2015 Certified small scale industry. Engaged in manufacturing advanced solar lighting equipments,
solar water heater system and solar rooftop net metering system in pune area. We also provide services like installation
& after sales services.

We are also integrating system for solar power packs. We are interested for above said work here we quote our best
offer for you. Rates are quoted with complete with installation including civil & electrical work & inclusive of all taxes.

Thanking you!

For Purandhar Power Vision.


3

Purandhar Power Vision


Salient Features of our solution


Turnkey solution for Engineering, Design, Procurement, Installation & commissioning.

Savings in electricity bill up to 90%.

Direct connection to MSEDCL

Net meter measure measures Import, Export and Net energy

All electrical loads work


AMC offered to the customer at very nominal charges.

Generation assured as per STC and NASA data.

Life of a Panel: 25 years, Solar Inverter: - 12 years.

All Components as per MNRE standards.

Battery less technology with high efficiency (>96%).

Our system saves CO2 emissions to save environment and maintain global warming effects

Fixed energy cost for lifetime - 25 years

Low maintenance cost.

Purandhar Power Vision


Solar plant components

Polycrystalline Modules

Rated power 250 Wp 335 Wp


Number of cells 72 cells 72 Cells

Open circuit Voltage- Voc 44.28 V 44.60 V

Short circuit current- Isc 7.63 A 9.10 A

Rated voltage- Vmpp 36.72 V 36.60 V

Rated current- Impp 6.81 A 8.20 A

Module efficiency- %ƞ 15.05 % 15.22 %

Module Dimensions 1663 X 997 X 1977 X 997 X 45


45 mm Mm
Module Net weight 19.8 kg. 27.5 kg.

Solar inverter - Grid tie Inverter

Design
Super flex, transformer-less

Inverter efficiency > 98%

Complying IEC standards


IEC 62109

IP 66
Ingress protection

Mounting structure

Fixed mounting structure

Corrosion resistant
Capable of withstanding high wind speed

Purandhar Power Vision


Consumer No. 1:- 170507161955 source by MSEB**

Purandhar Power Vision


AVERAGE SOLAR RADIATION
PUNE

Monthly solar radiation [wh/m2]

Purandhar Power Vision


Global Horizontal Solar Irradiation Data
This input is more relevant for Solar PV System design.

Purandhar Power Vision


TECHNICAL PROPOSAL
Products Make Description Quantity
Growatt/Zever/Delta/
INVERTERS Victronics 5 KW 1
Waaree/Zytech/Canadian/BLD
MODULES /HHV Solar 335 wp Multi Crystalline 15

Mounting Structure As Per Space

Array Junction Box STATCON/Cape Electrical /Equivalent IP65 rated 1

Earthing & Protection Reputed make As per IS 3043 At actual

Bill of Material
Solar Module Detail:
Make : Waaree/ Panasonic/AcuTech/Vikram
Wattage of each module : 335 watt
Number of Module :16
Inverter Detail:
Make : Delta/ GROWATT/ ABB / Victronics /Eqvivalent.
Total KW : 5 KW
Balance of System:
2 Pole AC MCB :C&S/ Havells/ Eqvivalent.
Inverter to ACDB, ACDB to Load with Cu. flexible cable : Polycab/ Havells
Earthing cable for ACDB, Inverter & LA to Earthing Electrode : Polycab/ Havells
MC4 connector : Synergy
Lugs for DC cable : Dowells/ Elmex
Lugs for AC cable : Dowells/ Elmex
Module Mounting Structure
standard
Net Meter
Genus/Secure

Purandhar Power Vision


SCOPE OF WORK

SR no SERVICE SCOPE
I SITE
1 Finalization of site location Client
Ensuring site availability all times without any hassles or hindrance for peaceful
2 exestuation of work Clirnt

II. ENGINEERIG
1 As built drawings and O & M manuals PPV
2 Project Handover Documentation PPV
III. PROJECT CONSTRUCTION ACTIVITIES
1 Water and power supply for construction CLIENT
2 Storage and other temporary constructions CLIENT
IV CIVIL DETAILS
1 Mounting Structure Foundations PPV
V MECHANICAL WORKS
1 Module Mounting Structure PPV
2 String Monitoring BOX Structure PPV
VI DC ELECTRICAL SYSTEM
1 Solar PV Module PPV
2 Solar Cable – From Module to string combiner Box PPV
3 MC4 Compatible Connectors PPV
4 Conduits for burying unarmored solar cable PPV
5 DC Cable from string combiner box to inverter PPV
6 Cable Terminations as per the scope above PPV
VII AC ELECTRICAL SYSTEM
1 LT Panel (ACB between inverter) PPV
2 AC Cable (AI) from inverter to LT panel PPV
VIII PROTECTION SYSTEM
4 Lighting Arrestors for DC side only PPV
IX SECURITY SYSTEM
1 Fire/ Smoke detect system for inverter/control room CLIENT
2 Security System (Plant Surveillance Camera) CLIENT
X MISCELLANEOUS
1 Fire Extinguishers and Electrical Safety Items CLIENT
2 Consumables (Paint, Cleaning, Accessories) CLIENT
XI TESTING AND COMMISSIONING
1 Inspection of equipment PPV
2 Pre-Commissioning tests of items PPV

3 system Commissioning as per the scope mentioned above PPV


On-site Training and system handover to client for the scope
4 PPV
mentioned above only
XII OPERATION AND MAINTENANCE
1 Operation & Maintenance CLIENT
2 O&M Spares CLIENT

10

Purandhar Power Vision


WARRANTY

• 10 years warranty on solar panels, product defects in materials & workmanship (best in industry) with 25
years linear output warranty, 10 years warranty for 90% of warranted minimum power output, 25 years
warranty for 80% of warranted minimum power output.
• 5 years warranty on Grid Inverter against any manufacturing defects.

• Cables / Electrical switchgears –warranty shall be transferred to the project Developers as given by the
manufacturer.

11

Purandhar Power Vision


ENERGY PRODUCTION IN PV SYSTEM
*Shall be calculated from historic data of energy bills or based on Energy Audit
** Above data is without considering distribution losses

Name of customer Mr. Rahul Patwekar

Proposed Solar System 5


Cons. No. 170507161955
Bill Amount Per Unit Solar Unit Gen
Month UNIT 1 charge 5kw

Oct-18 121 1,560.00


12.89 708.44

Sep-18 138 1,590.00


11.52 597.44

Aug-18 114 4,080.00


35.79 526.44

Jul-18 528 2,700.00


5.11 480.81

Jun-18 293 1,020.00


3.48 570.44


Total 1194
10,950.00
68.80 2883.56
₹ ₹ 576.71
Average 238.80 2,190.00 13.76

Monthly Avg Cons


6,642.43 Unit
Solar Power Generation with system
5.00 KW

Required Space
600.00 Sq. Ft

12

Purandhar Power Vision


Annual Energy Generated price
Generation
Years through Tariff
Initial
solar Actual Annual Saving By
plant(kwh)
Project
Billing ON-Grid system
Cost
Rs 351720
1 6912.00 12 82944 268776
2 6,842.89 12 82114.64211 186661.4
3 6,774.46 12 81293.57699 105367.8
4 6,706.73 12 80480.7217 24887.06 105367.7809
5 6,639.67 13.2 87643.59357 -62756.5 24887.0592
6 6,573.28 13.2 86767.2444 86767.2444
7 6,507.55 13.2 85899.65786 85899.65786
8 6,442.48 13.2 85040.74632 85040.74632
9 6,378.06 13.2 84190.42305 84190.42305
10 6,314.29 14.52 91683.46238 91683.46238
11 6,251.15 14.52 90766.71853 90766.71853
12 6,188.65 14.52 89859.1412 89859.1412
13 6,126.77 14.52 88960.63875 88960.63875
14 6,065.50 14.52 88071.12043 88071.12043
15 6,004.86 15.972 95909.54606 95909.54606
16 5,944.81 15.97 94938.65593 94938.65593
17 5,885.37 15.97 93989.36336 93989.36336
18 5,826.52 15.97 93049.56277 93049.56277
19 5,768.26 15.97 92119.15926 92119.15926
20 5,710.59 20.39 116438.8491 116438.8491
21 5,653.49 21.4095 121038.3047 121038.3047
22 5,596.96 21.4 119774.8704 119774.8704
23 5,540.99 21.4 118577.2403 118577.2403
24 5,485.59 21.4 117391.5852 117391.5852
25 5,430.74 21.4 116217.7856 116217.7856

13

Purandhar Power Vision


Commercial Offer:
Price for design, supply, installation,
testing and commissioning
Price offer for design, engineering,
supply, transportation, installation,
05 Kwp solar PV plant:

Item Description Rate Quantity Unit Amount

Design, Manufacture, Supply of 5 kw Solar rooftop power


generation under Net Metering arrangement ( As per BOM) 1.00 No 3,51,720.00
3,51,720.00
Installation & Commissioning of PV Plant & Equipment
Gross Total 3,51,720.00

Total Amount 3,51,720.00

• Any Extra electrical work or fabrication work required will be in client scope.
• Liaceaning charges extra will be in client scope.

14

Purandhar Power Vision


TERMS & CONDITIONS
SR Applicable Terms
No Heads
1 SOW PPV Scope is restricted to design, engineering, manufacture, supply, packing,
forwarding, erection, testing and commissioning of Equipment’s as per agreed
scope, technical offer and specifications.
This scope is for agreed timelines and in accordance with other provisions and
obligations of each party. Unless specifically agreed by us in writing, no other
supply or services shall be considered as part of our scope/ deliverable/
obligation.
2 Price Basis Deliver to site
3 Excise Duty Exemption certificate for availing concession on Excise Duty shall be arranged
by client. It will be charged extra at actuals in case certificates not made
available within timeline
4 Custom Duty Exemption certificate for availing concession on Custom Duty shall be
arranged by client, customs Duty is considered ‘nil’ for this proposal.
5 Taxes & Duties On Supply: VAT (5 %) or CST ( 2% against C form ) Excluding & will be
charged extra at actual.
On Services: S.Tax (15%) will be charged extra at actual if applicable.
Other Taxes: Entry Tax, Octroi shall be charged extra at actual by client.
Any change in taxes/duties due to statutory variation shall be to the
purchaser’s account.
4 Freight & Included in Price
Transit
5 Terms of Mentioned separately in commercial offer
Payment
6 Interest on In case Owner fails to make the due payment within the agreed stipulated
Overdue timeframe, the Contractor shall be eligible to charge an interest of @12% per
Payment annum on all overdue payments until the duration the payments are received.
7 Assumptions The Prices are quoted in INR taking into consideration the current US dollar
for Foreign Value at INR 66, (hereinafter referred to as base rate). In the event there is
Exchange change in this rate beyond 2% at the time of order and advance receipt the
price shall be deemed to be escalated to that extent (hereinafter referred to as
“Revised Value”). The Revised Value shall be also applicable at the time of
making payment to PPV.
8 Packing Packing will be done as per PPV standards. Included in offered Price.
9 Deemed If the grid is not made available by owner to PPV within 15days of the solar
Commissioning power plant being ready for grid connectivity because of which PPV cannot
conduct the final performance tests, it shall be construed as “Commissioned”
10 Approvals Any Type of approval by Government/third party is excluded from this offer,
if it is required then all the terms and conditions will be decided after mutual
understanding. And delay in projects due to any kind of approval will not be
responsibility of PPV.
11 Inspections Any Type of inspection by Government/ third party is excluded from this
offer, if it is required then all the terms and conditions will be decided after

15

Purandhar Power Vision


mutual understanding. All The cost for this inspection will be given by client.
12 Force Majeure PPV shall not be liable for any failure or delay in the performance of this
Agreement/proposal for the period that such failure or delay is due to causes
beyond its reasonable control, including but not limited to acts of God, Natural
calamities, war, strikes or labour disputes, embargoes, government orders or
any other force majeure event.

.
Sdbjkb
13 Confidentiality All the information exchanged between the parties, either oral or written, in
/ Do Not connection with this offer / contract. Shall be maintained strictly confidential,
Disclose (DND) except to the extent necessary to carry out obligations under it or to comply
with applicable laws.
14 Change in Any change in standard consideration/ considerations for technical designing
Standard of the system & scope of work will affect the design of the system as well as
considerations/ quoted price & increased price will be given by client.
considerations
15 Right & Lien of We shall retain the right on equipment, materials or parts supplied by us
Property under this quotation until full value there of as per our invoice has been fully
paid to us.
16 Acceptance All supplies of material or service works executed by contractor shall be
certified by owner within 3 days of submission of its documents or
measurement sheets or invoices.
Upon completion of the Scope of work, the owner shall issue a Final
Acceptance Certificate to the Contractor
17 Jurisdiction All disputes are subject to Hyderabad Jurisdiction only.

ADVANTAGES OF SPV PLANT


• It is an abundant Renewable Energy
• This source of energy is omnipresent and it can be captured from conversion on daily basis
• It is a Non –polluting technology, which means that it does not release greenhouse gases
• It is a Noiseless technology as there are no moving parts involved in energy generation
• This technology requires low-maintenance because of lack of moving parts
• It can be installed on modular basis and expanded over a period of time
• Most viable alternative for providing electricity in remote rural areas as it can be installed
where the energy demand is high and can be expanded on modular basis.