Professional Documents
Culture Documents
Capital Projects and Infrastructure
Capital Projects and Infrastructure
Capital Projects and Infrastructure
Capital
projects and
infrastructure
in East Africa,
Southern
Africa and
West Africa
www.pwc.co.za/infrastructure
Contents
Foreword 1
Executive summary 2
Africa’s infrastructure outlook 4
Harnessing the private sector 7
Changing funding models 11
Political risk and corruption 15
Project delays 18
Budget overruns 21
Project quality problems 25
Reporting and review process 27
Priorities for improvement 28
Local content in capital projects 31
Sector profiles 32
Transportation 32
Oil & gas 38
Power 43
Water 49
Regional overviews 56
East Africa 56
Southern Africa 61
West Africa 66
Conclusion 72
Sources 73
Contacts 75
About this survey and report
PwC’s Capital Projects and Infrastructure (CP&I) project team developed a standard questionnaire that was used to
conduct interviews with key players in the infrastructure sector, including donor funders, financiers, government
organisations and private companies across East, West and Southern Africa.
Respondents were spread fairly evenly across the three sub-regions, with 18% operating across more than one.
About half of respondents were owners playing multiple roles, including financier and operator, while the remainder
represented state-owned enterprises.
Sectors surveyed included water, transport and logistics, energy (power and oil & gas), mining, social infrastructure,
telecoms and real estate, with the main focus being on primary infrastructure. More than one-third (39%) of
respondents were involved in more than one sector.
Respondents reported extensive experience in infrastructure development with about one-third having been involved
in more than 20 projects in the last year. Southern Africa had the most respondents involved in more than 20 projects,
while East Africa had the largest number involved in 6-20 projects.
In most cases, interviews were conducted in person, which allowed meaningful conversations to take place. Responses to
quantitative survey questions were then captured with a survey tool. The CP&I team used this information, together with
our extensive knowledge of the infrastructure value chain and other research, to produce this report.
Foreword
PwC 1
Executive summary
The shallow economic recovery in Some of our key findings include: • Access to funding emerged as the top
most developed markets has shifted challenge in delivering large, complex
the focus to faster-growing markets. • More than half of respondents infrastructure projects. It was named
This is also true for the infrastructure indicated that their planned spending as a key challenge by almost half of
development sector. While the largest on infrastructure, both new projects respondents, followed by the policy
infrastructure spend will take place in and refurbishment of assets, would and regulatory environment and
Asia, led by China, the expected growth increase by more than 25% from the political risk/impact of political
in infrastructure spend in sub-Saharan previous year. They said much of interference, which were cited by
Africa is significant at around 10% per their spending would be focused on about a third of respondents.
annum to 2025. With an abundance of new development, with 51% of all
natural resources and recent mineral, oil respondents planning to spend more • Funding availability was a concern
and gas discoveries, demographic, social than half of their budgets on new across all regions, but respondents in
and political shifts and a more investor- assets. Southern Africa were more concerned
friendly environment, the investor about a lack of skills, internal capacity
spotlight shines brightly on Africa. • Respondents from West Africa were to handle major capital projects and
especially bullish, with 58% planning political risk.
One of the CEOs of a large state-owned an increase of more than 25% in
enterprise in Africa summed it up as spending, followed by those in East • Nearly all respondents said they
follows: Africa (53%) and Southern Africa consider external private sector
(40%). financing vitally important for capital
Among the emerging markets, we think
projects in Africa.
that Africa, for the first time in many
• All regions are expected to be major
centuries, is going to contribute quite
beneficiaries of infrastructural • Lack of skills and external contractors
significantly to global economic growth.
development, with 44% of across the infrastructure value chain
While it’s coming from a low base,
respondents indicating they would in Africa were cited by respondents
the continent’s economy is growing at
be targeting their capital project as challenging factors and among the
about 5%, making it the fastest-growing
and infrastructure spending in East primary reasons for quality problems,
region in the world.
Africa over the next 12 months. Next while funding issues were cited as
is Western Africa (25%), followed by a main reason for delays in project
Project bankability/viability and access
Southern Africa (22%). delivery.
to funding are the most common
challenges emerging from our survey.
• Respondents indicated that they • Project delays and cost overruns
In order to address this issue, African
would be increasing their focus on were significant problems in the past
countries must overcome the obstacles
power, oil & gas and transportation & year, with nearly half of respondents
of inadequate regulatory frameworks,
logistics while remaining constant in reporting delays of more than six
internal capacity limitations, political
the water sector. months and more than a third saying
instability, policy incoherence, reported
projects went 10–50% over budget.
corruption, and a debilitating shortage
of capacity and skills. • Almost 90% of respondents said their
capital projects had delivered the • Most respondents said their projects
expected benefits to stakeholders all had experienced few, if any, quality
or most of the time over the past problems or variations from original
12 months. specifications, but about a third did
encounter such problems in some or
most cases.
5%–25% pa
economic return
$1 spend on
capital projects
PwC 3
Africa’s infrastructure
outlook
Dealing with Africa’s infrastructure Figure 1: Real GDP growth (%)
backlogs and its future demands is
high on the agendas of leaders and civil
society on the continent and abroad.
There is widespread recognition of the 8
vast business opportunities in Africa as
a growing consumer market and future 7
skills and innovation pool as well as its 6
abundance of natural resources.
5
Taken as a whole, Africa’s infrastructure
lags well behind that of the rest of the 4
world with some 30% in a dilapidated
3
condition and massive backlogs in
almost every country across most 2
infrastructure types. Improving
infrastructure will be critical to spurring 1
Africa’s continued economic expansion
0
and enhancing its standard of living and
stability. -1
2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020
Speaking of Africa as a homogeneous
collective does not provide an accurate Sub-Saharan Africa
picture, though – there are vast country
and regional differences. For example,
South Africa’s overall transport World
infrastructure scores as well as India’s
and better than Indonesia’s. In fact, Source: IMF, World Economic Outlook database
when it comes to roads, ports and air
transport infrastructure, South Africa
scores higher than China, although
China has a clear edge in rail. Egypt and
Kenya score lower, but are ranked higher
than Vietnam, another of Southeast
Asia’s fastest growing economies.
60
50
40
30
20
10
0
Chemicals, metals Electricity production Water and sanitation
and fuels sector and distribution services
PwC 5
“I think the optimism reflects a few things. First,
Africa represents 15% of the world’s population
and 3% of the world’s GDP. Secondly, Africa has
a track record since the year 2000 of growing at
5.5%. It’s a tremendous opportunity. That’s why
we see sovereign wealth funds, multinational
corporations, African companies indigenous
to the home markets, Brazil, India and China,
all very active. We’re seeing the growth of two
things. First, the exploitation of natural resources
on the continent and two, the exploitation of
the demographic dividend in Africa, the rising
consumer and the need to address that.”
– Colin Coleman
Managing Director, Goldman Sachs SSA
The Africa Business Agenda, PwC, 2014
Q: How important is external private sector financing for capital projects in Africa?
5%
1%
5%
“Africa, though
increasingly taking
Not needed (projects funded internally)
on higher financing
Not critical
capacity on its own,
Growing importance
still requires substantial
Critical
external financial
Undecided
support to execute
critical infrastructural
Base: 95 respondents projects.”
Source: PwC analysis
– Survey respondent
Energy and mining sector
West Africa
PwC 7
Figure 4: Methods of funding in the short term
Q: How do you expect your infrastructure projects to be funded over the next year?
11%
29% 10%
50%
Base: 95 respondents
Source: PwC analysis
Sub-Saharan Africa
Advanced economies
PwC 9
“Chinese foreign direct investment (FDI) has infiltrated everything from shoe
manufacturing to food processing across Africa. Chinese firms have also made
major investments in African infrastructure, targeting key sectors such as
telecommunications, transport, construction, power plants, waste disposal
and port refurbishment. Given the scale of Africa’s infrastructure deficit, these
investments represent a vital contribution to the continent’s development.
Another common misconception is that Chinese companies now rule the African
economy. In fact, about 90% of the stock of FDI in Africa still originates from
firms in advanced countries, most of them in the US and the European Union.”
– Harry Broadman
‘Separating fact from fiction in the China-Africa relationship’
Gridlines, PwC, 2013
International financial institutions, What helped attract investors was the Defining a clear source of revenue
including the World Bank Group’s IFC’s decade-long focus on the Ivoirian through user payments or other sources
International Finance Corporation power sector’s financial stability. In for some projects, particularly those
(IFC), are helping to mobilise private 1998, the IFC played a key role in of a social nature such as hospitals
investment in Africa. After the prolonged designing a unique ‘cash waterfall’ and schools, is often difficult and a
political crisis in the Côte d‘Ivoire, the structure to manage the sector’s cash prerequisite for project financing.
IFC, as lead arranger, succeeded in flows and make the prospect of payment
mobilising about US$1 billion of private apparent to private independent power Weak infrastructure planning at the
investment in the country’s power sector, producers and gas suppliers. macro country level, characterised by
financing the expansion of the Azito and limited capacity to identify technically
CIPREL power plants. feasible and economically viable
programmes and projects, remains
among the greatest challenges to
securing private funding. Many
“The key risk is getting the assets completed on time countries lack capacity and skills to
and on budget. This risk needs to be significantly prepare project feasibilities and take
projects through to procurement. Lack
borne by the government at this stage until the of transparency and sound governance
market is sufficiently developed and predictable. practices, coupled with protracted
procurement processes, reduce investor
Managing completed projects is a much more appetite.
acceptable risk at the moment.”
Few African countries have a viable
structured PPP programme that supports
– Survey respondent both a structured process and a well-
Energy and power sector regulated system. This is necessary to
West Africa provide more certainty and reduce risks
for long-term investors.
29% 10%
More respondents in Southern Africa
than other regions expect projects to be
fully funded internally or through a mix
of government funding and government
bonds. Respondents in East and West
Africa are counting more on a mix of
private sector and government funding
or private sector debt and equity.
50%
PwC 11
Figure 7: Procurement models
Q: Which of the following procurement models do you believe will be used more
frequently in delivering your capital projects?
PPPs allow
cash-strapped
6%
governments
to put greater
financing risk and
burden onto the
private sector
45% 49%
Base 95 respondents
Source: PwC analysis
Support for different financing models The key criteria for PPP units have been established in a
also varied by sector. Traditional number of African countries ranging
successful partnership from South Africa to Nigeria, Senegal
procurement models were favoured
mainly by respondents from national
models include strong and Kenya. These units are at different
governments, water and mining political support, a levels of maturity, but are moving
organisations. committed sponsor, a sound towards standardisation and adoption of
leading practices.
regulatory framework, a
Power and oil & gas respondents were
viable off-taker or source of The Nigerian Government has also been
split on the issue of the traditional
procurement method versus PPPs. service fees, support from advocating the increasing use of public-
Meanwhile, local government, real users of the service and private partnerships for several transport
estate, telecoms, and transport sensible, logical allocation projects. Governance and management
respondents were more in favour of will need to be well-managed though, as
of risk and market interest many of Nigeria’s projects have been left
PPPs.
and capacity. unfinished including roads, factories and
oil & gas plants.
Organisations must be cognisant of
the existence (or lack thereof) of these
factors in their operating environments
when considering PPPs as a funding
method.
80
70
Sub-Saharan countries
60 are looking at
alternative ways to
50
fund their projects
40
30
The BMI Project Finance Ratings
20 assess the risk in raising and
repaying financing over the life
cycle of a project. The higher the
10 rating, the more conducive the
environment to successful PPP
0 procurement.
North America Asia Eastern Europe MENA Latin America Africa
and Western Europe
PwC 13
In South Africa, some of the larger state-owned companies have made progress
in issuing bonds to raise capital. For example, Transnet announced in
August 2013 it had raised ZAR1.5 billion, using a five-year bond through its
Domestic Medium Term Note Programme.
Q: What are your top three current challenges in relation to capital projects that you are involved in?
14%
Master planning
11%
Market capacity
0 10 20 30 40 50
Rank 1
Rank 2
Rank 3
Base: 95 respondents
Source: PwC analysis
PwC 15
Project sponsors, developers, and institutional reforms, the broader sector Cross-border integration is crucial
operators, along with investors, policy and legal measures, many of not only to facilitate trade, but also
often lack clarity around contracting, which can be accomplished by the stroke to link resources from source to point
government regulation, contracting of a pen. of consumption – e.g. bulk water and
arbitration, policy and process for power generation sources and feedstock.
procurement, planning and tariff setting. What have lagged are regulatory and In sub-Saharan Africa, 17 major river
In a number of cases this has resulted governance reforms. For instance, basins span as many as 35 countries.
in government officials terminating effective regulation requires building Regional cooperation and integrated
construction and concession contracts. organisations that challenge established, resource management are therefore
In others, significant claims have been vested interests. But interference from essential to ensure that water resources
brought by the private sector against government continues to undermine are managed optimally and efficiently,
governments. regulatory independence in many with consideration of long-term
countries. sustainability.
The greater the levels of political risk,
political interference and corruption, In addition to political and governmental Power is vital for infrastructure
the more cautious investors become. issues within individual countries, development and the establishment
Most capital projects are long term, project developers and investors see of multi-country ‘power pools’ aims
requiring many years of investment a growing need for countries to work to provide more stability in power
and development before returns are collaboratively on the development of supply and greater regional energy
realised and debts repaid. Often they infrastructure projects that frequently independence.
extend far beyond the political term extend beyond one country’s borders.
of office in democratic countries. There has already been much
To assist with project funding and A key factor in Africa’s future collaboration in the planning of
managing the issue of political risk, the development will be increasing infrastructure projects and some
World Bank’s Multilateral Investment cross-border trade, both within Africa implementation has started. The Eastern
Guarantee Agency is one of a number and with the rest of the world. This Electricity Highway Project – a 1 000km
of organisations providing political risk means solid road and rail networks that cross-border power line connecting
guarantees to debt financiers to increase span regions need to be established. Ethiopia’s and Kenya’s electricity grids –
the investment/credit grade of a project One example is the development of the is due to come online in 2018. However,
and hence move them to bankability. LAPSSET (Lamu Port-South Sudan- the pace of integration and collaboration
Ethiopia Transport) corridor, which will will need to increase substantially if
Infrastructure regulation in Africa is provide export routes for South Sudan sub-Saharan Africa is to meet its goals of
still in its early days. Typically, new and Ethiopia, linking them and Kenya. economic growth, poverty reduction and
laws and regulatory bodies exist for Another example is the 1 500km Trans- social upliftment.
telecommunications and electricity, Kalahari rail which is planned to link
whereas few countries have created Botswana with Namibia to support coal
water or transport regulators. Most exports from Botswana’s Mmamabula
African countries have undertaken initial coal mine via Walvis Bay.
If infrastructure projects
are to succeed, it is clear
that corruption needs to
be dealt with in a tough
manner, with a zero-
tolerance policy
PwC 17
Project delays
While all projects are susceptible to accessing supporting infrastructure Nearly half (47%) of our survey
going off track and experiencing costly (power, water, housing, airports, respondents said they experienced
delays, some are more vulnerable, such healthcare, etc.) and the need to import delays of more than six months on
as those involving new technologies, skilled labour, equipment, and materials. capital projects. Those in East Africa
those dependent on regulatory and This challenge manifests in many parts suffered the most delays of greater than
environmental approvals, those reliant of Africa. six months, while those in Southern
on substantial funding and those in Africa said the largest number of delays
politically unstable regions or requiring The impact of delays can extend beyond were between one and six months. Some
complex stakeholder management. the project itself. A 2013 PwC analysis well-publicised mega projects in the
of 52 capital project missteps at public region have suffered delays of between
Large projects are inherently risky, companies revealed that after a public 40% and 150% of the planned schedule.
encompassing many interconnected announcement of a capital project
parts, resources, contractors and some delay or shutdown, the majority of
with values in the US$ billions spanning companies experienced a steady decline
more than one or two decades. In in share price. By the three-month mark
immature markets, project developers following the announcement, the decline
face additional distinctive problems, in share price averaged 15%. In the most
including language and cultural barriers severe case of the companies analysed,
in contract negotiations, different one experienced an almost 90% decline
legal standards, a greater likelihood in share price.
of political interference, difficulty
47% 44% 7% 2%
Q: What do you consider your top three reasons for the delays to project completion?
(Summary of top three reasons)
68%
Internal related 33%
51%
18%
Finances/Funding related 27%
45%
21%
Supply chain related 27%
23%
21%
Government, regulatory and legal related 17%
23%
15%
Environmental issues 13%
21%
15%
Unplanned/External factors 13%
17%
3%
Local skills gap/capacity and related consequences 7%
26%
9%
Bureaucracy, delays in approvals 27%
9%
9%
Scope variation 27%
9%
21%
Supplier related 7%
9%
0 10 20 30 40 50 60 70 80
East
West
South
Base: 95 respondents
Source: PwC analysis
PwC 19
The most common reasons given for
delays were: “Delays are caused by the complex nature of oil &
• Internal problems gas projects and lack of certainty in the projects,
Including inadequate pre-
engineering, weak project
which are the first of this nature in Africa.”
management, internal procurement
issues involving staff and processes, – Survey respondent
weak governance, poor planning, Oil & gas sector
lack of visibility, deficient resource Operations across sub-Saharan Africa
planning, unrealistic expectations on
timing and scope change;
• Finance/Funding issues
Among the various sectors covered Another South African example is the
Including capital rationing, delays
in our survey, respondents in the construction of two coal-fired power
in the release funds, and failure to
power and oil & gas sectors ranked stations, Medupi and Kusile, which have
provide promised and approved
governmental complications and been running behind schedule with
funds;
regulatory and legal requirements significant cost overruns, due partly to
high on their list of reasons for project labour problems.
• Governmental complications delays. The lack of timely completion of
Including regulatory and legal environmental impact analyses as well State-owned power utility, Eskom, said
requirements, delayed approvals and as slow decision-making and approval the first power from its Medupi plant
changes in policy; and processes all contribute to project time would hit the grid only in the second
overruns. half of 2014, a delay of at least six
• Supply chain months that will increase the cost of
Including difficulties with the supply Availability of funding and the policy the project and possibly cause a gap in
chain into the organisation. and regulatory environment were supply in 2014. The power utility said it
the main concerns for respondents in was working with stakeholders to ensure
Whether in Africa or elsewhere, many the mining sector and government. security of electricity supply despite
projects experience delays because they Transport sector respondents identified the delay caused by labour unrest and
don’t get off to a good start to begin the impact of external, unplanned ‘underperformance’ by contractors.
with. There could be ill-defined cost factors such as weather and the Medupi was beset by a series of illegal
and schedule estimates, as well as a physical condition of sites as well as the strikes for five months from
failure to define the scope clearly and availability of skilled resources in the December 2012, the longest of which
set reasonable expectations. Sometimes market as some of their main challenges. lasted six weeks.
politicians and sponsors suffer from
‘optimism bias’ and set unrealistic One survey respondent reported delays
deadlines and budgets in an effort of more than six months and commented
to demonstrate their commitment to that delays are longer with government-
action and service delivery, only to funded projects, mainly because of
face the media and stakeholders with funding limitations and changes in
disappointing news later. scope.
Poor estimates during project planning Problems with labour and labour unions
and unrealistic or poor adherence to can also contribute significantly to
critical path deadlines are the largest project delays. It is estimated that 50%
contributors to project failure, according of construction companies operating in
to Insights and Trends, PwC’s 2012 global South Africa were affected and projects
survey of project management leaders. were delayed when around 90 000
workers downed tools in August 2013.
Delays, of course, usually result in Figure 11: Cost variances in the last 12 months
budget overruns, which bedevil many
projects and not only in Africa. In fact, a Q: On average, to what extent have your capital projects experienced cost
PwC analysis of industry research found variances from the original business case, in the past 12 months?
that mega projects often exceed their
budgets by 50% or more. 2%
2%
In our survey, 36% of the respondents
indicated that their projects had run 9%
over budget by between 10% and 50%.
Surprisingly, 2% indicated they had 19%
come in under budget. Respondents
from all three regions in sub-Saharan
Africa reported a similar number
of projects with budget overruns of
between 10% and 50%.
36%
32%
Under budget
On budget
Base: 95 respondents
Source: PwC analysis
PwC 21
Figure 12: Top three reasons for cost variances in the last 12 months
Q: What do you consider your top three reasons for these cost variances?
(Summary of top three reasons)
57%
Project management related 22%
30%
27%
Economic factors 48%
22%
30%
Delays 37%
27%
27%
Change of requirement 26%
22%
13%
Lack of internal capacity/Lack of skilled capacity 15%
32%
23%
Unforeseen events (force majeure) 7%
5%
13%
Procurement related 4%
14%
3%
Quality of materials and material costs 7%
11%
3%
Contractor/Service provider related 0%
11%
0%
Lack of market skills 0%
11%
0 10 20 30 40 50 60
East
West
South
Base: 95 respondents
Source: PwC analysis
Quality problems on capital projects Figure 13: Extent to which capital projects experienced quality issues
can be costly in terms of added expense
and delays. For example, in addition Q: On average, in the past 12 months, to what extent have your capital projects
to labour problems, Eskom’s Medupi experienced quality problems or variations from the original specifications?
power station also experienced welding
faults on the boilers and delays in the
installation of a software system that
was a critical part of the boiler safety
mechanisms. 11%
16%
About a third of survey respondents
said there were quality problems or
variations from original specifications
in some or most cases on their projects, 10%
21%
while 42% said that only in very few
cases did they experience quality
problems.
East Africa
Inadequate skills and
capacity In most cases
In some cases
In a few cases
Southern Africa
Poor project management Never
skills Unsure
Base: 95 respondents
Source: PwC analysis
West Africa
Quality of materials
When there were problems, these Respondents in East Africa named
resulted from poor project management inadequate skills and capacity to deliver
skills and planning; inadequate as the main cause of quality problems,
supervision of external contractors while those in the West Africa primarily
and other contractor issues, including cited materials-related issues and those
lack of adequate skills and corruption; in Southern Africa cited poor project
substandard materials or lack of quality planning and management skills.
materials; and inadequate capacity to
deliver, resulting in poor workmanship
and non-adherence to quality standards.
PwC 25
Owners are sometimes tempted Konan Bédié Toll Bridge project “Appropriate skills in local
to transfer too much risk to was awarded to the French government agencies and line
contractors and end up increasing construction company Bouygues ministries are often inadequate
their own risk in other ways. If for the building and operation of to assess and plan appropriately
an owner awards a fixed-price the 8km north-south connection for the formulation and
contract and shifts the cost risks linking the suburbs of Marcory and management of infrastructure
to the contractor, the contractor Riviera. development and services, as well
may choose to mitigate that risk as the enforcement of policies
by hiring less experienced labour Retaining foreign contractors and regulation,” according to
or using less expensive materials, isn’t necessarily a positive the Infrastructure Consortium
creating a quality risk for the development for project owners, for Africa. “This lack of technical
owner. In many cases a contractor developers or for Africa’s future capacity leads to a coordination
will also price in their view of the growth. Depending on a country’s failure on the part of government,
risk profile of the project, hence immigration requirements, there across the myriad of local
the owner may pay too high a may be long lead times to be able agencies involved in delivering
price premium for inappropriately to utilise foreign contractors, infrastructure services.”
transferred risks. potentially making it more difficult
to meet the project’s schedule. In
The growing talent gap in the addition, the use of contractors
construction and engineering does little to help build the skills
fields has the potential to spell and capacity of local people
trouble for projects in many unless the contractors are tied
countries. into stringent skills transfer
programmes. Furthermore, the
Respondents to our survey contractors’ compensation for their
noted the growing use of foreign work flows back to their homeland
contractors due to a lack of local and isn’t necessarily being
skills and expertise. For example, reinvested in the country where
China Harbour Engineering has the project is being undertaken.
been awarded a US$150 million
contract by the Ghana Ports Along with project contractors and
and Harbours Authority for the labourers, government entities
construction of a port as part of also received some blame in our
the Takoradi Port Infrastructure survey for quality issues.
Development Project. Similarly,
in Côte d’Ivoire, the Henri
An essential element of sound project Although most respondents indicated their projects on or below budget. This
controls and governance is ensuring that the project team regularly reported raises the question of whether the
that stakeholders and decision-makers to various stakeholders during the correct information is being reported
receive adequate warning of problems course of their projects and did not feel with sufficient depth and details to
and potential risks. Regular and detailed that reporting was an issue for their highlight the salient risks and issues.
reporting to the right people at the right organisations, almost 50% had project
time is vital. delays of more than six months and only
19% of respondents reported completing
PwC 27
Priorities for
improvement
Survey respondents named project too far down the path of planning. (procurement performance); asset
feasibility as their top priority for Respondents also cited the areas of management and optimisation; and
improvement in relation to capital project scheduling (completion date improving performance of capital project
projects. Ensuring projects are viable is forecasting and reliability of data in delivery. Once again, securing finance
a core consideration before embarking schedules); contracts and procurement was top of mind.
Q: What are your top three improvement priorities in relation to your capital projects?
0 5 10 15 20 25 30 35
Rank 1
Rank 2
Rank 3
Base: 95 respondents
Source: PwC analysis
In terms of their current operational assets, respondents said their highest priorities
were improving asset performance and developing an overall asset management
framework, including a strategy, plan, and asset risk framework. Some indicated
that they hope to implement major IT systems relating to asset management and
maintenance strategies, and to develop asset life cycle plans in conjunction with
establishing asset condition/performance monitoring systems.
PwC 29
This option is, however, best suited
to organisations that have a clear
understanding of what assets they have,
together with an asset life cycle plan and
a system to monitor the condition and/or
the performance of their assets. Where new
assets are added, respondents noted the
importance of integrating the old and new
assets into well-functioning networks.
PwC 31
Sector profiles
Transportation
Transportation accounts for a large Derelict and inefficient transportation Our survey is encouraging in that it
proportion of infrastructure investment infrastructure increases the costs shows there is at least a short-term
in most sub-Saharan countries. of moving goods, reducing the commitment to boost investment in
Nevertheless, the quality of roads and competitiveness of businesses, and transportation infrastructure in sub-
railroad networks still lags far behind impacts intra-country and inter-country Saharan Africa. More than half of
much of the rest of the world and they trade. In many African countries there is respondents in the transport sector said
are in serious need of improvement. just insufficient capacity to export much they planned to increase their capital
Many roads remain unpaved and most of the resource wealth that lies inland. project spending by more than 25% over
rail lines – constructed during the the next 12 months. Another 39% said
colonial period – are in poor repair and The African Development Bank reports their spending would also rise, but by a
outdated. The road access rate in Africa that high transport costs add up to smaller percentage. Slightly more than
is only 34%, compared with 50% in 75% to the price of goods in Africa. half of transport respondents said their
other parts of the developing world. It also notes that 30 countries have capital project spending in fiscal year
chronic power outages. It suggests that 2012 ranged between US$100 million
As Africa’s economies look to develop, it bridging these gaps alone could add two and US$500 million.
will be critical to create solid transport percentage points to Africa’s annual GDP
networks that span regions and the growth rate.
entire continent. Improved road and
rail linkages between economic centres,
resource-intensive export zones and the
port and airport linkages to the global
economy will spur greater cross-border
trade.
Q: What is your outlook for your capital project spend/funding for the next
12 months?
3% 3%
49%
56% 39%
of transport sector respondents
experienced delays for more
than six months on their
projects
50%
Significant increase (> 25%)
There is a firm commitment from Over the next decade, spending on the
funding organisations and governments various transport sub-sectors is expected
to develop transport infrastructure to continue growing, driven by the need
across sub-Saharan Africa and increasing to access the natural resources of the
attention now focuses on linking many region and achieve the goals of economic
of the transport corridors to create a development.
more effective integrated transport
network.
PwC 33
Anticipated spend on transport infrastructure across sub-Saharan Africa
Sector Estimated total spend by Anticipated annual spending Countries with largest spend
2025 growth rate planned by 2025
PwC 35
Transport respondents attributed cost variances was also cited as project
time delays primarily to internal management issues such as poor
problems such as weak planning and planning, poor design and rushing to
project management and thereafter to construction.
funding issues. The primary cause of
Figure 18: Transportation: Top three reasons for projects exceeding budgeted costs
Q: What do you consider your top three reasons for cost variances?
(Summary of top three reasons)
Delays 22%
0 5 10 15 20 25 30 35
Transport respondents said the Infrastructure improvements are not Certain countries have made strides
greatest challenges to their capital limited only to the physical assets but in this area. In Zambia, for example,
projects include internal capacity extend to the intangible components President Michael Sata’s anti-corruption
to plan and manage projects, the of regulatory reforms and policy drive has improved oversight of
availability of funding and the frameworks. Customs and clearance infrastructure procurement, and both
availability of skilled resources in the policies, trade agreements, tariffs, the state power company ZESCO and
market. External factors/unplanned – import permits and export licences the Road Development Agency have
for events such as unforeseen ground are just a few of the regulations and seen high-level personnel changes in an
conditions, standing time and variation policies underpinning the transport attempt to improve oversight in public
orders on most projects (dig then find) sector. With the increasing private sector sector contract awards.
were highlighted as factors impacting involvement in transport infrastructure
on the timely completion of projects. there is the requirement for clearer The associated impact of road
The policy and regulatory environment regulatory certainty (in rail, roads traffic congestion on an economy is
was also raised as a challenge by our and airports), which is absent in many becoming a growing concern across
respondents. countries. many of the major cities in sub-
Saharan Africa. Increased time in the
logistics chain correlates to increased focus is railways, often with emphasis The issuing of bonds and sovereign debt
costs of goods. Lost productivity on supporting access to Africa’s mineral are alternate means of raising finance.
time for employees, poor air quality resources. China has also heavily In September 2012, Zambia made its
affecting health and the environment, invested in airports, roads and ports. inaugural entry on the international
and the deteriorating quality of road capital market and raised
infrastructure due to the high volume In East Africa, China Merchants US$750 million through a bond issue.
of usage, are all consequences of this Holdings (International) Co Ltd has The bond proceeds were allocated
increased congestion. And these have signed a framework agreement with the among a number of infrastructure
the potential to directly or indirectly Tanzanian authorities to develop a new sectors with transport planned to receive
hinder economic development and port in the town of Bagamoyo to the US$430 million. The World Bank’s
growth. value of approximately US$10 billion. In Multilateral Investment Guarantee
March 2013, China pledged to provide Agency (MIGA) recently started
Countries in the region are looking US$5 billion in open-ended financial providing political risk guarantees to
to more efficient means to transport assistance to Transnet (South Africa’s debt financiers to encourage investment.
people through the construction of largest integrated freight transport
Bus Rapid Transport systems (BRTs), company) for its rail infrastructure Efficient transport is a crucial
Light Rail Transits (LRTs), subways upgrade programme. component of growing a strong
and the like. In Nigeria, the Lagos economy, and robust transportation
Metropolitan Area Transport Authority Chinese companies are also making their infrastructure is critical to a well-
is constructing a high-capacity LRT line mark in West Africa, where the functioning transport sector.
between Okokomaiko, Iddo and Marina US$1.49 billion Lagos-Ibadan railway Integration of transport network plans
which will be isolated from car traffic to contract has been awarded to China Civil into broader urban development master
ease road congestion and improve the Engineering Construction Corporation planning is essential to ensure that
flow of commuters. However, all this (CCECC) and the Olokola deepwater effective and sustainable developments
infrastructure development requires port project has been awarded to China are put in place for the longer-term
substantial funding. Ocean Shipping Group. Meanwhile, movement of people and goods into and
China Harbour Engineering has been out of towns, cities, and regions. Across
The respondents to our survey awarded a US$150 million contract by sub-Saharan Africa it is readily apparent
reported that government could not the Ghana Ports and Harbours Authority that this sector requires substantial
deliver the required infrastructure for the Takoradi Port Infrastructure rehabilitation and maintenance.
without assistance from the Development Project.
private sector. In fact, about half of At the same time, consideration must
the transport respondents said they be given to regulatory reforms and
expect public-private partnerships Countries are looking to frameworks to facilitate enhanced
to be used more frequently in Africa more efficient means to cross-border activity. Lengthy
for capital projects. Several countries transport people and highly administrative customs
have been initiating PPPs to raise procedures and clearance policies,
financing. Ghana’s Tamale Airport restrictive import permit and export
project is underway via a PPP and Most noticeable has been the approach licence regulation and inconsistent
Kenya is planning a PPP to develop by oil & gas and mining companies trade agreements all increase the
the Port of Mombasa. Uganda plans to which, in the absence of much of the costs of commodities and make the
use the model to run Kampala’s waste infrastructure needed, are taking continent less competitive. It is only
management system. a ‘build-your-own’ approach, and through reform at both the physical
providing their own funding. In PwC’s infrastructure and regulatory levels that
An example of the impact of financing latest Oil & Gas review, 2014 respondents the region will be able to fully capitalise
on infrastructure projects is the Lamu indicated that their companies would be on its potential.
portion of the LAPSSET project that predominantly relying on their own cash
was started in March 2012, but ran into flows to fund their businesses.
funding difficulties and stalled. In April
2013 a consortium of companies led by
China Communications Construction
Company (CCCC) won a US$484 million
contract to build the first three berths at
the Port of Lamu, but subsequent lack of “Government cannot deliver in mega projects and
funding has stalled the project again. hence requires private capital participation.”
China is playing a significant role in the
– Survey respondent
funding of infrastructure in the transport
sector in sub-Saharan Africa. Its Transport sector
involvement in the region spans project West Africa
funding to direct construction. The key
PwC 37
Oil & gas
Sub-Saharan Africa pipelines
With exciting new discoveries being
made in many parts of the African
continent, the region continues to appeal
to investors looking to participate in the
next frontier of oil & gas activity.
46%
Nigeria is the leading oil exporter in Once extracted, insufficient pipelines
Africa and also has the largest natural result in the below-optimal levels of oil
gas reserves on the continent, while & gas commodities being transported for
Angola is the continent’s second-largest domestic use and export. The security of
oil producer. Neither can currently take pipelines further impacts the functioning
full advantage of their resource reserves of the sector. Disruptions to Nigeria’s oil
due to insufficient infrastructure for and gas supply have been caused by local
of respondents in the sector the extraction, processing and storage militants attacking oil infrastructure
said their capital project of these commodities. Africa is also and damaging the pipelines. Oil theft,
spending in fiscal year 2012 exporting crude oil and re-importing commonly referred to as ‘bunkering’,
refined products as a result of a lack of often causes loss of production and
ranged between
infrastructure, specifically refineries. pollution. In 2013, pipeline vandalism
US$100 million and
The continent is giving away local in Nigeria increased by 58% to 3 505
US$500 million beneficiation and profits, foreign cases and this accounted for a loss of an
exchange as well as the opportunity to estimated US$12 billion in petroleum
skill up people. products and US$12 billion in crude oil
losses.
PwC 39
Benefits from the region’s gas reserves
are realised not only through export
revenue, but through the utilisation of
a portion of these reserves in support
of power generation through gas-fired
power stations. Recent gas discoveries
have fuelled the construction of gas-
fired power plants to support the power
sector, where there is a dire need for
additional electricity generation. The
introduction of more gas-fired power
plants as well as harnessing geothermal
sources will enable the power sector to
diversify power generation away from
being wholly reliant on hydropower in a
region with vast hydrological variances.
Q: What are your top three current internal challenges in relation to capital projects that you are involved in? (Summary of
top three challenges)
0 5 10 15 20 25 30
The severe shortage of trained oil & gas estimates that about
workers in Africa is a serious hindrance US$28 billion worth of investment has
for the industry. Governments are been deferred between 2010 and early
making localisation regulations and 2013, in anticipation of a new regulatory
policies more stringent, requiring framework.
oil & gas companies to contract with
local companies and hire local staff.
Due to lack of local skills, the cost
of employment for these oil & gas “Improved governance and transparency in the
companies may increase as additional
staff are hired as part of the skills
management of the oil and gas sectors reduce the
transfer process. risks facing investors, making African oil and gas
Regulatory and policy issues such as
developments more competitive with production
uncertainty and delays in passing laws from other sources.”
are impacting the growth of the oil &
gas sector. For example, in Nigeria, – ‘Africa Energy Outlook, 2014’
the political and legal challenges
surrounding the Petroleum Industry Bill International Energy Agency
(PIB) have created uncertainty among
investors with respect to the future legal
and fiscal environment. The country
PwC 41
Financing for oil & gas developments in PwC’s Africa Oil & Gas Review 2014,
comes from a number of sources. Oil,
gas and mining companies are taking
the biggest shift has been that companies
are now financing their operations more
“Africa, though
the ‘build-your-own’ approach, and through their own cash flow (from increasingly taking
providing their own funding in the either their local or global operations).
absence of much infrastructure. As cited
on higher financing
capacity on its
Figure 21: Oil & gas: Funding infrastructure projects in the next 12 months
own, still requires
Q: Which of the following procurement models do you believe will be used more
frequently in delivering your capital projects??
substantial external
financial support
to execute critical
5%
infrastructural
projects.”
– Survey respondent
Energy sector
49% West Africa
46%
Traditional procurement
PPPs
Disposal/privatisation
Almost half of our respondents indicated China is also providing essential Sub-Saharan Africa has a wealth
that PPPS would be their preferred financing for infrastructure projects in of natural resources and many of
funding procurement model for the sector. Most evident is activity in these remain untapped due to lack
upcoming projects, while the other half Angola, where infrastructure is being of infrastructure to access, process
deferred back to the traditional funding developed with support from Chinese and transport these resources. With
procurement models. investment as part of an ‘infrastructure- the advancement of the required
for-oil’ trade agreement. infrastructure to support it, the oil & gas
PPP financing of oil & gas projects has sector will see an increasing ability to
been predominately between national oil In the DRC a contract has been signed meet rising consumer demand.
companies (NOCs) and non-traditional between two Chinese state construction
oil & gas players (for example, oil & companies and the state copper
gas trading houses) who are willing to company, which is worth more than the
invest in the downstream industry of DRC’s state budget.
retail, marketing and refining. Over the
last decade, NOCs have taken a greater
stake in the downstream sectors as
many international oil companies have
divested due to low profit margins.
PwC 43
“Eskom is South Africa’s state-owned monopoly
power company. It generates about 95% of all
electricity consumed in South Africa. Not only does
South Africa rely on Eskom for all of its electricity,
but so do a number of its neighbours. The company
states that 45% of all electricity used in Southern
Africa is generated by Eskom. Botswana, Namibia
and Mozambique all depend upon imports from
Eskom to meet electricity demand. Coal is the
predominant source of electricity generation,
accounting for 90% of supply. Other sources are
nuclear and hydropower, but increasingly solar and
wind power are under development.”
– Business Monitor International (BMI)
‘South Africa Infrastructure Report’, Q1 2014
In Nigeria, spending across the In East Africa, BMI estimates that hydropower and other renewable
electricity sector is expected to grow there is US$17 billion worth of power energy supported by a programme
at an average annual rate of more than plants under construction or in the of sector reform. In Uganda, China
10%, underpinned by solid government pipeline with an estimated combined International Water and Electric
revenue growth from oil receipts. capacity of more than 7GW. The (CWE) has commenced construction
Following an ambitious process of Great Rift Valley in Eastern Africa has of a 183MW hydropower plant as part
privatisation and reform, spending on the potential to generate 7,000 MW of of a bilateral agreement signed by
power generation and transmission is geothermal electric power and to date Uganda and China in July 2013.
projected to total over US$180 billion about 400 MW has been exploited
per annum over the next decade. in Kenya while Ethiopia continues to Notwithstanding the challenges in
expand its generation capacity from this sector, the results of our survey
A large number of new power projects the same source. give grounds for optimism. Some
are under construction or in the pipeline 43% of the power sector respondents
across West Africa and these will help A regional priority is to diversify in our survey said they planned to
to ease shortages and meet growing away from reliance on a single increase their capital project spending
demand. source of power, as both Kenya and by more than 25% over the next
Tanzania have suffered from crippling 12 months. Another 47% said their
By way of example, Angola is aiming to electricity shortages owing to their spending would rise marginally, with
increase the country’s power production over-reliance on hydropower. The the remaining 10% expecting flat or
capacity from the current level of major drought in the mid-2000s declining expenditure. More than
1 800MW to 9 000MW by 2025 through caused substantial economic losses, 40% of respondents in the sector said
the construction of 15 new power plants, as high as 4% of GDP in Tanzania, and their capital project spending in fiscal
while in Gabon, the government is both countries were forced to import year 2012 ranged between
focusing on the development of non- expensive fuel to fill the supply gap. US$100 million and US$500 million
hydropower capacity to improve the and 31% said they had been involved
reliability of supply. Kenya is investing in new gas, coal with more than 20 projects in the last
and geothermal capacity as well as 12 months.
Ghana plans to expand its thermal in the exceptional wind resources of
capacity through investment in gas-fired the northern Rift Valley. Tanzania
generation, although it has recently is looking to expand its power
experienced disruptions to supplies system with investment in gas-fired,
through the West Africa Gas Pipeline
and gas production from the country’s
Jubilee field has been delayed.
Q: What is your outlook for your capital project spend/funding for the
next 12 months?
6%
4%
43%
31%
47%
of respondents in the
power sector have been
involved with more than
20 projects in the last
12 months
Significant increase (> 25%)
PwC 45
Figure 23: Power sector: Reasons for delays in completion of projects in the last 12 months
Q: What were the top three reasons for delays in completion of projects in the last 12 months?
(Summary of top three reasons)
Politically related 9%
0 5 10 15 20 25 30 35 40
Power sector respondents said the will need to fill the gap. When asked
greatest challenges to their capital what the top three areas of focus and
projects include political risk or immediate improvement would be
government interference, regulatory in the coming 12 months, our power
policy and processes, and the availability sector respondents indicated that
of funding. Internal capacity to plan project feasibility and project scheduling
and manage projects was also cited as (completion date forecasting and
a challenge. Respondents repeatedly reliability of data in schedules) would
said government simply cannot be their top consideration, followed by
meet the growing demand for power improving performance of capital project
infrastructure and that private investors delivery.
Q: What are your top three current internal challenges in relation to capital projects that you are involved in?
(Summary of top three challenges)
0 10 20 30 40 50 60
PwC 47
44% of our survey respondents in the
power sector took the view that privately
financed IPPs will be the preferred
“...too little electricity
model of funding going forward, is one of the biggest
whereas 43% believed that traditional
models of procurement, where the
challenges standing
current owner continues to own, finance in the way of Africa
and operate the asset, would continue to
prevail. achieving steadily
higher growth rates,
What is clear is that, with the large
number of power infrastructure projects better education
in the pipeline for the region, sufficient for its children and
and sustained financing will be critical
to the successful completion of these teenagers, good
projects. While investor appetite for quality health services
well-structured projects has proven
robust, the time taken to secure project that work, farms and
financing can be excessive; this may
itself become a barrier to the successful
agribusinesses that
delivery of projects and the broader can grow enough
goals for the sector.
affordable nutritious
food for Africans to eat
– just to name some of
the transformational
priorities which can
happen when we turn
the lights on across
Africa.”
– Makhtar Diop
World Bank Vice President
for Africa
‘Helping Africa benefit from
energy infrastructure’
The CBC Africa
Infrastructure Investment
Report 2013
Source: Water and Sanitation Coverage in Africa (Progress on drinking water and sanitation
2014 update, UNICEF & WHO)
PwC 49
There are still significant proportions of the population without access to basic
water supply and dignified sanitation. More than 40% of rural households in Africa
rely on unsafe surface water. Issues of inadequate funding, population growth and
migration within and between countries make service delivery all the more difficult.
Total capital spend/management of respondents in the water sector over the last
12 months
Q: What is your outlook for your capital project spend/funding for the next
12 months?
5%
40%
55%
PwC 51
Levels of unaccounted-for water, a Strengthening economic and service government interference and availability
consequence of poorly maintained regulation in most countries will of funding. Consistently raised across
infrastructure, are extremely high be drivers for investment in the all sectors and regions is organisations’
in most African cities, ranging from upgrade and refurbishment of water lack of internal capacity to plan,
35%–50%. It is estimated that around infrastructure. Policy and regulation procure, manage and implement capital
US$1billion is lost annually by was highlighted by water-sector infrastructure projects.
water utilities in Africa as a result of respondents in our survey as one of the
inefficiencies in water networks. This top challenges experienced in the last
loss impacts on the financial viability of 12 months. Other significant challenges
institutions and on water security. they experienced were political risk,
Figure 26: Water: Top three challenges experienced by respondents in the last 12 months
Q: What are your top three current internal challenges in relation to capital projects that you are involved in?
(Summary of top three challenges)
Corruption/Fraud 10%
0 5 10 15 20 25 30
Weak project management, internal When it came to achieving project project management skills and delays
procurement issues, poor governance completions on budget, 44% of in government approvals and client
and poor planning resulted in delays respondents experienced a cost decision-making were cited as the
in projects being delivered. Funding- variation of less than 10% from primary causes of projects of the water
related issues such as capital rationing original budget and 22% experienced respondents experiencing budget
and delays in releasing of funds cost variances of between 10% and overruns and cost variances.
also contributed to delays in project 50%. Insufficient project preparation,
completions. rushing to construction, inadequate
Q: On average, in the past 12 months, to what extent have your capital projects
experienced cost variances from the original business case?
6%
22%
28%
Improved sanitation and safe drinking Policies, regulation and agreements which were signed off in 2007, targeting
water are not the only factors driving on the effective and sustainable seven countries in West Africa with
investment in water infrastructure. management of these resources are the aim to develop IWRM road maps
Many African countries are looking crucial for optimum use of water and to towards building sustainable water
at expanding irrigated agriculture to ensure tensions do not escalate between infrastructure across the region.
facilitate food security and to boost countries over water usage rights.
agriculture-based industry and exports.
Food production in the region is almost There are already a number of large-
entirely rain-fed, with irrigation playing scale transnational water schemes in
a minor role. There are significant development. One example is the Lesotho
opportunities in East and West Africa Highlands Water Project Phase II, where
to expand irrigated farming. Kenya, South Africa and Lesotho have signed a
for example, is looking to increase bilateral agreement for the development
its irrigated farming by one million of the scheme. The US$1.5 billion project
hectares. Currently in sub-Saharan will augment water supply to the Vaal
Africa the area under irrigation makes catchment, which serves the economic
up just 4% of the total cultivated area, heartland of Gauteng in South Africa
compared to 37% in Asia and 14% in by transferring a further 465 million m3
Latin America. of water per annum from the Senqua
River to the Vaal River to meet long-term
Transboundary agreements are pivotal water demand. Another example is the
to effective water management in sub- development and implementation of
Saharan Africa as many of the water integrated water resources management
basins cross multiple country borders. (IWRM) master plans in West Africa,
PwC 53
Water is a central element in the water,
energy and food nexus. As Africa’s
electrification and oil & gas programmes
“Ghana has rehabilitated its infrastructure,
are rolled out, there will be a greater expanding and building new elements to meet
need to advance water infrastructure
to support these developments. It is
current and growing demand with funding from
estimated that only 7% of Africa’s government and development partners. Demand
hydropower potential is being exploited.
includes urban water supply, rural and small
towns’ water supply, irrigation and hydropower
infrastructure. These investments are enhancing
access to urban, rural and small town water supply
and improving irrigation facilities for more than
2 400 peasant farmers. Hydropower production
has been made more efficient.
PwC 55
Regional overviews
East Africa
Sudan
uti
Djibo
South Ethiopia
Sudan
ia
al
m
So
da
Kenya
n
ga
U
Rwanda
Burundi Seychelles
Tanzania
Reunion
“The most prominent risk faced in the development
of infrastructure in East Africa is completion on
time and within budget. Beyond financial close,
and the challenges of the funding gaps, the delivery
Many countries in East Africa are seeing
of projects requires new and robust cost control slow growth in their middle class
and project assurance management methods. because the majority of these countries’
households are low-income houses;
Given the complexity and size of these investments, however, with increasing urbanisation
of the region, the demand for goods and
independent project assurance and control will services is anticipated to grow, fuelling
become a critical success factor for completion.” the region’s economy.
– Kuria Muchiru
A consistent theme
CP&I Consulting Leader, PwC Kenya
across regions is
the crucial need for
interconnectivity to
boost trade, economic
“Financing infrastructure in East Africa will remain growth and social
a challenge that can only be met by the inclusion upliftment
of the private sector through various forms of PPP
structures. It will require the adaptation of the Economic communities and
intergovernmental bodies are essential
traditional PPP model to meet local realities and to make this happen.
the inclusion of local financing institutions in this
With all the best intentions to integrate
process. There is a significant amount of pent-up through regional economic communities
demand for investment capital into East African such as COMESA and EAC, East Africa
still has several challenges to overcome
infrastructure in the international markets. The in order to achieve this. These include
key for governments is to provide the vehicles for poor regional infrastructure, water
scarcity, difficulty in managing shared
investment so that this demand can be unlocked water resources, emerging regulations
while providing a reasonable return on capital and institutions, the diversity of
economies across countries and most
investments.” critically, various countries’ differing
attitudes towards regional integration.
– Tibor Almassy
CP&I Deals Leader, PwC Kenya East Africa has abundant natural
resources, minerals (gold, diamonds,
gemstones and, more recently,
significant oil and gas finds), water
basins, arable land and a host of natural
As with many references to large sub- Saharan Africa behind Nigeria, attractions. Many of these are relatively
geographical areas, it is tempting to South Africa, Angola and Sudan. untapped. In Tanzania, for example,
make the mistake of viewing East Progress has been made in the region to 20% of land is cultivatable, but only a
Africa as a single homogeneous region. achieve political stability and openness, third of arable land in the country is
On the contrary, the countries in the which are both key requirements for being cultivated.
region have diverse histories, cultures, financial investment and successful
ethnicities, politics, religions and economic development. The recent discoveries of oil in Kenya
languages. The region has a fast-growing and gas in Tanzania are further
and rapidly urbanising population of The spread of per-capita GDP across the opportunities to fuel resource-based
approximately 264 million. countries highlights the vast diversity economic growth. However, one of the
of economies in the region. Sudan has biggest constraints for East Africa is
Economic growth in East Africa is the highest per-capita GDP (US$1 753), the lack of reliable, efficient and robust
predicted to remain relatively strong, with Burundi (US$267) the lowest. infrastructure to support these activities.
above 6–7% to 2016, and perhaps The World Bank database cites Kenya’s
even beyond. Ethiopia is considered the current per capita GDP as $994. This Infrastructure across East Africa varies
fastest-growing economy in Africa and compares to the global per-capita GDP by country, with some having better
most recently Kenya was noted as the average of US$10 514 . quality of infrastructure in place.
fifth-largest economy in
PwC 57
Tanzania’s road infrastructure is Ageing and deficient physical risk due to instability of supply, it is set
sufficient for trade requirements, but infrastructure, difficulties accessing to provide the bulk source of electricity
the rail network requires considerable funding, an immature regulatory generation, along with geothermal, gas,
investment after a failed concession environment and protracted wind and coal.
neglected the asset over many years. procurement processes all place
In Uganda, only 25% of the national constraints on the energy sector. There is considerable infrastructure
roads are paved. Kenya is a regional development across other sectors
leader in air transportation with Kenya Governments in the region acknowledge too, at all stages of the infrastructure
Airways ranked among Africa’s top that there is a power crisis, and a development life cycle, from pre-
three international carriers, with an number of power generation projects feasibility and financing to construction
extensive network across the continent are in the pipeline for consideration and and hand-over.
and a safety record up to international implementation.
standards. The development in sub-Saharan Africa
Kenya is planning to add an additional does not come without challenges and
By far the biggest infrastructure 5 000MW of power over the next 10 difficulties. When asked to highlight
constraint in the region is energy years and considerable investment their main challenges in delivering
production. East Africa currently has has been set aside to rehabilitate capital projects, our survey respondents
the lowest access to power of all African and increase both generation and with operations in East Africa said
sub-regions, negatively impacting transmission capacity. Even though that lack of funding was one of the top
households, businesses and industries. hydropower presents higher levels of challenges, a sentiment already well
shared across the region.
Q: What are your top three current internal challenges in relation to the capital projects you are involved in?
Procurement/performance 27%
Other 22%
0 10 20 30 40 50 60 70 80
PwC 59
Figure 29: East Africa: Finance procurement methods
Q: Which of the following procurement models do you believe will be used more
frequently in delivering your capital projects?
5%
49%
46%
Traditional procurement
PPPs
Disposal/privatisation
The increased use of PPPs was confirmed East Africa is a region of diversity and
“Reduced capacity by 59% of survey respondents with
operations in East Africa who said they
complexity and great opportunity.
The development of its infrastructure
of government to believed a mix of PPPs and governmental through various public and private
funding is critical to support the initiatives will improve lives by providing
support all projects development of infrastructure projects access to economic opportunities,
means greater need going forward. Forty-six percent believe electricity, improved sanitation and
that PPPs are the procurement model to potable water, reliable transportation
for external funding.” be used in delivering funding for these and housing. There is much hard work to
projects, while another 46% were still be done and many gains to be made.
– Survey respondent in favour of traditional procurement
Mining sector methods. Overall, there is an increased
East Africa acknowledgement that alternate models
are required.
Southern Africa
Comoros
Malawi
Angola
Zambia
we e
qu
b
ba
bi
Zim
am
r
ca
oz
as
Namibia
M
ag
Botswana
ad
Mauritius
M
Swaziland
South Lesotho
Africa
“The pool of available capital is limited and while every dollar invested in
infrastructure can potentially have many-fold returns to governments, businesses
and citizens, planned shareholder value and stakeholder benefits are rapidly
eroded when delays and budgeted overruns occur due to poorly managed
project implementations. Infrastructure projects require an intense focus on
transparency and accountability to ensure that they are planned, funded and
completed in a timely, cost-effective manner and are efficiently run. There is
therefore a need to plan capital projects carefully to ensure that they return
maximum value and benefits, while perfectly aligning with strategy.”
– Mark Ally
CP&I Consulting Leader, PwC South Africa
PwC 61
Vast regional differences exist within services, telecommunications, regulation
Southern Africa in the maturity and and greater industrial and sector While the economies of the
structure of its economies, the extent capacity. The South African Government Southern African countries
and condition of its infrastructure and and businesses will continue to play a
the diversity of cultures and languages, major role in the development of the continue to improve,
climate and typography. This diversity region. regional integration,
provides significant opportunities and interconnectivity and
challenges for the region’s economic Robust and effective infrastructure cross-border cooperation
growth, development and integration. is vital to this regional integration
remain key challenges to
and trade growth. At a regional level,
With the exception of South Africa, infrastructure within Southern Africa enhancing trade, economic
countries in the region have achieved is relatively developed compared to development and poverty
positive growth over the past three years many other African countries, but there reduction
and this trend is predicted to continue. are variations in standards and quality
Mozambique, Zambia and Angola between countries.
registered the fastest growth rates in the Respondents to our survey that have
last year, exceeding SADC’s 7% growth Transport infrastructure in South Africa operations in Southern Africa said
rate target, while South Africa will have is the most developed in Africa and was that their most pressing challenges in
the slowest growth at around 1.5% in ranked 23rd of 155 countries in the 2012 delivering projects are the availability
2014. Logistic Performance Index. Elsewhere, of skills and a lack of internal capacity
however, infrastructure deficits are among state organisations to plan,
The IMF estimates the population of the vast. Angola has just 4km of roads per procure, manage and implement capital
region to be 294 million in 2014 and 100km2 of land area, while access to infrastructure projects.
the average per capita GDP ranges from electricity in Zambia is only 20%, less
US$9 210 per person in Mauritius to than half the African average, with much The third most highlighted challenge
US$226 per person in Malawi, reflecting of that power going to the mining sector, is the impact of political risk and
the vast disparities between the different limiting domestic consumption. The Port interference. With a number of
economies. of Luanda in Angola is known for lengthy concessions having been cancelled
delays and capacity constraints with a by governments in the region, an
With the rising population size general cargo vessel pre-berth waiting improvement in transparency, regulation
and economic growth has come an time of 144 hours (sub-Saharan African and procurement is needed to help
increase in the number of middle- average is about 18 hours). restore the confidence of foreign
class households. An estimated investors in partnership models.
15 million middle-class households in 11 As with East and West Africa, the two
of sub-Saharan Africa’s top economies most critical infrastructure deficiencies
(Angola, Ethiopia, Ghana, Kenya, across the region are:
Mozambique, Nigeria, South Sudan,
Sudan, Tanzania, Uganda and Zambia) • Insufficient power to meet increased
is the key driver for the increased demands at an industrial, business
demand for goods and services which and domestic level; and
the region has been experiencing.
• Inadequate, costly and unpredictable
The region’s wealth of natural resources, transport and logistics, which impacts
increasing consumer demand, the competitiveness of the region.
demographic shifts, urbanisation and
both regional and international trade are There is a vast amount of infrastructure
the main drivers of development. development activity being undertaken
across the region with commitment from
Despite its slow growth, South Africa funders, agencies and governments to
remains the economic powerhouse of close the infrastructure deficit.
the region with the most sophisticated
infrastructure, state-owned entities
(power and transport), financial
Q: What are your top three current internal challenges in relation to capital projects that you are involved in?
Other 17%
0 10 20 30 40 50
PwC 63
Figure 31: Southern Africa: Finance procurement methods
Funding
PwC 65
West Africa
Gambia
so
i
rk
Guinea Bissau
Benin
Bu
Guinea Nigeria
Ghana
Togo
PwC 67
Respondents recognise numerous
challenges in the execution of capital Energy is the focal area
projects in the region. Among these, for West Africa as the
availability of funding, political
risk and government interference
region remains in the
were seen as the main challenges to grip of a prolonged
delivering projects. Consistent with the power crisis
observations of survey respondents with
operations in East Africa and Southern
Africa, the regulatory and policy
environment was foremost on the list of
challenges frequently encountered.
Q: What are your top three current internal challenges in relation to capital projects that you are involved in?
Other 19%
0 10 20 30 40 50 60
As with most of sub-Saharan Africa, The challenges facing the power sector
energy is a focal area for investments are very similar in countries across the
in West Africa, as the region remains region with huge unmet demand being
in the grip of a prolonged power crisis. hindered by power shortages, ageing
Countries in the region have endured transmission facilities, load shedding
limited access to power for several and shortages of feedstock.
decades, with persistent shortages in
electricity supply despite the abundance
of energy resources.
PwC 69
Expansion is required to accommodate potable water and water supply for Healthcare demand in West Africa is
the projected increase in freight traffic, sanitation services, inefficiency and increasing given population growth and
especially transit traffic from landlocked wastage in water use, as well as threats the emergence of a middle class that is
countries, which is expected to increase to environmental sustainability. willing to pay for health services. While
by 10–14 times over the next 30 years. the potential for future growth in the
In order to tackle the region’s water sector is considerable, there are still
Nigeria stands as the largest oil producer resource issues, integrated water huge challenges related to inadequate
in West Africa and Africa. The US resources management (IWRM) master government funding, health insurance
Energy Information Administration plans targeting seven West African schemes and frequent strike action
reports that West Africa has 37 billion countries were developed and signed among public health workers.
barrels in proven oil & gas reserves, with off in 2007. The IWRM project aims to
a production capacity of 2.5 million provide assistance with the development Improved healthcare facilities
barrels a day. The industry is dominated of an IWRM road map towards building are increasingly being funded by
by the Nigerian market, which currently sustainable water infrastructure across international aid agencies, foreign
accounts for 95% of production capacity. the region. and local investors, and banks.
Côte d’Ivoire and Ghana produce the International healthcare equipment
remaining capacity. Apart from basic infrastructure, West companies continue to seek partnership
Africa is also seeing a heightened arrangements to support the
The Nigerian oil & gas industry’s major focus on investment and activity in the development of healthcare facilities
challenge is constant vandalism, which agricultural and healthcare sectors. through different financing mechanisms
leads to annual losses of petroleum There has been a renewed focus on such as leases and pay-per-use models
products worth millions of dollars. agriculture as is evident in the policy for expensive laboratory or hospital
Without sufficient operational and development agenda of national equipment.
infrastructure the region will not be able governments and international
to fully capitalise on the monetary gains development agencies who have
offered by its large reserve of natural committed to expanding the agriculture
resources. sector while also aiming to provide food
security and improved nutrition for the
Although significant progress has been rural poor.
made towards increasing the number
of people with access to safe water and Agriculture currently contributes around
sanitation there is still much to be done. 35% of West Africa’s GDP and accounts
for 65% of employment. The region has
large areas of arable land, incorporating
aquaculture and fruits and vegetables in
In rural regions of arid addition to grains and livestock.
West African countries
like Mali, Niger and Significant growth in cocoa production
is expected in Ghana with the
Mauritania, less than government committed to supplying free
10% of the population inputs and improving infrastructure.
have access to toilets Some of the major challenges in the
agriculture sector are inadequate credit
facilities, insufficient input supplies such
as seeds and fertilisers, limited access
Much of the West African region
to equipment and new technologies,
has abundant rainfall and relatively
increased competition with smuggled
low levels of withdrawals of water.
products, poor transport infrastructure
Agriculture remains the largest user of
and inadequate storage facilities.
water and the region’s water resources
present vast potential for energy
production through hydropower. The continued threat of disease and bad
weather pose significant risks to cocoa
and coffee production and smuggling
Supply-side challenges relate to the
of cocoa from Ghana into Côte d’Ivoire
multiplicity of transboundary water
to take advantage of higher prices
basins, high spatial and temporal rainfall
threatens to destabilise the Ghanaian
variability, inadequate institutional and
cocoa industry.
financing arrangements, inadequate
data and depletion of water resources
through human actions. Demand-side
challenges include lack of access to
Q: Which of the following procurement models do you believe will be used more
frequently in delivering your capital projects?
Funding
PPPs
Chinese investment in the region’s
transport infrastructure has grown Disposal/privatisation
significantly. Chinese firms have become
dominant players in the road sector
with companies such as China Civil Base: 27 respondents with operations in West Africa
Engineering Construction Corporation Source: PwC analysis
(CCECC) establishing a significant
presence in the market. CCECC has been
awarded the US$1.49 billion contract
to build the Lagos-Ibadan railway and
in Ghana, China has pledged to support
the US$6 billion Nsawam-Kumasi-Paga
railway.
“Governments cannot deliver in mega
PPPs are increasingly being considered projects and hence require private capital
as a viable model for financing airport
infrastructure. In Sierra Leone, the participation.”
Government recently announced
that the China Railway International – Survey respondent
Company will build a new Operations across multiple sectors
US$200 million international airport
West Africa
using a PPP with financing from China’s
Export-Import Bank.
West Africa remains the fastest-growing services both locally and for export will
region on the continent and with an continue to rise. The need for effective
ever-increasing population and middle- and robust infrastructure to underpin
income sector, as well as renewed the economy to support meeting and
interest from foreign businesses in capitalising on these demands is now
sectors such as minerals, resources more critical than ever to the success of
and mining, the demand for goods and the region.
PwC 71
Conclusion
Infrastructure plays a key role in • What is the optimal role and Through this survey and our interactions
economic growth and poverty procurement strategy for the private with key stakeholders in the sector,
reduction. Conversely, the lack of sector in state-led infrastructure we have confirmed the tremendous
infrastructure affects productivity and programmes? possibilities that lie ahead. Expectations,
raises production and transaction costs, optimism and willingness to embrace
which hinders growth by reducing • Where will the money come from? new ideas and partners are at a high
the competitiveness of businesses and point. We share this positive outlook
the ability of governments to pursue • How can the demand side be and remain committed to unlocking
economic and social development managed? these opportunities and the wealth of
policies. In Africa one of the most Africa for its people, through sound and
frequently cited barriers to entry • How can international interest be sustainable infrastructure delivery and
and economic growth is physical attracted? operation.
infrastructure.
• How can local content be increased?
Those countries that have been
most successful in developing and • How can project governance,
maintaining infrastructure have oversight and control be improved to
established programmes of prioritised ensure projects are delivered on time
investment opportunities with a number and within quality and budget?
of features, including clear political
support, a proper legal and regulatory PwC is a key player in capital projects
structure, a procurement framework that and infrastructure across the globe.
can be understood by both procurers and Our PwC Africa Capital Projects &
bidders, and credible project timetables. Infrastructure Advisory unit is part of a
These country programmes are more team of more than 9 000 in 34 African
than just marketing – they eliminate key countries who work across all key sectors
frictions such as long project lead times and countries on the continent. We
and unclear political risk, which directly have learned the lessons of mature and
impact the viability of the business case. other developing markets, which can be
leveraged in Africa to leapfrog linear and
Some of the leading questions which conventional infrastructure development
owners, regulators, policymakers and paths. Through our deep industry and
funders need to be asking include: technical insights we are beginning
to understand what works and what
• How can current infrastructure doesn’t in developing infrastructure in
output, reliability, costs and revenue Africa. Being independent of funders,
be optimised? engineers and contractors, lawyers,
suppliers and operators, we build trust
• How should programmes and projects and work with our clients to solve
be prioritised and sequenced to create complex infrastructure challenges free
the greatest impact on economic from conflicts of interest.
growth, social upliftment and
sustainability?
In addition to the information drawn from discussions African Development Bank, “Africa Regional Paper, Bridging
with clients and feedback provided by survey respondents, Divides in Africa’s Water Security- an Agenda to Implement
we utilised a range of additional sources in compiling this Existing Political Commitments”, 2008
document.
African Development Bank, “The African Development Bank at
“EU, DBSA launch R1.5bn infrastructure fund” posted March the Center of Africa’s transformation”, 2013
17th 2014 accessed at http://fundingconnection.co.za/
blog/2014/03/17/eu-dbsa-launch-r1-5bn-infrastructure-fund/ African Water Facility, “Reference Towards Water for All 2025,
Strategic Plan 2012-2016”, 2011
“Grand Ethiopian Renaissance Dam Project, Benishangul-
Gumuz, Ethiopia”, Water-Technology.net, accessed at http:// Any Freitas, “Water as a stress factor in sub-Saharan Africa”,
www.water-technology.net/projects/grand-ethiopian- European Union Institute for Security Studies, 2013
renaissance-dam-africa/
Bai-Mass Taal, Executive Secretary of the African Ministers’
“Nigeria Country Analysis”, US Energy Information Council on Water, “Water infrastructure for hydropower and
Administration, 30 December 2013, accessed at http://www. agriculture”, The_CBC_Africa_Infrastructure_Investment_
eia.gov/countries/cab.cfm?fips=ni Report_2013.pdf, 2013
“Nigerian Economy Overtakes South Africa’s on Rebased Briceño-Garmendia, Cecilia M., Shkaratan, Maria ,
GDP, April 2014”, Bloomberg, 2014 accessed at http://www. “AICD, Africa infrastructure Country Diagnostic, Kenya’s
bloomberg.com/news/2014-04-06/nigerian-economy- infrastructure a continental perspective” World Bank, 2010
overtakes-south-africa-s-on-rebased-gdp.html
Business Day, “Eskom’s Medupi plant delayed for at least six
“Rwanda moves to reform energy sector, reduce on blackouts” months”, 8 July, 2013, accessed at http://www.bdlive.co.za/
East Africa, 2014 accessed at http://www.theeastafrican. business/energy/2013/07/08/eskoms-medupi-plant-delayed-
co.ke/business/Rwanda-moves-to-reform-energy-sector- for-at-least-six-months
reduce-blackouts/-/2560/2160076/-/femr2v/-/index.html
Business Monitor International, “Ghana Infrastructure Report
“World Population fact sheet” United Nations, (2012) accessed Includes 10 Year Forecast to 2022, Q1 2014”, 2013
at http://www.un.org/en/development/desa/population/
publications/pdf/trends/WPP2012_Wallchart.pdf Business Monitor International, “Kenya Infrastructure Report
Includes 10 Year Forecast to 2023, Q3 2014”, 2014
African Development Bank, “The Middle of the Pyramid:
Dynamics of the Middle Class in Africa”, 2011 Business Monitor International, “Mozambique Infrastructure
Report Includes 10 Year Forecast to 2023, Q2 2014”, 2014
African Development Bank, “Eastern Africa Regional
Integration Strategy Paper 2011-2015, Regional Departments Business Monitor International, “Nigeria Infrastructure Report
East I & East II (Orea/Oreb)”, 2011 Includes 10 Year Forecast to 2022, Q1 2014”, 2013
African Development Bank Group, “African Economic Outlook Business Monitor International, “South Africa Infrastructure
2014”, 2014 Report Includes 10 Year Forecast to 2022, Q1 2014”, 2013
African Development Bank, “Southern Africa quarterly Business Monitor International, “Tanzania Infrastructure
overview and analysis 1st quarter 2014”, 2014 Report Includes 10 Year Forecast to 2022, Q1 2014”, 2013
PwC 73
Business Monitor International, “Zambia Infrastructure Report Raballand, Gaël, Salim Refas, Beuran, Monica and Isik, Gözde,
Includes 10 Year Forecast to 2022, Q3 2014”, 2014 “Why Does Cargo Spend Weeks in Sub-Saharan African Ports?
Lessons from six countries”, World Bank, 2012
Business Monitor International, “Zimbabwe Infrastructure
Report Includes 10 Year Forecast to 2022, Q4 2014”, 2014 Ranganathan, Rupa and Foster, Vivien , “East Africa’s
Infrastructure: A Regional Perspective”, The World Bank, 2011
Commonwealth Business Council, “Africa Infrastructure
Investment Report 2013”, 2013 Remmy Makumbe, “Infrastructure priorities in Southern
Africa: the SADC Regional Infrastructure Development Master
Infrastructure Consortium for Africa, “Infrastructure Funding Plan 2013’, The Commonwealth Business Council Africa
Trends in Africa”, ICA Annual Report, 2012 Infrastructure Investment Report, 2013
International Law Office, accessed at http://www. South Africa Info, “Sub-Saharan Africa’s middle class set to
internationallawoffice.com/Newsletters/detail. boom”, 2014 accessed at http://www.southafrica.info/africa/
aspx?g=141e9c7a-2a66-4ecc-8833-3fc26967a3be africa-middleclass-210814.htm
Kadigi, R; Tesfay, G; Bizoza, A; Zinabou, A; “UK GDN Working Standard Bank, “Rise of the middle class in sub-Saharan
Paper Series: Irrigation and Water Use Efficiency in Sub- Africa”, 2014
Saharan Africa” Working Paper No. 63, Global Development
Network, 2013 Study on Programme for Infrastructure Development in Africa
(PIDA), “Africa Infrastructure Outlook 2040”, 2011
News 24, “Lesotho Highlands Water Project phase 2
launched”. 2014-03-27 accessed at http://www.news24. United Nations, “MDG Report, 2013- Assessing progress in
com/Green/News/Lesotho-Highlands-Water-Project-phase-2- Africa towards achieving the Millennium Development Goals”,
launched-20140327 2013.
Nigerian National Petroleum Corporation, “2013 Annual United Nations, “Millennium development goals report 2014”,
Statistical bulletin”, 2013 2014
Ondiege, Peter, Mbabazi Moyo, Jennifer and Verdier- World Academy of Science, Engineering and Technology
Chouchane, Audrey, “Developing Africa’s Infrastructure for accessed at https://www.waset.org/
Enhanced Competitiveness”, The Africa Competitiveness
Report, 2013 World Bank and Africa Development Bank, “Africa
Infrastructure Knowledge Program, Handbook on
Population Action International, “Population, Climate Change, Infrastructure Statistics”, 2011
and Sustainable Development in Africa, 2012”, 2012
World Bank, “AICD, Africa infrastructure Country Diagnostic,
Population Pyramids of the World from 1950 to 2100, accessed Tanzania’s infrastructure a continental perspective”, 2010
at http://populationpyramid.net/southern-africa/2050/
World Bank, “Kenya a bigger better economy”, 2014
Popoola, O; Abiola, S; Adeniji, W; “Traffic Congestion
on Highways in Nigeria Causes, Effects and Remedies”, World Bank Data Bank accessed at http://data.worldbank.
International Journal of Civil, Architectural, Structural and org/indicator/NY.GDP.PCAP.PP.CD/countries/1W-
Construction Engineering Vol:7 No:11, (2013) NG?display=graph
Pratka, Ruby; “Water and Sanitation in Africa”, World Press, World Economic Forum, “Accelerating Infrastructure Delivery:
2012 New Evidence from International Financial Institutions”, 2014.
PwC, “On the brink of a boom: Africa oil & gas review”, 2014
Mohale Masithela
CP&I Deals Leader
+27(0)11 797 5669
mohale.masithela@za.pwc.com
Tanzania
Barbara Harris
CP&I Country Leader
+255 (0) 22 219 2710
barbara.harris@tz.pwc.com
PwC 75
www.pwc.co.za/infrastructure
The information contained in this publication is provided for general information purposes only,
and does not constitute the provision of legal or professional advice in any way. Before making
any decision or taking any action, a professional adviser should be consulted. No responsibility
for loss to any person acting or refraining from action as a result of any material in this
publication can be accepted by the author, copyright owner or publisher.
©2014 PricewaterhouseCoopers (“PwC”), the South African firm. All rights reserved. In this
document, “PwC” refers to PricewaterhouseCoopers in South Africa, which is a member firm of
PricewaterhouseCoopers International Limited (PwCIL), each member firm of which is a separate
legal entity and does not act as an agent of PwCIL. (14-16121)