Date : Billing No.

Project : ISLAND COVE JO No. :

Location : Island Cove-Kawit Cavite PO No.:

Subject : PROGRESS BILLING Total Amount (Php) PHP


Date Covered : DP total Amount (PHP) :
Service Provider : MAC 7 Retention (%): 10%

BILLING HISTORY
Billing %
Gross Amount DP Recoupment Retention Net Amount Due
No. Accomplishment
1 - - - -
2 - - - -
2 - - - -
4 - - - -
5 - - - -
6 - - - -
7 - - - -
8 - - - -
9 - - - -
10 - - - -
11 - - - -
12 - - - -
13 - - - -
14 - - - -
15 - - - -
TOTAL 0.00% - - - -
Remaining Contract Amount for billing = 1,128,160.00
*Note:
Remaining Contract Amount = (Contract) - (DP) - (Net Billings)

JOBSITE Service Provider Project Control Department


Monitored by: Noted by: Conforme: Checked by: Approved by:

Office Engineer Project-in-Charge Service Provider PCD Engineer Director for Engineering

FM-PCD-004, Rev.02
Project : CLC Warehouse
Location : Lingunan Valenzuela City
Sub-Con Awarded : Deep Well Drilling and Installation
Awarded to/ Sub-Contractor : Winnie Tagala Contractor : Mevbuilt Inc
Contract Code : Project code:
Date of Mobilization :
Date : August 12, 2019
Billing Number : 6.00

CONTRACT
DP Recoupment
Work Completed Relative weight (40%) Retention (10%)

Item # Description of Work QTY Unit price Total Amount Weight Net Amount
Percentage Previous Present Total Previous Present Total
Present Present
Qty Amount Qty Amount Qty Amount % % %
Deep Well Drilling and
1 Installation
Drilling 300.00 f 600.00 PHP 180,000.00 85.71% 280.00 PHP 168,000.00 20.00 PHP 12,000.00 300.00 PHP 180,000.00 80.00% 5.71% 85.71% PHP 4,800.00 PHP 1,200.00 PHP 6,000.00
Installation of Motors and Pumps 1.00 lot 30,000.00 PHP 30,000.00 14.29% 0.00 PHP 0.00 0.00 PHP 0.00 0.00 PHP 0.00 0.00% 0.00% 0.00% PHP 0.00 PHP 0.00 PHP 0.00
PHP 210,000.00 100.00% PHP 168,000.00 PHP 12,000.00 PHP 180,000.00 80.00% 5.71% 85.71% PHP 4,800.00 PHP 1,200.00 PHP 6,000.00

JOBSITE Subcontractor Project Control Department Finance


Monitored by: Noted by: Conforme: Inspected by: Checked by: Approved by: Release by:

Project-in-Charge Project Coordinator Subcontractor AJObejero MGAbbu MKKung Finance Head