Professional Documents
Culture Documents
N-1 Maximum Transfer Capability
N-1 Maximum Transfer Capability
Abstract: The increase in power transfer among areas of with the help of the University of Pavia and the Politecnico di
interconnected systems and the reduction of reactive power reserves Milano, developed the procedure VOSTA [3]. It is based on
together with the competition in the electncity markets, force system sensitivities of the maximum singular value of the inverted
operators and planners to look at the determination of the available Jacobian J of the LF equations. VOSTA is used to rank and
transfer capability (ATC) of the system in a new perspective. In
particular, a (N-1)security approach should be adopted in the quantify the risk of voltage collapse following a branch
determination of the ATC. contingency. The maximum loadability and the quantification
In this paper, second order information derived from the Singular of the risk of a contingency are assessed by means of quam
Value Decomposition of the load flow (LF) Jacobian matrix is linear indices, that allow the determination of the critical pre-
combined with an iterative procedure in order to obtain a suitable contingency power flow in the branches and/or of their critical
estimation of the ATC by means of a linear programming procedure. admittance. The procedures and the proposed indices can be
The effectiveness of the presented approach is supported by the used both in extended real time environment and in operation
tests on the IEEE 73 buses reliability test system and on the Italian planning to improve the security degree of the system,
EHV transmission system. VOSTA makes use of fictitious real and reactive power
Keywords: Voltage Collapse, Power System Security, Singular
Value Decomposition. Available Transfer Capability. injections [3] in the considered branch terminals that are
suitably modified to simulate the trip of this branch for
I. INTRODUCTION different values of the power flows. The adoption of this
technique leads to an important change in the network
Recently, due to the introduction of the competition in the structure, but the modification of the injections only in the
electricity market, transmission grids are operated close to terminal buses of the tripped lines does not take into account
their limits. The increase in power transfer among areas of the realistic distribution of the power flows attainable with the
interconnected systems and the reduction of the reactive power available control actions. Namely, i n the actual system. a
reserves on generation units are stimulating system operators change in the power flow of a critical branch influences also
and planners to consider the problem of the security also from the branches close to this branch; in particular, it is necessaq
the voltage/reactive point of view [1][2][3]. As a consequence. to take into account that a set of control actions to reduce ths
the contingency analysis is no more limited to the assessment power flow in a critical branch results in a subsequent
of the current overloads on the transmission equipment but it beneficial decreasing of the flows in the existing parallel
is extended to the investigation on the practicability of the branches. The use of fictitious injections can cause therefore
voltage profiles in the post contingency states. Voltage over conservative estimates of the maximum allowable
collapse constraints are frequently included in the optimisation "secure" pre-contingency power flows in the critical lines.
procedures suited for the operation of modern power systems To extend the capability of VOSTA, a more practical and
useful approach has been adopted. It allows the computation
I41M
An on-line Dynamic Security Assessment function is on
of more significant critical power flows in a branch or in a
defined corridor and of the control actions allowed to system
the way of being included in the improved EMS of ENEL to
be run after a fast contingency screening algorithm. Its main operators for the satisfaction of the operating constraints. Thz
goal is to determine the risk of voltage collapse following new procedure gives the system operators information on
foreseeable dangerous contingencies. For this purpose ENEL, control actions (power generation rescheduling or load
shedding) suitable to bring the power flows in the detected
critical branches below the maximum values pertinent to the
risk of the voltage collapse.
A constrained linear programming procedure makes it
possible, by using the sensitivities of the power flows in thz
branches with respect to the real power generations and the
real loads in the systems. An iterative procedure determines
the rescheduling actions on the real power generations that
bring the power flows in the critical branches or in a defined
power corridor to values that guarantee the existence of the LF
where:
PI, and Q,, are the real and reactive power flows of branch i-j;
/\\
\\
Critical line
Non critical lind
ipower flow
: .
pij
-
AP,= -AP,,, AQ,,= tgcplJAP, and AQJ1= tgcp,, APjj. ................ 4
Critical flow *
The use of ( I ) gives information on the risk associated to ............................................................
+d
each outage. It is worth noticing that second order information
J
Critical flow
is embedded in the ranking, because it makes use of the LF
equation Hessian fxx[7]. Given that the cubic matrix fxx is very Fig.2 - The use of the linear index to assess cnncal power flows.
sparse, the ranking of all the contingencies can be made in a
very short time, because it requires only the base case LF and In the case there is at least one critical line, the operator
the Singular Value Decomposition. should try to make the system secure forcing it to the N-1
Due to the non linearity of Q,, the calculated variations secure state. This can be made reducing the power flow in the
of U, cannot be used to quantify the risk of voltage collapse critical branch(es) by the remedial control actions as the
following each contingency. In order to quantify the risk of rescheduling of power generations and. in emergency
voltage collapse, in VOSTA two different approaches can be
@JANTIFIC4TMN
iE NG
where:
PI is the power generated in the i-th control generation bus;
PS is the slack bus power generation;
P,,, is the actual power flow of the i-th critical branch;
the superscripts 0 and cr are relevant to the variables
calculated in the initial conditions and pertinent to the
estimated critical value respectively; Fig.3 -Flow chart of the ( N - I ) secunty analysis.
According to the approach above described for a single V. TESTS AND RESULTS
branch. a similar procedure is presented in order to determine
if any critical power corridor could limit the power exchanges The procedures described above have been validated on
among different areas of the power system. two test systems: the Three Area Reliability Test System (73
A power corridor is defined as a set of branches that, due buses) and the Italian power system. The Three Area
to their "electrical proximity" behave approximately in the Reliability Test System [ll], modified to solve the maximum
same way and therefore can be considered together from the transfer capability problem by the CICRE Task Force [ 121 and
operation point of view. In a N-1 approach, a corridor is depicted in Fig.4, is well fitted to show the properties of the
critical when at least one of its branches is critical. Generally, proposed procedure. It is characterised by three different
the power flows in the branches of the same corridor have the control areas and by a significant power transfer to the load
same direction. busses located in the right lower part of Fig.4.
The concept of power corridor is particularly meaningful
for system operators because it takes into account the
relationships among lines: therefore they can control the
system considering that a control action on a line will affect, at
the same time, also some other lines, in particular those
belonging to the same corridor.
The benefit of making use of power corridors instead of
single lines derives from the best distribution of the flows that
can be achieved by the linear programming procedure, and
consequently from the best exploitation of the corridor
capacity. At the same time, the power flow reduction
determined by the procedure described in Sec.11, conservative
if applied to a single branch, is much more adequate if it is a
constraint on the global power flow through the relevant
power corridor.
The procedure starts making use of the ranking and
quantification results calculated as in Sec.11, i.e. determining
the critical lines and the relevant critical corridors. It exploits
the fact that the reduction in a branch flow results in a
reduction more or less significant also in the other branches of
the same corridor. The relevant formulation of the linear
problem is as follows:
subject to
CRITICAL
POWER FLOW
BRANCH
IMWI
BARKLA - BLOCH -360.5
BANKS - BAJER 75.7
BARDEEN BARRY - -266
BARRY - BASOV -502.6
Fig.5 - The central pm of the Italian power system. The Italian system is characterised, in the studied situation.
by a significant power flow from north to south. Therefore, the
V.I IEEE Reliability Test System critical lines are those connecting these two areas, as shown in
Tab.111.
The first results are relevant to the LEEE test system and to The control strategy described in Sec.111 can be used to
the application of the procedure presented in Sec.111. As reduce power flows in order to get a N-1 secure state. In this
mentioned, the first step is the determination of the critical case, the generation output rescheduling is able to reach the
lines following the ranking and the quantification procedure. goal, without load shedding. It is worth noticing that, as shown
The set of the critical lines is shown in Tab.1. in Tab.111, the procedure based on the injections on the branch
terminals give a very conservative estimate of the more
-
Tab. J Critical power flow in the IEEE Test System practical value determined after rescheduling the real power
generation (more than about 400 MW in the case of the line
BRANCH CRITICAL CURRENT POWER
Valmontone Presenzano).
POWER FLOW FLOW
BARKLA - BLOCH -369.98 [MW] -411.1 [MW Tab.111 - Results of the pmcedure in Sec.JIl on the Italian system. a) is the
63.1 [Mvu] 70.1 [Mvw]
-
critical power flow of the line Valmontone Presenzano [MW] estimated
using the procedure in Sccl; b) are the power flows [MW] obtained by the
BANKS - BAJER 64.5 [ M W 129 [MW] procedure in the N-1 secure state after the rescheduling pmedure of Sec.111.
-70.78 [Mvar] -141.6 [Mvx]
BARDEEN - BARRY -232.3 [MW] -331.9 [MW]
-49.5 [Mvx] -70.7 [Mv~x]
BARRY - BASOV -342.2 [MW] -570.3 [MW] Valmontone - Presenzano
Montalto - Villanova 825 564
150.4 [Mvar] 250.7 [Mvar] Villnnnvn - larino 706 393