Professional Documents
Culture Documents
BBU - Civil Final
BBU - Civil Final
6 MW PALATANA POWER PROJECT
Page 1 of 2
BILLING BREAKUP OF CIVIL WORKS FOR 400KV/132KV SUBSTATION (2 UNITS) ‐ FOR 726.6 MW PALATANA POWER PROJECT
10.0 Earthing Mat
10.1 Excavation KMS 2.00% 6,13,507 1,10,431 7,23,938
10.2 Mat Laying and Welding KMS 2.00% 6,13,507 1,10,431 7,23,938
10.3 Back Filling KMS 1.00% 3,06,754 55,216 3,61,970
Sub‐total: Earthing Mat KMS 5.00% 15,33,768 2,76,078 18,09,846
11.0 After completion of Dismantling of existing Lot. 1 1.00% 3,06,754 55,216 3,61,970
fencing
12.0 Misc Balance Work including all balance Lot. 1 2.00% 6,13,507 1,10,431 7,23,938
Levelling, Dressing work and full Drainage
System.
Note
1 The Approved billing break‐up is notional only. It may be revised during the contract period on completion of design document release / civil work.
2 The quantities mentioned above are indicative only, S&W shall carryout the work as per the required quantity of items as per Contract and approved engineering drawings and
documents.
3 The Billing Breakup is for on account payment (progressive payment) purpose only
4 The description of various item of work is only indicative and all the item of work shall be executed by S&W as per approved engineering drawings & documents.
5 Any other item not mentioned in the Billing Breakup but required for completion of scope of work shall be supplied / executed by S&W without any cost implication to OTPC
6 GST @ 18% shall be reimbursed subject to limit of Rs. 55,21,563/‐ as per the Contract.
Page 2 of 2