Draft Project Schedule
Draft Project Schedule
Finish Predecessors % Complete June 01 July 01 August 01 Septe 01 October 01 Novem 01 Decem 01 January 01 Febru 01 M
1/0 5/0 9/0 3/0 6/0 0/0 3/0 7/0 1/1 5/1 9/1 2/1 6/1 0/1 4/1 7/0 1/0 4/0 8/0 4/0
1 1 MANAGED PRESSURE DRILLING & RISER GAS HANDLING CO 153 days? Wed 18/07/12 Fri 22/02/13 66%
2 1.1 212377 SURFACE EQUIPMENT & AIR RECEIVER 124 days Wed 18/07/12 Mon 14/01/13 87%
3 1.1.1 Design 104 days Wed 18/07/12 Mon 10/12/12 90%
4 1.1.1.1 FDS 10 days Wed 18/07/12 Tue 31/07/12 100%
5 1.1.1.2 Software Requirements Specification 86 days Wed 18/07/12 Wed 14/11/12 90%
6 1.1.1.3 Control System Definition Document 14 days Wed 18/07/12 Mon 06/08/12 100%
7 1.1.1.4 Electrical Block / Single Line Diagrams 10 days Wed 18/07/12 Tue 31/07/12 100%
8 1.1.1.5 Electrical Interconnection Drawings 10 days Wed 18/07/12 Tue 31/07/12 100%
9 1.1.1.6 Pneumatic Interconnection Drawings 10 days Mon 19/11/12 Fri 30/11/12 20%
10 1.1.1.7 Power Supply Distribution Diagrams 10 days Wed 18/07/12 Tue 31/07/12 100%
11 1.1.1.8 Cable & Piping Schedule 2 days Mon 03/12/12 Tue 04/12/12 4,5,6,7,8,9,10 10%
13 1.1.1.10 Component Specification / BOM 75 days Wed 01/08/12 Tue 13/11/12 95%
16 1.1.2.2 Atex Solenoids / Actuators 3.7 wks Tue 30/10/12 Fri 23/11/12 80%
18 1.1.2.4 JWF Pressure Transmitters 13.3 wks Wed 22/08/12 Thu 22/11/12 95%
19 1.1.2.5 Parmley Graham CPU, Profibus equipment, WINCC etc 30 days Fri 14/09/12 Thu 25/10/12 95%
20 1.1.2.6 Powersolve Electronics - Power Supply / Battery equip. 11 wks Wed 05/09/12 Tue 20/11/12 95%
23 1.1.2.9 Zone 1 Touch Screen 12 wks Fri 31/08/12 Thu 22/11/12 95%
24 1.1.2.10 Air receiver 4 wks Fri 23/11/12 Thu 20/12/12 0% Graham / Tom