DETAIL PROJECT REPORT FOR CONSTRUCTION OF


Road from MONGRE TO SH via KHARDANG
IN THE DISTRICT OF GOALPARA UNDER KRISHNAI DEVELOPMENT BLOCK

PACKAGE NO. : AS-07-


ROAD CODE : L29

VOLUME 1 : REPORT & ESTIMATE

TOTAL LENGTH OF THE ROAD 0.419 KM

TOTAL COST OF PAVEMENT (₹) 32.06 Lakhs

TOTAL COST OF THE CD WORKS (₹) 0.00 Lakhs

TOTAL COST OF PROTECTION WORK (₹) 0.00 Lakhs

TOTAL COST FOR PREPARATION OF DPR (₹) 0.10 Lakhs

TOTAL COST OF THE PROJECT (EXCLUDING MAINTENANCE) (₹) 32.16 Lakhs

TOTAL COST OF THE PROJECT (INCLUDING MAINTENANCE) (₹) 34.25 Lakhs

COST OF ROAD CONSTRUCTION PER/Km (EXCLUDING MAINTENANCE) (₹) 76.76 Lakhs

FIVE YEAR ROUTINE MAINTENANCE COST (₹) 2.09 Lakhs

PUBLIC WORKS DEPARTMENT


Goalpara Rural Road Division
Goalpara
INDEX

SL NO. PARTICULARS
EXECUTIVE SUMMARY
1 ABSTRACT OF COST
2 PROJECT REPORT
3 MAPS
FORMAT
4 F-1 SUMMARY SHEET
5 F-2A PAVEMENTS LAYER
6 F-2B CROSS DRAINAGE STRUCTURES
7 F-4 TYPICAL CROSS SECTION
8 F-6 COST ESTIMATE FOR ROAD CONSTRUCTION
9 F-7 CROSS DRAINAGE WORK
10 F-8 RATE ANALYSIS
11 F-9A CERTIFICATE OF GROUND VERIFICATION
STATEMENT
12 QUANTITY STATEMENT
13 CULVERT STATEMENT
ANALYSIS
14 MAINTENCE COST OF ROAD
FIELD DATA
15 DESIGN OF FLEXIBLE PAVEMENT
16 TRAFFICVOLUME COUNT SURVEY
17 SSI DATA
18 QUARRY MAP
19 BAR CHART (TIME SCHEDULE)
PROFORMA
20 PROFORMA-B PACKAGE SUMMARY
21 PROFORMA-C CHECK LIST FOR P.I.U. & S.T.A.
PRADHAN MANTRI GRAM SADAK YOJANA
PACKAGE SUMMARY
Package No. : AS-07- MRL : 3 P
District: Goalpara Road Code- L29
State: ASSAM
CD Works & bridges upto Bridges above 15m upto
15m 100m Total cost
Cost of
Type of Proposed Pavement State Share for all works Maintenance
Sl. Protection Others
Name of Block Road Name proposal length Cost (Utility (Excluding Cost
No. Work (DPR Cost)
(N/U)* (km) (Rs. In Lakh) Numbers Cost Numbers of Cost Shifting) State Share) (Rs.in lakhs)
(Rs. In Lakh)
of CD (Rs. in lakhs) Bridges (Rs. in lakhs) (Rs.in lakhs)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Krishnai Chariali
1 Krishnai Pakhriguri to NH37 U 0.419 32.06 0 0.00 0 0.00 0.00 0.10 0.20 32.16 2.09
via Borjuk Manikpur

Total estimated cost of the package 0.419 32.06 0 0.00 0 0.00 0.00 0.10 0.20 32.16 2.09
* N: New Connectivity, U: Upgradation

Prepared by Signature Technical scrutiny done by Signature


Name Name
Designation Designation

Checked by Signature
Name
Designation

Co-ordinator STA Signature


Name
Scrutinized by Signature Designation
Name
PROFORMA-B Page 3 of 311
CD Works & bridges upto Bridges above 15m upto
15m 100m Total cost
Cost of
Type of Proposed Pavement State Share for all works Maintenance
Sl. Protection Others
Name of Block Road Name proposal length Cost (Utility (Excluding Cost
No. Work (DPR Cost)
(N/U)* (km) (Rs. In Lakh) Numbers Cost Numbers of Cost Shifting) State Share) (Rs.in lakhs)
(Rs. In Lakh)
of CD (Rs. in lakhs) Bridges (Rs. in lakhs) (Rs.in lakhs)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Designation

PROFORMA-B Page 4 of 311


RI GRAM SADAK YOJANA
AGE SUMMARY
PROFORMA: B
L29

Average cost per Km


(Rs. In Lakh)

Construction
(including Maint.
DPR etc.)

16 17

76.76 4.99

76.76 4.99

PROFORMA-B Page 5 of 311


Page 6 of 311

MAIN PART PROFORMA-C


PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
CHECK LIST FOR P.I.U. & S.T.A.
(FOR INDIVIDUAL ROAD WORKS)
To be filled by PIU

1 Location: State : ASSAM District : Goalpara Block : Krishnai

Package Road
2 AS-07- L29 MRL 3
No. Code:
Krishnai Chariali
3 Name of the Road : From : To : NH37
Pakhriguri
In Open
4 Length (Km.) Total 0.419 Km. In Built up area 0.27 0.15 KM.
Area

5 Estimated Cost Rs. 32.16 Lakhs Average Cost(In lakh) : 76.76

Item Total Cost in Rs. Cost per Km in Lakh

Flexible Pavement 3205953.00 76.51

CD Works 0.00 0.00

Cost of Protection Work 0.00 0.00

Others 10475.00 0.25

Total 3216427.00 76.76

6 Type of Proposal Upgradation

If the proposed road is a New connectivity

Is the road a part of core network Yes

If yes, Through/Link Route Number L29

Name of the unconnected Target Habitation (to be crosschecked with CN-6) Tultuliapara

List of unconnected enroute Habitation(s) (to be crosschecked with CN-6) -

Population sub served by the proposed road 256


Population served by the proposed road

Does the proposed Road lead up to the Habitation for which it is Supposed to
provide connectivity (In words are you sure that the road is not being made YES
partially ?)

Does the proposed Road connect the unconnected Habitation to (a) ✘ (b)
(a) Another Habitation having All-weather road(Connected status)
(b) Directly to an all weather road RR MDR SH NH
If (b) Indicate the nature of road to which the proposed road leads
If the proposal for upgradation Yes
.- Is the road a part of the core network Yes
.- Is the associated Through Route or not Yes
._ PCI Value 2
.- Age of the Road

Is it certified that there are no other Un-connected Habitation in the district Yes/No
Page 7 of 311

Index Map (Not To Scale):

Typical Section of the Road (Not To Scale):

6000
1125 3750 1125
4050
C
L
4.5 % 3.5% 3.5% 4.5 %
1.5 1.5
1 1

G.L. G.

EARTH WORK IN CORE 20 mm THICK PREMIX CARPETING


75 mm THICK WBM III
C
L
75 mm THICK WBM II
150 mm THICK GSB
0 - 300 mm THICK SUBGRADE (OPTIO

TYPICAL CROSS SECTION


C
L
75 mm THICK WBM II
Page 8 of 311
150 mm THICK GSB
(a) Whether the proposed Road has the desired carriageway width, Roadway width and 0Road
- 300 mm THICKYes/No
SUBGRADE (OPTIO
7
Land width (RLW)

In the Built
(b) TYPICAL
Indicate the actual widths of the following CROSSroad
for the proposed SECTION Up Area
In the open
Area (m)
(m)

a) Carriageway 3.75 3.75


b) Roadway 6.00 6.00
c) Road Land Width 10.00 12.00
8 Base year traffic volume :
Months and year of Traffic Volume Count
Motorised Traffic Non Motorised Traffic
Sl No Type of vehicle Day 1 Day 2 Day 3
1 Car, Jeep, Van 51 52 51
2 Motorised Auto Rikshaw 48 70 56
3 vehicle Motorised Two-wheeler (Scooters / Motorbikes) 35 36 35
4 Agricultural Tractor without Trailor / Light commercial Vehicles 7 8 7
5 Trucks (laden) 7 7 6
6 Trucks (unladen) 0 0 0
7 Bus / Minibus (laden) 2 1 4
8 Motorised Bus / Minibus (unladen) 2 2 2
commercia
9 l vehicle Agricultural Tractor with Trailor (laden) 0 0 0
10Agricultural Tractor with Trailor (unladen) 0 0 0
11 Other Medium commercial vehicles (laden) 1 0 0
12 Other Medium commercial vehicles (unladen) 0 0 0
13 Non Cycle 70 68 87
14 motorised Cycle Rickshaw / Cycle Van / Hand Cart 0 0 0
15 vehicle Horse Cart / Bullock Cart 5 4 3
16 Pedestrian 0 0 0
Total Commercial Vehicle per Day (CVPD)
Total Motorised Vehicle per Day
Total Non-Motorised Vehicle per Day
Total Vehicle / Traffic per Day (ADT)
Total ESAL
ADT in the year of Traffic Count = 277

Growth rate Adopted (%) = 6


Design life = 10 Years
Nos of Harvesting Seasons= 2
No of days in each harvesting Seasons
75
(t) =
value of ( n ) assumed= 1 Traffic Category= T4

9 Sub grade CBR (for Different Sections)=

400 m 1800 m
Borrowpit Borrowpit Borrowpit Borrowpit
Chainage (on Existing (on Existing
Sample 1 Sample 2 Sample 3 Sample 4
Road) Road)

Design CBR (%) 5.18 % 5.36 % 5.33 % 5.84 % 5.66 % 5.40 %

Chainage

Design CBR (%)


10 Cost Details Cost Rs. Cost/km(Rs.
A General Cost
B. Pavement Components
Description of layer Thickness(mm) Quantity Unit Cost in Rs. Cost/km(Rs.
Earthwork in Excavatiuon/cutting - 504.38 cum 62514.18 149198.51
Page 9 of 311

Earthwork- in Filling (Embankment) - 1587.45 cum 415485.35 991611.82

Construction of embankment with approved materials


- 504.38 cum 33203.50 79244.63
deposited at site from roadway cutting

Earthwork in Filling ( Shoulder) - 1483.27 cum 481989.93 1150333.97

Granular Sub Base Gr.II 150 254.54 cum 712201.18 1699764.15


WBM-2 75 117.84 cum 453664.67 1082731.90
WBM-3 75 117.84 cum 456144.37 1088650.06
Page 10 of 311

C.Bituminous Layers

Prime Coat 1571.25 sqm 49755.99 118749.38

Tack Coat 1571.25 sqm 18190.36 43413.75

Premix Carpeting 1571.25 sqm 258275.40 616409.07

Seal Coat 1571.25 sqm 82584.51 197099.06

D. Cement Concrete Road _ _

E. CD Works No. of Existing CD Works 1

Do they require any improvement-specify the nature of


No
improvement proposed
If Yes, their Number and cost of improvement

No. of proposed CD works with classification 0

Total Length / Dia. of Cost in Rs.


Location-Chainage (Similar Type of CD's may be grouped Bridge / Culvert
Type of CD & Their Nos
together)

41.0 m, 134.00 m, 584.00 m SHP 1 x 1000 mm 0.00

Cost in Rs. Cost/km(Rs.


Cost of proposed CD works
0.00 0.00

F. Protection works

Boulder Slope Protection 0.00 0.00

Total = 0.00 0.00

(i) Road Logo, other Road Furniture 165848.04 395818.71


H
(ii) DPR Preparation 10475.00 25000.00

Any other Provisions (Please Specify)


I
i) Cost of Clearing & Grubbing 16096.00 38415.27

Total Cost of the Project (Rs) 3216427.58 7676438.14


Page 11 of 311

Krishnai L29
Name of the Road Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur

J Cost of Utility Shifting 20000.00 20000.00

% of
K Five Year Routine Maintenance Year Cost in Lakh Constn. Cost/km
Cost
I 0.08 0.26% 20005.00

II 0.09 0.29% 22090.00

III 0.49 1.53% 117796.00

IV 0.59 1.84% 141125.00

V 0.83 2.57% 197543.00

Total Maintenance Cost 2.09 498559.00

Whether the road has Geometric as per Rural Roads Manual (RRM)/Latest Circular
11 Yes
of NRRDA

Whether CD works/Protection works are provided as per RRM /Latest Circular of


12 Yes
NRRDA/Respective Codes

13 Whether the cost estimates are as per standard data analysis and SSR Yes

14 Sources and the Lead Distances of materials are as under Yes

Material Source Lead Material Source Lead

Earth Private Land Within 1000 m WBM Gr.III Nakhola Quarry 28 km

GSB Silchang Quarry 50 km Boulder Silchang Quarry 50 km

WBM Gr.II Nakhola Quarry 28 km Sand Silchang Quarry 50 km

Certified that information provided is true

Prepared By :
(Name) Checked By : Scrutinized By :

Counter Signatures of
Co-ordinator STA
Page 12 of 311

TO BE FILLED BY STA
Name of the STA : IIT Guwahati.
Name of the Road Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur
If the Proposed Road entired on th OMMS:
15 Yes / No.
(Data entries to be verified by STA before Clicking the Proposal)
16 If the proposal is for new connectivity
Have you satisfied yourself that the proposed Road is a part of the Core Network Yes / No.
Is the unconnected habitation (s) part of list of unconnected Habitation as per CN-6 Yes / No.
Does the proposal ensure full connectivity of the Target Habitation Yes / No.
a) If no, the name of unconnected Habitation upto which it is connected.
b) In such Unconnected Habitation eligible under PMGSY Yes / No.
17 Are you satisfied with the following
Engineering Surveys (L section, X Section must be verified) Yes / No.
Soil/Material Investigation (CBR, Density, LL, PI, Gradation to be verified) Yes / No.
Traffic Surveys
Hyrraulic studies / Estimation Yes / No.
(Catchment areas for structures more than two vents to be verified from topo sheet, Location and Yes / No.
18 requirment of allisCd
In case, Traffic Structures
projected to beTverified
beyond from are
4 category; L Section)
you satisfied with the reason given by PIU. Yes / No.
In case sub grade CBR is less than 3; has soil stabilization etc been proposed.(if not specific reasons given by
19 Yes / No.
PIU)
20 Is the design of the following elements as per Rural Roads Manulal/Circular of NRRDA
Alignment & Geometric Yes / No
Location and Type of CD works and Yes / No
Side drains Yes / No
Integration for cross and Longitudinal drainage Yes / No
Protection Works Yes / No
Is the design of Flexible Pavement as per IRC SP:72 -2015 and Design of Rigid Pavement as per IRC:
21 Yes / No
SP:62-2004
22 Does the Estimation conformed to Standard rate Analysis and SSR generated for the current phase Yes / No
23 Does the proposal have provision for
PMGSY Logo, Sign Boards and information Boards. Yes / No
Km / Hm Stones Yes / No
Guard Stones (Where necessary) Yes / No
Traffic Sign Boards (as necessary) Yes / No
24 Specific remarks if any by STA
(Specific Remarks of STA about the over all project are necessary on each DPR)

Certified that the Design and Estimation for the Proposed Road work are based on the data and SSR provided by
Engineers. The Proposal after final correction is entered on the OMMS. The proposal may be considered for clearance.

Technical Scrutiny at STA : Coordinator


Done by S.T.A.

Signature Signature
Name Name
Page 13 of 311

Date Date
Page 14 of 311

6000
3750 1125
4050
C
L
3.5% 3.5% 4.5 %
1.5
1

G.L.
20 mm THICK PREMIX CARPETING
75 mm THICK WBM III
C
L
75 mm THICK WBM II
150 mm THICK GSB
0 - 300 mm THICK SUBGRADE (OPTIONAL)

CAL CROSS SECTION


C
L
75 mm THICK WBM II
Page 15 of 311
150 mm THICK GSB
0 - 300 mm THICK SUBGRADE (OPTIONAL)

CAL CROSS SECTION

Non Motorised Traffic


Average
51
58
35
7
7
0
2
2
0
0
0
0
75
0
4
0
26
105
79
277
186155

Cost/km(Rs.)

Cost/km(Rs.)
149198.51
Page 16 of 311

991611.82

79244.63

1150333.97

1699764.15
1082731.90
1088650.06
Page 17 of 311

118749.38

43413.75

616409.07

197099.06

Cost in Rs.

0.00

Cost/km(Rs.)

0.00

0.00

0.00

395818.71

25000.00

38415.27

7676438.14
Page 18 of 311

L29

20000.00

Cost/km

20005.00

22090.00

117796.00

141125.00

197543.00

498559.00

Lead

28 km

50 km

50 km

Scrutinized By :

ounter Signatures of
Co-ordinator STA
Page 19 of 311

L29

Yes / No.

Yes / No.
Yes / No.
Yes / No.

Yes / No.

Yes / No.
Yes / No.
Yes / No.
Yes / No.
Yes / No.

Yes / No.

Yes / No
Yes / No
Yes / No
Yes / No
Yes / No

Yes / No

Yes / No

Yes / No
Yes / No
Yes / No
Yes / No

e Proposed Road work are based on the data and SSR provided by PIU
ntered on the OMMS. The proposal may be considered for clearance.
Cross Drainage Structures statement

Road from: Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur

Prop.
Dia / Dia /
Sl No Chainage(m) Existing No Culvert/ No Remarks
Span Span
Reconstruct

1 5.00 SHP 1000 mm 1

Total= 1 Total= 0
PACKAGE NO. AS-07-
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY) FORMAT F-1 F
SUMMARY SHEET O
R
M
Unconnected Habitations A
T
Name of Block Total No. of 250-499 Total eligible
<250
Code Habitations >1000 500-999 Total Eligible habitations F
1
Krishnai L29 1 0 0 1 1 0 1

Type of Proposal No. of Roads Total Length of Roads No. of New Estimated Cost (Rs. In Lakh)
(KM) CD
Structures Pavement CD Total (5) +(6) No. of
from Format Structure Unconnected
F-6 Habitations /
connected
Habitations
1 2 3 4 5 6 7 8
New Connectivity
Associated Through
Route
Upgradation 1 0.419 0 32.06 0.00 32.06 1

Other Upgradation

Executive Engineer , PWD


Asstt. Executive Engineer, PWD Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division Goalpara
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
ROADS PROPOSED IN PMGSY FOR RURAL CONNECTIVITY (PAVEMENT LAYER)

District Goalpara Block: Krishnai PACKAGE NO.

Sl. Details of Thickness & Cost for

Route (A)/ Upgradation


New construction (N)/
connected / Benifitted

No.
Name of habitations

Associated Through

Existing Surface Type*


Details

Stripping,Storing and
Cleaning & grubbing

Sub-base GSB Gr.II


Road length (km)
Facility accessed

Relaying Top soil


Name of Block

WBM Grade 2
Subgrade and
Earthwork

Shoulder
(U)

From To N A U
1 2 3 4 4A 4B 4C 5 6 7 8 9 10 11 12 13 14
Pakhriguri
Krishnai

Krishnai
Chariali

NH37

1 U D 0.419 Earthen Thickness (mm) 0.30 0.15 0.075

Cost (Rs.) 0.04 0.00 5.11 4.82 7.12 4.54

Thickness (mm)

Cost (Rs.)

Thickness (mm)
Cost (Rs.)

Total Cost (Rs.) 0.04 0.00 5.11 4.82 7.12 4.54

Facility Access Code:


A'
B' for
for Market
Educational
Facilities
C' for Health Centre
D' for Combination of any of the above

Asstt. Executive Engineer, PWD


Goalpara/Dudhnoi Rural Road Sub
Division
FORMAT F-2A
GRAM SADAK YOJANA (PMGSY)
OR RURAL CONNECTIVITY (PAVEMENT LAYER)

AS-07- CNCPL NO. 0

Details of Thickness & Cost for Pavement Layers

pavement (Rs. Lakh)


Seal Coat (Type B)

Cement Concrete
pavement(M-30)

Existing Culvert
Dismentleing of
Road Furniture
WBM Grade 3

Total Cost of
Prime Coat

Tack Coat

OGPC
15 16 17 18 19 20 21 23 24

0.075 0.02

4.56 0.50 0.18 2.58 0.83 0.00 1.66 0.12 32.06


4.56 0.50 0.18 2.58 0.83 0.00 1.66 0.12 32.06

Note: The amount from state Govt.= 0.00

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
FORMAT F-2B
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
ROADS PROPOSED IN PMGSY FOR RURAL CONNECTIVITY (CROSS DRAINAGE STRUCTURES)

District : Goalpara Block: Krishnai Package No.: AS-07- CNCPL NO: 0

Existing CD Structure by Type Details of Proposed CD structure by Type

Habitations Connected /

Population (Served +

Road length (km)


Name of Block

Name of Road

Hume Pipe Culvert Box / Slab Minor Bridge Hume Pipe Culvert Box/Slab Culvert Major /

Sub-served)
Block Code

Benefitted Culvert Minor Bridge

proposed CD
Sl. No.

Total cost of

structures
No. Dia No. Length No. Length No. Dia No. Length No. Length
(m) (mm) (m) (m)

1 2 3 4 5 6 7 4 9 10 11 12 13 14 15 16 17 18 19 20 21
Pakhriguri to NH37
Krishnai Chariali

1.50 m Span
0 1x1000 0 0.00
via Borjuk
Manikpur

Slab
Krishnai

1 0 1 256 0.42 Cost (Rs.)

2.74 5.38

2.0 m Span
0 2x1000 0
Slab
2 Cost (Rs.)
5.30 7.39

4.0 m Span
0
Slab
3 Cost (Rs.)
16.36

0 1 cell 2 x 2
4 Cost (Rs.)
10.16

0 2 cell 2 x 2
5 Cost (Rs.)
13.11

Total 0 0 0 0 0 0.00
Asstt. Executive Engineer, PWD
Goalpara/Dudhnoi Rural Road Sub
Division
FORMAT F-2B
GRAM SADAK YOJANA (PMGSY)
ral Development, Govt of India)
RAL CONNECTIVITY (CROSS DRAINAGE STRUCTURES)

Works ( from F-6)


Protection Works

Cost of Drainage

Total Cost of the


Pavement from
Total Cost of

Cost of DPR
Format F -6

Preparation
(from F-6)

Total cost

Road
22 23 24 25 26

0.00 0.00 32.06 0.10 32.16

0.00 0.00 32.06 0.10 32.16


Executive Engineer , PWD
Goalpara Rural Road Division
Goalpara
FORMAT F3
TYPICAL CROSS SECTION
Existing Road

2.90m to 3.00m

Asstt. Executive Engineer, PWD Executive Engineer , PWD


Goalpara/Dudhnoi Rural Road Sub Goalpara Rural Road Division
Division Goalpara
FORMAT F4
TYPICAL CROSS SECTION
Proposed Road
0-300 mm Subgrade
150 mm GSB
75 mm WBM GR II
75 mm WBM Gr III
20 mm PC&SC

3.75 m
6.00 m

SUBGRADE
4.05 m
1.5:1 CORE 1.5:1
CORE

3.00 m - 4.

Asstt. Executive Engineer, PWD Executive Engineer , PWD


Goalpara/Dudhnoi Rural Road Sub Goalpara Rural Road Division
Division Goalpara
FORMAT F4
TYPICAL CROSS SECTION
Proposed Road
0-300 mm Subgrade
150 mm GSB
75 mm WBM GR II
75 mm WBM Gr III
20 mm PC&SC

3.75 m
6.00 m

SUBGRADE

1.5:1 CORE 1.5:1


CORE

3.00 m - 4.

Asstt. Executive Engineer, PWD Executive Engineer , PWD


Goalpara/Dudhnoi Rural Road Sub Goalpara Rural Road Division
Division Goalpara
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
FORMAT F5
STATE : ASSAM
DISTRICT : Goalpara
BLOCK : Krishnai
PACKAGE No. : AS-07-
MRL : 3

Name of Work : Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur

TOTAL LENGTH OF ROAD = 0.419 Km

GENERAL ABSTRACT OF COST

Sl No DESCRIPTION AMOUNT

1 TOTAL COST OF PAVEMENT Rs. 3205953.00

2 TOTAL COST OF CD WORKS Rs. 0.00

3 TOTAL COST OF CONSTRUCTION (1+2+3+4) Rs. 3205953.00

4 TOTAL COST OF CONSTRUCTION PER KM Rs. 7651439.00

5 TOTAL COST FOR PREPARATION OF DPR Rs. 10475.00

6 MAINTANENCE COST Rs. 208897.00

GRAND TOTAL (5+7+8) Rs. 3425325.00

Asstt. Executive Engineer, PWD Executive Engineer , PWD


Goalpara/Dudhnoi Rural Road Sub Goalpara Rural Road Division
Division Goalpara
Item
No.

Chapter 1 - LOADING, UNLOADING, CARRIAGE CRUSHING OF MATERIALS Description


AND SETTING OUT

1.1 Loading and Unloading of Lime, Aggregate, Stone Boulder, Brick Aggregate,
Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work by Manual
Means

(I) Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building
Rubbish, Crushed Slag, Stone for Masonry Work by manual means including a lead
upto 30 m

(ii) Loading of Earth, Sand, Moorum, Manure, Flyash by manual means including a lead
upto 30 m

(iii) Unloading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building
Rubbish, Crushed Slag, Stone for Masonry Work by manual means including a lead
upto 30 m

(iv) Unloading of Earth,Sand, Moorum,Manure,Fly ash, by manual means including lead


upto 30M

1.2 Loading and Unloading Lime, Aggregate, Stone Boulder, Brick Aggregate,
Kankar, Building Rubbish, Crushed Slag, Stone for Masonry Work by
Mechanical Means
I Loading of Lime, Aggregate, Stone Boulder, Brick Aggregate, Kankar, Building
Rubbish, Crushed Slag, Stone for Masonry Work by mechanical means including a
lead upto 30 m

ii Loading of earth,sand,moorum,manure,fly ash by mechanical means including a lead


upto 30 M

iii Unloading of Earth, Sand, Lime, Moorum, Aggregate, Stone Boulder, Brick Aggregate,
Kankar, Building Rubbish, Manure, Crushed Slag, Flyash, Stone for Masonry Work by
mechanical means.

1.3 Loading, Unloading and Stacking of Bricks by Manual Means

I Loading of Bricks by manual means including a lead upto 30 m

ii Unloading and Stacking of Bricks by manual means including a lead upto 30 m

1.4 Loading and Unloading of Cement by Manual Means

I Loading of Cement by manual means including a lead upto 30 m

ii Unloading of Cement by manual means including a lead upto 30 m

1.5 Loading and Unloading of Structural Steel and Steel Bars by manual means

I Loading of Structural Steel, Steel Bars by manual means including a lead upto 30 m

ii Unloading of Structural Steel, Steel Bars by manual means including a lead upto 30 m

1.6 Loading and Unloading of Bitumen Drums by Manual Means

I Loading of Bitumen Drums by manual means including a lead upto 30 m

Page 34
Unit Rate
(Rs.)

SHING OF MATERIALS Description


AND SETTING OUT

cum 94.00

cum 47.00

cum 47.00

cum 30.00

cum 61.00

cum 48.00

cum 12.00

1000 Nos. 163.00

1000 Nos. 163.00

t 112.00

t 112.00

t 117.00

t 117.00

t 135.00

Page 35
Item
No.

ii Unloading of Bitumen Drums by Manual Means includingDescription


a lead upto 30 m

1.7 Loading and Unloading of Timber by Manual Means

I Loading of Timber by manual means including a lead upto 30 m

ii Unloading of Timber by manual means including a lead upto 30 m

1.8 Loading and Unloading of C.C. Blocks, Kerb, etc.

I Loading with care C.C. Blocks, km Stone, 200 m Stone, Boundary Pillar, Kerb,
Channel, Bond Stone, etc. by manual means including a lead upto 30 m

ii Unloading with care C.C. Blocks, km Stone, 200 m Stone, Boundary Pillar, Kerb,
Channel, Bond Stone, etc. by manual means including a lead upto 30 m

1.9 Loading and Unloading of Hume Pipes

I Loading of RCC Hume pipes by mechanical means including a lead upto 30 m

A. 1000 / 1200 mm dia Hume pipe

B. 750 mm dia Hume pipe

C. 600/450 mm dia Hume pipe

II Unloading of RCC Hume pipe by manual means including a lead upto 30 m

A 1000/1200 mm dia RCC Hume pipes

B. 750 mm dia Hume pipe

C. 600/450 mm dia Hume pipe

III Unloading of RCC Hume pipes by mechanical means including a lead upto 30 m

A 1000/1200 mm dia Hume pipe

B 750 mm dia Hume pipe

C. 600/450 mm dia Hume pipe

1.10 Haulage excluding Loading & Unloading

Haulage of materials by tipper excluding cost of loading, unloading and stacking.

Case-I : Surfaced Road

Case-II: Unsurfaced Gravel Road

Page 36
Unit Rate
(Rs.)

Description t 128.00

t 206.00

t 206.00

cum 298.00

cum 298.00

per pipe 71.00

per pipe 43.00

per pipe 30.00

per pipe 396.00

per pipe 330.00

per pipe 248.00

per pipe 47.00

per pipe 28.00

per pipe 20.00

t.km 7.00

Cum/km 12.75

t.km 9.00

Cum/km 16.40

Page 37
Item
No.

Description
Case-III: Katcha Track and Track in River Bed/Nallah Bed and Choe Bed

1.11
1.16 Supply of
Setting Quarried stone and hand breaking
Out

Unit=1Km

The analysis of rate per km shall account for the following:

(I) Reference benchmark one no.

(ii) Working benchmark 4 nos. per Km and near all drainage

structure and bridges.

(iii0 Reference pillars/Burjees @ 50 m interval on both sides of

formation width.

(iv) The marking of centre line setting out curves and recording

of levels,etc. by the surveyor will be incidental to the work and

no extra payment shall be made for the same.

(v) Typical benchmark as per Drawing 200.1

(vi)Typical reference pillar as per Drawing 200.2

Chapter 2 - SITE CLEARANCE

2.1 Clearing Grass and Removal of Rubbish

Clearing grass and removal of rubbish up to a distance of 30 m outside the periphery


of the area as per Technical Specification Clause 201.

By Manual Means

2.2 Clearing and Grubbing Road Land

Clearing and grubbing road land including uprooting wild vegetation, grass, bushes,
shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut
earlier and disposal of unserviceable materials and stacking of serviceable material to
be used or auctioned, upto a lead of 1000 m including removal and disposal of top
organic soil not exceeding 150 mm in thickness as per Technical Specification Clause
201.

(I) By Manual Means


(A) In area of non thorny jungle
In area of thorny jungle
(ii) By Mechanical Means

In area of non-thorny jungle


In area of thorny jungle
2.3 Cutting of Trees including Cutting of Trunks, Branches and Removal of Stumps

Page 38
Unit Rate
(Rs.)

Description t.km 14.00

Cum/km 25.50

each 6247.00

each 3143.00

hectare 7,079.00

hectare 26,209.00
hectare 35,522.00

hectare 24,628.00
hectare 29,913.00

Page 39
Item
No.

Cutting of trees, including cutting of trunks, branches andDescription


removal of stumps & roots,
refilling, compaction of backfilling and stacking of serviceable material by manual
means with all lifts as per Technical Specification Clause 201.
A Lead upto 100 m

I Girth above 300 mm to 600 mm

ii Girth above 600 mm to 900 mm

iii Girth above 900 mm to 1800 mm

iv Girth above 1800 mm to 2700 mm

v Girth above 2700 mm to 4500 mm

vi Girth above 4500 mm

B Lead upto 1000 m

I Girth above 300 mm to 600 mm

ii Girth above 600 mm to 900 mm

iii Girth above 900 mm to 1800 mm

iv Girth above 1800 mm to 2700 mm

v Girth above 2700 mm to 4500 mm

vi Girth above 4500 mm

2.4 Uprooting and Removing Stumps & Roots

Uprooting and removing stumps & roots,compaction of backfilling and staking of


servicable material by manual means as per Technical Specification clause 201.
as per Technical Specification Clause 201
A Lead upto 100 m

I Girth above 300 mm to 600 mm

ii Girth above 600 mm to 900 mm

iii Girth above 900 mm to 1800 mm

iv Girth above 1800 mm to 2700 mm

v Girth above 2700 mm to 4500 mm

vi Girth above 4500 mm

B Lead upto 1000 m

I Girth above 300 mm to 600 mm

ii Girth above 600 mm to 900 mm

iii Girth above 900 mm to 1800 mm

iv Girth above 1800 mm to 2700 mm

Page 40
Unit Rate
(Rs.)

Description

each 140.00

each 262.00

each 490.00

each 913.00

each 1,903.00

each 5,400.00

each 153.00

each 306.00

each 544.00

each 1,001.00

each 2,001.00

each 5,644.00

each 80.00

each 131.00

each 269.00

each 525.00

each 1,065.00

each 3,020.00

each 83.00

each 143.00

each 284.00

each 545.00

Page 41
Item
No.

v Girth above 2700 mm to 4500 mm Description

vi Girth above 4500 mm

2.5 Dismantling of Structures


Dismantling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonry, cement concrete, wood work, steel work, including
T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable material with all lifts and lead of
1000 m as per Technical Specification Clause 202.

I By Manual Means
(A) Lime Concrete
(B) Cement Concrete

© Reinforced Cement Concrete

II By Mechanical Means
(A) Cement Concrete
(B) Reinforced Cement Concrete

2.6 Dismantling Brick/Tile Work


Dismantling of existing structures like culverts, bridges, retaining walls and other
structures comprising of brick masonry, including disposal of unserviceable material
and stacking the serviceable material with all lift and lead of 1000 m as per Technical
Specification Clause 202.

(A) Lime mortar


(B) Cement mortar
© M
Mud Morter
(D) u
Dry Brick Pitching or Brick Soling
d
2.7 Dismantling Stone Masonry as per Technical Specification Clause 202.
M
o
Dismantling of existing structures like culverts, bridges, retaining walls and other
r
structure comprising of stone masonry, including disposal of unserviceable material
t
and stacking the serviceable material with all lift and lead of 1000 m as per Technical
a
Specification Clause 202.
r
(A) Rubble Stone Masonry in Lime Mortar

(B) Rubble Stone Masonry in Cement Mortar

© Rubble Stone Masonry in Mud Mortar

(D) Dry Rubble Masonry

(E) Dismantling Stone Pitching / Dry Stone Spalls

(F) Dismantling boulders laid in wire crates including opening of crates and stacking
dismantled materials

2.8 Dismantling Wood Work Wrought and Planed Fixed in Frames of Trusses upto a
height of 5 m above Plinth Level as per Technical Specification Clause 202.

2.9 Dismantling Steel Work in all Types of Sections upto a height of 5 m above Plinth
Level excluding Cutting of rivet as per Technical Specification Clause 202.

Page 42
Unit Rate
(Rs.)

Description each 1,089.00

each 3,142.00

cum 220.00
cum 259.00

cum 626.00

cum 376.00
cum 462.00

cum 149.00
cum 181.00
cum 138.00
cum 131.00

cum 171.00

cum 151.00

cum 149.00

cum 142.00

cum 137.00

cum 157.00

cum 321.00

Page 43
Item
No.

(A) Including dismembering Description

(B) Excluding dismembering

© Extra over Items (A) and (B) for cutting rivets

2.10 Scraping of bricks dismantled from brick work including stacking as per Technical
Specification Clause 202.

2.11 Scraping of Stone from Dismantled Stone Masonry as per Technical Specification
Clause 202.

In Cement or Lime Mortar

2.12 Scraping Plaster in Lime or Cement Mortar from Brick / Stone Masonry as per
Technical Specification Clause 202.

2.13 Removing all types of Hume pipes and stacking within a lead of 1000 m including
Earthwork and Dismantling of Masonry Works as per Technical Specification
Clause 202.

(A) Upto 600 mm dia Hume pipe


(B) Above 600 mm to 900 mm dia Hume pipe
(C) Above 900 mm dia Hume pipe
Note : 1. The excavation of earth,dismantling of stone masonary
work in head walls and protection works is not included which is
to be measured and paid seperately.
2. Credit for retrives stone from masonary work may be
taken as per actual availability.
2.14 Dismantling of Flexible Pavements

Dismantling of flexible pavements and disposal of dismantled materials upto a lead of


100 m, stacking serviceable and unserviceable materials separately as per Technical
Specification Clause 202

I By Manual Means
(A) Bituminous Courses
(B) Granular Courses
II By Mechanical Means
(A) Bituminous Courses
2.15 Dismantling of Cement Concrete Pavements as per Technical Specification
Clause 202.
Dismantling of cement concrete pavements by mechanical means using pneumatic
tools breaking to pieces not exceeding 0.02 cum in volume and stock piling at
designated locations and disposal of dismantled materials upto a lead of 1000 m,
stacking serviceable and unserviceable materials separately

2.16 Dismantling Guard Rails


Dismantling guard rails by manual means and disposal of dismantled material with all
lifts and upto a lead of 1000 m, stacking serviceable materials and unserviceable
materials separately as per Technical Specification Clause 202.
2.17 Dismantling Kerb Stones
Dismantling kerb stones by manual means and disposal of dismantled material with all
lifts and upto a lead of 1000 m as per Technical Specification Clause 202.

2.18 Dismantling Kerb Stone Channels

Page 44
Unit Rate
(Rs.)

Description t 748.00

t 558.00

t 5.00

1000 Nos. 619.00

cum 249.00

sqm 9.00

m 92.00
m 124.00
m 213.00

cum 402.00
cum 304.00

cum 206.00

cum 917.00

running m 46.00

running m 10.00

Page 45
Item
No.

Dismantling kerb stone channels by manual means and Description


disposal of dismantled material
with all lifts and upto a lead of 1000 m as per Technical Specification Clause 202.

2.19 Dismantling Kilometre Stones

Dismantling of kilometre stones including cutting of earth, foundation and disposal of


dismantled material with all lifts and lead upto 1000 m and backfilling of pit as per
Technical Specification Clause 202.
(A) 5th km Stone
(B) Ordinary km Stones
© 200 m Stones
2.20 Dismantling of Fencing

Dismantling of barbed wire fencing / wire mesh fencing including posts, foundation
concrete, backfilling of pit by manual means including disposal of dismantled material
with all lifts and upto a lead of 1000 m, stacking serviceable material and unserviceable
material separately as per Technical Specification Clause 202.

2.21 Dismantling of CI Water Pipe Line

Dismantling of CI water pipe line 600 mm dia including disposal with all lifts and lead
upto 1000 m and stacking of serviceable material and unserviceable material
separately under supervision of concerned department as per Technical Specification
Clause 202.

2.22 Removal of Cement Concrete Pipe of Sewer Gutter


Removal of cement concrete pipe of sewer gutter 1500 mm dia under the supervision
of concerned department including disposal with all lifts and upto a lead of 1000 m and
stacking of serviceable and unserviceable material separately but excluding earth
excavation and dismantling of masonry works as per Technical Specification Clause
202.

2.23 Removal of Telephone/Electric Poles and Lines


Removal of telephone/electric poles with wires including excavation and dismantling of
foundation concrete and lines under the supervision of concerned department, disposal
with all lifts and upto a lead of 1000 m and stacking the serviceable and unserviceable
material separately as per Technical Specification Clause 202.

Chapter 3-EARTHWORK, EROSION CONTROL AND DRAINAGE


3.1 Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means

a Manual means

Scarifying existing granular surface to a depth of 50 mm and disposal of scarified


material with a lift upto 3 m and leads upto 1000 m as per Technical Specification
Clause 301.4.

b Mechanical means
Scarifying existing granular surface to adepth of 50mm and disposal of scarified
material with a lift upto 3 m and lead upto 1000m as per Technical specification Clause
301.4

3.2 Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Mean


Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of
scarified material with a lift upto 3 m and lead upto 1000 m as per Technical
Specification Clause 301.4.

Page 46
Unit Rate
(Rs.)

Description running m 16.00

m 206.00
m 125.00
m 26.00

running m 26.00

running m 81.00

running m 154.00

each 95.00

RAINAGE

sqm 14.00

sqm 4.00

sqm 6.00

Page 47
Item
No.

3.3 Construction of Embankment with Material ObtainedDescription


from Roadway Cutting

Construction of embankment with approved materials deposited at site from roadway


cutting and excavation from drain and foundation of other structures graded and
compacted to meet requirement of Tables 300.1 and 300.2 as per Technical
Specification Clause 301.5

3.4 Construction of Embankment with Material Obtained from Borrow Pits

Construction of embankment with approved material obtained from borrow pits with a
lift upto 1.5 m, transporting to site, spreading, grading to required slope and
compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as
per Technical Specification Clause 301.5

(I) Private Land


(ii) Govt. Land
3.5 Excavation in Cutting in Soil by manual means with lead upto 50 m
Excavation for roadway in soil using manual means for carrying of cut earth to
embankment site with a lift upto 1.5 m and lead upto 50 m as per Technical
Specification Clause 302.3 (Manual should be use where machines can not be
deployed due to site condition)

ii Excavation in Soil with Dozer with lead upto 100 m

Excavation for roadway in soil by mechanical means including cutting and pushing the
earth to site of embankment upto a distance of 100 m, including trimming bottom and
side slopes in accordance with requirements of lines, grades and cross-sections.

iii Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 m

Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity
including cutting and loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross-sections, and transporting to
the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical
Specification Clause 302.3

3.6 Excavation in Marshy Soil


Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum bucket
capacity including cutting and loading in tippers and disposal with a lift upto 1.5 m and
lead upto 1000 m, trimming of bottom and side slopes in accordance with requirements
of lines, grades and cross- sections as per Technical Specification Clause 302.3.6.

3.7 Removal of Unsuitable Soil with Disposal upto 1000 m


Removal of unsuitable soil including excavation, loading and disposal upto 1000 m
lead but excluding compaction ground supporting embankment subgrade replacement
by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical
Specification Clause 302.3.11

Note: This item does not include replacement of unsuitable soil by suitable soil
Replacement,Where required, is to be provided and paid seperately under Clause
303.5.2
3.8 Excavation in ordinary Rock by manual means

Page 48
Unit Rate
(Rs.)

Description

cum 70.00

cum 167.00
cum 125.00

cum 66.00

cum 77.00

cum 52.00

cum 59.00

cum 52.00

Page 49
Item
No.

I Description
Excavation in ordinary rock using manual means including loading in a truck and
carrying of excavated material to embankment site with a lift upto 1.5 m and lead upto
50 m as per Technical Specification Clause 302.3.5. (Manual means should be use
where machines can not be deployed due to site condition)

ii Excavation in Ordinary Rock with Dozer with lead upto 100 m

Excavation for roadway in ordinary rock by deploying a dozer D-50 including cutting
and pushing the cut earth to site of embankment upto a distance of 100 m (average
lead 50 m), trimming bottom and side slopes in accordance with the requirements of
lines, grades and cross-sections with lift upto 1.5 m.

iii Excavation in Ordinary Rock using Hydraulic Excavator and Tippers with disposal
upto 1000 m
Excavation for roadway in ordinary rock with hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in tippers, transporting to embankment site with
a lift upto 1.5 m and lead upto 1000 m, trimming bottom and side slopes in accordance
with requirements of lines, grades and cross-sections as per Technical Specification
Clause 302.3.5

3.9 Excavation in Hard Rock (requiring blasting) with disposal upto 1000 m
1000M
I Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and
breaking, trimming of bottom and side slopes in accordance with requirements of lines,
grades and cross-sections, loading and disposal of cut rock with a lift upto 1.5 m and
leads upto 1000 m as per Technical Specification Clause 302.3.5

ii Excavation in Hard Rock (blasting prohibited)

Excavation for roadway in hard rock (blasting prohibited) with rock breakers including
breaking rock, loading in tippers and disposal with a lift upto 1.5 m and lead upto 200
metres, trimming bottom and side slopes in accordance with requirements of lines,
grades and cross- sections as per Technical Specification Clause 302.3.5

A Manual Means

B Mechanical Means

iii Excavation in Hard Rock (controlled blasting) with disposal upto 1000 m

Excavation for roadway in hard rock with controlled blasting by drilling, blasting and
breaking, trimming of bottom and side slopes in accordance with requirements of lines,
grades and cross-sections, loading and disposal of cut rock with a lift upto 1.5 m and
leads upto 1000 m as per Technical Specification Clause 302.3.5

3.10 Stripping, Storing and Relaying Top Soil from Right-of-Way (R.O.W)

SStriping,storing and preservatio of top soil by keeping it damp in stock piles and keep
wet till it is used by road side at 15 M interval and reapplication on embankment
slopes,cut slopes and other areas in localities where the available embankment mate

3.11 Stripping,Storing and Relaying Top soil from Borrow areas in Agricultural fields.

Page 50
Unit Rate
(Rs.)

Description cum 103.00

cum 80.00

cum 80.00

cum 221.00

cum 534.00

cum 371.00

cum 241.00

cum 126.00

Page 51
Item
No.

Stripping of top soil from borrow areas located in agriculture Description


fields, storing at a suitable
place, spreading and relaying after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels to the satisfaction of the farmer/land
owner as per Technical Specification Clause 302.3.2.

3.12 Turfing with Sods


Furnishing and laying of the live sods of perennial turf forming grass on embankment
slope, verges or other locations shown on the drawing or as directed by the Engineer
including preparation of ground, fetching of sods and watering as per Technical
Specification Clause 309.

3.13 Seeding and Mulching


Preparation of seed bed on previously laid top soil, furnishing and placing of seeds,
fertilizer, mulching material, applying bituminous emulsion @ 0.23 litre per sqm and
laying and fixing jute netting, including watering for 3 months all as per Technical
Specification Clause 310.

3.14 Construction of Subgrade and Earthen Shoulders


Construction of subgrade and earthen shoulders with approved material obtained from
borrow pits with all lifts and leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per
Technical Specification Clause 303.1.

(I) Private Land


(ii) Govt. land
3.15 Compacting Original Ground
(I) Compacting original ground supporting embankment

Loosening, Levelling and Compacting original ground supporting embankment to


facilitate placement of first layer of embankment, scarified to a depth of 150 mm, mixed
with water at OMC and then compacted by rolling so as to achieve minimum dry
density as given in Tables 300.1 and 300.2 for embankment construction as per
Technical Specification Clause 301.4.1.

(ii) Compacting original ground supporting subgrade

Loosening of the ground upto a level of 300 mm below the subgrade level, watered,
graded and compacted in layers to meet requirement of Tables 300.1 and 300.2 for
subgrade construction as per Technical Specification Clause 303.5.2.

3.16 Repairs of damages caused by rain/spillage of water

Preparation and surface treatment of formation by removing mud and slurry, watering
to the extent needed to maintain the desired moisture content, trimming to the required
line, grade, profile and rolling with three wheel 80-100 kN static roller, complete as per
Technical Specification Clause 301.5.5.1

3.17 Presplitting Rock Excavation Slopes

Carrying out excavation in hard rock to achive a specified slope of the rock face by
controlled use of explosives and blasting accessories in properly aligned and spaced
drill holes, collection of the excavated rock by a D-50 dozer, loading in tipper by a front
end loader and disposing of the material with a lift upto 1.5 m and lead upto 1000 m as
per Technical Specification Clause 304.3

3.18 Construction of Embankment with Flyash/Pond ash available from Coal or


Lignite Burning Thermal Plants as Waste Material

Page 52
Unit Rate
(Rs.)

Description cum 113.00

sqm 16.00

sqm 96.00

cum 207.00
cum 195.00

cum 24.00

cum 73.00

sqm 2.00

sqm 127.00

Page 53
Item
No.

Description
Construction of embankment with flyash conforming to Table 1 of IRC:SP:58 obtained
from coal or lignite burning thermal power stations as waste material, spread and
compacted in layer of 200 mm thickness each at OMC, all as specified in IRC:SP:58
and as per approved plans with lead upto 1000 m as per Technical Specification
Clause 306.

3.19 Surface Drains in Soil

(I) Construction of unlined surface drains of average cross-sectional area 0.40 sqm in soil
to specified lines, grades, levels and dimensions. Excavated material to be used in
embankment with a lift upto 3m and lead of 50 m (average lead 25 m) as per Technical
Specification Clause 307.

(A) Manual Means


(B) Mechanical Means
(II) Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross-sectional area 0.4 sqm in
ordinary rock to specified lines, grades, levels and dimensions as per approved design
and Technical Specification Clause 307. Excavated material to be used in
embankment at site.

(A) Manual Means

(B) Mechanical Means

(III) Surface Drains in Hard Rock

Rate per m may be worked out based on quantity of hard rock as per design.

For rate of hard rock cutting refer releavant item in this chapter.

Note: Where
Note: Wherelining
liningofofdrain
drainis is provided,quantity
provided,quantity shallshall be worked
be worked out out

3.20 Chute Drains

A Providing chute drains across embankment slopes in approches of bridges and on


horizontal curves as per drawings.

(a)Earthwork in exavation for foundation of structure as per drawings and technical


specification clause 307 including setting out construction of shoring and bracing
deleterious matter, dressing of sides and bottom and backfilling with approved
material(

Rate as per item No. 11.1 of Chapter 11.


(b)Providing and laying plain cement concrete M15 grade Rate as per 12.5 of Chapter
12
© Brick masonry in cement morter 1:5. Rate asper item no 12.1 (iii) of Chapter 12

(d)Plastering with cement morter 1:4. Rate as per item no 12.3 of Chapter 12.
(e)Providing P.C.C. M 20 coping on the top of chute walls. As per item no 12.13 of
Chapter 12.
B Providing chute drains across embankment slopes in approches of bridges and
on horizontal curves as per drawings.

(a) Earthwork in exacavation for foundation of structure as per drawing and technical
specifications clause 307 including setting out construction of shoring and bracing
deleterious matter, dressing of sides and backfilling with approved material (By manu

Page 54
Unit Rate
(Rs.)

Description cum 193.00

m 35.00
m 22.00

m 53.00

m 27.00

srovided,quantity
provided,quantity
shallshall be worked
be worked out out basedbased on
on appr

m -

Cum
cum

cum

cum
cum

m -

Page 55
Item
No.

Rate as per item no 11.1 of chapter 11. Description

(b) Providing and laying plain cement concrete M 15 Grade

Rate as item No.12.5 of Chapter 12.


© Coursed ruble stone masonary (2 nd sort) in cement morter 1:4

Rate as item No.12.4 II of Chapter 12.

(d) Plastering with cement morter 1:4

Rate as per item No. 12.3 of Chapter 12.

(e) Providing P.C.C. M 20 Coping on the top of chute walls


Rate as per item No. 12.13 of chapter 12

Chapter 4 - GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) AND SHOULDERS

4.1 Granular Sub-base with Well Graded Material (Table 400.1)


(Only for PMGSY work)
(A) By Mix in Place Method

Construction of granular sub-base by providing well graded material, spreading in


uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with smooth wheel roller to achieve the
desired density, complete as per Technical Specification Clause 401.

(I) For Grading I Material


(ii) For Grading II Material
(iii) For Grading III Material
4.2 Plant Mix Method
Gravel/Soil-Aggregate Base (Table 400.2) Grading A
(Only for PMGSY work)
I) Construction of gravel/soil-aggregate base by providing well graded material,
spreading in uniform layers with motor grader on prepared surface, mixing by mix in
place method with rotavator at OMC, and compacting with three wheel 80-100 kN
static roller to achieve the desired density, complete as per Technical Specifications
Clause 402

ii) Gravel/Soil-Aggregate Base (Table 400.2) Grading B


Construction of granular sub-base by providing well graded material, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with three wheel 80-100 kN static roller
capacity to achieve the desired density, complete as per Technical Specification
Clause 402

iii) Gravel/Soil-Aggregate Base (Table 400.2) Grading C

Construction of granular sub-base by providing well graded material,

iv) Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 80 mm (Table


2.3 of IRC SP 77-2008

Page 56
Unit Rate
(Rs.)

Description cum

cum

cum

cum

cum

ITUMINOUS) AND SHOULDERS

cum 1,474.00
cum 1,375.00
cum 1,254.00

cum 1,706.00

cum 1,476.00

cum 1,344.00

cum
1228.00

Page 57
Item
No.

Description

Construction of Gravel/soil aggregate sub-base/Base by providing well graded material


of nominal size grading 80 mm as per Table 2.3 of IRC SP 77-2008, spreading in
uniform layers with tractor mount appropriate grading arrangement on prepared
surface,mixi
v)
Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 40 mm (Table
2.3 of IRC SP 77-2008

Construction of Gravel/soil aggregate sub-base/Base by providing well graded material


of nominal size grading 40 mm as per Table 2.3 of IRC SP 77-2008, spreading in
uniform layers with tractor mount appropriate grading arrangement on prepared
surface,mixi
vi)
Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 20 mm (Table
2.3 of IRC SP 77-2008

Construction of Gravel/soil aggregate sub-base/Base by providing well graded material


of nominal size grading 40 mm as per Table 2.3 of IRC SP 77-2008, spreading in
uniform layers with tractor mount appropriate grading arrangement on prepared
surface,mixi
4.3 Gravel/Soil-Aggregregate surface course (table 400.3)
(Only for PMGSY work)
I Construction of granular sub-base by providing well graded material, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with three wheel 80-100 kN static roller
capacity to achieve the desired density, complete as per Technical Specification
Clause 402

ii
Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 10 mm (Table
2.3 of IRC SP 77-2008

C0nstruction of Gravel/Soil aggregrete Base/Surface by providing well graded material


of nominal maximum size grading 10 mm as per Table 2.3 of IRC SP 77-
2008,spreading in uniform layers with tractor mount appropriate grading arrangement
on prepared surfa
iii) Gravel/Soil Aggeregate Base/Sub-Base Nominal Maximum size Grading 5 mm (Table
2.3 of IRC SP 77-2008

Construction of Gravel/Soil aggregrete Base/Surface by providing well graded material


of nominal maximum size grading 5 mm as per Table 2.3 of IRC SP 77-2008,
spreading in uniform layers with tractor mount appropriate grading arrangement opn
prepared surf
4.4 Lime Stabilisation for Improving Subgrade

Page 58
Unit Rate
(Rs.)

Description

cum 1163.00

cum 1105.00

cum 1,204.00

cum 1,154.00

cum 1,120.00

Page 59
Item
No.

Laying and spreading available soil in the subgrade on aDescription


prepared surface, pulverising,
mixing the spread soil in place with rotavator with 2 per cent slaked lime having
minimum 70 per cent of contents of CaO, grading with motor grader and compacting
with the smooth wheel road roller at OMC to the desired density to form a layer of
improved Sub-grade as per Technical Specification Cluase 403.

(A) By Manual Means

(B) By Mechanical Means

4.5 Lime Treated Soil for Sub-Base

Providing, laying and spreading soil on a prepared sub-grade, pulverising, mixing the
spread soil in place with rotavator with 4 per cent slaked lime with minimum content of
70 per cent of CaO, grading with motor grader and compacting with the road roller at
OMC to achieve atleast 98 per cent of the max dry density to form a layer of sub-base
as per Technical Specification Clause 403.

4.6 Cement Treated Soil Sub-Base/Base

Providing, laying and spreading soil on a prepared sub-grade, pulverising, adding the
designed quantity of cement to the spread soil, mixing in place with rotavator, grading
with the motor grader and compacting with the road roller at OMC to achieve the
desired unconfined compressive strength and to form a layer of sub-base/base as per
Technical Specification Clause 404.

For 4 per cent quantity of cement by weight of soil

4.7 Water Bound Macadam Sub-base/base


(Only for PMGSY work)
1) WBM Grading 1
Using stone screening Type-A 13.2 mm for Gr.I
Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and
camber, applying and brooming, stone screening/binding materials to fill-up the
interstices of coarse aggregate, watering and compacting to the required density
Grading 1 as per Technical Specification Clause 404.

(A) By Manual Means

(B) By Mechanical Means

2) WBM Grading 2
Using stone screening Type-B 11.2 mm for Gr.II
Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and
camber, applying and brooming, stone screening/binding materials to fill-up the
interstices of coarse aggregate, watering and compacting to the required density
grading 2 as per Technical Specification Clause 405.

(A) By Manual Means


(B) By Mechanical Means
3) WBM Grading 3
Using stone screening Type-B 11.2 mm for Gr.III

Page 60
Unit Rate
(Rs.)

Description

cum 308.00

cum 373.00

cum 608.00

cum 854.00

cum 2,230.00

cum 2,214.00

cum 2,174.00
cum 2,073.00

Page 61
Item
No.

Description
Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and
camber, applying and brooming, stone screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density Grading 3 as per Technical
Specification Clause 405.

(A) By Manual Means

(B) By Mechanical Means

4.8 Water Bound Macadam with Crushable Screenings


(Only for PMGSY work)
1) WBM Grading 1
Using crushable screening such as moorum gravel for Gr.I
Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and
camber, applying and brooming, crushable screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density Grading 1 as per Technical
Specification Clause 405.

A) By Manual Means
B) By Mechanical Means
2) WBM Grading 2
Using crushable screening such as moorum gravel for Gr.II
Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and
camber, applying and brooming, crushable screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density Grading 2 as per Technical
Specification Clause 405.

(A) By Manual Means

(B) By Mechanical Means

3) WBM Grading 3

Using crushable screening such as moorum gravel for Gr.III


Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and
camber, applying and brooming, crushable screening to fill-up the interstices of coarse
aggregate, watering and compacting to the required density Grading 3 as per Technical
Specification Clause 405.

(A) By Manual Means

(B) By Mechanical Means

4.9 Wet Mix Macadam

Page 62
Unit Rate
(Rs.)

Description

cum 2,153.00

cum 2,141.00

cum 2,024.00
cum 1,883.00

cum 1,972.00

cum 1,942.00

cum 2,042.00

cum 1,982.00

Page 63
Item
No.

Providing, laying, spreading and compacting graded stone Description


aggregate to wet mix
macadam specification including premixing the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in
uniform layers in sub-base/base course on a well prepared sub-base and compacting
with smooth wheel roller of 80 to 100kN weight to achieve the desired density
including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 &
400.12 and Technical Specification Clause 406.

By Mechanical Means with 1 km lead

4.10 Construction of Shoulders as per Technical Specification Clause 407.

A Earthen Shoulders

The rate as applicable for sub-grade construction may be adopted.

B Hard Shoulders

Rate as applicable for sub-base and/or base may be adopted as per approved design.

C Paved Shoulders

The rates may be adopted as applicable for different layers of pavement depending
upon approved design of paved shoulders.

4.11 Granular sub-base/base/surface course with local materials (Table 400.13) by mix in
place method normal Construction of granular sub-base by providing local material
spreading in uniform layers with motor grader on prepared surface, mixing by mix in
place method with rotavator at once and compacting with smooth wheel roller to
achieve the desired density complete as per Clause 401.4 as per Technical
Specification Clause 408.

I Using naturally occuring gravel


ii Using Gravel mix soil using
4.12 Construction of Water Bound Macadam using locally available material (Table
400.13)

Providing, laying spreading and compacting local material in block or large discrete
particles, such as kankar, Laterite, Dhandla etc. as per Table 400.13 to water bound
macadam specification including spreading in uniform thickness, hand packing, rolling
with three wheel 80-100 kN static roller in stages to proper grade and camber,
applying and brooming requisite type of screening /binding materials to fill-up the
interstices of laid material watering and compacting to the required density as per
Clause 405.3 and Technical Specification Cluase 408.

4.13 Lime-Flyash Stablised Soil Sub-base


Construction of sub-base using lime-flyash admixture with granular soil, free from
organic matter/deleterious material or clayey silts and low plasticity clays having PI
between 5 and 20 and liquid limit less than 25 and commercial dry lime, slaked at site
or pre-slaked with CaO content not less than 50 per cent, flyash to conform to
gradation as per Clause 4.3 of IRC:SP:20, lime+flyash content ranging between 10 to
30 per cent, the minimum un-confined compressive strength and CBR value after 28-
days curing and 4-days soaking to be 0.75 MPa and 25 per cent respectively, all as
specified in IRC:88 including a lead upto 1000 m as per Technical Specification Cluase
409.

(A) For earth taken from Private source

(B)For earth taken from Govt.Land

Page 64
Unit Rate
(Rs.)

Description

cum 1,673.00

cum 1,127.00
cum 1,126.00

cum 1,437.00

cum 489.00

cum 469.00

Page 65
Item
No.

4.14 Description
Construction of Sub-base/Course Using Crushed Slag as per Table 400.19

Construction of Sub-base by providing crushed slag spreading in uniform layer with


motor grader on prepared surface mixing by mix-in-place method with Rotavator @
OMC, and compacting with three wheel 80-100 kN static roller to achieve the desired
density complete as per Technical Specifications Cluase 402.4 and 410.3.2

4.15 Water Bound Macadam using crushed slag


Providing, laying, spreading and compacting crushed slag to water Bound Macadam
specification including spreading in uniform thickness, hand packing rolling with smooth
wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming
requisite type of screening/binding materials to fill up the interstees of crushed slag
watering and compacting to the required density as per Clause 405.3 and Technical
Specification Cluase 410.3.2.

4.16 Cement Bound Granular Material sub-base/base


Providing laying and spreading granulated blast furnace slag on a prepared sub-grade
pulverising adding the designed quantitity of cement to the spread granulated blast
furnace slag mixing in place with rotavator grading with the mortar grader and
compacting with smooth wheel roller 80-100 kN at OMC to achieve the desired
unconfined compressive strength and to form a layer of sub-base/base as per
Technical Specification Clauses 404.3 and 410.4.2.

4.17 Crusher Run Macadam Base


Providing crushed run stone aggregate greading conforming to table 400.20 depositing
on a prepared surface by hauling vehicles, spreading and mixing with a motor grader,
watering and compacting with a three wheel 80-100 kN static roller as per Technical
Specification Clause 411 to form a layer of sub-base/base

A) By mix-in-place method

I With 53 mm maximum size of aggregates

ii With 37.5 mm maximum size of aggregates

(B) By mixing plant method

I With 53 mm maximum size of aggregates

ii With 37.5 mm maximum size of aggregates

4.18 Brick Soling


Laying brick soling layer on prepared sub-grade with brick on end edging according to
lines, graded and cross-section shown on the drawing filling joints with sand and earth,
spreading 25 mm thick layer of earth over brick soling, watering and rolliing the same
with three wheel road roller 80-100 kN as per Technical Specification Clause 412

4.19 Stone Set Pavement


Providing and laying stone set pavement on prepared surface with sub-base 100 mm
thick compacted Granular Sub-base as per Clause 401.4 and base 75 mm thick
compacted water bound macadam grading 2 as per Clause 405.3. The 150 mm thick
hammer desired stones are laid in the herring one or stretched bond pattern. The
stones are compacted into the bedding sand of 40 mm over the WBM base bounded
by edge stone using suitable compacting device. The gaps are filled with fine sand
stone dust as per Technical Specification Clause 413.4

Chapter 5 - BASES AND SURFACE COURSES (BITUMINOUS)

5.1 Prime Coat

Page 66
Unit Rate
(Rs.)

Description

cum 1,372.00

cum 1,454.00

cum 832.00

cum 1,651.00

cum 1,707.00

cum 1,913.00

cum 1,830.00

sqm 571.00

sqm 747.00

MINOUS)

Page 67
Item
No.

I) Low porosity Description


Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface
of granular base including cleaning of road surface and spraying primer at the rate of
0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502

ii) Medium porosity


Providing and applying primer coat with Bitumen emulsion (SS-1) on prepared surface
of granular base including cleaning of road surface and spraying primer at the rate of
0.90- 1.2 kg/sqm using mechanical means as per Technical Specification Clause 502.

iii) High porosity

Providing and applying primer coat with Bitumen emulsion (SS-1) on prepared surface
of granular base including cleaning of road surface and spraying primer at the rate of
1.2-1.5 kg/sqm using mechanical means as per Technical Specification Clause 502.

5.2 Tack Coat


I) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion
distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous surface
cleaned with Hydraulic broom as per Technical Specification Clause 503.

ii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion
distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry
bituminous surface cleaned with Hydraulic broom as per Technical Specification
Clause 503.

iii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion
distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces
treated with primer & cleaned with Hydraulic broom as per Technical Specification
Clause 503.

iv) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion
pressure distributor at the rate of 0.30 to 0.35 kg per sqm on the prepared non-
bituminous surfaces (cement concrete pavement) cleaned with Hydraulic broom as per
Technical Specification Clause 503.

5.3 Bituminous Macadam

Providing and laying bituminous macadam with hot mix plant using crushed
aggregates of grading as per Table 500.4 premixed with bituminous binder,
transported to site upto a lead of 1000 m laid over a previously prepared surface with
paver finisher to the required grade, level and alignment and rolled to achieve the
desired compaction as per Technical Specification Clause 504.

5.4 Built-Up Spray Grout


Providing, laying and rolling of built-up spray grout layer over prepared base consisting
of a two layer composite construction of crushed coarse aggregates using motor
grader for aggregates. Key stone chips spreader may be used with application of
bituminous binder after each layer, and with key aggregates placed on top of the
second layer to serve as a base, conforming to the line, grades and cross-section
specified, the compacted layer thickness being 75 mm as per Technical Specification
Clause 505.

A By Manual Means

I Bitumen (S-90)

ii Bitumen (S-65)

Page 68
Unit Rate
(Rs.)

Description
sqm 46.00

sqm 57.00

sqm 73.00

sqm 12.00

sqm 15.00

sqm 15.00

sqm 17.00

cum 7,619.00

sqm 330.00

sqm 334.00

Page 69
Item
No.

B By Mechanical Means Description

5.5 Modified Penetration Macadam


Construction of penetration macadam over prepared base by providing a layer of
compacted crushed coarse aggregate using chips spreader with alternate applications
of bituminous binder and key aggregates and rolling with a three wheel 80-100 kN
static roller to achieve the desired degree of compaction as per Technical Specification
Clause 506.

A 50 mm thick
I) Bitumen (S-90)

B 75 mm thick

I) Bitumen (S-90)

ii) Bitumen (S-65)

5.6 Surface Dressing using Bituminous (Penetrations grade / modified bitumen)


Binder

Providing and laying surface dressing as wearing course consisting of a layer of


bituminous binder laid on the prepared surface, followed by a cover of crushed stone
aggregates of specified size and rolling with three wheel 80-100 kN static roller
including cleaning the road surface as per Technical Specification Clause 507.

A By Manual Means

Case – I: Nominal chipping size 13.2 mm

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

Case – II: Nominal chipping size 9.5 mm

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

B By Mechanical Means

Case – I: Nominal chipping size 13.2 mm

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

Page 70
Unit Rate
(Rs.)

Description sqm 311.00

sqm 204.00

sqm 254.00

sqm 256.00

sqm 90.00

sqm 91.00

sqm 86.00

sqm 91.00

sqm 79.00

sqm 80.00

sqm 75.00

sqm 80.00

sqm 76.00

sqm 83.00

Page 71
Item
No.

iii) (III)
Polymer Modified Bitumen Description

iv) (IV)
Crumb Rubber Modified Bitumen

Case – II: Nominal chipping size 9.5 mm

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen
5.7 Surface Dressing using Bitumen Emulsion

Providing and laying surface dressing as wearing course consisting of a layer of


bitumen emulsion laid on the prepared surface, followed by a cover of crushed stone
chippings of specified size and rolling with 80-100 kN roller including cleaning the road
surface as per Technical Specification Clause 507.

A By Manual Means

Case – I: Nominal aggregate size 13.2 mm

Case – II: Nominal chipping size 9.5 mm

B By Mechanical Means

Case – I: Nominal chipping size 13.2 mm

Case – II: Nominal chipping size 9.5 mm

5.8 Pre-coating Chips


Pre-coating of chips with 1 per cent of paving bitumen by weight of chips in a suitable
mixer duly heated to 160 degree C as per Technical Specification Clause 507.2.5

I) Bitumen (S-90)

ii) Bitumen (S-65)

5.9 20mm thick Open-Graded Premix Carpet using Bituminous (penetration


grade/modified bitumen) Binder

Providing, laying and rolling of open-graded premix carpet of 20 mm thickness


composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or
emulsion to required line, grade and level to serve as wearing course on a previously
prepared base, including mixing in a suitable plant, laying and rolling with a three
wheel 80-100 kN static roller capacity, finished to required level and grades to be
followed by seal coat of either Type A or Type B or Type C as per Technical
Specification Clause 508.

Case - I By Manual Means

I) Bitumen (S-90)

Page 72
Unit Rate
(Rs.)

Description sqm 78.00

sqm 85.00

sqm 72.00

sqm 74.00

sqm 69.00

sqm 74.00

sqm 106.00

sqm 96.00

sqm 98.00

sqm 89.00

cum 1,447.00

cum 1,465.00

sqm 160.00

Page 73
Item
No.

ii) Bitumen (S-65) Description

iii) Polymer Modified Bitumen

iv) Crumb Rubber Modified Bitumen

Case - II By Mechanical Means

I) Bitumen (S-90)

ii) Bitumen (S-65)

iii) Polymer Modified Bitumen

iv) Crumb Rubber Modified Bitumen

5.10 20 mm thick Open Graded Premix Carpet using Bitumen Emulsion as per
Technical Specification Clause 508.2

5.11 Mix Seal Surfacing

Providing, laying and rolling of close-graded premix surfacing material of 20 mm


thickness composed of 11.2 mm to 0.9 mm (Type-A) or 13.2 mm to 0.9 mm (Type-B)
aggregates using penetration grade bitumen to required line, grade and level to serve
as wearing course on a previously prepared base, including mixing in a suitable plant,
laying and rolling with a three wheel 8-10 kN static roller and finishing to required level
and grades as per Technical Specification Clause 509

By Manual Means
TType A
y
I) (I)
pBitumen (S-90)
ii) e
(II)
Bitumen (S-65)
iii) A
(III)
Polymer Modified Bitumen
iv) (IV)
Crumb Rubber Modified Bitumen

TType B
y
I) (I)
pBitumen (S-90)
ii) e
(II)
Bitumen (S-65)
iii) B
(III)
Polymer Modified Bitumen
iv) (IV)
Crumb Rubber Modified Bitumen

By Mechanical Means

T
Type A
y
I) p
(I)
Bitumen (S-90)
e
ii) (II)
Bitumen (S-65)
A
iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

Page 74
Unit Rate
(Rs.)

Description sqm 162.00

sqm 155.00

sqm 163.00

sqm 153.00

sqm 155.00

sqm 48.00

sqm 56.00

sqm 160.00

sqm 210.00
sqm 213.00
sqm 202.00
sqm 214.00

sqm 193.00
sqm 195.00
sqm 186.00
sqm 196.00

sqm 186.00

sqm 188.00

sqm 178.00

sqm 190.00

Page 75
Item
No.

T
Type B Description
y
I) p
(I)
Bitumen (S-90)
e
ii) (II)
Bitumen (S-65)
B
iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

5.12 Seal Coat

Providing and laying seal coat sealing the voids in a bituminous surface laid to the
specified levels, grade and cross fall using Type A, Type B and Type C as per Technical
Specification Clause 510

A By Manual Means

Case - I : Type A

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

(V)

Case - II : Type B

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

(V)

Case - III : Type C

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii0 (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

B. By Mechanical Means

Case - I : Type A

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii) (III)
Polymer Modified Bitumen

Page 76
Unit Rate
(Rs.)

Description

sqm 169.00

sqm 171.00

sqm 162.00

sqm 172.00

sqm 78.00

sqm 79.00

sqm 74.00

sqm 80.00

sqm 53.00

sqm 50.00

sqm 49.00

sqm 58.00

sqm 59.00

sqm 60.00

sqm 57.00

sqm 60.00

sqm 78.00

sqm 79.00

sqm 74.00

Page 77
Item
No.

iv) (IV)
Crumb Rubber Modified Bitumen Description

Case - II : Type B

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

Case - III : Type C

I) (I)
Bitumen (S-90)

ii) (II)
Bitumen (S-65)

iii) (III)
Polymer Modified Bitumen

iv) (IV)
Crumb Rubber Modified Bitumen

Chapter 6 - CEMENT CONCRETE PAVEMENT


6.1 Granual Sub-base

Rate as per item No.4.1 of Chapter 4

6.2 Lime Treated Soil

Rate as per item No.4.5 of Chapter 4


6.3 Water Bound Macadam (WBM) - Sub-base
(A) By Manual Means
As per item No.4.7 of Chapter 4
(B) By Mechnical Means
As per item No.4.7 of Chapter 4
6.4 Cement concrete pavement

Construction of un reinforced, dowel jointed at expansion and construction joint


only,plain cement concrete pavement, thickness as per design,over a prepared sub
base,with 43 grade cement or any other type as per clause 1501.2.2 M30 grade
,coarse and fine

Page 78
Unit Rate
(Rs.)

Description sqm 80.00

sqm 50.00

sqm 51.00

sqm 48.00

sqm 55.00

sqm 59.00

sqm 60.00

sqm 57.00

sqm 60.00

cum 6,837.00

Page 79
Item
No.

6.5 Roller Compacted Concrete Pavement Description

Construction of Roller Compacted Concrete Pavement (RCCP) with coarse and fine
aggregates conforming to IS:383, the size of coarse aggregate not exceeding 25 mm
with minimum aggregate cement ratio of 5:1 mm and with minimum cemnt content of
310 kg per cum, aggregate gradation to be as per Table 602.2 after blending, mixing in
concrete mixer at optimum moisture content, transporting to site, laying with wheel
barrows or steel pans or with mechanical paver, compacting with 80-100 kN smooth
wheel, tandem vibratory roller, to achieve, the designed flexural strength, finishing and
curing as per drawings and Technical Specification Clause 1502

Note: Carraige of c.c block to site of is payable seperately as per chapter of carriage of
materials from manufacturing site to the site of work

6.6 Rectangular Concrete Block Pavement

Manufacturing, laying of cement concrete blocks of size 0.450 m x 0.300 m x 0.15 m of


Cement Concrete (C.C.) M30 garde and spreading 25 mm thick sand under neath and
filling joints with sand on existing W.B.M. base as per Technical Specification Clause
1503.

6.8 Inter locking concrete Block pavement

I) dProviding and laying interlocking concrete block pavement having thickness 80mm as
iper echnical specification clause 1504
n
ii) d
gProviding and laying interlocking concrete block pavement having thickness 60mm as
iper echnical specification clause 1504
n
g
Note: I Carriage of interlocking blocks is payable seperately as per Chapter of carriage
of material from manufacturing site to the site of work.
ii Edge blocks may be cast-in situ. Brick masonary toe wall or cc block
300mmx300mmx150mm or any other shape can also be used and their cost shall be
analysed/included accordingly.
iii The rates for sub-grade, sub-base course can be taken from Chapters 3 and 4
Chapter 7 - CAUSEWAY AND SUBMERSIBLE BRIDGES

7.1 Construction of Cut-off Walls/Head Walls

I Earthwork in excavation for structures as per drawing and technical specification


Clause 305.
Rate as per item No.11.1 of Chapter 11
ii Plain cement concrete M15 grade
Rate as per item No.11.4 (ii) of Chapter 11
iii) Brick masonry in cement mortar 1:4
Rate as per item No.11.5 (ii) of Chapter 11
iv) Stone masonry in cement mortar 1:4
Rate as per item No.11.6 (ii) of Chapter 11
v Providing P.C.C M20 architectural coping on top of wall
Rate as per item No.12.13 of Chapter 12
7.2 Preparation of Subgrade
Rate as per item No.3.15 of Chapter 3
7.3 Granular Sub-base

Page 80
Unit Rate
(Rs.)

Description

cum 6,008.00

sqm 1,436.00

sqm 932.00

sqm 833.00

cum

cum

cum

cum

cum

Page 81
Item
No.

Rate as per item No.4.1 of Chapter 4 Description


7.4 W.B.M. Base Course
Rate as per item No.4.7 of Chapter 4
7.5 Cement Concrete Slab
Rate as per item No.6.4 of Chapter 6
7.6 Providing and Laying Apron with Stone Boulders as per Drawings & Technical
Specification Clause 1301

Rate as per item No.14.1 of Chapter 14

ii Providing and Laying of Boulder Apron Laid in Wire Crates as per Drawing and
Technnical Specification Clause 1301
Rate as per item No.14.2 of Chapter 14
iii) Providing and Laying of Apron with Cement Concrete Blocks as per Drawing and
Technical Specification Clause 1301

Rate as per item No.14.3 of Chapter 14


7.7 Guide Posts

Construction of R.C.C. guide posts of 250 mm dia, M25 grade as per drawing and
technical specification Clause 1401.6

Rate as per item No.8.8 of Chapter 8

7.8 Bedding for Causeway

I Type A (concrete cradle) Bedding Clause 1402.5

As per item No.9.2 of Chapter 9

ii Type B (first class) Bedding Clause 1402.5

As per item No.9.2 of Chapter 9

7.9 Laying Reinforced Cement Concrete Pipe NP3 as per drawing and technical
specification Clause 1402.6

As per item No.9.3 of Chapter 9

7.10 Laying Reinforced Cement Concrete Pipe NP4 as per technical specification Clause
1402.6
As per item No.9.4 of Chapter 9

Chapter 8 - HILL ROADS

8.1 Site Clearance


8.2 Setting Out
1) Construction of reference pillars as per Fig. 1600.1 (b) as per drawing and Technical
Specification Clause 1602.1

2) Construction of back piller as per Fig. 1600.1( c) as per drawing and Technical
Specification Clause 1602.3

3) Construction of Job pillers as per Fig. 1600.1 (d) and Technical Specification Clause
1602.4

8.3 Earthwork in Hill Road


Page 82
Unit Rate
(Rs.)

Description cum

cum

cum

cum

cum

cum

cum

cum

cum

per Km 4,268.00

per Km 9,814.00

each 423.00

Page 83
Item
No.

I) Excavation in Hilly Areas in Soil by manual means. Description


A) Excavation in soil in Hilly Area by manual means including cutting and trimming of side
slopes and disposing of excavated earth with a lift upto 1.5 m and a lead upto 20 m as
per drawing and Technical Specification Clause 1603.1 (Manual means should be use
where machines can not be deployed due to site condition)

B) Extra for Every Additional Lift of 1.5 m or Part thereof


ii) Excavation in Hilly Areas in Soil by mechanical means
A) Excavation in soil in Hilly Area by mechanical means including cutting and trimming of
side slopes and disposing of excavated earth with a lift upto 1.5 m and a lead upto 20
m as per Technical Specification Clause 1603.1

B) Extra for Every Additional Lift of 1.5 m or Part thereof


iii) Excavation in Hilly Area in Ordinary Rock by manual means

A) Excavation in ordinary rock using manual means including loading in a truck and
carrying of excavated material to embankment site with a lift upto 1.5 m and lead upto
20 m as per Clause 1603.2. (Manual means should be use where machines can not be
deployed due to site condition)

B) Extra for Every Additional Lift of 1.5 m or Part thereof

iv) Excavation in Hilly Areas in Ordinary Rock by mechanical means not requiring blasting

A) Excavation in hilly area in ordinary rock not requiring blasting by mechanical means
including cutting and trimming of slopes and disposal of cut material with a lift upto 1.5
m and lead upto 20 m as per Clause 1603.2.

v) Excavation in Hilly Areas in Hard Rock requiring blasting


A) Excavation in hilly areas in hard rock requiring blasting, by mechanical means, lift upto
1.5 m and disposal of excavated rock upto a lead of 20 m as per Clause 1603.2.

B) Extra for Every Additional Lift of 1.5 m or Part thereof

vi) Excavation in Hard Rock (blasting prohibited)


Excavation for roadway in hard rock (blasting prohibited) with rock breakers including
breaking rock, loading in tippers and disposal with a lift upto 1.5 m and lead upto 200
metres, trimming bottom and side slopes in accordance with requirements of lines,
grades and cross- sections as per Technical Specification Clause 302.3.5

a) Manual Means
b) Mechanical Means
8.4 Retaining Walls / Breast Walls
Construction of retaining walls/breast walls in cement mortar 1:5 as per drawing and
technical specifications Clause 1604

I) Earthwork in excavation for structures


Rate as per item No.11.1 of Chapter 11
ii) Plain cement concrete M 10 grade
Rate as per item No.11.4 of Chapter 11
iii) Stone masonry in cement mortar 1:5
Rate as per item No. 12.4 (III) (iii) of Chapter 12
iv) Pointing with cement mortar 1:3
Rate as per item No.12.2 of Chapter 12

Page 84
Unit Rate
(Rs.)

Description
cum 88.00

cum 9.00

cum 107.00

cum 9.00

cum 195.00

cum 15.00

cum 156.00

cum 297.00

cum 18.00

cum 489.00
cum 432.00

cum

cum

cum

sqm

Page 85
Item
No.

v) Description
Providing P.C.C. M 20 architectural coping on top of retaining wall/breast wall
Rate as per item No.12.13 of Chapter 12
vi) Filter material behind retaining wall / breast wall as per Specification 1204.3.8 in a
width of 600 m

Rate as per item No. 12.11 of Chapter 12

vii) Back filling behind retaining wall/breast wall


Rate as per item No. 12.10 of Chapter 12

8.5 Construction of Hill side Drain

Construction of Hill side drain in accordance with the requrement of


of specification true to lines and grades. Dimensions and other particulars as per
drawing and technical specification. Clause 1606.1

I) Earthwork in excavation for structures as per drawing and technical specification.

Rate as per item no 11.1 of chapter 11

ii) Plain cement concrete M10 grade

Rate as per item no 11.4of chapter 11

iii) Stone masonary in cement morter 1:5

Rate as per item no 12.4(iii) (iii) of chapter 12

(iv) Plain cement concrete M15 grade

Rate as per item 11.4 of chapter 11

(v) Cement plaster 15 mm thick 1:4 on stone masonary

Rate as per item no 12.3 of chapter 12

(vi) Providing P.C.C. M 20 Architectural coping on top of wall


Rate as per item no.12.13 of chapter 12
Rate per m length (I+II+III+IV+V+VI)
Note:
1.Quantities of material/work shall be as per Design and Drawing.

2.Earth work in excavation may be taken as per site conditions.


It may coprise of a number of sub-items depending upon the type
typy of soil/rock.

8.6 Construction of catch water/Intercepting drain.

Construction of catch water/Intercepting drain in Random ruble masonary in 1:5


cement morter true to the specified lines grades lavel and dimensions as per the
requirements of the specification Clause 1606.2

Unit=1M

Page 86
Unit Rate
(Rs.)

Description
m

cum

cum

cum

cum

cum

cum

cum

cum
m

Page 87
Item
No.

I) Earthwork in excavation for structure as per drawing andDescription


technical specificatuion

Rate as per item no 11.2 of chapter 11

ii) Plain cement concrete M10 grade


Rate as per 11.4 of chapter 11.
iii) Stone masonary in cement morter 1:5
Rateas per item no 12.4 (III) (iii) of chapter 12
iv) Plain cement cioncrete M 15 grade
Rate as per 11.4 of chapter 11.
v) Cement plaster 15 mm thick 1:4 on stone masonary
Rate as per 12.3 of chapter 12.
vi) Providing P.C.C. M20 architectural coping on top of wall
Rate as per item No. 12.3 of chapter 12

Note: 1. Quantities of material/work shall beas per design and drawings.


2. Earth work in excavation may be taken as per site condition.It may comprise of a
number of sub-items depending upon the type of soil/rock encountered.

8.7 Construction of Scupper

Construction of scupper with dry stone masonry as per drawing and technical
specifications as per Clause 1606.5.

8.8 Construction of RCC guide posts of 250 mm dia M15 grade cast-in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of vertical RCC posts not to
exceed 1 in 500 as per drawing and Technical Specification Clause 1608.2

I) Earth work in excavation for structures

Rates as per item No. 11.1 of Chapter 11

ii) RCC M15 grade


Rate as per item No. 11.4 of Chapter 11
iii) HYSD steel bars

Rate as per item No. 12.6 of Chapter 12


iv) Painting two coats including prime coat on new concrete surface

Rate as per item No.10.5 of Chapter 10


8.9 Providing edge stones on valley side of formation as per drawing and Technical
Specification Clause 1608.2.6

8.10 Turfing with Sods

Furnishing and laying of the live sods of perennial turf forming grass on embankment
slope, verges or other locations shown on the drawing or as directed by the Engineer
including preparation of ground, stacking the sods and watering as per Clause 309
8.11 Seeding and Mulching

Preparation of seed bed on previously laid top soil, furnishing and placing of seeds,
fertilizer, multching material, applying bituminous emulsion at the rate of 0.23 l per sqm
and laying and fixing jute netting, including watering for 3 months all as per Clause
310.

Page 88
Unit Rate
(Rs.)

Description

cum

cum

cum

cum

sqm

cum

Running m 14,976.00

cum

cum

sqm
m 179.00

sqm 16.00

sqm 282.00

Page 89
Item
No.

Chapter 9 - PIPE CULVERTS Description

9.1 Excavation for Structures

Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and
technical specification Clause 1104 includding setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides and bottom
and backfilling with approved material.

Rate as per item No.11.1 of Chapter 11

9.2 B
Bedding of pipe
e
(I) Type A (Concrete Cradle) Bedding
d
d
Laying
i concrete cradle bedding with M15 Grade Cement Concrete as per Clause 1105
(i)
n
g
Rate as per Item No.11.4 (II)(i) of Chapter 11
f
(ii) o
Type B (First Class) Bedding
r
Laying (First Class) bedding on well compacted sand, moorum or approved granular
P
material as per Clause 1105 (ii)
i
p
I) Rate as per Item No.11.2 of Chapter 11
e
ii) Granular Material

9.3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in
Single Row

Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar
1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets Clause 1106.

1200 mm dia
1000 mm dia

600 mm dia
9.4 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design in
Single Row

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
bedding of granular material in single row including fixing collar with cement mortar
1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets Clause 1106.

1200 mm dia
9.5 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design in
Double Row
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in double row including fixing collar with cement mortar
1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets as per Clause 1106.

A) 1200 mm dia

Page 90
Unit Rate
(Rs.)

Description

cum

cum 4,908.00

cum 903.00

cum 857.00

m 8,754.00
m 6,225.00

m 3,300.00

m 10,808.00

m 17,544.00

Page 91
Item
No.

B) 1000 mm dia Description

9.6 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per Design in
Double Row

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
bedding of granular material in double row including fixing collar with cement mortar
1:2 but excluding excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets as per Clause 1106.

A) 1200 mm dia

B) 1000 mm dia

9.7 Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course below open
foundation of Head walls as per drawings & Technical Specification Clause 1109

Rate as per item No.11.4 of Chapter 11

9.8 Brick Masonry Work in cement mortar in foundation of Head walls complete
exculding pointing and plastering as per drawing and technical specification
Clause 1109

A Brick Masonry in 1:4 cement mortar

Rate as per item No.11.5 (ii) Chapter 11

B In cement-lime mortar (1:0.5:4.5)

Rate as per item No.11.5 (iii) Chapter 11

9.9 Stone Masonry Work in cement mortar in foundation of Head walls complete as
per drawing and technical specification Clasue 1109

A In 1:4 cement mortar

Rate as per item No.11.6 (II) (ii) Chapter 11

B In cement-lime mortar (1:0.5:4.5)

Rate as per item No.11.6 (II) (iii) Chapter 11

9.10 Pointing with Cement Mortar (1:3) on brickwork as per technical specification Clause
613.3

Rate as per item No.12.2 of Chapter 12


9.11 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in substructure as per
technical specification

Rate as per item No.12.3 of Chapter 12


9.12 Backfilling in Foundation Trenches as per drawing and technical specification Clause
1108

Rate as per Item No.11.2 of Chapter 11


9.13 Providing PCC M20 Architectural Coping on the top of wing wall, return wall etc.
complete as per drawing and technical specification Clause 615

Rate as per Item No.12.13 of Chapter 12


Chapter 10 - TRAFFIC SIGNS, MARKINGS AND OTHER ROAD APPURTENANCES

Page 92
Unit Rate
(Rs.)

Description m 13,162.00

m 21,651.00

m 17,694.00

cum

cum

cum

cum

cum

sqm

sqm

cum

m
R ROAD APPURTENANCES

Page 93
Item
No.

10.1 Printing New Letters and Figures of any Shade Description

Printing new letter and figures of any shade with synthetic enamel paint black or any
other approved colour to give an even shade as per drawings and Technical
Specification Clause 1701

I Hindi (Matras commas and the like not to be measured and paid for. Half letters shall
be counted as half only)

ii English and Roman

10.2 Traffic Signs

A Retro-reflectorised Traffic Signs

(!) Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign
as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause
1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle
iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with M15 grade cement concrete 450 mm x 450 mm x 600 mm,
600 mm below ground level as per drawings and Technical Specification Clause 801

(I) 90 cm equilateral tringle

(ii)60 cm equilateral tringle

(iii)60 cm circular

(iv)80 cmx 60 cm rectangular

(v)60 cmx45 cm rectangular

(vi)60 cmx60 cm square

vii)90 cm side octagon

-2 Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign


as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 1.5 mm thick supported on GI pipe 50 mm dia
firmly fixed to the ground by means of properly designed foundation with M-15 grade
cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as per
drawings and Technical Specification Clause 1701

(I) 90 cm equilateral tringle

(ii)60 cm equilateral tringle

(iii)60 cm circular

Page 94
Unit Rate
(Rs.)

Description

per cm 0.47
height per
letter

per cm 0.32
height per
letter

each

each 5,731.00

each 3,830.00

each 5,100.00

each 7,044.00

each 4,971.00

each 5,860.00

each 8,939.00

each 5,691.00

each 3,663.00

each 4,991.00

Page 95
Item
No.

(iv)80 cmx 60 cm rectangular Description

(v)60 cmx 45 cm rectangular

(vi)60 cmx60 cm square

(vii)90 cm side octagon

-3 Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign


as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 1.5 mm thick supported on RCC Post 100
mm x 100 mm firmly fixed to the ground by means of properly designed foundation with
M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level
as per approved drawing Clause 1701

(I) 90 cm equilateral tringle


(ii)60 cm equilateral tringle
(iii)60 cm circular
(iv)80 cmx 60 cm rectangular
(v)60 cmx 45 cm rectangular

(vi)60 cmx60 cm square

(vii)90 cm side octagon


Please ensure that area of aluminium plate of required size is entered in the analysis
item

(B) Semi Reflective Traffic Signs


Providing and fixing of semi reflective cautionary, mandatory and informatory sign
board as per IRC:67 made of 1.5 mm thick MS Sheet duly stove white colour in front
and gray colour on back with red reflective border of 65 mm width and required letters
and figures with reflective tape engineering grade as per Clause 1701.3.9 of MORD for
Rural Roads of required shade and colour supported and welded on 47mm x 47 mm x
12 SWG sheet tube firmly fixed to the ground by mean of properly designed
foundations with M-15 grade cement concrete 450x450x600 mm, 600 mm below
ground level as per approved drawing Clause 1701.2.2

(I) 90 cm equilateral tringle

(ii)60 cm equilateral tringle


(iii)60 cm circular
(iv)80 cmx 60 cm rectangular

(v)60 cmx 45 cm rectangular


(vi)60 cmx60 cm square
(vii)90 cm side octagon
10.3 Direction and Place Identification signs upto 0.9 sqm size board

A Retro-reflectorised Traffic Signs


(I) Providing and erecting direction and place identification retro-reflectorised sign as per
IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed
over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a
mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means of
properly designed foundation with M-15 grade cement concrete 450 x 450 x 600 mm,
600 mm below ground level as per approved drawing and Technical Specification
Clause 1701

Page 96
Unit Rate
(Rs.)

Description each 7,050.00

each 4,855.00

each 5,796.00

each 10,102.00

each 5,246.00
each 3,283.00
each 4,568.00
each 6,562.00
each 4,436.00

each 5,347.00

each 8,505.00

each 3,849.00

each 2,472.00
each 3,373.00
each 4,772.00

each 3,281.00
each 3,920.00
each 6,846.00

sqm 12,800.00

Page 97
Item
No.

(ii) Providing and erecting direction and place identification Description


retro-reflectorised sign as per
IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed
over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on 2
inch dia GI Pipe firmly fixed to the ground by means of properly designed foundation
with M-15 grade cement concrete 450 x 450 x 600 mm, 600 mm below ground level as
per approved drawing and Tehnical Specification Clause 1701.

(iii) Providing and erecting direction and place identification retro-reflectorised sign as per
IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed
over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on
RCC Post 100 mm x 100 mm firmly fixed to the ground by means of properly designed
foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600 mm below
ground level as per approved drawing and Technical Specification Clause 1701

B Semi-Reflective Traffic signs


Direction and place indentification signs up to 0.9 sqm size board

(I) Providing and erecting direction and place identifications of semi reflective sign boards
as per IRC:67 made of 2 mm thick M.S. Sheet duly stove enameled paint in white
colour in front and grey colour on back with red reflective border of 70 mm width and
required message, letters, figures with reflective engineering grade tape as per MORD
specifications of required shade and colour. Supported and welded on 47 mm x 47mm
of 12 SWG Square tube of 3050 mm height duly strengthened by 25 mm x 5 mm M/s
flat iron on edges on back firmly fixed to the ground by means of properly designed
foundations with M-15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm
below ground level as per approved drawing and Technical Specification Clause 1701

10.4 Direction and Place Identification signs with size more than 0.9 sqm size board
A Retro-reflectorised Traffic Signs
(I) Providing and erecting direction and place identification retro-\reflectorised sign as per
IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed
over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on mild
steel angle iron posts 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the ground by
means of properly designed foundation with M-15 grade cement concrete 450 mm x
450 mm x 600 mm, 600 mm below ground level as per approved drawing and
Technical Specification Clause 1701

(ii) Providing and erecting direction and place identification retro-reflectorised sign as per
IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed
over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on dia
GI Pipe firmly fixed to the ground by means of properly designed foundation with M-15
grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level as
per approved drawing and Technical Specification Clause 1701

(iii) Providing and erecting direction and place identification retro- reflectorised sign as per
IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3, fixed
over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported on RCC
Posts 100 mm x 100 mm firmly fixed to the ground by means of properly designed
foundation with M 15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm
below ground level as per approved drawing and Technical Specification Clause 1701

B Semi-Reflective Traffic Signs

Page 98
Unit Rate
(Rs.)

Description sqm 12,466.00

sqm 12,153.00

sqm 9,604.00

sqm 13,144.00

sqm 12,797.00

sqm 12,016.00

Page 99
Item
No.

Description
Direction and place identification signs more than 0.90 sqm sign board

Providing and erecting direction and place identification of semi reflective sign boards
as per IRC-67 made of 2 mm thick M.S. Sheet duly stove enameled paint white colour
in front and grey colour on back with reflective border of 70 mm width and required
message, letters, figures with reflective tape of engineering grade as per MORD
specifications of required shade and colour. Supported and welded on two nos. 47 mm
x 47 mm of 12 SWG square tube of 3050 mm height duly strengthened by 25 mm x 5
mm MS flat iron on edges on back firmly fixed to the ground by means of properly
designed foundations with M-15 grade cement concrete 450 mm x 450 mm x 600 mm,
600 mm below ground level as per approved drawing and Technical Specification
Clause 1701

10.5 Painting Two Coats on New Concrete Surfaces

Painting two coats including primer coat after filling the surface with synthetic enamel
paint in all shades on new, plastered / concrete surfaces as per drawing and Technical
Specification Clause 1701

10.6 Painting on Steel Surfaces

Providing and applying two coats of ready mix paint including primer coat of approved
brand on steel surface after through cleaning of surface to give an even shade as per
drawing and Technical Specification Clause 1701

10.7 Painting on Concrete/Steel Surfaces with Epoxy


Painting two coats including prime coat with epoxy paint of approved brand on
concrete/steel surfaces after through cleaning of surface to give an even shade as per
drawing and Technical Specification Clause 1701

10.8 Painting lines, Dashes, Arrows, etc. on Road in Two Coats on New Work
Painting lines, dashes, arrows, etc. on roads in two coats on new work with ready
mixed road marking paint conforming to IS:164 on bituminous/concrete surface,
including cleaning the surface of all dirt, dust and other foreign matter, demarcation at
site and traffic control as per drawing and Technical Specification Clause 1702

10.9 Painting lines, Dashes, Arrows, etc. on Roads in Two Coats on Old Work

Painting lines, dashes, arrows, etc. on roads in two coats on old work with ready mixed
road marking paint conforming to IS:164 on bituminous/concrete surface, including
cleaning the surface of all dirt, dust and other foreign matter, demarcation at site and
traffic control as per drawing and technical specification Clause 1702

10.10 Kilometre Stone


Reinforced cement concrete M15 grade kilometre stone/local stone of standard design
as per IRC:8 fixing in position including painting and printing, etc as per drawing and
Technical Specification Clause 1703

I) 5th Kilometre Stone (precast)

ii) Ordinary Kilometer Stone (Precast)

iii) 200 m stone (precast)

10.11 Boundary Pillar

Page 100
Unit Rate
(Rs.)

Description

sqm 9,519.00

sqm 45.00

sqm 49.00

sqm 86.00

sqm 50.00

sqm 38.00

each 3,192.00

each 1,940.00

each 531.00

Page 101
Item
No.

Reinforced cement concrete M15 grade boundary pillars/localDescription


stone of standard design
as per IRC:25, fixed in position including finishing and lettering but excluding painting
as per drawing and Technical Specification Clause 1704

10.12 G.I Barbed Wire Fencing 1.2 m high

Providing and fixing 1.2 m high GI barbed wire fencing with 1.8 m RCC posts 150 mm
x 150 mm placed every 3 m centre-to-centre founded in M15 grade cement concrete,
0.6 m below ground level, every 15th post, last but one end post and corner post shall
be strutted on both sides and end post on one side only and provided with 9 horizontal
lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn
buckles etc. complete as per Clause 1705.

10.13 G.I Barbed Wire Fencing 1.8 m high


Providing and fixing 1.8 m high GI barbed wire fencing with 2.4 m RCC M15 grade 150
mm x 150 mm concrete post placed every 3 m centre-to-centre founded in M15 grade
cement concrete, 0.6 m below ground level, every 15th post, last but one end post and
corner post shall be strutted on both sides and end post on one side only and provided
with 12 horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI
staples, turn buckles etc. complete as per Clause 1705.

10.14 Tubular Steel Railing on Medium Weight Steel Channel (ISMC series) 100 mm x
50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on
medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 m high above
ground, 2 m centre-to-centre, complete as per approved drawings Clause 1706

10.15 Tubular Steel Railing on Precast RCC posts, 1.2 m high above Ground Level

Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on
precast M-20 grade RCC vertical posts 175 mm x 175 mm x 1.8 m high (1.2 m above
Gl) with 3 holes 50 mm dia for pipe, fixed 2 m centre-to- centre complete as per
approved drawings Clause 1706

10.16 Providing and Fixing 'Logo' of PMGSY Project

Providing and fixing of typical PMGSY informatory sign board with Logo as per MORD
specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle plate duly
welded with MS flat iron 25mm x 5m size on back on edges. The lower plate will be
welded with MS angle iron frame of 25mm x 25mm x 5mm. The angle iron frame of the
lower most plate and flat iron frame of middle plate will be welded to 2 nos. 75mm x 75
mm of 12 SWG sheet tubes posts duly embedded in cement concrete M-15 grade
blocks of 450mm x 450mm x 600mm, 600mm below ground level. The top most
diamond plate will be welded to middle plate by 47mm x 47mm of 12 SWG steel plate
tube. All M.S. will be stove enameled on both sides. Lettering and printing arrows,
border etc. will be painted with ready mixed synthetic enamel paint of superior quality
in required shade and colour. All sections of framed posts and steel tube will be
painted with primer and two coats of epoxy paint as per drawing Clause 1701 and
Annexure 1700.1

10.17 Traffic Cone

Provision of red fluorescent with white reflective sleeve traffic cone made of Low
Density Polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and a
height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS:873

Page 102
Unit Rate
(Rs.)

Description each 447.00

Running m 240.00

Running m 417.00

Running m 2,128.00

Running m 1,183.00

each 19,477.00

each 639.00

Page 103
Item
No.

10.18 Rumble Strips Description

Provision of 15 n0s.rumble strips covered with premix bituminous carpet,15.2 mm high


at centre,250mm wide placed at 1m centre to centre at approved location to control
speed, marked with white strips of road marking paint.

The rate per sqm of premix carpet and road marking may be adopted from Chapters
5&10 respectively for the quantities calculated from approved drawings.
10.19 Safety Device and sign in Construction Zones

Provision and fixing of traffic sign for limited period at a suitable location in construction
zone comprising of warning zone,approach transition zone,working zoneand terminal
transition zone with a minimunm distance of 2-3 m from the edgeof the carraige

Following types of signs are required to be fixed in construction zones for safety of
traffic.

a) Diversion one km ahead

b) Traffic sign ahead

c) Road ahead closed

d)Men at work

e)Road narrow

f)Un even road

g)slipery road

h)Loose chipping

I)Diversion

J)Do not enter

k)Road closed

l)Stop

k)Slow

Speed limit

Note: The rate for traffic signs are already worked out and given elsewhere in this
chapter.The same may be adopted

10.20 Road Markers/Road Stud with Lens Reflector


Providing and fixing of road stud 100 x 100 mm die cast in aluminium, resistant to
corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or
asphaltic surface by drilling holes 30 mm upto a depth of 600 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per BS:873 (Part 4) 1973.

Chapter 11 - FOUNDATION

Page 104
Unit Rate
(Rs.)

Description

each 397.00

Page 105
Item
No.

11.1 Excavation for Structures Description

Earthwork in excavation for structures as per drawing and technical specifications


Clause 305.1 including setting out, construction of shoring and bracing, removal of
stumps and other deleterious material and disposal upto a lead of 50 m, dressing of
sides and bottom and backfilling in trenches with excavated suitable material.

I Ordinary soil

Upto 3 m depth
3 m to 6 m depth

II Ordinary rock (not requiring blasting)

Upto 3 m depth

III Hard rock (requiring blasting)

IV Hard rock (blasting prohibited)

V Marshy soil

11.2 Fillling in foundation trenches as per drawing and technical specification Clause
305.3.9

I Sand filling

ii Earth filling (For marshy soil)

11.3 Filling annular space around footing in rock as per technical specification
Clause 1203.4.3.

P.C.C grade M 15
A. With crushed Stone
B With natural Gravel
11.4 Providing concrete for plain/reinforced concrete in open foundations complete as per
drawings and technical specifications Clause 802, 803, 1202 & 1203

A. With crushed stone.


I P.C.C grade M 10
Nominal mix 1:3:6
Nominal mix 1:3.6 (Hand mixing)
II P.C.C grade M 15
Nominal mix (1:2.5:5)
Nominal mix 1:2.5:5 (Hand mixing)
III P.C.C. grade M 20
Nominal mix (1:2:4)
Nominal mix 1:2:4 (Hand mixed)
IV R.C.C grade M 20
V R.C.C. grade M 25
B. With Natural Gravel
I C
P.C.C Grade M 10

Page 106
Unit Rate
(Rs.)

Description

cum 61.00
cum 89.00

cum 98.00

cum 262.00

cum 353.00

cum 283.00

cum 903.00

cum 97.00

cum 4,636.00
cum 4,586.00

cum 4,898.00
cum 4,870.00

cum 4,908.00
cum 4,880.00

cum 5,654.00
cum 5,626.00
cum 5,990.00
cum 6,526.00

Page 107
Item
No.

Nominal mix 1:3:6 Description

Nominal mix 1:3:6 (Hand mixing)


II C
P.C.C Grade M15
Nominal mix 1:2.5:5
Nominal mix 1:2.5:5 (Hand mixing)
III C
P.C.C Grade M 20
Nominal mix (1:2:4)
Nominal mix 1:2:4 (Hand mixed)
IV R.C.C. M 20
V R.C.C. M 25
11.5 Brick masonry work in cement mortar in foundation complete excluding pointing and
plastering as per drawing and technical specifications Clauses 600, 1202 & 1203
I. Brick masonry in 1:3 cement mortar

ii Brick masonry in 1:4 cement mortar

iii Brick masonry in cement-lime-mortar (1:0.5:4.5)

11.6 Stone masonry work in cement mortar in foundation complete as per drawing and
technical specifications Clauses 702, 704, 1202 & 1203.

I Coursed rubble masonry (1st sort)

In 1:3 cement mortar

In 1:4 cement mortar

in 1:6 Cement morter

II Coursed rubble masonry (2nd sort)

In 1:3 cement mortar

In 1:4 cement mortar

in 1:6 Cement morter

III Random Rubble Masonry

In 1:3 cement mortar

In cement mortar 1:4

in 1:6 Cement morter

11.7 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per
drawings and technical specifications Clauses 1000 and 1202

11.8 Supplying, fitting and placingTMT bar reinforcement in foundation complete as per
drawings and technical specifications Clauses 1000 and 1202

Page 108
Unit Rate
(Rs.)

Description cum 4,725.00


cum 4,698.00

cum 4,767.00
cum 4,739.00

cum 5,492.00
cum 5,465.00
cum 5,828.00
cum 6,365.00

cum 5,585.00

cum 5,047.00

cum 5,590.00

cum 3,161.00

cum 2,936.00

cum 2,605.00

cum 3,209.00

cum 2,794.00

cum 2,550.00

cum 2,977.00

cum 2,844.00

cum 2,456.00

t 64,562.00

t 64,863.00

Page 109
Item
No.

11.9 Description
Supplying, fitting and placing MS bar reinforcement in foundation complete as per
drawings and technical specifications Clauses 1000 and 1202

Chapter 12 - SUBSTRUCTURE

12.1 Brick masonry work in cement mortar in substructure complete excepting


pointing and plastering, as per drawing and technical specification Clauses 602,
603, 604, 1202 & 1204

I In 1:3 cement mortar

ii In 1:4 Cement mortar

iii In 1:5 cement mortar

12.2 Pointing with cement mortar (1:3) on brickwork as per drawing and technical
specification Clauses 613.3 and 1204

12.3 Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per
technical specification Clauses 613.4 & 1204

12.4 Stone masonry in cement mortar for substructure complete as per drawing & technical
specification Clauses 702, 704, 1202 and 1204

I Coursed rubble masonry (1st sort)

In 1:3 cement mortar

In 1:4 cement mortar

In cement mortar (1:5)

In 1:6 Cement morter

II Coursed Rubble masonry (2nd sort)

In cement mortar (1:3)

In 1:4 cement mortar

In cement mortar (1:5)

In 1:6 cement morter

III Random rubble masonry

In cement mortar (1:3)

In 1:4 cement mortar

In cement mortar (1:5)

In1:6 Cement morter

12.5 Plain/reinforced cement concrete in substructure complete as per drawings and


technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204

A. With Crushed Stone

Page 110
Unit Rate
(Rs.)

Description t 66,432.00

cum 5,898.00

cum 5,649.00

cum 5,526.00

10 sqm 323.00

10 sqm 1,173.00

cum 3,401.00

cum 3,147.00

cum 2,945.00

cum 2,586.00

cum 3,314.00

cum 3,009.00

cum 2,914.00

cum 2,638.00

cum 3,123.00

cum 2,880.00

cum 2,877.00

cum 2,468.00

Page 111
Item
No.

I P.C.C grade M 15 Description

I) Nominal mix (1:2.5:5)

ii) Nominal mix 1:2.5:5 (Hand mixing)

II P.C.C. grade M 20

I) Nominal mix (1:2:4)

ii) Nominal mix 1:2:4 (Hand mixed)

III RCC Grade M20 for height upto 5 m

ii) For height above 5 m upto 10 m

IV RCC Grade M25 for height upto 5 m

ii) For height above 5 m upto 10 m

B. With Natural Gravel

I CP.C.C grade M15

N
I)Nominal mix (1:2.5:5)
o
m
N
ii)Nominal mix 1:2.5:5) Hand mixing
i
o
II m
CP.C.C Grade M20
i
NI)Nominal mix(1:2:4)
o
m
Nii)Nomimix(1:2:4) Hand mix
io
III m
C
R.C.C Grade M20
i
F I) Forheight up to 5M
o
rFii)Forheight above 5M upto 10M
o
IV rC
R.C.C.Grade M 25

F I)Height upto 5M
o
rFii)Height above 5 M upto 10 m
o
12.6 rSupplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructrue
complete as per drawings and technical specification Clauses 1002, 1005, 1010 &
1202

12.7 Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete
as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202

12.8 Supplying, fitting and placing with MS bar reinforcement (Fe 415) in substructrue
complete as per drawings and technical specification Clauses 1002, 1005, 1010 &
1202

Page 112
Unit Rate
(Rs.)

Description

cum 5,191.00

cum 5,162.00

cum 5,981.00

cum 5,951.00

cum 6,335.00

cum 6,451.00

cum 6,528.00

cum 6,663.00

cum 4,698.00

cum 4,767.00

cum 5,809.00

cum 5,698.00

cum 6,164.00

cum 6,276.00

cum 6,380.00

cum 6,496.00

t 64,640.00

t 64,941.00

t 66,510.00

Page 113
Item
No.

12.9 Description concrete


Providing weepholes in brick masonry/stone masonry, plain/reinforced
abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full
width of the structures with slope of 1(V):20(H) towards drawing face complete as per
drawing and technical specification Clauses 614, 709, 1204.3.7

12.10 Backfilling behind abutment, wing wall and return wall complete as per drawings &
technical specification Clause 1204.3.8

I Granular material

ii Sandy material

12.11 Providing and laying filter media with granular crushed aggregates as per specification
to a thickness of not less than 600 mm with smaller size towards the soil and bigger
size towards the wall and providing over the entire surface behind abutment, wing wall,
return wall to the full height, compacted to firm condition complete as per drawing and
technical specification Clause 1204.3.8

12.12 Supplying, fitting and fixing in position true to line and level elastomeric bearing
conforming to IRC:83 (Part-II) Section IX complete, including all accessories as per
drawings and technical specification Clause 1207.1

12.13 Providing PCC M-20 architectural coping on the top of wing wall, return wall etc.
complete as per drawing and technical specification Clauses 615, 710 and 1204.3.11

I With Crushed stone

ii With Natural Gravel

12.14 Providing pressure relief pipes 100 mm dia in bottom slab of box cell on a filter media
base of 500 mm x 500 mm as per drawing and technical specification Clause 1205.5.7

Chapter 13 - SUPERSTRUCTURE

13.1 Providing and laying reinforced cement concrete in superstructure as per drawing and
technical specifications Clauses 800, 1205.4 and 1205.5

A With crushed stone

I R.C.C grade M 20

(I) For nominal mix 1:2:4

a) (Height upto 5 M
a
b) )(Height from 5m to 10M
b
c) )(Height above 10 M
c
II 0
For nominal mix 1:2:4 (Hand mixed)

a) (Height upto 5 M
a
b) )(Height 5m to 10M
b
c) )©
Height above 10M

Page 114
Unit Rate
(Rs.)

Description Nos. 168.00

cum 1,048.00

cum 1,010.00

cum 1,113.00

cum 1.00

Running m 388.00

Running m 377.00

Nos. 385.00

cum 6,858.00

cum 7,143.00

cum 7,429.00

cum 6,851.00

cum 7,137.00

cum 7,422.00

Page 115
Item
No.

III For design mix RCC M 20 Description

a) (Height upto 5M
a
b) )(Height 5Mto 10 M
b
c) )©
Height above 10 M

IV R.C.C M 25

a) Height upto 5M

b) Height from 5M to 10 M

c) Height above 10 M

V R.C.C. Grade M 30

a) Height upto 5M

b) Height from 5M to 10M

c) Height above 10M

BB. With Natural Gravel


.
I GR.C.C. grad M 20
r
(I) a
FFor Nominal mix 1:2:4
d
o
a) rHeight upto 5M

b) Height from 5M to 10M

c) Height above 10M

II FNominal mix 1:2:4 (Hand Mixed)


o
a) rHeight upto 5M

b) Height from 5M to 10M

c) Height above 10M

(III) FFor Design mix RCC M 20


o
a) rHeight upto 5 M

b) Height from 5m to 10M

c) Height above 10 M

II R.C.C M25

a) Height upto 5M

b) Height from 5M to 10M

c) Height above 10M

Page 116
Unit Rate
(Rs.)

Description

cum 6,675.00

cum 6,954.00

cum 7,232.00

cum 7,501.00

cum 7,814.00

cum 8,126.00

cum 7,855.00

cum 8,182.00

cum 8,510.00

cum 6,724.00

cum 7,005.00

cum 7,285.00

cum 6,665.00

cum 6,942.00

cum 7,220.00

cum 6,556.00

cum 6,829.00

cum 7,102.00

cum 7,314.00

cum 7,619.00

cum 7,924.00

Page 117
Item
No.

III GR.C.C M30 Description


r
a) aHeight upto 5M
d
b) Height from 5M to 10 M

c) Height above 10 M

13.2 Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as
per drawing and technical specifications Clauses 1002, 1010 and 1202

13.3 Supplying, fitting, and placing TMT bar reinforcement in superstructure complete as per
drawing and technical specifications Clauses 1002, 1010 and 1202

13.4 Supplying, fitting, and placing MS bar reinforcement in superstructure complete as per
drawing and technical specifications Clauses 1002, 1010 and 1202

13.5 Providing and laying cement concrete wearing course M 30 grade including
reinforcement complete as per drawing and technical specifications Clauses 800 and
1206.3

A With crushed stone

B With Natural Gravel

13.6 Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal size


aggregate, true to line and grade, tolerance of vertical railing post not to exceed 1 in
500, centre-to-centre spacing between vertical posts not to exceed 2000 mm as per
drawing and technical specifications Clauses 800, 900 and 1208.3

13.7 Providing fitting and fixing mild steel railing complete as per drawing and technical
specifications Clause 1208.2

13.8 Providing and fixing in position pipe railing consisting of IS Rolled steel joist posts
designation IS MB 100 (100x75) at 2.5 m interval and three rows of 50 mm dia steel
pipes (light) including fixing in position on bridge deck complete as per drawing and
technical specifications Clause 1208.2

13.9 Brick masonry work in cement mortar 1:3 in parapet excluding pointing and plastering
as per drawing and technical specifications Clauses 600, 900 and 1208.4

13.10 Drainage spouts complete as per drawing and technical specifications Clause 1209

13.11 P.C.C. M 15 ordinary grade (1:2.5:5) levelling course below approach slab complete as
per drawing and technical specifications Clauses 800 and 1211

A With crushed stone

I Nominal mix (1:2.5:5)

ii Nominal mix 1:2.5:5 (Hand mixing)

B With Natural Gravel

Page 118
Unit Rate
(Rs.)

Description

cum 7,668.00

cum 7,988.00

cum 8,307.00

t 65,364.00

t 65,664.00

t 67,234.00

cum 11,845.00

cum 11,463.00

Running m 2,722.00

Running m 3,509.00

Running m 2,065.00

cum 5,614.00

Nos. 1,520.00

cum 4,719.00

cum 4,644.00

Page 119
Item
No.

I nmix(1:2.5:5) Description
a
ii lnmix(1:2.5:5)Hand mixed
a
13.12 lReinforced Cement Concrete M 25 grade approach slab including reinforcement
and formwork complete as per drawing and technical specifications Clauses 800
and 1211

A With crushed stone

B With Natural Gravel

13.13 Providing and laying of an elastomeric slab seal expansion joint compleate as per
approved drawing and approved specification to be installed by manufacturer/supplier
or their authorised representative ensuring compliance to the manufacturers instructuio

13.14 Providing and laying of ancompression seal consisting of steel armoured nosing at
two edges of the joint gapsuitably anchored to the deck concrete and a preformed
chloroprene elastomer or closed cell foam joint sealer compressed and formed intothe
joint

13.15 Providing and laying a buried expansion joint, covered with 12 mm thick, 200 mm wide
galvanised weldable structrual steel plate as per IS:2062, placed symmetrical to centre
line of the joint, resting freely over the top surface of the deck concrete, welding of 8
mm dia, 100 mm long galvanised nails spaced 300 mm c/c along the centre line of the
plate, as per technical specifications Clauses 1207.2.3

13.16 Filler Joint

I Providing and fixing 2 mm thick corrugated copper plate in expansion joint as per
drawing and technical specifications Clause 1207.2.2

ii Providing and fixing 20 mm thick compressible fibre board in expansion joint complete
as per drawing and technical specifications

iii Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for
fixedends of simply supported spans,covered with sealant complete as per drawing
and technical specification.

iv Providing and fillling joint sealing compound as per drawings and technical
specifications with coarse sand and 6 per cent bitumen by weight.

iv
13.17 Stone masonry in cement mortar 1:3 for parapet complete as per drawing and
technical specifications Clauses 700 and 1208.4

I Random rubble masonry

II Coursed rubble masonry (1st sort)

13.18 Pointing with cement mortar (1:3) on brickwork in parapet as per technical
specifications Clauses 613.3 and 1208.4

13.19 Plastering with cement mortar (1:3) 15 mm thick on brickwork in parapet as per
technical specifications Clauses 613.4 and 1208.4

Page 120
Unit Rate
(Rs.)

Description cum 4,591.00

cum 4,557.00

cum 10,769.00

cum 10,167.00

Running m 15,013.00

14,726.00

Running m 1,156.00

Running m 1,119.00

Running m 316.00

Running m 284.00

Running m 11.00

cum 3,123.00

cum 3,401.00

10 sqm 323.00

10 sqm 1,173.00

Page 121
Item
No.

13.20 Description
Providing and laying parapet with PCC M 15 as per drawing & technical specifications
Clauses 800 and 1208.4

A With crushed stone

I Nominal mix 1:2.5:5 (Hand mixing)

ii Nominal mix (1:2.5:5)

B With Natural Gravel

I nMix 1:2.5:5(Hand mixing)


a
ii lnMix (1:2.5:5)
a
13.21 lProviding bituminous wearing coat comprising of 20 mm thick premix carpet with 5 mm
thick seal coat Type B for culverts as per drawing and technical specifications Clauses
1206.2 and 500

I Rate for wearing coat as per item No. 5.9 of Chapter 5

ii Rate for seal coat Type B as per item No. 5.12 of Chapter 5

13.22 Providing bituminous wearing coat comprising of 50 mm thick bituminous macadam


overlaid by 20 mm thick premix carpet with 5 mm thick seal coat Type B

I Rate for BM layer may be analysed as per item No 5.3 of Chapter 5

ii Rate of 20 mm premix carpet wearing course as per item No.5.9 of Chapter 5

iii Rate of seal coat Type B as per item No. 5.12 of Chapter 5

13.23 Brickwork in arches in cement mortar 1:4 complete including centering and shuttering
excluding pointing and plastering as per drawing and technical specifications Clauses
606 and 1205.1

13.24 Coursed rubble stone masonry arch (Ist sort) in cement mortar (1:4) complete including
centering etc. complete as per drawing and technical specifications Clauses 706 and
1205.1

I AFor arch above 6Mspan


r
ii cFor Arch 4 m to 6 m span
iii h
For Arch less than 4 m span
13.25 Providing & Laying reinforced cement concrete arch complete including
centering and shuttering excluding reinforcement as per drawings and technical
specifications Clauses 800, 900 and 1205.1

A With crushed stone


I RCC grade M20 (1:2.4) nominal mix

a) For arch above 6 m span

b) For arch 4 m to 6 m span

c) For arch less than 4 m span

Page 122
Unit Rate
(Rs.)

Description

cum 5,162.00

cum 5,191.00

cum 4,597.11

cum 4,658.33

sqm

sqm

cum

sqm

sqm

cum 13,285.00

cum 7,177.00

cum 6,460.00
cum 5,383.00

cum 8,689.00

cum 8,109.00

cum 7,530.00

Page 123
Item
No.

II RCC Grade M 25 Description

a) For arch above 6 m span

b) For arch 4 m to 6 m span

c) For arch less than 4 m span

B B With Natural Gravel

I GR.C.C.Grade M20 (1:2:4) nominal mix


r
I a
F Arch above 6M
d
o
ii rF Arch 4M to 6M span
o
iii rF Arch less than 4M span
o
II rGR.C.C Grade M25
r
I a
F Arch above 6M span
e
o
ii rF Arch 4M to 6M span
o
iii rFArch less than 4 M span
o
13.26 rProviding steel R.S.Js/built-up steel sections including cutting, welding/rivetting,
hoisting, fixing in position for composite girders with shear connectors complete with
painting as per drawing and technical specifications Clause 1205.6

Steel section

Chapter 14 - PROTECTION WORKS

14.1 Providing and laying boulder apron for bed protection with stone boulders of minimum
size and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry
complete as per drawing and technical specifications Clause 1301

14.2 Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire
conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally)
including 10 per cent extra for laps and joints laid with stone boulders weighing not less
than 25 kg each as per drawing and technical specifications Clause 1301

14.3 Providing and laying of apron with cement concrete blocks of size as per Table 1300.1
cast-in-situ and made with nominal mix of M-15 grade cement concrete as per drawing
and technical specifications Clause 1301

14.4 Single bamboo palasiding / walling of whole 2nd class bamboo (Jati or Bethua) 75mm
dia and closely packed & driven including fitting fixing with half bamboo kamis
horizontally in three rows with cane or tying with wire complete and struts 1.5 m apart
longitudinally and providing brush wood as per drawing and technical specifications
Clause 1302.5

Driven at least 900 mm below ground and 1200 mm above ground

Driven at least 900 mm below ground and 900 mm above ground on average

Page 124
Unit Rate
(Rs.)

Description

cum 9,485.00

cum 8,853.00

cum 8,220.00

cum 8,466.00

cum 7,901.00

cum 7,337.00

cum 9,262.00

cum 8,645.00

cum 8,027.00

quintal 8,592.00

cum 1,097.00

cum 1,839.00

cum 4,886.00

Running m 487.00

Running m 459.00

Page 125
Item
No.

14.5 Description
Providing and laying pitching on slopes laid over prepared filter media as per
drawing and technical specifications Clause 1302

I Stone/Boulder

I Cement concrete blocks of size as per Table 1300.2 cast in cement concrete of grade
M 15

ii Concrete grade M 15

iii Brick pitchng set in cement mortar 1:4

14.6 Providing and laying filter material underneath pitching in slopes complete as
per drawing and technical specifications Clause 1302

14.7 Providing and laying flooring laid over cement concrete bedding complete as per
drawing and technical specification Clause 1303

I Rubble stone laid in cement mortar 1:3

ii Cement conrete blocks grade M 15

ii Brick on edge laid in cement mortar (1:3)

Note : Cement concrete bedding to be measured and paid extra.

14.8 Providing and laying of dry rubble flooring complete as per drawings and technical
specifications Clause 1303.3

14.9 Providing and laying curtain walls complete as per drawing and technical specification
Clause 1304

I Brick masonry in cement mortar (1:4)

ii Coursed rubble masonary (2nd sort) in cement mortar (1:4)

iii Cement concrete grade M 10

14.10 Construction of flexible apron 1 m thick comprising of loose stone boulders weighing
not less then 25 kg beyond curtain wall

14.11 Construction of toe walls for protection of slopes as per drawing and technical
specifications Clause 1302.5

I Random rubble masonry in case of stone pitching laid with cement mortar (1:5)

ii Brick masonry in cement mortar 1:4 in case of brick pitching

iii Cement concrete grade M 10 in case of concrete block pitching

Nominal mix 1:3:6

14.12 Single bamboo spur and palisading of whole 2nd class bamboo (jati or Bethua) 65 mm
to 75 mm dia and closely packed & driven, including fitting, fixing with half bamboo
kamis horrizontally in three rows with cane or tying wire complete and struts 1500 mm
apart longitudinally and providing brush wood as per drawing and technical
specifications Clause 1302.5

I Driven at least 900 mm below ground and 1800 mm above ground on average

Page 126
Unit Rate
(Rs.)

Description

cum 1,097.00

cum 5,006.00

cum 5,261.00

cum 1,291.00

cum 2,897.00

cum 5,453.00

cum 4,117.00

cum 1,183.00

cum 5,552.00

cum 3,009.00

cum 4,653.00

cum 885.00

cum 2,424.00

cum 5,106.00

cum 4592.00

Running m 571.00

Page 127
Item
No.

ii Description
Driven at least 900 mm below ground and 900 mm above ground on average

14.13 Single bamboo spur and palisading of whole 1st class bamboo (Bholuka or Barua) 85
mm to 100 mm dia. Closely packed & driven including fitting, fixing with half 2nd class
bamboo (jati or Bethua) horizontally in three rows with cane or tying wire complete and
struts 1500 mm apart longitudinally and providing brush wood in the spur as per
drawings and technical specifications

A Driven at least 900 mm below ground and 1800 mm above ground

B Driven at least 900 mm below ground and 900 mm above ground on average

C Driven at least 600 mm below ground and 1200 mm above ground on average.

14.14 Bamboo spur 'A' type with whole bamboo 85mm-100mm dia, placed 230 mm centre to
centre driven 900 mm below ground and 1200 mm to 1500 mm above ground tied with
2nd class bamboo (jati or Bethua) on either side at 450 mm apart horizontally with
galvanised wire etc. complete as per drawings and technical specifications

A 2nd class bamboo (jati or Bethua) 75 mm dia

B 1st class bamboo (Bholuka or Barua ) 85 mm to 100 mm dia

14.15 Providing 'A' type single spur with 1st class bamboo (Bholuka or Barua) 85 mm to 100
mm dia. Driven closely placed 3m to 4m above ground and 1200 mm to 1500 mm
below ground tied with cane or coir string, half 2nd class bamboo (jati or Bethua)
horizontally on both face placed not more than one metre apart including whole
bamboo struts inside one metre apart and 2 nos. of purlin at top and bottom fitted with
vertical struts at 1500 mm apart and filling with brushwood or jungle wood inside the
spur complete as per drawing and technical specifications

14.16 Providing close bamboo toe walling consisting of 65mm to 75mm dia bamboos of
length ranging from 1.2 m to 3m driven at 150 mm centre to centre and provided with
three horizontal split bamboo runner fixed with nails. All bamboos to be duly protected
by coal tar painting.

14.17 Double timber spur with two rows at 800 mm c/c apart of 1st class local wood piles with
timber of Azar/Nahar/Nageswar / Zarul wood 150 mm to 200 mm dia driven 2000 mm
minimum below ground and 3600 mm above ground average placed at 800 mm belts,
bracings etc. of 100 mm x 75 mm size 1st class local wood longitudinally & crosswiswe
at ends fitted with 10 mm dia bolts and nuts etc. including coaltarring of timber
members and cost of necessary bamboo stagings etc. as directed by the Engineer as
per drawing and technical specifications

14.18 Supplying and filling up hollows of the timber spur to an average height of 3600 mm
above ground with jungle wood branches as per drawing and technical specifications
as directed by the Engineer.

Chapter 15 - MAINTENANCE OF ROADS

15.1 Restoration of Rain Cuts

Page 128
Unit Rate
(Rs.)

Description Running m 463.00

Running m 646.00

Running m 352.00

Running m 328.00

Running m 604.00

Running m 486.00

Running m 846.00

Running m 700.00

Running m 23,886.00

Running m 44.00

Page 129
Item
No.

Description
Restoration of rain cuts with soil, moorum gravel or a mixture of these, clearing the
loose soil, benching for 300mm width laying fresh material in layers not exceeding 250
mm and compaction with plate compactor or power rammer to restore the original
alignment, level and slopes as per drawings and technical specifications Clause 1902

A Manual Means

B Mechanical Means

15.2 Maintenance of Earthen shoulder (filling with fresh selected soil)

1 Making up loss of material/irregularities on shoulders to the design level by adding


fresh approved selected soil and compacting it with appropriate equipment at OMC
upto a lead of 1000 m as per technical specification Clause 1903

Maintenance of Earhen shoulder (stripping of excess soil)

2 Stripping excess soil from the shoulder surface to achieve the approved level and
compacting with plate compactor at OMC as per drawings and Technical Specification
Clause 1903

15.3 Maintenace of bituminous surface road


Repair to pot holes by removal of failed material, trimming the sides to vertical and
15.3 levelling the bottom,
Maintenance cleaning the
of Bituminous sameroad
surface with compressed air or any appropriate method

I Repair to pot holes by removal of failed material,trimming the sides to vertical and
levelling the bottom,cleaning the same with compressed air or any appropriate method
filled with 75 mm B.M. applying bitumen emulsion prime coat at the bottom and
bitumen

ii Patch repair on already filled pot holes with 75 mm BM with 20 mm premix carpet and
seal coat Type B as per drawings and technical specification Clause 1904.2

iii Repair to pot holes and removal of loose material, trimming of sides, cleaning of
surface by providing tack coat, 20 mm thick pre-mix carpet and seal coat type B
specification Clause 1904.2
iv Repair to pot holes and removal of loose material, trimming of sides, cleaning of
surface by providing tack coat with bitumen emulsion, 20 mm thick pre-mix carpet
using catonic bitumen emulsion and seal coat type B with bitumen emulsion

15.4 Maintenance of Gravel Road

Maintenance of gravel road including making up the loss of profile, rectifying


corrugated surface, filling up of depressions, pot holes and erosion gullies by adding
fresh material and compacting it with appropriate equipment or to strip excess of
material from the road surface as per drawings and technical specification Clause 1905

15.5 Maintenance of WBM Road


Maintenance of WBM road including filling up of pot holes, ruts and rectifying
corrugated surface, damaged edges and ravelling as per technical specification Clause
1906.

15.6 Maintenance of Drains

The maintenance of drains include erosion, repair, clearing, cleaning, reshaping,


regrading, deepening of side drains as well as catch water drains as per technical
specification Clause 1907.

Page 130
Unit Rate
(Rs.)

Description

cum 90.00

cum 90.00

sqm 60.00

sqm 13.00

cum 7,867.00

cum 7,867.00

sqm 169.00

sqm 169.00

sqm 177.00

sqm 332.00

sqm 251.00

m 1.00

Page 131
Item
No.

15.7 Maintenance of Culverts Description

I Maintenance of Hume pipe Culvert by way of Clearing, Cleaning, Erosion repair,


repairs to cracks, parapet wall and protection work as per drawing and technical
specification Clause 1908

ii Maintenance of Culverts Slab type

Maintenance of Slab type Culverts by way of clearing, Cleaning, Erosion repair, repairs
to cracks, parapet walls and Protection works as per drawing and technical
specification Clasue 1908

15.8 Maintenance of Causeway

Maintenance of Causeway by way of minor Surface repairs, replacing Guide Posts,


repair of flood gauges, removal of debris, providing boulders and protection work and
painting as per technical specification Clause 1909

15.9 Maintenance of Road Signs

Maintenance of road signs by way of cleaning and repainting of mandatory /


requlatory / cautionary / informatory and place identifications sign board as
perdrawings and technical specification Clause 1910

15.10 Maintenance of steel and RCC Railing

I Repair of steel railing to bring it to original shape cleaning and repainting as per
drawing and technical specification Clause 1911
Steel Railing
ii Repair of RCC railing to bring it to the original shape, cleaning and repainting as per
drawings and technical specification Clause 1911

RCC Railing

15.11 Maintenance of 200 metre and km stones

Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with
cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km
stone as per drawing and technical specification Clause 1912

I Painting two coats with synthetic enamel paint

ii Printing letters and figures of any shade with synthtic enamel paint of any approved
colour to give an even shade
15.12 Cutting of branches of trees shrubs and trimming of grass and weeds

I Cutting of branches of trees and shrubs from the road way or with in R.O.W including
disposal of wood and leaves to suitable location as per technical specification Clause
1914

ii Cutting of shrubs from the road way or with in R.O.W and disposal of shrubs to suitable
locations as per technical specifications Clause 1914

iii Trimming of grass and weeds from the shoulders/berms and disposing off the same to
suitable locations as per technical specifications Clause 1914

15.13 White washing of parapet walls of CD work and tree truncks

Page 132
Unit Rate
(Rs.)

Description

One No. 1,204.00


Hume Pipe

Culvert 2,361.00

m 37.00

km 861.00

Running m 314.00

m 154.00

km 86.00

km 303.00

one tree 54.00

each 4.00

sqm 1.00

Page 133
Item
No.

White washing two coats on parapet walls and tree trunks Description
including preparation of
surface by cleaning scraping etc. as per technical specifications Clause 1915

15.14 Periodical Renewal to existing bituminous surface

1 Open graded Premix carpet 20 mm thick


I) Tack coat

Rates as per item 5.2 (ii)

ii) Pre-mix carpet using bituminous (penetration grade modified bitumen) binder
Rates as per item No. 5.9
OR
iii) Premix carpet using bitumen Emulsion
Rates as per item No. 5.10
iv) Seal coat Type A, B or C
Rates as per item No. 5.11
2 Surface dressing single coat/first coat or 2nd coat
Rates as per item No. 5.6

Page 134
Unit Rate
(Rs.)

Description sqm 11.00

sqm

sqm

sqm

sqm

sqm

Page 135
FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
COST ESTIMATE FOR ROAD CONSTRUCTION
Road from Package No.: AS-07-
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur District Goalpara
Block Krishnai
Length of the Road (km): 0.419

Rate
Sl. Item Length Breath D/H Rate
Description of item Unit Quantity (Including
No. No. (m) (m) (m) (Rs.)
13.50% GST)

1 2 3 4 5 6 7 8 9 10
1 2.2 Clearing and grubbing road land including uprooting wild vegetation, grass,
bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of
such trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, upto a lead of 1000 m including
removal and disposal of top organic soil not exceeding 150 mm in thickness as
per Technical Specification Clause 201.

(I) By Manual Means-


(A) In area of non thorny jungle Hectare 2.45 1.20 0.00 42648.30 48405.82
2 2.13 Removing all types of Hume pipes and stacking within a lead of 1000 m
including Earthwork and Dismantling of Masonry Works as per Technical
Specification Clause 202.
(A) Upto 600 mm dia Hume pipe RM 22.50 151.09 171.49
(C) Above 900 mm dia Hume pipe RM 350.22 397.50
3 2.6 Dismantling Brick Work
Dismantling of existing structures like culverts, bridges, retaining walls and
other structures comprising of brick masonry, including disposal of
unserviceable material and stacking the serviceable material with all lift and
lead of 1000 m as per Technical Specification Clause 202.

B. Cement mortar cum 43.00 226.39 256.95


4 12.1 Brick masonry work in cement mortar in substructure complete excepting
pointing and plastering, as per drawing and technical specification Clauses 602,
603, 604, 1202 & 1204
(ii) In 1:4 Cement mortar cum 0.00 6925.70 7860.67
5 12.5 Plain/reinforced cement concrete in substructure complete as per drawings and
technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204
A(I) P.C.C grade M 15
i Nominal mix (1:2.5:5) sqm 0.00 5379.00 6105.17
FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
COST ESTIMATE FOR ROAD CONSTRUCTION
Road from Package No.: AS-07-
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur District Goalpara
Block Krishnai
Length of the Road (km): 0.419

Rate
Sl. Item Length Breath D/H Rate
Description of item Unit Quantity (Including
No. No. (m) (m) (m) (Rs.)
13.50% GST)

1 2 3 4 5 6 7 8 9 10
6 2.3(A) Cutting of trees, including cutting of trunks, branches and removal of stumps &
roots, refilling, compaction of backfilling and stacking of serviceable material by
manual means with all lifts as per Technical Specification Clause 201.

ii Girth above 300 mm to 600 mm each 5.00 206.90 234.83


7 3.5 Excavation in Cutting in Soil by manual means with lead upto 50 m
Excavation for roadway in soil using manual means for carrying of cut earth to
embankment site with a lift upto 1.5 m and lead upto 50 m as per Technical As per E/W Statement
Specification Clause 302.3 (Manual should be use where machines can not be
deployed due to site condition)
cum 504.38 109.20 123.94
8 3.3
Construction of embankment with approved materials deposited at site from
roadway cutting and excavation from drain and foundation of other structures
graded and compacted to meet requirement of Tables 300.1 and 300.2 as per
Technical Specification Clause 301.5

cum 504.38 58.00 65.83


9 3.4 Construction of Embankment with Material Obtained from Borrow Pits
Construction of embankment with approved material obtained from borrow pits
with a lift upto 1.5 m, transporting to site, spreading, grading to required slope
and compacting to meet requirement of Tables 300.1 and 300.2 with a lead
upto 1000 m as per Technical Specification Clause 301.5

(I) Private land Cum As per E/W Statement 1587.45 230.60 261.73
10 3.14 Construction of Subgrade and Earthen Shoulders
Construction of subgrade and earthen shoulders with approved material
obtained from borrow pits with all lifts and leads, transporting to site, spreading,
grading to required slope and compacted to meet requirement of Table 300.2
with lead upto 1000 m as per Technical Specification Clause 303.1.

(I) Private land Cum As per E/W Statement 1483.27 286.30 324.95
FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
COST ESTIMATE FOR ROAD CONSTRUCTION
Road from Package No.: AS-07-
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur District Goalpara
Block Krishnai
Length of the Road (km): 0.419

Rate
Sl. Item Length Breath D/H Rate
Description of item Unit Quantity (Including
No. No. (m) (m) (m) (Rs.)
13.50% GST)

1 2 3 4 5 6 7 8 9 10
11 4.1 Granular Sub-base with Well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by providing well graded material, spreading
in uniform layers with motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with smooth wheel roller to
achieve the desired density, complete as per Technical Specification Clause
401.

(ii) For Grading Material (Gr - II ) Cum 419 4.05 0.15 254.54 2465.17 2797.97
12 4.7 Water Bound Macadam Sub-base/base
2) WBM Grading 2
Using stone screening Type-B 11.2 mm for Gr.II
Providing, laying, spreading and compacting stone aggregates of specific sizes
to water bound macadam specification including spreading in uniform
thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages
to proper grade and camber, applying and brooming, stone screening/binding
materials to fill-up the interstices of coarse aggregate, watering and compacting
to the required density grading 2 as per Technical Specification Clause 405.
Cum
(B) By Mechanical Means 419 3.75 0.075 117.84 3391.82 3849.71
3) WBM Grading 3
Using stone screening Type-B 11.2 mm for Gr.III
Providing, laying, spreading and compacting stone aggregates of specific sizes
to water bound macadam specification including spreading in uniform
thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages
to proper grade and camber, applying and brooming, stone screening to fill-up
the interstices of coarse aggregate, watering and compacting to the required
density Grading 3 as per Technical Specification Clause 405.

(B) By Mechanical Means 419 3.75 0.075 117.84 3410.36 3870.76


FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
COST ESTIMATE FOR ROAD CONSTRUCTION
Road from Package No.: AS-07-
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur District Goalpara
Block Krishnai
Length of the Road (km): 0.419

Rate
Sl. Item Length Breath D/H Rate
Description of item Unit Quantity (Including
No. No. (m) (m) (m) (Rs.)
13.50% GST)

1 2 3 4 5 6 7 8 9 10
13 5.1 Prime-Coat
(I) Low porosity: Providing and applying primer coat with
bitumen emulsion (SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm
using mechanical means as per Technical Specification Clause 502
Sqm 419 3.75 1571.25 27.90 31.67
14 5.2 Tack-coat
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the
(III) rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer & cleaned
with Hydraulic broom as per Technical Specification Clause 503. Sqm 419 3.75 1571.25 10.20 11.58
15 5.9 20mm thick Open-Graded Premix Carpet using Bituminous (penetration
grade/modified bitumen) Binder
Providing, laying and rolling of open-graded premix carpet of 20 mm thickness
composed of 13.2 mm to 5.6 mm aggregates either using penetration grade
bitumen or emulsion to required line, grade and level to serve as wearing course
on a previously prepared base, including mixing in a suitable plant, laying and
rolling with a three wheel 80-100 kN static roller capacity, finished to required
level and grades to be followed by seal coat of either Type A or Type B or Type C
as per Technical Specification Clause 508.

Case - II By Mechanical Means


(i) Bitumen (S-90) Sqm 419 3.75 1571.25 144.82 164.38
FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
COST ESTIMATE FOR ROAD CONSTRUCTION
Road from Package No.: AS-07-
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur District Goalpara
Block Krishnai
Length of the Road (km): 0.419

Rate
Sl. Item Length Breath D/H Rate
Description of item Unit Quantity (Including
No. No. (m) (m) (m) (Rs.)
13.50% GST)

1 2 3 4 5 6 7 8 9 10
16 5.12 Seal-Coat
Providing and laying seal coat sealing the voids in a bituminous
surface laid to the specified levels, grade and cross fall using Type A, Type B
and Type C as per Technical Specification Clause 510
B By Mechanical Means
Case - II : Type B
(i) Bitumen (S-90) Sqm 419 3.75 1571.25 46.31 52.56
17 10.2 Trafic - Signs
B. Semi Reflective Traffic Signs
Providing and fixing of semi reflective cautionary, mandatory and informatory sign
board as per IRC:67 made of 1.5 mm thick MS Sheet duly stove white colour in front
and gray colour on back with red reflective border of 65 mm width and required
letters and figures with reflective tape engineering grade as per Clause 1701.3.9 of
MORD for Rural Roads of required shade and colour supported and welded on
47mm x 47 mm x 12 SWG sheet tube firmly fixed to the ground by mean of properly
designed foundations with M-15 grade cement concrete 450x450x600 mm, 600 mm
below ground level as per approved drawing Clause 1701.2.2

(i) 60 cm circular Each 0 3813.30 4328.10


(ii) 90 cm equilateral tringle Each 0 4265.00 4840.78
(iii) 60 cm x 60 cm square Each 0 4332.40 4917.27
18 10.10 Kilometre Stone
Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per
IRC:8 fixing in position including painting and printing, etc as per drawing and Technical
Specification Clause 1703

(ii) 5th Kilometer Stone Each 0 3524.80 4000.65


(ii) Ordinary Kilometer Stone (precast) Each 1 2116.40 2402.11
(iii) 200 m Stone (precast) Each 2 563.20 639.23
FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
COST ESTIMATE FOR ROAD CONSTRUCTION
Road from Package No.: AS-07-
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur District Goalpara
Block Krishnai
Length of the Road (km): 0.419

Rate
Sl. Item Length Breath D/H Rate
Description of item Unit Quantity (Including
No. No. (m) (m) (m) (Rs.)
13.50% GST)

1 2 3 4 5 6 7 8 9 10
19 8.8 Construction of RCC guide posts of 250 mm dia M15 grade cast-in-situ with 20 mm nominal size
aggregate, true to line and grade, tolerance of vertical RCC posts not to exceed 1 in 500 as per
drawing and Technical Specification Clause 1608.2
Rate as per the Annexure - II Each 82 632.00 717.32
20 10.16 Providing and Fixing 'Logo' of PMGSY Project
Providing and fixing of typical PMGSY informatory sign board with Logo as per MORD
specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle plate duly welded with
MS flat iron 25mm x 5m size on back on edges. The lower plate will be welded with MS angle iron
frame of 25mm x 25mm x 5mm. The angle iron frame of the lower most plate and flat iron frame of
middle plate will be welded to 2 nos. 75mm x 75 mm of 12 SWG sheet tubes posts duly embedded
in cement concrete M-15 grade blocks of 450mm x 450mm x 600mm, 600mm below ground level.
The top most diamond plate will be welded to middle plate by 47mm x 47mm of 12 SWG steel plate
tube. All M.S. will be stove enameled on both sides. Lettering and printing arrows, border etc. will
be painted with ready mixed synthetic enamel paint of superior quality in required shade and
colour. All sections of framed posts and steel tube will be painted with primer and two coats of
epoxy paint as per drawing Clause 1701 and Annexure 1700.1

Each 2 10444.05 11854.00


21 Analysis Providing and fixing of typical Citizens Information Board and Maintanance
Information Board with Logo as per MORD specifications and drawing. Two nos.
1.6mm thick MS sheet duly welded with 5mm thick steel plate on back on edges. The 4
nos. steel plate will be welded horizontally with 2 nos. 75mm x 75mm of 12 SWG sheet
tubes posts duly embedded in cement concrete M-15 grade blocks of 600mm x 600mm x
750mm, 750mm below ground level. The 2 nos. steel plate will be welded vertically to 2
nos. 75mm x 75mm of 12 SWG sheet tubes posts duly welded to vertical tubes. All M.S.
will be stove enameled on both sides. Lettering and printing arrows, border etc. will be
painted with ready mixed synthetic enamel paint of superior quality in required shade
and coloue. All sections of framed posts and steel tube will be painted with primer and
two coats of epoxy paint as per drawing Clause 1701 and Annexure 1700.1

Each 2 24354.72 27642.61


FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
COST ESTIMATE FOR ROAD CONSTRUCTION
Road from Package No.: AS-07-
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur District Goalpara
Block Krishnai
Length of the Road (km): 0.419

Rate
Sl. Item Length Breath D/H Rate
Description of item Unit Quantity (Including
No. No. (m) (m) (m) (Rs.)
13.50% GST)

1 2 3 4 5 6 7 8 9 10
22 Title Informatory Board with Logo as per MORD specifications and drawing. Two nos.
1.6mm thick MS sheet duly welded with 5mm thick steel plate on back on edges. The 4
nos. steel plate will be welded horizontally with 2 nos. 75mm x 75mm of 12 SWG sheet
tubes posts duly embedded in cement concrete M-15 grade blocks of 600mm x 600mm x
750mm, 750mm below ground level. The 2 nos. steel plate will be welded vertically to 2
nos. 75mm x 75mm of 12 SWG sheet tubes posts duly welded to vertical tubes. All M.S.
will be stove enameled on both sides. Lettering and printing arrows, border etc. will be
painted with ready mixed synthetic enamel paint of superior quality in required shade
and coloue. All sections of framed posts and steel tube will be painted with primer and
two coats of epoxy paint as per drawing Clause 1701 and Annexure 1700.1

1 21457.27 24354.00
Total Cost of Pa
FORMAT F-6
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
(Ministry of Rural Development, Govt of India)
COST ESTIMATE FOR ROAD CONSTRUCTION
Road from Package No.: AS-07-
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur District Goalpara
Block Krishnai
Length of the Road (km): 0.419

Rate
Sl. Item Length Breath D/H Rate
Description of item Unit Quantity (Including
No. No. (m) (m) (m) (Rs.)
13.50% GST)

1 2 3 4 5 6 7 8 9 10
24 Preparation of DPR KM 0.419 25000.00
25 Utility shifting Each 2.00 10000.00

Executive Engineer , PWD


Asstt. Executive Engineer, PWD Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division Goalpara
RAM SADAK YOJANA (PMGSY)
Development, Govt of India)
FOR ROAD CONSTRUCTION

Amount (Rs.)

11

14.25

3858.46
0.00

11048.96

0.00

0.00
RAM SADAK YOJANA (PMGSY)
Development, Govt of India)
FOR ROAD CONSTRUCTION

Amount (Rs.)

11

1174.16

62514.18

33203.50

415485.35

481989.93
RAM SADAK YOJANA (PMGSY)
Development, Govt of India)
FOR ROAD CONSTRUCTION

Amount (Rs.)

11

712201.18

453664.67

456144.37
RAM SADAK YOJANA (PMGSY)
Development, Govt of India)
FOR ROAD CONSTRUCTION

Amount (Rs.)

11

49755.99

18190.36

258275.40
RAM SADAK YOJANA (PMGSY)
Development, Govt of India)
FOR ROAD CONSTRUCTION

Amount (Rs.)

11

82584.51

0.00
0.00
0.00

0.00
2402.11
1278.46
RAM SADAK YOJANA (PMGSY)
Development, Govt of India)
FOR ROAD CONSTRUCTION

Amount (Rs.)

11

58820.24

23708.00

55285.22
RAM SADAK YOJANA (PMGSY)
Development, Govt of India)
FOR ROAD CONSTRUCTION

Amount (Rs.)

11

24354.00
3205953.00
RAM SADAK YOJANA (PMGSY)
Development, Govt of India)
FOR ROAD CONSTRUCTION

Amount (Rs.)

11
10475.00
20000.00
30475.00

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
FORMAT F-7

Item No / Rate
SOR Ref Item Unit Quantity Rate (Including Amount
13.50%GST)

1/11.1 Earthwork in excavation for structures as per drawing and


technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
sides and bottom and backfilling in trenches with excavated suitable
material.

Cum
(I) Ordinary soil
Hume Pipe Culvert 0.000
Slab Culvert 0.000
Box Culvert 0.000
0.000 102.00 115.77 0.00
2/9.9 Providing and laying parapet with PCC M 15 as per drawing &
technical specifications Clauses 800 and 1208.4
A) With crushed stone ii. Nominal mix
(1:2.5:5)

Cum
Hume Pipe Culvert 0.000
Cum
Box Culvert 0.000
0.000 5085.60 5772.16 0.00
3/9.2 Bedding for Pipe
(ii) Type B (First Class) Bedding
Laying (First Class) bedding on well compacted sand, moorum or
approved granular material as per Clause 1105 (ii)
(ii) Granular material
Hume Pipe Culvert cum 0.000
Slab Culvert cum 0.000
0.000 1369.05 1553.87 0.00
Item No / Rate
SOR Ref Item Unit Quantity Rate (Including Amount
13.50%GST)
4/9.5
Providing and Laying Reinforced Cement Concrete Pipe NP3
as per Design in Double Row
Providing and laying reinforced cement concrete pipe NP3 for
culverts on first class bedding of granular material in double row
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets as per Clause 1106.
(B) 1000 mm dia RM
Hume Pipe Culvert 0.00
0.00 14560.10 16525.71 0.00
5/9.8 Brick Masonry Work in cement mortar in foundation of Head walls
complete exculding pointing and plastering as per drawing and
technical specification Clause 1109
I. Brick masonry in 1:3 cement mortar
Hume Pipe Culvert 0.000

0.000 6464.44 7337.14 0.00


6/14.1 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per drawing
and technical specifications Clause 1301
Hume Pipe Culvert cum
0.000 2286.22 2594.86 0.00
7/9.11 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in
substructure as per technical specification
Hume Pipe Culvert sqm 0.000
0.000 121.17 137.53 0.00
Stone masonry work in cement mortar in foundation complete as per
drawing and technical specifications Clauses 702, 704, 1202 &
8/11.6 1203. Cum
II. In 1:4 cement mortar
Rate as per SOR PMGSY - 2016-17
Hume Pipe Culvert
Item No / Rate
SOR Ref Item Unit Quantity Rate (Including Amount
13.50%GST)
0 4160.15 4721.774 0.00
Stone masonry work in cement mortar in sub structure complete as
per drawing and technical specifications Clauses 702, 704, 1202 &
9/12.4 1203. Cum
II. In 1:4 cement mortar
Rate as per SOR PMGSY - 2016-17
Hume Pipe Culvert
0 4582.68 5201.337 0.00
Providing and laying reinforced cement concrete pipe NP3 for
culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding
10/9.3 excavation, protection works, backfilling, concrete and masonry Rm
works in head walls and parapets Clause 1106.
(B) 1000 mm dia
Rate as per F-8

Hume Pipe Culvert


0 6880.50 7809.368 0.00
11/9.7 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203
A. With crushed stone. (I) P.C.C grade M 10 Nominal mix
1:3:6 Cum
Slab Culvert 0.00 5216.60 5920.84
Total = 0.00
12/11.5 Brick masonry work in cement mortar in foundation complete
excluding pointing and plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203
(I) Brick masonry in 1:3 cement mortar Cum
Slab Culvert 0.00 6464.40 7337.09
Total = 0.00
13/13.1 Providing and laying reinforced cement concrete in
superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5 B. With Natural Gravel
(ii) R.C.C M25 (a) Height upto 5M
Cum
Slab Culvert 0.00 6997.71 7942.40
Total = 0.00
Item No / Rate
SOR Ref Item Unit Quantity Rate (Including Amount
13.50%GST)
14/12.11 Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not less than
600 mm with smaller size towards the soil and bigger size
towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted
to firm condition complete as per drawing and technical
specification Clause 1204.3.8
Cum
Slab Culvert 0.00 1797.00 2039.60
Total = 0.00
15/12.9 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7 Eac
h
Slab Culvert 0.00
Box Culvert 0.00
0.00 117.66 134 0.00
16/12.7 Supplying, fitting and placing TMT bar reinforcement (Fe 415)
in substructrue complete as per drawings and technical
specification Clauses 1002, 1005, 1010 & 1202 Ton
Slab Culvert 0.00
Box Culvert 0.00
0.00 56316.20 63918.89 0.00
Backfilling behind abutment, wing wall and return wall complete as
per drawings & technical specification Clause 1204.3.8 ii)
17/12.10 (ii) Sandy material
Box Culvert 0.00 1576.00 1789
Total = 0.00
Plain/Reinforced cement concrete, in open foundation complete as
per drawing and technical specification including steel shuttering
formwork. A) With crushed stone
18/16.72 (N)A (A) 'PCC Grade M15
Box Culvert 0.00 5085.60 5772
Total = 0.00
Item No / Rate
SOR Ref Item Unit Quantity Rate (Including Amount
13.50%GST)

Plain/Reinforced cement concrete, in open foundation complete as


per drawing and technical specification including steel shuttering
formwork. N) A) With crushed
stone '(I)RCC Grade M20
19/16.72 (N) C(i) Case-I Using concrete mixer
Box Culvert 0.00 6108.90 6934
Total = 0.00
Drainage spouts complete as per drawing and technical
20/13.1 specifications Clause 1209
Box Culvert 0.00 1640.90 1862
Total = 0.00
Providing and laying cement concrete wearing course M 30 grade
including reinforcement complete as per drawing and technical
specifications Clauses 800 and 1206.3
21/13.5 (A) A) With crushed stone
Box Culvert 0.00 12407.50 14083
Total = 0.00

Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20


mm nominal size aggregate, true to line and grade, tolerance of
vertical railing post not to exceed 1 in 500, centre-to-centre spacing
between vertical posts not to exceed 2000 mm as per drawing and
22/16.99.20 technical specifications Clauses 800, 900 and 1208.3
Box Culvert 0.00 1683.00 1910
Total = 0.00
Providing and laying filter material underneath pitching in slopes
23/14.6 complete as per drawing and technical specifications Clause 1302
Box Culvert 0.00 1768.60 2007
Total = 0.00
Providing and laying of dry rubble flooring complete as per drawings
24/14.8 and technical specifications Clause 1303.3
Box Culvert 0.00 2216.80 2516
Total = 0.00
Grand Total = 0.00
0.00
Item No / Rate
SOR Ref Item Unit Quantity Rate (Including Amount
13.50%GST)

Executive Engineer , PWD


Asstt. Executive Engineer, PWD Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division Goalpara
BASIC RATES AS PER SOR 2017-18 & FINAL RATES WITH ALL LEADS

Sl. Basic Rate as


Item of Work Unit per SOR Rate with
No.
2017-18 all leads Ref. of SOR
A Road Works
Clearing and Grubbing of road land Hct 42648.30 42648.30 2.2 (I) A
Shifting of Electric Pole each 10000.00 10000.00
Dismantling of KM stones
5th km Stone No. 287.40 287.40 2.19 (a)
Ordinary km Stones No. 180.10 180.10 2.19 (b)
200 m Stones No. 35.60 35.60 2.19 (c)
Removal of Hume Pipes
(i)Upto 600 mm dia Hume pipe m 151.10 151.10 2.13(A)
(ii)Above 600 mm to 900 mm dia Hume pipe m
204.60 204.60 2.13(B)
(iii)Above 900 mm dia Hume pipe m 350.20 350.20 2.13(C)
Dismantling of Flexible Pavements
(i)Bituminous courses Cum 531.80 531.80 2.14 (I) A
(ii)Granular courses Cum 388.00 388.00 2.14 (I) B
Cutting of Trees
(i)Girth above 300 mm to 600 mm each 206.90 206.90 2.3 A (i)
(ii)Girth above 600 mm to 900 mm each 358.70 358.70 2.3 A (ii)
(iii)Girth above 900 mm to 1800 mm each 711.20 711.20 2.3 A (iii)
(iv)Girth above 1800 mm to 2700 mm each 1358.00 1358.00 2.3 A (iv)
(v)Girth above 2700 mm to 4500 mm each 2789.60 2789.60 2.3 A (v)
(vi)Girth above 4500 mm each 8199.70 8199.70 2.3 A (vi)
Excavation in Cutting in Soil by cum
manual means with lead upto 50 m
(Manual)
109.20 109.20 3.5 (i)
Construction of embankment cum 58.00 58.00 3.3
Construction of Embankment with cum
Material Obtained from Borrow Pits 230.60 230.60 3.4
Construction of Subgrade and cum
Earthen Shoulders 286.30 286.30 3.14 (i)
Granular Sub-base cum 1466.00 2465.17 4.1 (A) (ii)
WBM - Grading II cum 2732.70 3391.82 4.7 ( 2 ) A
WBM - Grading III cum 2764.60 3410.36 4.7 (3) A
Prime Coat sqm 27.90 27.90 5.1 (i)
Tack Coat sqm 10.20 10.20 5.2 (iii)
OGPC cum 132.80 144.82 5.9 , Case II (i)
Seal Coat cum 42.30 46.31 5.12 ( B )Case II ( i)
B Traffic Signs
Kilometer Stone
(i)5th Kilometre Stone (precast) each 3524.80 3524.80 10.10 (i)
(ii)Ordinary Kilometer Stone (Precast) each 2116.40 2116.40 10.10 (ii)
(iii)200 m stone (precast) each 563.20 563.20 10.10 (iii)
RCC guide post each 632.00 632.00 From analysis
Semi Reflective Traffic Signs 10.2 (B)
(i)900mm equilateral triangle each 4265.00 4265.00 (i)
(ii)600mm equilateral triangle each 2957.20 2957.20 (ii)
(iii)600mm circular each 3813.30 3813.30 (iii)
(iv)800mm x 600mm rectangular each 5141.30 5141.30 (iv)
(v)600mm x 450mm rectangular each 3725.70 3725.70 (v)
(vi)600mm x 600mm square each 4332.40 4332.40 (vi)
(vii)900mm side octagon each 7109.70 7109.70 (vii)
PMGSY logo board each 10444.05 10444.05 13.2
Citizen Information Board each 24354.72 24354.72 From analysis
Title Information Board each 21457.27 21457.27 From analysis
C Protection Work
Floor Apron/Boulder Apron cum 1349.50 2286.22 14.1
Boulder apron laid in wire crates cum 2178.20 3114.92 14.2
Stone/Boulder Pitching cum 1349.50 2286.22 14.5 (i)
Filter material cum 1768.60 2767.77 14.6
Geo-Textiles
(i)Wooven Jute Geo Textile for Road sqm
Construction and slope management 100.00 100.00 16.7 (a)
(ii)Wooven Jute Geo Textile for River sqm
Bank Protection 118.00 118.00 16.7(b)
(iii)Open weave Jute Geo Textiles for sqm
control of surficial soil erosion 45.00 45.00 16.7 (c )
D New Technology
Cell Filled Concrete Pavement 851.00 851.00 17.16 (I) (a)
TENAX 3D GRID TECHNOLOGY
148.00 148.00 17.17 (i)

E Drain

Brick masonary drain


(i)Earthwork in excavation ( upto 3m cum
depth) 102.00 102.00 11.1
(ii)Brick masonary work in cement cum
morter in substructure (In 1:4 Cement
mortar)
6925.70 6925.70 12.1 ii.
(iii)Plain/ Reinforced concrete in open Cum
foundation -(a) With crushed stone
(i) PCC grade M15
(ii) Nominal mix (1:2.5:5)
5085.60 5085.60 11.4 (A) II
(iv)Plain/ Reinforced concrete in open Cum
foundation -(a) With crushed stone
(i) PCC grade M20 (ii)
Nominal mix 1:2:4
5756.20 5756.20 11.4 (A) III
(v)Plastering with cement morter ( 1:4 , sqm
15 mm thick on brick work in
substructure)
121.17 121.17 12.3

F CD Structure
Hume Pipe Summary
(i) Earthwork in excavation for cum
structures 102.00 102.00 11.1
(ii) PCC M15 Nominal mix (1:2.5:5) cum 5085.60 5085.60 11.4 A) II
(iii) Bedding for pipe cum 1369.05 1369.05 9.2 B (ii)
(iv) Providing and Laying Reinforced RM
Cement Concrete Pipe NP3 as per
Design in Single Row
6880.50 6880.50 9.3 (B)
(v) Providing and Laying Reinforced RM
Cement Concrete Pipe NP3 as per
Design in Double Row
14560.10 14560.10 9.5 (B)
(vi) Brick Masonry Work in cement cum
mortar (1:4) 6464.44 6464.44 11.5 (II)
(vii) Providing and laying boulder
apron cum 1349.50 2286.22 14.1
(viii) Plastering sqm 121.17 121.17 12.3
(ix) Stone masonry in foundation 1:4 cum 4160.15 4160.15 11.6 (ii)
(x) Stone masonry in sub structure 1:4 cum
4582.68 4582.68 12.4 (ii)
Slab Summary
(i) Earthwork in excavation for cum
structures 102.00 102.00 11.1
(ii)) Providing concrete for cum
plain/reinforced concrete in open
foundations
5216.60 5216.60 11.4 A. (i)
(iii) Brick masonry work in cement cum
mortar in foundation (Brick masonry
in 1:4 cement mortar)
6464.40 6464.40 11.5 (ii)
(iv) Providing and laying reinforced cum
cement concrete in superstructure 6997.71 6997.71 13.1 A) I. (i)
(v) Providing and laying filter media cum
with granular crushed aggregates 1797.00 1797.00 12.11
(vi) Providing weepholes in brick each
masonry/stone masonry 117.7 117.66 12.9
(vii) Supplying, fitting and placing TMT Ton
bar reinforcement (Fe 415) in
substructrue
56316.20 56316.20 13.2
(viii) Bedding on well compacted sand, cum
moorum or approved granular material
1369.05 1369.05 9.2 B (ii)

Box Culvert Summary


(i) Backfilling behind abutment Cum 1576 1576.00 12.10 (ii)
(ii) Excavation for Structures Cum 102 102.00 11.1
(iii) Providing and laying parapet Cum 5403.90 5403.90 13.20 A (ii)
(iv) Plain/Reinforced cement concrete, Cum
in open foundation (PCC Grade M15) 5085.60 5085.60 11.4 A)ii.
(v) Plain/Reinforced cement concrete, Mt
in open foundation (RCC Grade M20) 6108.90 6108.90 11.4 A)iv
(vi) Plain/reinforced cement concrete Cum
in substructure 5379 5379.00 12.5 A I (i)
(vii) Supplying, fitting and placing TMT Mt
(Fe-500 D) reinforcement bar 55091 55091.00 12.6
(viii) Providing weepholes in brick No
masonry/stone masonry 117.7 117.70 12.9
(ix) Drainage spouts No 1640.9 1640.90 13.10
( x ) Providing and laying cement Cum
concrete wearing course M 30 grade 12407.5 12407.50 13.5 (A)
( xi ) Construction of RCC railing Rm 1683 1683.00 16.99.20
(xii) Providing and laying filter Cum
material underneath pitching in slopes 1768.6 1768.60 14.6
( xiii ) Providing and laying of dry Cum
rubble flooring 2216.8 2216.80 14.8
Name of Work :- Construction of Road from Ashigarh West Sallagarh

QUANTITY STATEMENT
FOR CORE WIDENING:- FOR CORE CUTTING FOR SHOULDER
Ch. Distance Area Mean area Volume Area Mean area Volume Area Mean area Volume
0.00 0.00 0.000 0.000 0.000 2.166 0.000 0.000 0.775 0.000 0.000
10.00 10.00 0.829 0.415 4.145 0.537 1.352 13.515 0.837 0.806 8.059
30.00 20.00 2.108 1.469 29.370 0.000 0.269 5.370 0.837 0.837 16.740
60.00 30.00 1.816 1.962 58.860 0.000 0.000 0.000 0.837 0.837 25.110
90.00 30.00 0.611 1.214 36.405 0.000 0.000 0.000 0.837 0.837 25.110
120.00 30.00 0.541 0.576 17.280 0.005 0.003 0.075 0.837 0.837 25.110
150.00 30.00 0.233 0.387 11.610 0.024 0.015 0.435 0.837 0.837 25.110
180.00 30.00 0.288 0.261 7.815 0.011 0.018 0.525 0.837 0.837 25.110
210.00 30.00 0.478 0.383 11.490 0.000 0.006 0.165 0.837 0.837 25.110
240.00 30.00 0.432 0.455 13.650 0.159 0.080 2.385 0.837 0.837 25.110
270.00 30.00 0.244 0.338 10.140 0.407 0.283 8.490 0.837 0.837 25.110
300.00 30.00 1.122 0.683 20.490 0.744 0.576 17.265 0.837 0.837 25.110
330.00 30.00 1.080 1.101 33.030 0.872 0.808 24.240 0.837 0.837 25.110
360.00 30.00 1.423 1.252 37.545 0.694 0.783 23.490 0.837 0.837 25.110
390.00 30.00 4.124 2.774 83.205 0.668 0.681 20.430 0.837 0.837 25.110
420.00 30.00 3.852 3.988 119.640 0.630 0.649 19.470 0.837 0.837 25.110
450.00 30.00 5.213 4.533 135.975 0.357 0.494 14.805 0.837 0.837 25.110
480.00 30.00 3.230 4.222 126.645 0.075 0.216 6.480 0.837 0.837 25.110
497.00 17.00 15.270 9.250 157.250 1.760 0.918 15.598 0.837 0.837 14.229

529.00 32.00 13.358 0.000 0.000 1.250 0.000 0.000 0.837 0.000 0.000
530.00 11.00 6.120 3.060 33.660 0.000 0.000 0.000 0.837 0.419 4.604
560.00 30.00 2.033 7.696 230.865 0.000 0.625 18.750 0.837 0.837 25.110
590.00 30.00 1.080 1.557 46.695 0.000 0.000 0.000 0.837 0.837 25.110
610.00 20.00 0.550 0.815 16.300 0.048 0.024 0.480 0.837 0.837 16.740
640.00 30.00 0.319 0.435 13.035 0.015 0.032 0.945 0.837 0.837 25.110
670.00 30.00 0.189 0.254 7.620 0.149 0.082 2.460 0.837 0.837 25.110
690.00 20.00 0.135 0.162 3.240 0.267 0.208 4.160 0.837 0.837 16.740
720.00 30.00 0.211 0.173 5.190 0.251 0.259 7.770 0.837 0.837 25.110
750.00 30.00 0.132 0.172 5.145 0.281 0.266 7.980 0.837 0.837 25.110
780.00 30.00 0.106 0.119 3.570 0.362 0.322 9.645 0.837 0.837 25.110
810.00 30.00 0.067 0.087 2.595 0.403 0.383 11.475 0.837 0.837 25.110
840.00 30.00 0.082 0.075 2.235 0.390 0.397 11.895 0.837 0.837 25.110
870.00 30.00 0.062 0.072 2.160 0.453 0.422 12.645 0.837 0.837 25.110
900.00 30.00 0.065 0.064 1.905 0.419 0.436 13.080 0.837 0.837 25.110
930.00 30.00 0.000 0.033 0.975 0.511 0.465 13.950 0.837 0.837 25.110
960.00 30.00 2.210 1.105 33.150 0.297 0.404 12.120 0.837 0.837 25.110
990.00 30.00 3.384 2.797 83.910 0.221 0.259 7.770 0.837 0.837 25.110
1020.00 30.00 3.428 3.406 102.180 0.181 0.201 6.030 0.837 0.837 25.110
1050.00 30.00 3.659 3.544 106.305 0.219 0.200 6.000 0.837 0.837 25.110
1080.00 30.00 1.679 2.669 80.070 0.263 0.241 7.230 0.837 0.837 25.110
1110.00 30.00 1.961 1.820 54.600 0.179 0.221 6.630 0.837 0.837 25.110
1140.00 30.00 0.010 0.986 29.565 0.247 0.213 6.390 0.837 0.837 25.110
1170.00 30.00 0.015 0.013 0.375 0.262 0.255 7.635 0.837 0.837 25.110
1200.00 30.00 0.005 0.010 0.300 0.244 0.253 7.590 0.837 0.837 25.110
1230.00 30.00 0.007 0.006 0.180 0.313 0.279 8.355 0.837 0.837 25.110
1260.00 30.00 0.001 0.004 0.120 0.310 0.312 9.345 0.837 0.837 25.110
1290.00 30.00 0.002 0.002 0.045 0.382 0.346 10.380 0.837 0.837 25.110
1320.00 30.00 0.000 0.001 0.030 0.401 0.392 11.745 0.837 0.837 25.110
1350.00 30.00 0.001 0.001 0.015 0.321 0.361 10.830 0.837 0.837 25.110
1380.00 30.00 0.402 0.202 6.045 0.323 0.322 9.660 0.837 0.837 25.110
1410.00 30.00 0.436 0.419 12.570 0.215 0.269 8.070 0.837 0.837 25.110
1440.00 30.00 1.590 1.013 30.390 0.224 0.220 6.585 0.837 0.837 25.110
1470.00 30.00 1.548 1.569 47.070 0.184 0.204 6.120 0.837 0.837 25.110
1500.00 30.00 1.603 1.576 47.265 0.174 0.179 5.370 0.837 0.837 25.110
1520.00 20.00 0.720 1.162 23.230 0.129 0.152 3.030 0.837 0.837 16.740
1550.00 30.00 0.009 0.365 10.935 0.276 0.203 6.075 0.837 0.837 25.110
1580.00 30.00 0.000 0.005 0.135 0.402 0.339 10.170 0.837 0.837 25.110
1610.00 30.00 0.000 0.000 0.000 0.526 0.464 13.920 0.837 0.837 25.110
1640.00 30.00 0.407 0.204 6.105 0.366 0.446 13.380 0.837 0.837 25.110
1670.00 30.00 0.355 0.381 11.430 0.173 0.270 8.085 0.837 0.837 25.110
1700.00 30.00 0.279 0.317 9.510 0.059 0.116 3.480 0.837 0.837 25.110
1710.00 10.00 0.373 0.326 3.260 0.023 0.041 0.410 0.837 0.837 8.370
1740.00 30.00 0.439 0.406 12.180 0.007 0.015 0.450 0.837 0.837 25.110
1770.00 30.00 0.546 0.493 14.775 0.000 0.004 0.105 0.837 0.837 25.110
1800.00 30.00 1.233 0.890 26.685 0.230 0.115 3.450 0.837 0.837 25.110
TOTAL= 2042.165 TOTAL= 504.383 TOTAL= 1483.272

Deduct re-use of
cutting soil for = 504.383
filling
Total = 1587.45

Asstt. Executive Engineer, PWD Executive Engineer , PWD


Morigaon Rural Road Sub Division Goalpara Rural Road Division
Mayong Goalpara
Statement No. - 6
Quantity Calculation of 1000mm dia Single HP Culvert

Name of Road : . Betani to Baralimari Pathar

Depth/
Sl.No. Item Unit No Length Breadth Quantity
Thickness
1 Earthwork in
exacavation cum
Face Wall 2 1.400 5.400 1.200 18.144
Bed 1 5.400 1.530 0.550 4.544
Total = 22.688
2 C.C.Work in
Proportion 1:3:6 cum
Face Wall 2 1.400 5.400 0.150 2.268
Total = 2.268
3 Bedding cum
Bedding 1 7.500 1.530 0.550 6.311
Deduct for pipe 0.220
Total = 6.091
4 Stone Masonary in
CM 1:4 cum
Fndtn wall 2 5.100 (1.25+1.05)/2 1.500 17.595
17.595
Sub strctr wall 2 5.1 0.83 2.640 22.350
Deduct of pipe 1.840
Parapet wall 0 0.000 0.000 0 0.000

Total = 20.510
5 Plastering sqm
Outer side of Face
wall 2 5.100 1.500 15.300
Deduct for pipe 2 1.130 -2.260
Top 2 5.1 0.4 4.080
Inner Side of Face 2 5.1 0.6 6.120
End sidewall
of the
face wall (top) 4 0.400 0.600 0.960
End side of the face wall 4 0.600 1.2 2.880
Total = 27.08
6 NP3 HP Rm 7.50m 7.50
Total = 0.00
Statement No. - 7
Quantity Calculation of 1000mm dia Double HP Culvert
Considering Length = 7.50m

Name of Road: . Betani to Baralimari Pathar

Depth/
Sl.No. Item Unit No Length Breadth Quantity
Thickness
1 Earthwork in cum
exacavation
Face Wall 2 9.340 1.600 1.950 58.282
Bed 1 10.340 1.600 0.550 9.099
Total = 67.381
2 C.C.Work in cum
Proportion 1:3:6
Face Wall 2 9.140 1.400 0.150 3.839
Total = 3.839
3 Bedding cum
Bedding 1 10.340 3.380 0.550 19.222
Deduct for pipe 2 10.340 0.308 1.000 6.365
Total = 12.857
4 Stone Masonary in cum
CM 1:4
Foundation 2 8.850 (1.25+1.05)/2 1.500 30.533
Sub structure 2 8.850 (1.05+0.4)/2 1.920 24.638
Deduct for pipe 2 (0.83+0.4)/2 2 1.130 2.780
Total = 52.391
5 Plastering sqm
Outer side of Face
wall 2 8.850 1.800 31.860
Deduct of pipe 4 1.000 1.130 -4.520
Top 2 8.850 0.400 7.080
Inner Side of face
wall 2 8.850 0.600 10.620
End side of face
wall (Top) 4 0.400 0.6 0.960
End side of face
wall 4 0.60 1.20 2.88
Total = 48.880
6 NP3 HP Rm 8 2.5 20.00
Earth work in
7 cushioning Cum 8.85 10.7 0.725 68.65
2 10 (10.7+6.00)*1/2 0.3 50.10
Total = 118.75
CROSS DRAINAGE WORKS
Format - F7A
Name of Road : . Betani to Baralimari Pathar

Type of Cross Drainage works :


1. Single Hume Pipe Culvert (1000mm dia)

Sl. Length Width Thickness Rate in


Description of Item Item No. Unit Quantity
No (m) (m) (m) (Rs)

1 2 3 4 5 6 7 8 9
Earthwork in excavation for foundation of structures upto 3 m
depth as per drawing and technical specification Clause 1104
includding setting out, construction of shoring and bracing, 9.1/1100
1 removal of stumps and other deleterious matter, dressing of sides Qty. as per Statement No. - 8 Cum 22.688 102.00
& 300
and bottom and backfilling with approved material.
Rate as per SOR 2016-17
Plain Cement Concrete M15 (1:3:6 nominal mix) in levelling
course below open foundation of Head walls as per drawings & 9.9 / 1100
2 Technical Specification Clause 1109 Qty. as per Statement No. - 8 Cum 2.268 5085.60
& 800
Rate as per SOR 2016-17

Bedding for pipe


(ii) Type B(First Class) Bedding
Laying (First Class) bedding on well compacted sand moorum as 9.2 / 1100
3 per Clause 1105(ii) Qty. as per Statement No. - 8 Cum 6.091 1369.05
& 800
(ii) Granular material
Rate as per SOR 2016-17
Sl. Length Width Thickness Rate in
Description of Item Item No. Unit Quantity
No (m) (m) (m) (Rs)

1 2 3 4 5 6 7 8 9
Stone masonry work in cement mortar in foundation complete as
per drawing and technical specifications Clauses 702, 704, 1202 &
11.6 / 700
4 1203. Qty. as per Statement No. - 8 Cum 17.595 4160.15
II. In 1:4 cement mortar & 1200
Rate as per SOR PMGSY - 2016-17
Stone masonry work in cement mortar in sub structure complete as
per drawing and technical specifications Clauses 702, 704, 1202 &
12.4 / 704
4 1203. Qty. as per Statement No. - 8 Cum 20.510 4582.68
II. In 1:4 cement mortar & 1202
Rate as per SOR PMGSY - 2016-17
Sl. Length Width Thickness Rate in
Description of Item Item No. Unit Quantity
No (m) (m) (m) (Rs)

1 2 3 4 5 6 7 8 9
Plastering with cement mortar (1:4), 15 mm thick on brickwork in
5 substructure as per technical specification Clauses 613.4 & 1204 12.3 / 600 Qty. as per Statement No. - 8 10sqm 2.708 121.17
Rate as per SOR 2016-17
Providing and laying reinforced cement concrete pipe NP3 for
culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding
6 excavation, protection works, backfilling, concrete and masonry 9.3 / 1100 Qty. as per Statement No. - 8 Rm 7.500 6880.50
works in head walls and parapets Clause 1106.
(B) 1000 mm dia
Rate as per F-8

Construction of subgrade and earthen shoulders with approved


material obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope and 3.4 /
7 compacted to meet requirement of Table 300.2 with lead upto 1000 Qty. as per Statement No. - 8 Cum 0.000 209.00
301.5
m as per Technical Specification Clause 303.1.
(i) Private Land (for Earth Work in cushioning)
Total =
Format - F7A

Rate
inclusive of
Amount in
GST
(Rs.)
@13.5%
(Rs)

10

115.77 2626.60

5772.16 13091.25

1553.87 9465.02
Rate
inclusive of
Amount in
GST
(Rs.)
@13.5%
(Rs)

10

4721.77 83079.61

5201.34 106679.42
Rate
inclusive of
Amount in
GST
(Rs.)
@13.5%
(Rs)

10

137.53 372.42

7809.37 58570.26

237.22 0.00

273884.58
FORMAT F-7
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
Road from PACKAGE NO :
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur DISTRICT :
TYPE OF CROSS DRAINAGE WORKS : Double Hume Pipe (DHP 2x1000 mm Dia.) DESIGN DISCHARGE : 3.00 Cumec
BLOCK : Krishnai TYPE OF SOILL:

Item No /
SOR Ref Item Unit No. Length Breadth Height Quantity Rate

1/11.1 Earthwork in excavation for structures as per drawing and


technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
sides and bottom and backfilling in trenches with excavated suitable
material.

Cum
(I) Ordinary soil
2 6.75 1.40 1.800 34.020
1 5.00 3.30 0.550 9.075
Total = 43.095 102.00
2/9.9 Plain Cement Concrete M15 (1:3:6 nominal mix) in levelling course
below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Rate as per SOR 2016-17

Cum
2 6.45 1.40 0.15 2.709
Total = 2.709 5085.60
3/9.2 Bedding for Pipe
(ii) Type B (First Class) Bedding
Laying (First Class) bedding on well compacted sand, moorum or
approved granular material as per Clause 1105 (ii)
(ii) Granular material
Bedding cum 1 5.588 3.30 0.550 10.142
Total = 10.142 1369.05
Item No /
SOR Ref Item Unit No. Length Breadth Height Quantity Rate

4/9.5
Providing and Laying Reinforced Cement Concrete Pipe NP3
as per Design in Double Row
Providing and laying reinforced cement concrete pipe NP3 for
culverts on first class bedding of granular material in double row
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets as per Clause 1106.
(B) 1000 mm dia RM 6 2.50 15.00
Total = 15.00 14560.10
5/9.8 Brick Masonry Work in cement mortar in foundation of Head walls
complete exculding pointing and plastering as per drawing and
technical specification Clause 1109
I. Brick masonry in 1:3 cement mortar
Head wall 2 0.825 6.15 3.12 31.660
deduct 2 0.825 1.130 -1.865
Total = 29.795 6464.44
6/14.1 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per drawing
and technical specifications Clause 1301
Up stream cum 6.15 1.5 0.3 2.768
Down stream cum 6.15 3.00 0.3 5.535
Total = 8.303 2286.22
7/9.11 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in
substructure as per technical specification
sqm 2 6.15 1.92 23.616
sqm 4 0.825 1.92 6.336
sqm 2 6.15 0.40 4.920
sqm 2 6.15 0.62 7.651
deduct sqm 1.13 -1.13
Total = 41.392 121.17
Grand Total =
Item No /
SOR Ref Item Unit No. Length Breadth Height Quantity Rate

Executive Engineer , PWD


Asstt. Executive Engineer, PWD Goalpara Rural Road Divis
Goalpara/Dudhnoi Rural Road Sub Division Goalpara
MANTRI GRAM SADAK YOJANA (PMGSY)
N OF CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
AS-07-
Goalpara

Aluvial

Rate
(Including Amount
13.50%GST)

115.77 4989.00

5772.16 15637.00

1553.87 15759.00
Rate
(Including Amount
13.50%GST)

16525.71 247886.00

7337.14 218610.00

2594.86 21545.00

137.53 5692.00
Grand Total = 530118.00
###
Rate
(Including Amount
13.50%GST)

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
FORMAT F-7
Hume Pipe Summary

Item No / Rate
SOR Ref Single Double
Item Unit Quantity Rate (Including Amount
Hume Pipe Hume Pipe
13.50%GST)
0.00 0.00
1/11.1 Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
sides and bottom and backfilling in trenches with excavated suitable
material.

Cum
(I) Ordinary soil
22.69 34.020 0.000
9.075 0.000
Total = 0.000 102.00 115.77 0.00
2/9.9 Plain Cement Concrete M15 (1:3:6 nominal mix) in levelling course
below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Rate as per SOR 2017-18

Cum
2.27 2.71 0.000
Total = 0.000 5085.60 5772.16 0.00
3/9.2 Bedding for Pipe
(ii) Type B (First Class) Bedding
Laying (First Class) bedding on well compacted sand, moorum or
approved granular material as per Clause 1105 (ii)
(ii) Granular material
Bedding cum 6.09 10.142 0.000
Total = 0.000 1369.05 1553.87 0.00
Item No / Rate
SOR Ref Single Double
Item Unit Quantity Rate (Including Amount
Hume Pipe Hume Pipe
13.50%GST)
4/9.5
Providing and Laying Reinforced Cement Concrete Pipe NP3
as per Design in Double Row
Providing and laying reinforced cement concrete pipe NP3 for
culverts on first class bedding of granular material in double row
including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets as per Clause 1106.
(B) 1000 mm dia RM 15.00 0.00
Total = 0.00 14560.10 16525.71 0.00
5/9.8 Brick Masonry Work in cement mortar in foundation of Head walls
complete exculding pointing and plastering as per drawing and
technical specification Clause 1109
I. Brick masonry in 1:3 cement mortar
Head wall 29.795 0.000

Total = 0.000 6464.44 7337.14 0.00


6/14.1 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry complete as per drawing
and technical specifications Clause 1301
Up stream cum 2.768 0.000
Down stream cum 5.535 0.000
Total = 0.000 2286.22 2594.86 0.00
7/9.11 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in
substructure as per technical specification
sqm 23.62 0.000
sqm 6.34 0.000
sqm 4.92 0.000
sqm 7.65 0.000
deduct sqm -1.13 0.000
Total = 0.000 121.17 137.53 0.00
Item No / Rate
SOR Ref Single Double
Item Unit Quantity Rate (Including Amount
Hume Pipe Hume Pipe
13.50%GST)
Stone masonry work in cement mortar in foundation complete as per
drawing and technical specifications Clauses 702, 704, 1202 &
8/11.6 1203. Cum 17.595 0
II. In 1:4 cement mortar
Rate as per SOR PMGSY - 2017-18

Total = 0 4160.153035 4721.774 0.00


Stone masonry work in cement mortar in sub structure complete as
per drawing and technical specifications Clauses 702, 704, 1202 &
9/12.4 1203. Cum 20.51 0
II. In 1:4 cement mortar
Rate as per SOR PMGSY - 2017-18

Total = 0 4582.675687 5201.337 0.00


Plastering with cement mortar (1:4), 15 mm thick on brickwork in
substructure as per technical specification Clauses 613.4 & 1204 10sq
10/12.3 2.708 0
Rate as per SOR 2017-18 m

Total = 0 121.168 137.526 0.00


Providing and laying reinforced cement concrete pipe NP3 for
culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding
11/9.3 excavation, protection works, backfilling, concrete and masonry Rm 7.5 0
works in head walls and parapets Clause 1106.
(B) 1000 mm dia

Total = 0 6880.5 7809.368 0.00


Grand Total = 0.00
0.00

Executive Engineer , PWD


Asstt. Executive Engineer, PWD Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division Goalpara
ANALYSIS OF 1.5 M SPAN SLAB CULVERT FORM
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
Road Name: Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur PACKAGE NO :
DISTRICT :
BLOCK : Krishnai TYPE OF SOILL:

ABUTMENT
HEIGHT OF ABUTMENT = 0.800 m
SPAN = 1.500 m
OVERALL SPAN = 2.300 m
WIDTH = 6.000 m
SLAB THICK = 0.210 m

RETURN WALL
HEIGHT OF RETURN WALL = 1.360 m
LENGTH = 0.650 m
TOP WIDTH = 0.400 m
FOUNDATION DEPTH = 1.200 m
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

1/11.1 Earthwork in excavation for structures as per drawing and


technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
side
(I) Ordinary Soil
Upto 3 m depth
Cum
Abutment 2 2.14 6.40 1.40 38.35
Return Wall 4 2.14 1.05 1.40 12.58
Total = 50.93 102.00 115.77
2/9.7 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203
A. With crushed stone.
(I) P.C.C grade M 10
Nominal mix 1:3:6
Cum
Below Abutment 2 2.14 6.40 0.20 5.48
Below Return Wall 4 2.14 1.05 0.20 1.80
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

Total = 7.28 5216.60 5920.84


3/11.6 Brick masonry work in cement mortar in foundation complete
excluding pointing and plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203
(I) Brick masonry in 1:3 cement mortar Cum
Above Ground Level
Abutment Walls 2 6.00 0.70 0.800 6.72
2 6.00 (1/2*0.44*1.32) 3.48
Return Wall 4 0.65 0.40 1.880 1.96
4 0.65 (1/2*0.63*1.88) 1.54
Below Ground Level
Abutment Walls 2 6.00 1.34 1.40 22.51
2 6.00 (1/2*0.60*1.4) 5.04
Return Wall 4 0.65 1.23 1.400 4.48
4 0.65 (1/2*0.5*1.4) 0.91
Total = 46.63 6464.40 7337.09
4/13.1 Providing and laying reinforced cement concrete in
superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5
(A) With crushed stone
I. R.C.C grade M 20 (I) For nominal mix 1:2:4
(a) Height upto 5 M
Cum
Cap 2 0.70 6.00 0.20 1.68
Dirt wall 2 0.40 6.00 0.24 1.15
Slab 1 6.00 2.30 0.21 2.90
Kerb 1 2.30 0.30 0.45 0.31
RCC Pillars at Start and at End 6 0.40 0.40 0.60 0.58
Total = 6.62 6997.71 7942.40
5/12.11 Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not less than
600 mm with smaller size towards the soil and bigger size
towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted to
firm condition complete as per drawing and technical
specification Clause 1204.3.8
Cum
Along Abutment Walls 2 1.39 6.00 0.60 10.01
Along Return Wall 4 1.98 2.00 0.60 9.50
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

Total = 19.51 1797.00 2039.60


6/12.9 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7
Each
Along Abutment Walls 8 8
Along Return Wall 8 8
Total = 16 117.66 133.54
7/13.2 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar .
(From Primary Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) in superstructure complete as per
drawing and technical specifications Clauses 1002, 1010 and
1202 Ton
12 mm Tor
(i) Abutment Cap
Main Bars 7 4 5.90 165.20
(ii) Back Wall
Main Bars 4 4 5.90 94.40
(iii) Kerb
Main Bars 4 2 2.20 17.60
(iv) Pillars
Main Bars 4 6 0.60 14.40
Total = 291.60
@ 0.62 Kg./Rm = 0.18
8 mm Tor
(i) Abutment Cap Distribution Rft 48 4 0.60 115.20
(ii) Back Wall Distribution Rft 48 4 0.14 26.88
(iii) Kerb Distribution Rft 19 2 0.45 17.10
(iv) Pillars 5 6 1.36 40.80
Total = 199.98
@ 0.39 Kg./Rm = 0.08
20 mm Tor
Deckslab: Bottom Rft.: Along long. Dir. 48 2.60 124.80
At Kerb 4 2 2.30 18.40
Total = 143.20
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

@ 2.47 Kg./Rm = 0.35


12 mm Tor
Deckslab: Bottom Rft: Along Transverse direction 18 6.30 113.40
Top Rft: Along Long. Direction 40 2.60 104.00
Top Rft: Along Transverse Direction 16 6.30 100.80
Side Rft. 4 5.90 23.60
Total = 341.80
@ 0.62 Kg./Rm = 0.21
Total = 0.82 56316.20 63918.89
Grand
Total
= =
Say

Executive Engineer , PWD


Asstt. Executive Engineer, PWD
Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division
Goalpara
OF 1.5 M SPAN SLAB CULVERT FORMAT F-7
RI GRAM SADAK YOJANA (PMGSY)
CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
AS-07-
Goalpara
Aluvial

Amount

5896.00
Amount

43080.00

342158.00

52551.00
Amount

39797.00

2137.00
Amount

52695.00
538314.00
538310.00

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
ANALYSIS OF 2.0 M SPAN SLAB CULVERT FORM
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
Road Name: Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur PACKAGE NO :
DISTRICT :
BLOCK : Krishnai TYPE OF SOILL:

ABUTMENT
HEIGHT OF ABUTMENT = 1.320 m
SPAN = 2.000 m
OVERALL SPAN = 2.800 m
WIDTH = 6.000 m
SLAB THICK = 0.240 m

RETURN WALL
HEIGHT OF RETURN WALL = 1.880 m
LENGTH = 2.000 m
TOP WIDTH = 0.400 m
FOUNDATION DEPTH = 1.400 m
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

1/11.1 Earthwork in excavation for structures as per drawing and


technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
side
(I) Ordinary Soil
Upto 3 m depth
Cum
Abutment 2 2.14 6.40 1.60 43.83
Return Wall 4 2.14 2.40 1.60 32.87
Total = 76.70 102.00 115.77
2/9.7 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203
A. With crushed stone.
(I) P.C.C grade M 10
Nominal mix 1:3:6
Cum
Below Abutment 2 2.14 6.40 0.20 5.48
Below Return Wall 4 2.14 2.40 0.20 4.11
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

Total = 9.59 5216.60 5920.84


3/11.6 Brick masonry work in cement mortar in foundation complete
excluding pointing and plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203
(I) Brick masonry in 1:3 cement mortar Cum
Above Ground Level
Abutment Walls 2 6.00 0.70 1.320 11.09
2 6.00 (1/2*0.44*1.32) 3.48
Return Wall 4 2.00 0.40 1.880 6.02
4 2.00 (1/2*0.63*1.88) 4.74
Below Ground Level
Abutment Walls 2 6.00 1.34 1.40 22.51
2 6.00 (1/2*0.60*1.4) 5.04
Return Wall 4 2.00 1.23 1.400 13.78
4 2.00 (1/2*0.5*1.4) 2.80
Total = 69.45 6464.40 7337.09
4/13.1 Providing and laying reinforced cement concrete in
superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5
(A) With crushed stone
I. R.C.C grade M 20 (I) For nominal mix 1:2:4
(a) Height upto 5 M
Cum
Cap 2 0.70 6.00 0.20 1.68
Dirt wall 2 0.40 6.00 0.24 1.15
Slab 1 6.00 2.80 0.24 4.03
Kerb 1 2.80 0.30 0.45 0.38
RCC Pillars at Start and at End 6 0.40 0.40 0.60 0.58
Total = 7.82 6997.71 7942.40
5/12.11 Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not less than
600 mm with smaller size towards the soil and bigger size
towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted to
firm condition complete as per drawing and technical
specification Clause 1204.3.8
Cum
Along Abutment Walls 2 1.39 6.00 0.60 10.01
Along Return Wall 4 1.98 2.00 0.60 9.50
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

Total = 19.51 1797.00 2039.60


6/12.9 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7
Each
Along Abutment Walls 8 8
Along Return Wall 8 8
Total = 16 117.66 133.54
7/13.2 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar .
(From Primary Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) in superstructure complete as per
drawing and technical specifications Clauses 1002, 1010 and
1202 Ton
12 mm Tor
(i) Abutment Cap
Main Bars 7 4 5.90 165.20
(ii) Back Wall
Main Bars 4 4 5.90 94.40
(iii) Kerb
Main Bars 4 2 2.70 21.60
(iv) Pillars
Main Bars 4 6 0.60 14.40
Total = 295.60
@ 0.62 Kg./Rm = 0.18
8 mm Tor
(i) Abutment Cap Distribution Rft 48 4 0.60 115.20
(ii) Back Wall Distribution Rft 48 4 0.14 26.88
(iii) Kerb Distribution Rft 23 2 0.45 20.70
(iv) Pillars 5 6 1.36 40.80
Total = 203.58
@ 0.39 Kg./Rm = 0.08
20 mm Tor
Deckslab: Bottom Rft.: Along long. Dir. 48 3.10 148.80
At Kerb 4 2 2.80 22.40
Total = 171.20
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

@ 2.47 Kg./Rm = 0.42


12 mm Tor
Deckslab: Bottom Rft: Along Transverse direction 22 6.30 138.60
Top Rft: Along Long. Direction 40 3.10 124.00
Top Rft: Along Transverse Direction 19 6.30 119.70
Side Rft. 4 5.90 23.60
Total = 405.90
@ 0.62 Kg./Rm = 0.25
Total = 0.94 56316.20 63918.89
Grand
Total
= =
Say

Executive Engineer , PWD


Asstt. Executive Engineer, PWD
Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division
Goalpara
OF 2.0 M SPAN SLAB CULVERT FORMAT F-7
RI GRAM SADAK YOJANA (PMGSY)
CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
AS-07-
Goalpara
Aluvial

Amount

8879.00
Amount

56763.00

509576.00

62094.00
Amount

39797.00

2137.00
Amount

59904.00
739150.00
739150.00

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
ANALYSIS OF 4.0 M SPAN SLAB CULVERT FOR
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
Road Name: Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur PACKAGE NO :
DISTRICT :
BLOCK : Krishnai TYPE OF SOILL:

ABUTMENT
HEIGHT OF ABUTMENT = 3.090 m
SPAN = 4.000 m
OVERALL SPAN = 4.800 m
WIDTH = 7.500 m
SLAB THICK = 0.370 m

RETURN WALL
HEIGHT OF RETURN WALL = 3.610 m
LENGTH = 2.500 m
TOP WIDTH = 0.400 m
FOUNDATION DEPTH = 1.400 m
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

1/11.1 Earthwork in excavation for structures as per drawing and


technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
side (I) Ordinary Soil Upto 3 m depth Cum
Abutment 2 3.70 7.50 1.60 88.68
Return Wall 4 3.70 2.22 1.60 52.50
Total = 141.18 102.00 115.77
2/9.7 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203
A. With crushed stone. (I) P.C.C grade M 10 Nominal mix 1:3:6
Cum
Below Abutment 2 3.70 7.50 0.20 11.09
Below Return Wall 4 3.70 2.22 0.20 6.56
Total = 17.65 5216.60 5920.84
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

3/11.5 Brick masonry work in cement mortar in foundation complete


excluding pointing and plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203
(I) Brick masonry in 1:3 cement mortar Cum
Below Ground Level
(2.395+2.995)
Abutment Walls 2 7.50 1.40 56.60
2
(2.71+2.11)
Return Wall 2 2.50 1.40 16.87
2
Above Ground Level
(2.245+0.7)
Abutment Walls 2 7.50 3.09 68.25
2
(1.96+0.40)
Return Wall 2 2.50 3.61 21.30
2
Total = 163.01 6464.40 7337.09
4/13.1 Providing and laying reinforced cement concrete in
superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5 B. With Natural Gravel (ii)
R.C.C M25 (a) Height upto 5M
Cum
Cap 2 0.70 7.50 0.20 2.10
Dirt wall 2 0.37 7.50 0.30 1.67
Slab 1 7.50 4.80 0.37 13.32
Kerb 2 4.80 0.30 0.45 1.30
Total = 18.38 6997.71 7942.40
5/12.9 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7
Each
Along Abutment Walls 8 8
Along Return Wall 8 8
Total = 16 117.66 133.54
6/12.7 Supplying, fitting and placing TMT bar reinforcement (Fe 415) in
substructrue complete as per drawings and technical
specification Clauses 1002, 1005, 1010 & 1202 Ton
12 mm Tor
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

(i) Abutment Cap


Main Bars 7 4 7.40 207.20
(ii) Back Wall
Main Bars 4 4 7.40 118.40
(iii) Kerb
Main Bars 4 2 4.70 37.60
Total = 363.20
@ 0.62 Kg./Rm = 0.23
8 mm Tor
(i) Abutment Cap Distribution Rft 60 4 0.60 144.00
(ii) Back Wall Distribution Rft 60 4 0.20 48.00
(iii) Kerb Distribution Rft 39 2 0.45 35.10
Total = 227.10
@ 0.39 Kg./Rm = 0.09
20 mm Tor
Deckslab: Bottom Rft.: Along long. Dir. 65 5.10 331.50
Deckslab: Top Rft.: Along long. Dir. 65 5.10 331.50
At Kerb 4 2 4.80 38.40
Total = 701.40
@ 2.47 Kg./Rm = 1.73
12 mm Tor
Deckslab: Bottom Rft: Along Transverse direction 32 7.80 249.60
Top Rft: Along Transverse Direction 50 7.80 390.00
Side Rft. 4 7.40 29.60
Total = 669.20
@ 0.89 Kg./Rm = 0.60
Total = 2.64 56316.20 63918.89
7/9.2 (ii) Type B (First Class) Bedding
Laying (First Class) bedding on well compacted sand, moorum or
approved granular material as per Clause 1105 (ii) Cum
1 7.5 4.00 0.05 1.50
Total = 1.50 1369.05 1553.87
Grand Total =
Say =
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit No. Length Breadth Height Quantity Rate (Including
13.50%GST)

#REF! #REF!
F 4.0 M SPAN SLAB CULVERT FORMAT F-7
GRAM SADAK YOJANA (PMGSY)
OSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
AS-07-
Goalpara
Aluvial

Amount

16344.00

104485.00
Amount

1196052.00

145989.00

2137.00
Amount

168861.00

2331.00
1636199.00
1636200.00
Amount

#REF!
FORMAT F-7
Slab Summary

Item No/
SOR Ref / Rate
MoRTH Ref Description Unit 1.5 m 2.0 m 3.0 m 4.0 m Quantity Rate (Including
13.50%GST)

0.00 0.00 0.00 0.00


1/11.1 Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
side (I) Ordinary Soil Upto 3 m depth Cum
Abutment 38.35 43.83 0.00 88.68 0.00
Return Wall 12.58 32.87 0.00 52.50 0.00
Total = 0.00 102.00 115.77
2/9.7 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203
A. With crushed stone. (I) P.C.C grade M 10 Nominal mix 1:3:6
Cum
Below Abutment 5.48 5.48 0.00 11.09 0.00
Below Return Wall 1.80 4.11 0.00 6.56 0.00
Total = 0.00 5216.60 5920.84
3/11.5 Brick masonry work in cement mortar in foundation complete
excluding pointing and plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203
(I) Brick masonry in 1:3 cement mortar Cum
Below Ground Level
Abutment Walls 28 27.55 56.60 0.00
Return Wall 5 16.58 16.87 0.00
Above Ground Level
Abutment Walls 10 14.57 68.25 0.00
Return Wall 3 10.76 21.30 0.00
Total = 0.00 6464.40 7337.09
4/13.1 Providing and laying reinforced cement concrete in
superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5 B. With Natural Gravel (ii)
R.C.C M25 (a) Height upto 5M
Cum
Cap 1.68 1.68 2.10 0.00
Dirt wall 1.15 1.15 1.67 0.00
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit 1.5 m 2.0 m 3.0 m 4.0 m Quantity Rate (Including
13.50%GST)

Slab 2.90 4.03 13.32 0.00


Kerb 0.31 0.38 1.30 0.00
RCC Pillars at Start and at End 0.58 0.58 0.00
Total = 0.00 6997.71 7942.40
5/12.11 Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not less than
600 mm with smaller size towards the soil and bigger size
towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted to
firm condition complete as per drawing and technical
specification Clause 1204.3.8
Cum
Along Abutment Walls 10.01 10.01 0.00 0.00
Along Return Wall 9.50 9.50 0.00 0.00
Total = 0.00 1797.00 2039.60
5/12.9 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7
Each
Along Abutment Walls 8.00 8.00 8.00 0
Along Return Wall 8.00 8.00 8.00 0
Total = 0 117.66 133.54
6/12.7 Supplying, fitting and placing TMT bar reinforcement (Fe 415) in
substructrue complete as per drawings and technical
specification Clauses 1002, 1005, 1010 & 1202 Ton
12 mm Tor
(i) Abutment Cap
Main Bars 165.20 165.20 207.20 0.00
(ii) Back Wall
Main Bars 94.40 94.40 118.40 0.00
(iii) Kerb
Main Bars 17.60 21.60 37.60 0.00
(iv) Pillars
Main Bars 14.40 14.40 0.00
Total = 0.00
@ 0.62 Kg./Rm = 0.00
Item No/
SOR Ref / Rate
MoRTH Ref Description Unit 1.5 m 2.0 m 3.0 m 4.0 m Quantity Rate (Including
13.50%GST)

8 mm Tor
(i) Abutment Cap Distribution Rft 115.20 115.20 144.00 0.00
(ii) Back Wall Distribution Rft 26.88 26.88 48.00 0.00
(iii) Kerb Distribution Rft 17.10 20.70 35.10 0.00
(iv) Pillars 40.80 40.80 0.00
Total = 0.00
@ 0.39 Kg./Rm = 0.00
20 mm Tor
Deckslab: Bottom Rft.: Along long. Dir. 124.80 148.80 331.50 0.00
Deckslab: Top Rft.: Along long. Dir. 331.50 0.00
At Kerb 18.40 22.40 38.40 0.00
Total = 0.00
@ 2.47 Kg./Rm = 0.00
12 mm Tor
Deckslab: Bottom Rft: Along Transverse direction 113.40 138.60 249.60 0.00
Top Rft: Along Long. Direction 104.00 124.00 0.00
Top Rft: Along Transverse Direction 100.80 119.70 390.00 0.00
Side Rft. 23.60 23.60 29.60 0.00
Total = 0.00
@ 0.89 Kg./Rm = 0.00
Total = 0.00 56316.20 63918.89
7/9.2 (ii) Type B (First Class) Bedding
Laying (First Class) bedding on well compacted sand, moorum or
approved granular material as per Clause 1105 (ii) Cum
1.50 0.00
Total = 0.00 1369.05 1553.87
Grand Total =
Say =

Executive Engineer , PWD


Asstt. Executive Engineer, PWD
Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division
Goalpara
FORMAT F-7

Amount

0.00

0.00

0.00
Amount

0.00

0.00

0.00
Amount

0.00

0.00
0.00
0.00

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
Cost Estimate for Causway.

Causway at Ch. 500.0m to 522.00m

Quantit Rate in
S.No. Description of Item No. L B H unit Unit
y Rs.

1/ Earth work in excavation of foundation of structures as


12.1 per drawing and technical specifications clause 305.1
A including setting out,construction of shoring and
bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m dressing of
sides and bottom and backfilling in tranches with
excavated suitable
material. .....Face Wall
2 21.5 2.0 1.55 m3 133.30 Cum
For Toe wall 2 21.5 0.75 0.75 m3 24.19 Cum
For Protection Work
U/S 1 21.5 5.0 0.6 m3 64.50 Cum
D/S 1 21.5 3.0 0.6 m3 38.70 Cum
260.69 102.00
2/ Providing concrete for plain/reinforced concrete in open
11.4 A foundations complete as per drawing and Technical
I specifications Clause 802, 803, 1202, & 1203.(PCC
Grade M-10) (I) Nominal Mix. PCC
Grade M10

Face Wall 2 21.5 2.0 0.15 m3 12.90 Cum


For Toe wall 2 21.5 0.75 0.15 m3 4.84 Cum
17.74 5216.60
Plain Cement Concrete M15 (1:3:6 nominal mix) in
9.9 / levelling course below open foundation of Head walls
1100 & as per drawings & Technical Specification Clause 1109
800

Below PCC Pavement


1 21.50 7.28 0.15 m3 23.49 Cum
23.49 5286.00
Bedding for pipe
(ii) Type B(First Class) Bedding
Laying (First Class) bedding on well compacted sand
9.2 / moorum as per Clause 1105(ii)
1100 (i) Sand Filling
Below Face Wall
& 800 1 21.50 6.85 0.25 m3 36.82 Cum
36.82 969.00
3/ 12.4 A Stone
III masonry work in cement mortar in sub structure
complete as per drawing and technical specifications
Clauses 702, 704, 1202 & 1203.
II. In 1:4 cement mortar
Face Wall
2 21.5 1.50 2.85 m3 183.83 Cum
For Toe wall
2 21.5 0.45 0.6 m3 11.61 Cum
For Kerb
20 1 0.25 0.25 m3 1.25 Cum
Deduct pipe portion
2 3.14 X 1.20 10 -75.36
121.33 3207.00
3/ 11.4 A Providing
III and laying reinforced cement concrete pipe
NP3 for culverts on first class bedding of granular
material in single row including fixing collar with
cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head
walls and parapets Clause 1106.
(B) 1000 mm dia

10 7.5 Rm 75.00 Rm 6235.00


12/ Providing and laying boulder apron for bed protection
14.1 with stone boulders of minimum size and weight as per
table 1300.1, no fragment weighing not less than 25kg
laid dry complete as per drawings and technical
specifications clause 1301.

Upstream 1 21.5 5.00 0.60 m3 64.50 Cum


Downstream 1 21.5 3.00 0.60 m3 38.70 Cum
103.20 1349.50
3/ 12.4 A Stone
III masonry work in cement mortar in sub structure
complete as per drawing and technical specifications
Clauses 702, 704, 1202 & 1203.
II. In 1:4 cement mortar
3/ 12.4 A III

Face Wall
2 46 7.48 0.15 m3 103.22 Cum
103.22 3207.00
3/ 13.11 APlain
1 Cement Concrete (1:2.4 nominal mix) in levelling
course below open foundation of Head walls as per
drawings & Technical Specification Clause 1109

2 46 7.48 0.15 m3 103.22 Cum


103.22 4890.00
13.3.2 Cement Concrete ( 1 :1.5: 3 ) of as per drawings &
Technical Specification Clause 1109

2 46 7.48 0.075 m3 51.61 Cum


51.61 6467.38
Gabion protections
12 Providing and laying boulder apron for bed protection
with stone boulders of minimum size and weight as per
table 1300.1, no fragment weighing not less than 25kg
laid dry complete as per drawings and technical
specifications clause 1301.

4 13.00 2.00 1.75 m3 182.00 Cum 1349.50


Total

J.E./A.E Asstt. Executive Engineer,PWD Executive Engineer,PWD


Morigaon Rural Road Sub-Division, Morigaon Rural Road Division,
Rate with
Amount in Remark
GST in
Rs. s
Rs.

115.77 30180

5920.84 105021
5999.61 140936

1099.82 40494
3639.95 441616

7076.73 530754

1531.68 158070
3639.95 375730

5550.15 572909

7340.48 378857

1531.68 278766
3045952

ve Engineer,PWD
Rural Road Division,
PRADHAN MANTRI GRAM SADAK YOJANA
(Ministry of Rural Development, Govt. of India)

ANALYSIS OF 10.0 M SPAN SLAB CULVERT


Name of Road Design Discharge:
:-
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS Block : Nazir
CULVERTS ANDWidth
Length MINOR BRIDGES
Thickness Rate
Sl. Ref. SOR
Description of Item No Unit Quantity (Rs) 13.5%
No. Item No.
(m) (m) (m) GST
1 2 3 4 5 6 7 8 9 10

Excavation for Structures: Earthwork in excavation for structures as per


drawing and technical specification Clause 305 including setting out,
construction of shoring and bracing, removal of slums and other
deliterious materials and disposal up to a lead of 50m, dressing of side
slopes bottom and backfilling in trenches with excavated suitable material
11.1 in ordinary soil up to 6m depth.
1
/I/A(a)/i

Abutment 2 6.00 5.00 4.50 Cum 270.00


Return Wall 4 4.00 5.00 4.50 Cum 360.00 115.77
Total : 630.00

Providing concrete for plain/reinforced concrete in open foundation


complete as per drawing and technical specification clause 802, 803, 1202,
1203 B. With natural gravel I)PCC M-10 (ii) Nominal Mix 1:3:6 (Hand
Mixing)
2 11.4
Abutment 2 5.50 4.08 0.30 Cum 13.46
5,947.51
2 11.4

Return Wall 4 4.00 4.256 0.30 Cum 20.43 5,947.51


Total : 33.89

Plain/ Reinforced cement concrete in substructure complete as per drawing


and technical specification Clauses 802, 804, 805, 806, 807, 1202 & 1204
B) with natural gravel Grade M-15 Nominal Mix (1:2.5:5). (Exclusive of
reinforcement)

3 12.5/B/I/i Abutment 13.49(c/


2 5.50 Cum 148.39
s area)
11.535( 5,725.51
Return Wall 4 4.00 c/s Cum 184.56
area)
Total : 332.95
Plain/ Reinforced cement concrete in substructure complete as per drawing
and technical specification Clauses 802, 804, 805, 806, 807, 1202 & 1204
-B) with natural gravel V) RCC Grade M-20 Nominal Mix (1:2:4).
12.5/B/III (Exclusive of reinforcement)
4
/ii 2 5.50 0.9 0.3 Cum 2.97
Abutment Cap/D-Wall
2 5.50 0.3 0.6 Cum 1.98 6,781.63
Total : 4.95
Providing and laying reinforced cement concrete in super structure as
per technical specification clause 800, 1205.4 & 1205.5 with crushed
stone RCC M-25 up to height 5m-10m.
5 13.1/A/II/b
Ref. IRC-SP-20 Plate no
Deck Slab and kerb Cum 51.130
-7.08 8,861.04
Total : 51.130
Drainage Spouts complete as per drawing and technical specification
6 13.1 6 6 1862.42
clause 1209.
Construction of RCC railing of M-25 Grade cast in situ with 20mm
nominal size aggregate true to line and grade toleance of vertical
7 13.6 railing post not to exceed 1 in 500 center to center spacing between 2 11.2 metre 22.4 2720.60
vertical post not to exceed 2000mm as per drawing and technical
specification caluse 800, 900 and 1208.3 with natural gravel.

Providing and laying cement concrete wearing course M-30 grade


9 13.5/A including reinforcement complete as per drawing and technical 1 11.2 5.5 0.025 cum 1.54 14082.51
specification clause 800 and 1206.3 with crushed stone
Supplying fitting and placing HYSD bar reinforcement (Fe 415) in
substrcture complete as per drawing and technical specification
clause 1002, 1005, 1010 & 1202.
Surface Reinforcement for abutments @ 4 Kg/Cum
148.39x 4 = 593.56 Kg MT 0.594
for total vol =148.39Cum

10 12.6
62,528.29
2.97x85kg/cum =252.45 kg
10 12.6 1.98x75kg/cum =148.50 kg
Abutment Cap & dirt wall (2.97+1.98) cum MT 0.401
62,528.29
Ref plate No 7.25 (IRC SP -20)

Surface reinforcements for return walls @ 4 Kg/Cum


184.56 x 4 =738.24 Kg MT 0.738
for total vol = 184.56 Cum
Total : 1.733
Supplying fitting and placing HYSD bar reinforcement (Fe 415) in
superstrcture complete as per drawing and technical specification Ref. IRC-SP-20 Plate no -7.08 MT 3.486 63918.89
13.2 clause 1002, 1005, 1010 & 1202.
Deck Slab and kerb

Making 120 cm wide bamboo foot bridge with 100mm Bholuka or


Barua Bamboo posts driven 120 cm to 180 cm underground 3 no's in
11 each row and rows being 3 m apart bholuka or Barua Bamboo dham
placed over the posts and tied with cane or wire, Bholuka or barua
16.42 Rm 11 980.64
bamboo struts in each row both up and down stream , jati bambo
long gorhs closely packed and tied with dham. single layer layer og
mat placed over 75 mm thick brush wood and tied with bholuka or
barua bamboo rail stand fixed in one side of the bridge etc. comple.

Total :
TOTAL =
Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no fragment
12 14.1 weighing less than 25 kg laid dry complete as per drawing and technical 4 216.21 2193.92
specifications Clause 1301
Cum
Providing and laying pitching on slopes laid over prepared filter media
as per drawing and technical specifications Clause 1302.
13 14.5 (i) (i)Stone/Boulder 198.63 2,193.92

Cum
Providing and laying filter material underneath pitching in slopes
complete as per drawing and technical specifications Clause 1302
14 14.6 82.76 2,713.66
Cum

TOTAL FOR PROTECTION WORK


=

GRAND TOTAL =
SAY 4,237,944.00
FORMAT: F7

Design Discharge: Cumec


Block : Nazira Block.

Amount
(Rs)

11

72,935.10

201,577.89
201,577.89

1,906,307.72

33,569.04

453,064.76

11174.53
60941.33

21687.07

108,361.52
108,361.52

222821.240082

10,787.04

3,103,227.24

474,356.42
435,778.52

224,582.14

1,134,717.08

4,237,944.32
4,237,944.00
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur
PACKAGE NO. :- AS 22 321

Summation of All Quantities


Earth Work for Cutting = Cum 155.01
FOR Reuse Cutting soil @40% = Cum -62.00
Earthwork for Core Widening = Cum 7755.38
Total = Cum 7693.37
Subgrade = Cum 0.00
Shoulder = Cum 1011.92
Total = Cum 1011.92
G.S.B. = Cum 1111.73
W.B.M Gr. - II = Cum 514.69
W.B.M Gr. - III = Cum 514.69
Prime coat = Cum 6862.50
OGPC = Cum 6862.50
Tack Coat Sqm 6862.50

QUANTITY STATEMENT
FOR CORE WIDENING:- FOR CUTTING FOR SUBGRADE FOR SHUOLDER FOR G.S.B FOR W.B.M. II FOR W.B.M. III
Mean Mean Mean Mean Mean Mean Mean
Ch. Distance Area Volume Area Volume Area Volume Area Volume Area Volume Area Volume Area Volume
area area area area area area area
0.00 0.00 0.000 0.000 0.000 2.312 0.000 0.000 0.00 0.000 0.000 0.556 0.000 0.000 0.608 0.000 0.000 0.281 0.000 0.000 0.281 0.000 0.000
30.00 30.00 0.080 0.040 1.207 0.011 1.162 34.845 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
60.00 30.00 0.621 0.351 10.524 0.000 0.006 0.165 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
90.00 30.00 1.001 0.811 24.339 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
120.00 30.00 1.156 1.079 32.359 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
150.00 30.00 1.327 1.242 37.247 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
180.00 30.00 1.017 1.172 35.172 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
210.00 30.00 5.752 3.385 101.546 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
240.00 30.00 5.087 5.420 162.593 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
270.00 30.00 5.752 5.420 162.593 1.000 0.500 15.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.356 0.319 8.438 0.356 0.319 8.438
300.00 30.00 6.417 6.085 182.543 2.000 1.500 45.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.431 0.394 8.438 0.431 0.394 8.438
330.00 30.00 4.323 5.370 161.096 0.000 1.000 30.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.356 8.438 0.281 0.356 8.438
360.00 30.00 5.586 4.954 148.628 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
390.00 30.00 5.087 5.337 160.099 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
420.00 30.00 4.821 4.954 148.628 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
450.00 30.00 4.349 4.585 137.555 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
480.00 30.00 4.555 4.452 133.565 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
500.00 20.00 4.345 4.450 89.003 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 11.120 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
506.00 6.00 0.000 0.000 0.000 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
510.00 30.00 4.309 4.432 132.967 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
540.00 30.00 3.977 4.143 124.289 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
570.00 30.00 5.087 4.532 135.959 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
600.00 30.00 5.752 5.420 162.593 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
630.00 30.00 5.599 5.676 170.273 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
660.00 30.00 5.626 5.613 168.378 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
690.00 30.00 5.087 5.357 160.697 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
720.00 30.00 4.555 4.821 144.638 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
750.00 30.00 5.180 4.868 146.034 1.000 0.500 15.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.356 0.319 8.438 0.356 0.319 8.438
780.00 30.00 4.309 4.745 142.343 0.000 0.500 15.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.319 8.438 0.281 0.319 8.438
810.00 30.00 4.289 4.299 128.977 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
840.00 30.00 3.757 4.023 120.698 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
870.00 30.00 3.977 3.867 116.009 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
900.00 30.00 3.225 3.601 108.029 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
930.00 30.00 3.737 3.481 104.438 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
960.00 30.00 3.977 3.857 115.710 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
990.00 30.00 5.087 4.532 135.959 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1020.00 30.00 5.752 5.420 162.593 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1050.00 30.00 5.599 5.676 170.273 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1080.00 30.00 5.626 5.613 168.378 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1110.00 30.00 5.087 5.357 160.697 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1140.00 30.00 4.555 4.821 144.638 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1170.00 30.00 5.180 4.868 146.034 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1200.00 30.00 4.309 4.745 142.343 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1230.00 30.00 4.289 4.299 128.977 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1260.00 30.00 3.757 4.023 120.698 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1290.00 30.00 3.977 3.867 116.009 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1320.00 30.00 3.225 3.601 108.029 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1350.00 30.00 3.737 3.481 104.438 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1380.00 30.00 3.977 3.857 115.710 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1410.00 30.00 5.087 4.532 135.959 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1440.00 30.00 5.752 5.420 162.593 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1470.00 30.00 5.599 5.676 170.273 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1500.00 30.00 5.626 5.613 168.378 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1530.00 30.00 5.087 5.357 160.697 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1560.00 30.00 4.555 4.821 144.638 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1590.00 30.00 5.180 4.868 146.034 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1620.00 30.00 4.309 4.745 142.343 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1650.00 30.00 4.289 4.299 128.977 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1680.00 30.00 3.757 4.023 120.698 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1710.00 30.00 3.977 3.867 116.009 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1740.00 30.00 3.225 3.601 108.029 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1770.00 30.00 3.737 3.481 104.438 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
1800.00 30.00 3.650 3.694 110.810 0.000 0.000 0.000 0.00 0.000 0.000 0.556 0.556 16.680 0.608 0.608 18.225 0.281 0.281 8.438 0.281 0.281 8.438
TOTAL= 7755.376 TOTAL= 155.010 TOTAL= 0.000 TOTAL= 1011.920 TOTAL= 1111.725 TOTAL= 514.688 TOTAL= 514.688

Asstt. Executive Engineer, PWD Executive Engineer , PW


Goalpara/Dudhnoi Rural Road Sub Goalpara Rural Road Divis
Division Goalpara
hriguri to NH37 via Borjuk Manikpur
AGE NO. :- AS 22 321

UANTITY STATEMENT
PC & SC
SURFACE
AREA
0.000
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
0.000
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
112.500
6862.500

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
QUANTITY STATEMENT
NAME OF ROAD: KrishnaiKrishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur
Earthwork GSB WB
C/S AREA MEAN AREA VOLUME
INTERMEDI
SUB CUT SUB CUTT C/S MEAN C/S
CHAINAGE ATE CUTTING SHOULDER CORE SHOULDER CORE SUBGRADE SHOULDER CORE VOLUME
GRADE TING GRADE ING AREA AREA AREA
DISTANCE

0.00 0.00 2.86 0.00 0.837 0.00 1.429 0.000 0.837 0.000 0.000 0.000 0.000 0.000 0.608 0.000 0.281
10.00 10.00 0.00 0.00 0.837 0.66 0.000 0.000 0.837 0.332 0.000 0.000 8.370 3.320 0.608 0.608 6.080 0.281
30.00 20.00 0.00 0.00 0.837 1.04 0.000 0.000 0.837 0.854 0.000 0.000 16.740 17.070 0.608 0.608 12.160 0.281
60.00 30.00 0.00 0.00 0.837 1.34 0.000 0.000 0.837 1.193 0.000 0.000 25.110 35.775 0.608 0.608 18.240 0.281
90.00 30.00 0.00 0.00 0.837 2.73 0.000 0.000 0.837 2.035 0.000 0.000 25.110 61.050 0.608 0.608 18.240 0.281
120.00 30.00 0.00 0.00 0.837 11.32 0.000 0.000 0.837 7.026 0.000 0.000 25.110 210.780 0.608 0.608 18.240 0.281
121.50 1.50 0.00 0.00 0.837 10.69 0.000 0.000 0.419 11.007 0.000 0.000 0.628 16.511 0.608 0.608 0.912 0.281
Proposed Slab Culvert of 1x2.0m Span
122.00 2.00 0.00 0.00 1.317 13.41 0.000 0.000 1.077 12.369 0.608 0.281
150.00 28.00 0.00 0.00 1.317 6.14 0.000 0.000 1.317 9.777 0.000 0.000 36.876 273.756 0.608 0.608 17.024 0.281
180.00 30.00 0.00 0.00 1.317 4.81 0.000 0.000 1.317 5.478 0.000 0.000 39.510 164.325 0.608 0.608 18.240 0.281
210.00 30.00 0.00 0.00 1.317 5.39 0.000 0.000 1.317 5.104 0.000 0.000 39.510 153.120 0.608 0.608 18.240 0.281
240.00 30.00 0.00 0.00 1.317 6.34 0.000 0.000 1.317 5.869 0.000 0.000 39.510 176.070 0.608 0.608 18.240 0.281
270.00 30.00 0.00 0.00 1.317 5.58 0.000 0.000 1.317 5.964 0.000 0.000 39.510 178.920 0.608 0.608 18.240 0.281
300.00 30.00 0.00 0.00 1.317 6.72 0.000 0.000 1.317 6.150 0.000 0.000 39.510 184.500 0.608 0.608 18.240 0.281
330.00 30.00 0.00 0.00 1.317 6.07 0.000 0.000 1.317 6.395 0.000 0.000 39.510 191.835 0.608 0.608 18.240 0.281
360.00 30.00 0.00 0.00 1.317 6.20 0.000 0.000 1.317 6.134 0.000 0.000 39.510 184.020 0.608 0.608 18.240 0.281
390.00 30.00 0.00 0.00 1.317 7.69 0.000 0.000 1.317 6.942 0.000 0.000 39.510 208.245 0.608 0.608 18.240 0.281
420.00 30.00 0.00 0.00 1.317 8.13 0.000 0.000 1.317 7.911 0.000 0.000 39.510 237.330 0.608 0.608 18.240 0.281
450.00 30.00 0.00 0.00 1.317 8.51 0.000 0.000 1.317 8.321 0.000 0.000 39.510 249.630 0.608 0.608 18.240 0.281
480.00 30.00 0.00 0.00 1.317 8.72 0.000 0.000 1.317 8.612 0.000 0.000 39.510 258.360 0.608 0.608 18.240 0.281
510.00 30.00 0.00 0.00 1.317 8.39 0.000 0.000 1.317 8.552 0.000 0.000 39.510 256.545 0.608 0.608 18.240 0.281
540.00 30.00 0.00 0.00 1.317 8.08 0.000 0.000 1.317 8.233 0.000 0.000 39.510 246.990 0.608 0.608 18.240 0.281
570.00 30.00 0.00 0.000 1.317 5.70 0.000 0.000 1.317 6.888 0.000 0.000 39.510 206.625 0.608 0.608 18.240 0.281
600.00 30.00 0.00 2.696 1.317 5.82 0.000 1.348 1.317 5.759 0.000 40.440 39.510 172.755 0.608 0.608 18.240 0.281
630.00 30.00 0.00 2.696 1.317 10.34 0.000 2.696 1.317 8.081 0.000 80.880 39.510 242.430 0.608 0.608 18.240 0.281
660.00 30.00 0.00 2.696 1.317 7.26 0.000 2.696 1.317 8.801 0.000 80.880 39.510 264.030 0.608 0.608 18.240 0.281
690.00 30.00 0.00 2.696 1.317 7.68 0.000 2.696 1.317 7.471 0.000 80.880 39.510 224.115 0.608 0.608 18.240 0.281
700.00 10.00 0.00 2.696 1.317 11.44 0.000 2.696 1.317 9.561 0.000 26.960 13.170 95.610 0.608 0.608 6.080 0.281
Existing SHPC
701.50 1.50 0.00 2.696 1.317 11.45 0.000 2.696 1.317 11.447 1.976 0.608 0.608 0.912 0.281
720.00 18.50 0.00 2.696 1.317 10.08 0.000 2.696 1.317 10.764 0.000 49.876 24.365 199.134 0.608 0.608 11.248 0.281
730.00 10.00 0.00 3.981 1.375 28.62 0.000 3.339 1.346 19.346 0.000 33.385 13.460 193.460 0.608 0.608 6.080 0.281
Earthwork GSB WB
C/S AREA MEAN AREA VOLUME
INTERMEDI
SUB CUT SUB CUTT C/S MEAN C/S
CHAINAGE ATE CUTTING SHOULDER CORE SHOULDER CORE SUBGRADE SHOULDER CORE VOLUME
GRADE TING GRADE ING AREA AREA AREA
DISTANCE

Proposed Box Culvert of 3/33/0


742.00 12.00 0.00 3.981 1.375 32.00 0.608 0.281
752.00 10.00 0.00 2.696 1.317 12.69 0.000 3.339 1.346 22.347 0.000 33.385 13.460 223.465 0.608 0.608 6.080 0.281
765.00 13.00 0.00 2.696 1.317 10.14 0.000 2.696 1.317 11.413 0.000 35.048 17.121 148.369 0.608 0.608 7.904 0.281
Existing DHPC
768.00 3.00 0.00 2.696 1.317 10.56 0.000 2.696 1.317 10.350 3.951 0.608 0.608 1.824 0.281
770.00 2.00 0.07 2.696 1.317 8.16 0.037 2.696 1.317 9.360 0.074 5.392 2.634 18.720 0.608 0.608 1.216 0.281
775.00 5.00 0.01 2.696 1.317 8.06 0.044 2.696 1.317 8.106 0.218 13.480 6.585 40.528 0.608 0.608 3.040 0.281
Proposed SHPC 1x1000mm Dia.
776.50 1.50 0.01 2.696 1.317 8.18 0.012 2.696 1.317 8.116 1.976 0.608 0.608 0.912 0.281
780.00 3.50 0.02 2.696 1.317 6.96 0.016 2.696 1.317 7.570 0.054 9.436 4.610 26.495 0.608 0.608 2.128 0.281
790.00 10.00 0.00 2.696 1.317 7.79 0.011 2.696 1.317 7.374 0.105 26.960 13.170 73.740 0.608 0.608 6.080 0.281
Existing SHPC
791.50 1.50 0.00 2.696 1.317 8.23 0.000 2.696 1.317 8.010 1.976 0.608 0.608 0.912 0.281
810.00 18.50 0.00 2.696 1.317 9.44 0.000 2.696 1.317 8.838 0.000 49.876 24.365 163.494 0.608 0.608 11.248 0.281
840.00 30.00 0.00 2.696 1.317 9.37 0.000 2.696 1.317 9.407 0.000 80.880 39.510 282.195 0.608 0.608 18.240 0.281
860.00 20.00 0.00 2.696 1.317 7.91 0.000 2.696 1.317 8.640 0.000 53.920 26.340 172.800 0.608 0.608 12.160 0.281

Proposed Slab Culvert of 1x4.0m Span

864.00 4.00 0.00 2.696 1.317 8.66 0.000 2.696 1.317 8.284 0.608 0.281
880.00 16.00 0.00 2.696 1.317 7.38 0.000 2.696 1.317 8.019 0.000 43.136 21.072 128.304 0.608 0.608 9.728 0.281
900.00 20.00 0.07 2.696 1.317 5.43 0.036 2.696 1.317 6.404 0.710 53.920 26.340 128.070 0.608 0.608 12.160 0.281
930.00 30.00 0.00 2.696 1.317 10.41 0.036 2.696 1.317 7.918 1.065 80.880 39.510 237.525 0.608 0.608 18.240 0.281
960.00 30.00 0.14 2.696 1.317 5.57 0.072 2.696 1.317 7.986 2.160 80.880 39.510 239.580 0.608 0.608 18.240 0.281
990.00 30.00 0.18 2.696 1.317 4.08 0.163 2.696 1.317 4.824 4.890 80.880 39.510 144.705 0.608 0.608 18.240 0.281
1020.00 30.00 0.09 2.696 1.317 5.20 0.138 2.696 1.317 4.642 4.125 80.880 39.510 139.245 0.608 0.608 18.240 0.281
1050.00 30.00 0.00 2.696 1.317 5.69 0.047 2.696 1.317 5.444 1.395 80.880 39.510 163.305 0.608 0.608 18.240 0.281
1080.00 30.00 0.00 2.696 1.317 5.31 0.000 2.696 1.317 5.497 0.000 80.880 39.510 164.910 0.608 0.608 18.240 0.281
1110.00 30.00 0.00 2.696 1.317 5.96 0.000 2.696 1.317 5.633 0.000 80.880 39.510 168.975 0.608 0.608 18.240 0.281
1140.00 30.00 0.00 2.696 1.317 6.41 0.000 2.696 1.317 6.181 0.000 80.880 39.510 185.430 0.608 0.608 18.240 0.281
1170.00 30.00 0.00 2.696 1.317 7.79 0.000 2.696 1.317 7.099 0.000 80.880 39.510 212.970 0.608 0.608 18.240 0.281
1200.00 30.00 0.00 2.696 1.317 7.03 0.000 2.696 1.317 7.413 0.000 80.880 39.510 222.390 0.608 0.608 18.240 0.281
Existing SHPC
1201.50 1.50 0.00 2.696 1.317 8.12 0.000 2.696 1.317 7.576 1.976 0.608 0.608 0.912 0.281
1230.00 28.50 0.00 2.696 1.317 8.25 0.000 2.696 1.317 8.185 0.000 76.836 37.535 233.258 0.608 0.608 17.328 0.281
Earthwork GSB WB
C/S AREA MEAN AREA VOLUME
INTERMEDI
SUB CUT SUB CUTT C/S MEAN C/S
CHAINAGE ATE CUTTING SHOULDER CORE SHOULDER CORE SUBGRADE SHOULDER CORE VOLUME
GRADE TING GRADE ING AREA AREA AREA
DISTANCE

1260.00 30.00 0.00 2.696 1.317 6.83 0.000 2.696 1.317 7.541 0.000 80.880 39.510 226.230 0.608 0.608 18.240 0.281
1290.00 30.00 0.00 2.696 1.317 4.90 0.000 2.696 1.317 5.866 0.000 80.880 39.510 175.965 0.608 0.608 18.240 0.281
1300.00 10.00 0.00 2.696 1.317 6.29 0.000 2.696 1.317 5.596 0.000 26.960 13.170 55.955 0.608 0.608 6.080 0.281
1310.00 10.00 0.00 3.231 1.375 13.75 0.000 2.964 1.346 10.021 0.000 29.635 13.460 100.205 0.608 0.608 6.080 0.281
1330.00 20.00 0.00 3.981 1.375 34.37 0.000 3.606 1.375 24.062 0.000 72.120 27.500 481.230 0.608 0.608 12.160 0.281
1340.00 10.00 0.00 3.981 1.375 43.96 0.000 3.981 1.375 39.165 0.000 39.810 13.750 391.645 0.608 0.608 6.080 0.281
Proposed RCC Bridge 2x14.50 m Span
1370.00 30.00 0.00 3.981 1.375 53.90 0.000 3.981 1.375 48.930 0.608 0.281
1380.00 10.00 0.00 3.981 1.375 44.74 0.000 3.981 1.375 49.321 0.000 39.810 13.750 493.210 0.608 0.608 6.080 0.281
1400.00 20.00 0.00 3.231 1.375 13.53 0.000 3.606 1.375 29.132 0.000 72.120 27.500 582.640 0.608 0.608 12.160 0.281
1410.00 10.00 0.00 2.696 1.317 5.26 0.000 2.964 1.346 9.392 0.000 29.635 13.460 93.920 0.608 0.608 6.080 0.281
1440.00 30.00 0.00 2.696 1.317 3.63 0.000 2.696 1.317 4.443 0.000 80.880 39.510 133.275 0.608 0.608 18.240 0.281
1470.00 30.00 0.15 2.696 1.317 3.26 0.076 2.696 1.317 3.444 2.265 80.880 39.510 103.305 0.608 0.608 18.240 0.281
1500.00 30.00 0.18 2.696 1.317 2.88 0.163 2.696 1.317 3.071 4.890 80.880 39.510 92.130 0.608 0.608 18.240 0.281
1530.00 30.00 0.14 2.696 1.317 2.79 0.156 2.696 1.317 2.833 4.680 80.880 39.510 84.990 0.608 0.608 18.240 0.281
1560.00 30.00 0.03 2.696 1.317 3.69 0.084 2.696 1.317 3.237 2.520 80.880 39.510 97.095 0.608 0.608 18.240 0.281
1570.00 10.00 0.00 2.696 1.317 6.92 0.016 2.696 1.317 5.305 0.155 26.960 13.170 53.045 0.608 0.608 6.080 0.281
Proposed SHPC 1x1000mm Dia.
1571.50 1.50 0.00 2.696 1.317 6.99 0.000 2.696 1.317 6.958 1.976 0.608 0.608 0.912 0.281
1590.00 18.50 0.01 2.696 1.317 4.54 0.003 2.696 1.317 5.765 0.046 49.876 24.365 106.653 0.608 0.608 11.248 0.281
1620.00 30.00 0.00 2.696 1.317 4.88 0.003 2.696 1.317 4.707 0.075 80.880 39.510 141.195 0.608 0.608 18.240 0.281
1650.00 30.00 0.00 2.696 1.317 6.66 0.000 2.696 1.317 5.769 0.000 80.880 39.510 173.070 0.608 0.608 18.240 0.281
1680.00 30.00 0.00 2.696 1.317 6.11 0.000 2.696 1.317 6.386 0.000 80.880 39.510 191.565 0.608 0.608 18.240 0.281
1710.00 30.00 0.00 2.696 1.317 3.66 0.000 2.696 1.317 4.885 0.000 80.880 39.510 146.535 0.608 0.608 18.240 0.281
1740.00 30.00 0.17 2.696 1.317 3.30 0.083 2.696 1.317 3.481 2.475 80.880 39.510 104.430 0.608 0.608 18.240 0.281
1770.00 30.00 0.09 2.696 1.317 2.77 0.127 2.696 1.317 3.038 3.795 80.880 39.510 91.125 0.608 0.608 18.240 0.281
1800.00 30.00 0.00 2.696 1.317 4.31 0.044 2.696 1.317 3.543 1.320 80.880 39.510 106.275 0.608 0.608 18.240 0.281
1820.00 20.00 0.00 2.696 1.317 11.68 0.000 2.696 1.317 7.995 0.000 53.920 26.340 159.900 0.608 0.608 12.160 0.281
Proposed DHPC 2x1000mm Dia.
1821.50 1.50 0.00 2.696 1.317 11.79 0.000 2.696 1.317 11.735 1.976 0.608 0.608 0.912 0.281
1840.00 18.50 0.00 2.696 1.317 8.00 0.000 2.696 1.317 9.896 0.000 49.876 24.365 183.067 0.608 0.608 11.248 0.281
Existing SHPC
1841.50 1.50 0.00 2.696 1.317 9.78 0.000 2.696 1.317 8.889 1.976 0.608 0.608 0.912 0.281
1860.00 18.50 0.09 2.696 1.317 4.65 0.043 2.696 1.317 7.216 0.786 49.876 24.365 133.496 0.608 0.608 11.248 0.281
1890.00 30.00 0.00 2.696 1.317 5.82 0.043 2.696 1.317 5.236 1.275 80.880 39.510 157.080 0.608 0.608 18.240 0.281
Earthwork GSB WB
C/S AREA MEAN AREA VOLUME
INTERMEDI
SUB CUT SUB CUTT C/S MEAN C/S
CHAINAGE ATE CUTTING SHOULDER CORE SHOULDER CORE SUBGRADE SHOULDER CORE VOLUME
GRADE TING GRADE ING AREA AREA AREA
DISTANCE

1920.00 30.00 0.00 2.696 1.317 3.94 0.002 2.696 1.317 4.878 0.045 80.880 39.510 146.325 0.608 0.608 18.240 0.281
1950.00 30.00 0.00 2.696 1.317 4.18 0.002 2.696 1.317 4.059 0.045 80.880 39.510 121.770 0.608 0.608 18.240 0.281
1980.00 30.00 0.02 2.696 1.317 4.11 0.010 2.696 1.317 4.144 0.285 80.880 39.510 124.305 0.608 0.608 18.240 0.281
2010.00 30.00 0.00 2.696 1.317 5.15 0.010 2.696 1.317 4.628 0.285 80.880 39.510 138.840 0.608 0.608 18.240 0.281
2040.00 30.00 0.00 2.696 1.317 5.06 0.000 2.696 1.317 5.103 0.000 80.880 39.510 153.090 0.608 0.608 18.240 0.281
2070.00 30.00 0.00 2.696 1.317 4.99 0.000 2.696 1.317 5.025 0.000 80.880 39.510 150.735 0.608 0.608 18.240 0.281
2100.00 30.00 0.00 2.696 1.317 4.45 0.000 2.696 1.317 4.723 0.000 80.880 39.510 141.690 0.608 0.608 18.240 0.281
2130.00 30.00 0.00 2.696 1.317 4.34 0.000 2.696 1.317 4.397 0.000 80.880 39.510 131.895 0.608 0.608 18.240 0.281
2150.00 20.00 0.21 2.696 1.317 3.66 0.105 2.696 1.317 3.999 2.100 53.920 26.340 79.980 0.608 0.608 12.160 0.281
2153.00 3.00 0.26 2.696 1.317 1.95 0.234 2.696 1.317 2.805 0.701 8.088 3.951 8.415 0.608 0.608 1.824 0.281
TOTAL = 42.539 4147.216 2719.953 14481.058 1280.752

Asstt. Executive Engineer, PWD


Goalpara/Dudhnoi Rural Road Sub
Division
STATEMENT
###
WBM GR II/GR III PC & SC
###

MEAN SURFACE
VOLUME
AREA AREA

0.000 0.000
0.281 2.813 37.500
0.281 5.625 75.000
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 0.422 5.625

0.281 7.875 105.000


0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 2.813 37.500

0.281 0.422 5.625


0.281 5.203 69.375
0.281 2.813 37.500
WBM GR II/GR III PC & SC
###

MEAN SURFACE
VOLUME
AREA AREA

0.281 2.813 37.500


0.281 3.656 48.750

0.281 0.844 11.250


0.281 0.563 7.500
0.281 1.406 18.750

0.281 0.422 5.625


0.281 0.984 13.125
0.281 2.813 37.500

0.281 0.422 5.625


0.281 5.203 69.375
0.281 8.438 112.500
0.281 5.625 75.000

0.281 4.500 60.000


0.281 5.625 75.000
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500

0.281 0.422 5.625


0.281 8.016 106.875
WBM GR II/GR III PC & SC
###

MEAN SURFACE
VOLUME
AREA AREA

0.281 8.438 112.500


0.281 8.438 112.500
0.281 2.813 37.500
0.281 2.813 37.500
0.281 5.625 75.000
0.281 2.813 37.500

0.281 2.813 37.500


0.281 5.625 75.000
0.281 2.813 37.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 2.813 37.500

0.281 0.422 5.625


0.281 5.203 69.375
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 5.625 75.000

0.281 0.422 5.625


0.281 5.203 69.375

0.281 0.422 5.625


0.281 5.203 69.375
0.281 8.438 112.500
WBM GR II/GR III PC & SC
###

MEAN SURFACE
VOLUME
AREA AREA

0.281 8.438 112.500


0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 8.438 112.500
0.281 5.625 75.000
0.281 0.844 11.250
592.453 7899.375

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
Analysis for R.C.C.Box Cell Culvert (3/33/0)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
Road Name: Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur PACKAGE NO :
DISTRICT :
Block:
Evaluation of Cost for Box Culvert of span 7.50 m

Rate
SL. Depth/
Description of item No. Length (m) Breath (m) Unit Quantity Rate (Rs.) (Including
No. Height (m)
13.50%GST)

1 2 3 4 5 6 7 8 9
1 Labour for dismantling all members of bridge
(EXCEPT PILE) 1 12.00 RM 12.00 1116.00 1266.66
2 Labour for taking out old piles……. 12 Each 12.00 1393.00 1581.06
3
Earthwork in excavation for structures as per
drawing and technical specifications Clause
305.1 including setting out, construction of
shoring and bracing, removal of stumps and
other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom
and backfilling in trenches with excavated
suitable material.
I. Ordinary soil Upto 3 m depth
Cum 102.00 115.77
Raft 1 10.40 7.50 0.70 54.60
For Cut off walls, Longer part 1 10.40 0.30 1.55 4.84
Shorter part 1 10.40 0.30 1.55 4.84
For curtain wall, U/S side. 1 10.40 0.60 0.85 5.30
D/S Side 1 10.40 0.60 0.85 5.30
For dry stone pitching, U/s side 1 10.40 3.00 0.60 18.72
D/s side 1 10.40 5.00 0.60 31.20
For return wall 4 3.00 1.93 1.50 34.69
4 Backfilling behind abutment, wing wall and
return wall complete as per drawing and
Technical specification clause 1204.3.8 Cum 1576.00 1788.76
Sand filling
1 10.40 7.50 0.85 66.30
5
Plain Cement Concrete M10 (1:3:6 nominal
mix) in levelling course below open foundation
of Head walls as per drawings & Technical
Specification Clause 1109
Rate as per SOR PMGSY - 2011-12
Raft 1 10.40 7.50 0.10 Cum 7.80 5216.59 5920.83
For Cut off walls, Longer part 1 10.40 0.30 0.15 0.47
Shorter part 1 10.40 0.30 0.15 0.47
below curtain wall, U/S side. 1 10.40 0.75 0.10 0.78
DF/S Side 1 10.40 0.75 0.10 0.78
Below return wall 4 3.00 1.93 0.20 4.62
6 Plain/reinforced cement concrete in
substructure complete as per drawings and
technical specification Clauses 802, 804, 805,
806, 807, 1202 ans 1204
A. With Crushed Stone
RCC Grade M20 for height upto 5 m

for Raft 1 7.50 10.4 0.30 23.40


For ends walls, 2 7.50 0.4 3.00 Cum 18.00
For intermediate walls 2 7.50 0.3 3.00 13.50
For Haunches 12x1/2 7.50 0.15 0.15 1.01
6461.00 7333.24
For Cut off walls, Longer part 1 10.40 0.3 1.55 4.84
Shorter part 1 10.40 0.3 1.55 4.84
below curtain wall, U/S side. 1 10.40 0.45 0.75 3.51
D/S Side 1 10.40 0.45 0.75 3.51
7 Providing and laying reinforced cement
concrete in superstructure as per drawing and
technical specifications Clauses 800, 1205.4
and 1205.5
(A) With crushed stone
(iv) R.C.C M 25
(a) Height upto 5M

Bottom Raft 1 10.40 6 0.30 18.72


Top Slab 1 10.40 6 0.30 18.72
Outer Walls 2 3.00 6 0.45 Cum 16.20 7494.79 8506.59
Inner Walls 2 3.00 6 0.30 10.80
Hunch 12x1/2 0.15 0.15 6.00 0.81
8 Supplying, fitting and placing TMT bar
reinforcement (Fe 415) in substructrue
complete as per drawings and technical T 5.30 55090.98 62528.26
specification Clauses 1002, 1005, 1010 &
1202

9 Brick masonry work in cement mortar in


foundation complete excluding pointing and
plastering as per drawing and technical
specifications Clauses 600, 1202 & 1203
Brick masonry in 1:3 cement mortar
Return Walls 4 3.00 1.727 0.20 4.14
Do 4 3.00 1.627 0.20 3.90
Cum 6672.76 7573.58
Do 4 3.00 1.527 0.20 3.66
Do 4 3.00 1.427 0.20 3.42
Do 4 3.00 1.327 0.20 3.18
Do 4 3.00 1.227 0.20 2.94
Do 4 3.00 1.127 0.20 2.70
In Substructure of return walls 4 3.00 0.664 1.88 14.98
In sup str for curbs 2 16.40 0.45 0.375 5.54
10 Plastering with cement mortar (1:4), 15 mm
thick on brickwork in substructure as per
technical specification Clauses 613.4 & 1204
Sqm 121.17 137.53
to return walls 4 3.00 2.03 24.36
to kerbs sides and top 2 16.40 1.2 39.36
to kerbs end 4 0.45 0.375 0.675
11 Providing weepholes in brick masonry/stone
masonry, plain/reinforced concrete abutment,
wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the
structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and Nos. 117.66 133.54
technical specification Clauses 614, 709,
1204.3.7

Abutments 30 30
to return Walls 12 12
12 Providing and laying boulder apron for bed
protection with stone boulders of minimum
size and weight as per Table 1300.1, no
fragment weighing less than 25 kg laid dry
complete as per drawing and technical Cum 1349.53 1531.72
specifications Clause 1301

U/S side 1 10.40 3.00 0.60 18.72


D/s side 1 10.40 5.00 0.60 31.20
Total =

Executive Engineer , PWD


Asstt. Executive Engineer, PWD
Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division
Goalpara
FORMAT F-7
C.Box Cell Culvert (3/33/0)
RAM SADAK YOJANA (PMGSY)
SS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
AS-07-
Goalpara
Krishnai

Amount (Rs.)

10
15199.92
18972.66

6321.04
559.86
559.86
614.04
614.04
2167.21
3612.02
4015.60

118594.79
46182.47
2770.95
2770.95
4618.25
4618.25
27382.65

171597.70
131998.23
98998.67
7424.90
35463.52
35463.52
25739.65
25739.65

159243.30
159243.30
137806.70
91871.14
6890.34
331524.85

31390.99
29573.33
27755.67
25938.01
24120.35
22302.69
20485.03
113451.06
41919.78

3350.18
5413.10
92.83136625

4006.32
1602.53
28673.73
47789.56
2106445.00

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
0 0 0 0 0 0 0 0

SOR No Item No. Unit


1 2.0X2.0 2 2.0X2.0 3 2.0X2.0 4 2.0X2.0 1 3.0X3.0 2 3.0X3.0 3 3.0X3.0 1 4.0X4.0
Backfilling behind abutment, wing wall and
return wall complete as per drawings &
technical specification Clause 1204.3.8
12.10 (ii) ii) Sandy material Cum 39.02 71.53 104.04 136.55 53.47 100.43 147.39 67.92

Excavation for Structures


Earthwork in excavation for foundation
of structures upto 3 m depth as per drawing
and technical specification Clause 1104
includding setting out, construction of
shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides
and bottom and backfilling with approved
9.1 material. Cum 184.44 225.37 266.30 307.23 202.63 261.75 320.87 220.82

Providing and laying parapet with PCC M 15


as per drawing & technical specifications
Clauses 800 and 1208.4
A) With crushed stone
13.20 A (ii) ii. Nominal mix (1:2.5:5) Cum 17.83 19.87 21.906 23.94 18.74 21.68 24.62 19.64
Providing concrete for plain/reinforced
concrete in open foundations complete as
per drawings and technical specifications
Clause 802, 803, 1202 & 1203
With crushed Stone
(A) 'PCC Grade M15
11.4 A)ii. Cum 8.844 10.35 11.859 13.37 9.514 11.6915 13.869 10.184
Providing concrete for plain/reinforced
concrete in open foundations complete as
per drawings and technical specifications
Clause 802, 803, 1202 & 1203

'(I)With crushed Stone M20


11.4 A)iv Case-I Using concrete mixer Mt 0.324 0.324 0.324 0.324 0.324 0.324 0.324 0.324
Plain/reinforced cement concrete in
substructure complete as per drawings and
technical specification Clauses 802, 804,
805, 806, 807, 1202 ans 1204
A. With Crushed Stone
I. P.C.C grade M 15
i.Nominal mix (1:2.5:5)
12.5 A I (i) Cum 33.74 53.94 74.14 94.34 47.74 77.27 106.80 61.74

Supplying, fitting and placing TMT (Fe-500


D) reinforcement bar (From Primary
Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) in substructrue
complete as per drawings and technical
specification Clauses 1002, 1005, 1010 &
12.6 1202 Mt 6.04 6.04 6.04 6.04 6.04 6.04 6.04 6.04

Providing weepholes in brick masonry/stone


masonry, plain/reinforced concrete
abutment, wing wall, return wall with 100 mm
dia AC pipe extending through the full width
of the structures with slope of 1(V):20(H)
towards drawing face complete as per
drawing and technical specification Clauses
12.9 614, 709, 1204.3.7 No 76 76 76 76 76 76 76 76
Drainage spouts complete as per drawing
13.10 and technical specifications Clause 1209 No 12 12 12 12 12 12 12 12.00

Providing and laying cement concrete


wearing course M 30 grade including
reinforcement complete as per drawing and
technical specifications Clauses 800 and
1206.3
13.5 (A) A) With crushed stone Cum 1.52 2.78 4.05 5.32 2.08 3.91 5.74 2.64
Construction of R.C.C. railing of M 25 grade
in cast-in-situ with 20 mm nominal size
aggregate, true to line and grade, tolerance
of vertical railing post not to exceed 1 in 500,
centre-to-centre spacing between vertical
posts not to exceed 2000 mm as per
drawing and technical specifications Clauses
16.99.20 800, 900 and 1208.3 Rm 5.40 9.90 14.40 18.90 7.40 13.90 20.40 9.40
Providing and laying filter material
underneath pitching in slopes complete as
per drawing and technical specifications
14.6 Clause 1302 Cum 27.54 50.49 73.44 96.39 37.74 70.89 104.04 47.94
Providing and laying of dry rubble flooring
complete as per drawings and technical
14.8 specifications Clause 1303.3 Cum 23.49 29.57 35.64 41.72 26.19 34.97 43.74 28.89

Executive E
Asstt. Executive Engineer, PWD
Goalpara Ru
Goalpara/Dudhnoi Rural Road Sub Division
Go
0
Total Rate Rate with Amount
Quantity GST
2 4.0X4.0

129.33 0.00 1576 1788.76 0

298.13 0.00 102 115.77 0

23.49 0.00 5403.9 6133.427 0

13.0315 0.00 5085.60 5772.156 0

0.324 0.00 6108.90 6933.602 0


100.60 0.00 5379 6105.165 0

6.04 0.00 55091 62528.29 0

76 0.00 117.7 133.5895 0

12 0.00 1640.9 1862.422 0

5.03 0.00 12407.5 14082.51 0


17.90 0.00 1683 1910.205 0

91.29 0.00 1768.6 2007.361 0

40.37 0.00 2216.8 2516.068 0


0

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)

NAME OF ROAD : Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur


PACKAGE NO. AS-07-
MONTHS
SL. Total
ACTIVITIES 1 2 3 4 5 6 7 8 9 10 11
No. Quantity

1 MOBILISATION

CLEARING AND
2
GRABING

0.000

0.000
Quantity in Hect. 0.00

3 EARTH WORK

511.79

511.79

511.79

511.79

511.79

511.79
Quantity in Cum 3070.72

4 GSB

36.36

36.36

36.36

36.36

36.36

36.36

36.36
Quantity in Cum 254.54

5 BASE COURSE
29.46

29.46

29.46

29.46

29.46

29.46

29.46

29.46
Quantity in Cum 235.69

6 BITUMINOUS WORK

785.63

785.63

785.63

785.63

785.63

785.63

785.63

785.63
Quantity in Sqm 6285.00

7 CD WORK

a. Slab Culvert

Quantity nos 0

8 ROAD FURNITURE

Quantity nos 89
TENTITIVE COMPLETION TIME 12 MONTHS
GRAM SADAK YOJANA (PMGSY)

nikpur

MONTHS

12
MPLETION TIME 12 MONTHS
For Guide Post
Quantites in
S.No. Chainage(in m) Side Length No.s Remarks

From To

1 1700 1750 2 50 41 Both side of alignment

2 1840 1890 2 50 41 Both side of alignment

Total 82

For Slope Protection (Jute Textile)


Slope Quantites in
S.No. Chainage(in m) Side Length Length Sqm Remarks

From To

1 0 0 2 0 2.25 0 left side of alignment

2 0 0 1 0 2.25 0 Left side of alignment

Total 0

Asstt. Executive Engineer, PWD


Morigaon Rural Road Sub Executive Engineer , PWD
Division Goalpara Rural Road Division
Mayong Goalpara
Annexure -II
A Boulder Wall Protection Works
Length in Quantity in
Sl no No From To M Width (m) Height (m) Cum Remarks

1 1 0 0 0 0.45 0.6 0.00 Left Side

Total = 0.00
Statement No. - 4

Name of Road : Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur

DETAILS OF ROAD FURNITURE

Specification Location Unit Quantity

Curve No. 0

Feeder Road No. 0

90cm Equilateral triangle

Junction No. 0

Total = 0

Km Post km Each 1

5th Km Stone 5th km Each 0

200 m Stone 200 m Each 2


Annexure II
Cost Estimate For Guide Post

1/11.1 Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal
upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.
1.Ordinary soil
Upto 3 m depth 1 0.55 0.55 0.95 = 0.287 cum
@ 102.00 /cum = Rs. 29.00
2/11.4 Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203
(A) (II) P.C.C grade M 15
Nominal mix (1:2.5:5)
1 0.0491.5 = 0.074 cum
@ 5,216.59 /cum = Rs. 384.00
3/12.6 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructrue complete as per drawings and
technical specification Clauses 1002, 1005, 1010 & 1202
12 Tor= 1.65 3 1 @ 0.89 kg/m = 4.406
6 Tor= 0.745 11 1 @ 0.22 kg/m = 1.804
= 6.209
Total = 0.01
@ 55,090.98 tonne = Rs. 551.00
4/10.5 Painting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on new,
plastered / concrete surfaces as per drawing and Technical Specification Clause 1701
1 0.785 0.75 = 0.589 Sqm
@ 65.36 /cum = Rs. 39.00
Total Estimated Cost = Rs. 1,003.00
Say, Rs. 1,003.00
Annexure II
ost Estimate For Guide Post

es as per drawing and technical specifications Clause 305.1 including


nd bracing, removal of stumps and other deleterious material and disposal
and bottom and backfilling in trenches with excavated suitable material.

Rs. 29.00
d concrete in open foundations complete as per drawings and technical
& 1203

Rs. 384.00
ar reinforcement (Fe 415) in substructrue complete as per drawings and
1005, 1010 & 1202
kg
kg
kg
tonne
Rs. 551.00
at after filling the surface with synthetic enamel paint in all shades on new,
rawing and Technical Specification Clause 1701

Rs. 39.00
Rs. 1,003.00
Rs. 1,003.00
Annexure III

COST ESTIMATE FOR SPEAD BREAKER

Sl Item Description Unit Dimension Quantity


No. No

No L B D
1 2 3 4 5 6 7 8 9
5.2 Tack-coat:
1 sqm 1 6.00 5.00 30.00
(III)
Providing
20mm thick Open-Graded and applying
Premix Carpet
using Bituminous (penetration
grade/modified bitumen) Binder
Providing, laying and rolling of open-
graded premix carpet of 20 mm thickness
composed of 13.2 mm to 5.6 mm
aggregates either using penetration grade
bitumen or emulsion to required line,
grade and level to serve as wearing
5.9 course on a previously prepared base,
2 sqm 1 6.00 5.00 30.00
(II) including mixing in a suitable plant, laying
and rolling with a three wheel 80-100 kN
static roller capacity, finished to required
level and grades to be followed by seal
coat of either Type A or Type B or Type C
as per Technical Specification Clause
508.

TOT
SA
Annexure III

IMATE FOR SPEAD BREAKER

Rate Amount
(Rs) (Rs)

10 11
10.20 306.00

144.82 4344.73

TOTAL = 4650.73
SAY = 4840.00
Appendix C.25 e : Three Cell RCC Box Culvert of size 2 x 2 (U/S & D/S Pitching)

Estimate of Quantity for 2.00m x .00m (without earth cushion) Triple cell box culvert
Span of Culvert = 2.0 m
Height of Culvert = 2.0 m
No. of Cell single = 3 no.s
Length of Box 7.50 m

Sl.
No SoR No Descriptions Unit No. Length Width Ht./Th. Area
.

1 11.1 Excavation
Box Portion cum 7.00 7.50 1.00
L=3x2+2x0.25+2*0.25 = 7.00 m
Width = 7.50 m
Depth = 1.0 m from natural ground level
For cut-off walls cum 2 7.00 0.50 1.50
L=3x2+2x0.25+2*0.25 = 7.00 m
No. = 2
For Curtain walls cum 2 13.32 1.00 0.75
L=3.12x (1 : 2.828) = 8.82 m + 4.50m
No. = 2
For Aprons, Upstream cum 1 10.16 3.00 0.60
For Aprons, Downstream cum 1 10.16 5.00 0.60
L=(7.00 + 13.32) / 2 = 10.16 m
No. = 1
Wing wall cum 4 3.82 3.02 1.50
Length of wing wall = 3.82 m
Depth of Foundation = 1.50 m
Width = (3.07+ 4.36)/2 = 3.72 m
(Refer MOST Dwq. No. SD/113 sheet 6 of 6)
No. = 4
Total =
2 11.4 A. Levelling course plain cement concrete
II) grade M-15 in foundation.
Box Portion cum 7.00 7.50 0.10
L=3x2+2x0.25+2*0.25 = 7.00 m
Width = 7.50 m
Thick = 0.10 m
Wing wall cum 4 3.82 3.02 0.15
Length of wing wall = 3.82 m
Depth of PCC = 0.15 m
Width = (3.07+ 4.36)/2 = 3.72 m
(Refer MOST Dwg. No. SD/113 sheet 6 of 6)
No. = 4
Total =
11.4 A.
3 II) PCC grade M-15
Curtain walls 2 13.32 0.75 0.15
Curtain walls 2 13.32 0.45 0.60
Total =
4 Box Portion
RCC grade M-20 cum
12.5 A.
III).
12.5 A. Bottom & Top slab Cum 2 7.50 7.00 0.30
III). Outer wall Cum 2 7.50 0.25 2.00
Inner wall Cum 2 7.50 0.25 2.00
Huanch Cum 12 7.50 0.08 0.15
Wheel guard Cum 2 14.00 0.25 0.23
Parapet Cum 2 14.00 0.20 0.38
Return wall Cum 4 4.50 0.30 0.60
Cum 4 3.00 0.30 3.00
Cut-off walls Cum 2 7.00 0.30 1.50
Total =
5 Wing wall
12.5 A. PCC grade M-20 cum
II). (Refer MOST Dwg. No. SD/113 sheet 6 of 6)
Total =
6 13.6 RCC Railing Rm 2 14.00
No. = 2
L = 7+2x3.5 = 14.00 m
7 12.11 Filling with Filter media (Both side)
a) For Box Portion cum 2 0.60 7.50 1.40
No. =2
L= 0.6m
W = 7.50m
Ht. = 1.4m
b) For wing wall cum 4 3.82 0.60 2.85
Length of wing wall = 3.82 m
Ave.Ht. = (4.62+2.15)/2 = 3.39 m
Width = 0.60 m
No. = 4
Total =
8 14.8 Dry Rubble Flooring for Floor Apron, 600 mm thick
Upstream cum 1 10.16 3.00 0.60
Downstream cum 1 10.16 5.00 0.60
Total =
9 12.10 Backfilling behind Abutment, wing wall etc.
a) Behind Abutment cum 2 7.50 3.50 1.70
b) Behind Wing wall cum 4 3.82 3.50 1.50
Total =
10 13.10 Drainage Spout No.
11 12.9 Weep holes 150 mm dia. No.
12 13.5 B RCC wearing coat sqm 1 7.00 7.00 0.075
13 13.3 Reinforcement (As per MOST)
a) For Box Portion MT
14 13.16 iii 25 mm Premould Bituminous Rm 2 7.50
(U/S & D/S Pitching)

Rate
Quantity including Amount
13.5% GST

52.500

10.500

19.980

18.288
30.480

69.218

200.966 115.77 23265.88

5.250

6.922

12.172 5772.16 70257.76

2.997
7.193
10.190 5772.16 58817.16
31.500
7.500
7.500
1.013
1.575
2.100
3.240

6.300
60.728 7333.24 445329.03

99.800

99.800 6910.22 689640.01


28.000 2720.60 76176.66
12.600

26.129

38.729 2039.60 78991.07

18.288
30.480
48.768 2516.07 122703.60

89.250
80.220
169.470 1453.25 246282.96
2.000 1862.42 3724.84
50.000 133.59 6679.48
3.675 13565.86 49854.54

3.371 ### 215470.57


15.000 260.26 3903.83
Total = 2091097.0
Format - F8
ANALYSIS OF RATES

Name of Road : Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur


Name of Block : Krishnai
Route No. : L29
Haulage
Rate as
Ref. Item No. of per SOR Loading Unloading Unsurfaced
Sl. Loose Surfaced Road Katcha Road Total of haulage Final Rate
Item of works SOR 2017-18 2017-18 Unit Gravelled Road
No. Qty 6x{(9x10)+(11x12)+ (4+7+8+15)
(Rural Roads) (Rural
Roads) (13x14)}
Amount Amount Km Rate Km Rate Km Rate

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1 Granular Sub-base 4.1/(A) (ii) 1466.00 cum 1.280 46.00 14.90 2.00 18.50 2.00 29.10 999.17 2465.17

1.210 23.50 14.90 2.00 18.50 2.00 29.10 538.87


2 WBM Grading - II 4.7/2(B) 2732.70 cum 3391.82
0.270 23.50 14.90 2.00 18.50 2.00 29.10 120.24

1.210 23.50 14.90 2.00 18.50 2.00 29.10 538.87


3 WBM Grading - III 4.7/3(B) 2764.60 cum 3410.36
0.240 23.50 14.90 2.00 18.50 2.00 29.10 106.88

20mm thick Open-Graded 5.9/


4 132.80 cum 0.027 23.50 14.9 2.00 18.50 2.00 29.10 12.02 144.82
Premix Carpet Case -II (i)

5.12/ B
5 Seal Coat 42.30 cum 0.009 23.50 14.9 2.00 18.50 2.00 29.10 4.01 46.31
Case -II (i)

6 Boulder Apron 14.1 1349.50 cum 1.200 46.00 14.90 2.00 18.50 2.00 29.10 936.72 2286.22

7 Boulder Pitching 14.5 (I) 1349.50 cum 1.200 46.00 14.90 2.00 18.50 2.00 29.10 936.72 2286.22

8 Filter metarial 14.6 1768.60 cum 1.280 46.00 14.90 2.00 18.50 2.00 29.10 999.17 2767.77

Executive Engineer , PWD


Asstt. Executive Engineer, PWD
Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division
Goalpara
2
1
Sl. No.

Chainage

750.00
415.00
Catchment area (A) in hecters

11.65
13.14
Dist. From critical point to

3.48
3.20
structure (L) in KM

Fall in level from critical point to

1.36
1.15
structure (H) in m

Severest rainfall in 20 years (F)

15
15
in mm

Duration of severest rainfall (T)

2.5
2.5
in Hrs

Design Intensity of rainfall (Io) =

10.5
10.5
F/2(1+1/T) in mm

Concentration time
9.54

10.38
tc=(0.87XL3/H)0.385
Coef of runnof for the
catchment
0.5
0.5

P
1
1

λ=0.056fP/(tc+1)
0.0025
0.0027

Discharge of catchment
0.31
0.37

Q=Aioλ in m3/sec

Silt factor (Ksf) = 1.76(dm)0.5


0.88
0.88
Hydraulic design chart for Slab culvert

Regime fow Velocity


0.01
0.01

V = 0.44Q1/6Ksf1/3

Regime fow Sectional area


0.90
1.05

A=2.3Q5/6/Ksf1/3
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur

Size of culvert provided


1.5
1.5

Formation Level
99.781
99.800

Bed / Invert level


98.581
98.668

Depth of Slab in m
0.21
0.21

Vertical clearence in m
0.15
0.15

Weted Sectional area of culvert


1.485
1.383
iguri to NH37 via Borjuk Manikpur
sign chart for Slab culvert

Remarks
OK

OK
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur

Hydraulic design chart of Single HP culvert

Height
Theoritical No. of
between
discharge by Operating Length Conveyance Discharge cell
Ch. of Catchment R.L. of Invert Road Diameter
Dickens head (H1= of factor l per pipe require
Sl. No Proposed area in Sq. Road Level level & of pipe Remarks
formula H-D) Culvert (plate -27 (Q ) (plate - d=
culvert Km in M In M Invert (D) in m
Q=CM3/4(Cum/ in m in m IRC:SP 13 27 curve) QR/Q
Level H
sec)
in m
1 2 3 4 5 6 7 8 9 10 11 12
Single Hume
1 845 0.075 2.006 66.68 65.48 1.200 1.00 0.20 7.5 0.7 1.387 1 pipe culvert
Proposed

Double Hume
2 1980 0.150 3.374 66.32 64.10 1.200 1.00 0.20 7.5 0.7 1.387 2 pipe culvert
Proposed

Single Hume
3 2195 0.060 1.697 66.32 64.10 1.200 1.00 0.20 7.5 0.7 1.387 1 pipe culvert
Proposed
Anne
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR PROTECTION WORK ALONG THE SLOPE ON RIVER SIDE EMBANKMENT
Road Name: Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur PACKAGE NO :
DISTRICT :
300 BLOCK : Krishnai

DATA INPUT FOR TOE WALL


HEIGHT OF TOE WALL = 1.20
COUNTRY SITE LENGTH = 50.00
1200 LENGTH ALONG SLOPE = 4.00
GL WIDTH OF TOE WALL = 0.40
WIDTH OF TOE WALL FOOTING = 1.20
450 900 TOP WIDTH OF TOE WALL = 0.30
P.C.C 100 mm Thick (1:3:6) BOTTOM WIDTH OF TOE WALL = 0.90
1200 DEPTH OF TOE WALL BELOW GL = 0.45
Section of Stone Masonary Toe Wall

Item No/
SOR Ref / Description Unit No. Length Breadth Height Quantity Rate
MoRTH Ref
1/11.1 Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
side
(I) Ordinary Soil
Upto 3 m depth
Cum
Foundation for Toe wall 1 50.00 1.20 0.45 27.00
Total = 27.00 71.00
2/11.4 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203
A. With crushed stone.
(I) P.C.C grade M 10
Nominal mix 1:3:6
Cum
Below Foundation 1 50.00 1.20 0.10 6.00
Total = 6.00 5299.00
Item No/
SOR Ref / Description Unit No. Length Breadth Height Quantity Rate
MoRTH Ref
3/12.4 Stone masonry in cement mortar for substructure complete as
per drawing & technical specification Clauses 702, 704, 1202
and 1204 (III) Random rubble masonry
In cement mortar (1:5) Cum
(0.30+0.9)
Toe Wall 1 50.00 1.200 36.00
2
Total = 36.00 3241.00
4/13.5 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7
Nos.
100 100
Total = 100 182.00
5/14.5 Providing and laying pitching on slopes laid over prepared filter
media as per drawing and technical specifications Clause 1302
(I) Stone/Boulder Cum
Along Sloping Length 1 4.00 50.00 0.50 100.00
Total = 100.00 1166.00
6/14.6 Providing and laying filter material underneath pitching in slopes
complete as per drawing and technical specifications Clause
1302 Cum
Along Sloping Length 1 4.00 50.00 0.15 30.00
Total = 30.00 1332.00
7/12.13 Providing PCC M-20 architectural coping on the top of wing wall,
return wall etc. complete as per drawing and technical
specification Clauses 615, 710 and 1204.3.11
(i) With Crushed stone Rm
1 20.00 20.00
Total = 20.00 413.00
Grand Total =
Say =

Executive Engineer , PWD


Asstt. Executive Engineer, PWD
Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division
Annexure - I
NTRI GRAM SADAK YOJANA (PMGSY)
N WORK ALONG THE SLOPE ON RIVER SIDE EMBANKMENT
AS-07-
Goalpara

m
m
m
m
m
m
m
m

Amount

1917.00

31794.00
Amount

116676.00

18200.00

116600.00

39960.00

8260.00
333407.00
333410.00

Executive Engineer , PWD


Goalpara Rural Road Division
CROSS DRAINAGE WORKS
Format - F7C

Name of Road : Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur

Type of Cross Drainage works :


1. Box Culvert (Double Cell) (3.00m x 3.00m) = 1 No.

Sl. Length Width Thickness Rate in Amount in


Description of Item Item No. Unit Quantity
No (m) (m) (m) (Rs) (Rs.)
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures upto 3 m depth
as per drawing and technical specification Clause 1104 includding
setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
Rate as per SOR PMGSY - 2011-12
11.1 (i) Qty. as per Statement No. - 11 Cum 162.563 102.00 16581.38
2 Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course
below open foundation of Head walls as per drawings & Technical
Specification Clause 1109
Rate as per SOR PMGSY - 2011-12
11.4 A(i) Qty. as per Statement No. - 11 Cum 11.813 5216.60 61621.09
3 Plain/Reinforced cement concrete, in sub structure complete as per
drawing and technical specification Clauses 802, 804, 805, 806, 807,
1202 and 1204
A. With Crushed Stone
RCC Grade M20 for Height upto 5m
Qty. as per Statement No. - 6
Rate as per SOR PMGSY - 2011-12 12.5 A III
(i) Qty. as per Statement No. - 11 Cum 89.168 6461.00 576111.22
4 Supplying, fitting and placing TMT bar reinforcement (Fe-500) in
sub-structure complete as per drawing and technical specifications
Clauses 1002, 105, 1010 & 1202
Qty. as per Statement No. - 6
16.99.3(A
Rate as per SOR PMGSY - 2011-12
) Qty. as per Statement No. - 11 Cum 6.900 55477.00 382791.30
5 Providing and laying Cement concrete wearing coat M-30 grade
including reinforcement complete as per drawing and Technical
Specifications Clauses 1002, 1010 and 1202
A. With crushed stone
Rate as per SOR PMGSY - 2011-12
16.99.17 Qty. as per Statement No. - 11 Cum 4.050 11203.00 45372.15
6 Construction of RCC railing of M30 Grade in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of vertical
RCC post not to exceed 1 in 500, centre to centre spacing between
vertical post not to exceed 2000 mm, as per drawings and technical
specifications clauses 800, 900 and 1208.3
Rate as per SOR PMGSY - 2011-12
13.6 Qty. as per Statement No. - 11 Rm 15.000 1683.00 25245.00
7 Providing and laying boulder apron for bed protection with stone
boulders of minimum size and weight as per Table 1300.1, no
fragment weing less than 25 kg laid dry complete as per drawing and
technical specifications clause 1301
Rate as per SOR PMGSY - 2011-12
14.1 Qty. as per Statement No. - 11 Cum 36.000 1025.00 36900.00
Total = 1107722.13
FORMAT F-7
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
Road from PACKAGE NO :
Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur DISTRICT :
TYPE OF CROSS DRAINAGE WORKS : Single Hume Pipe (1x1000 mm) DESIGN DISCHARGE 1.50 Cumec
BLOCK : Krishnai TYPE OF SOILL:

Item No/ Rate


SOR Ref / Description Unit No. Length Breadth Height Quantity Rate (Including
MoRTH Ref 13.50%GST)

1/11.1 Earthwork in excavation for structures as per drawing and technical


specifications Clause 305.1 including setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and disposal upto a
lead of 50 m, dressing of side
(I) Ordinary Soil
Upto 3 m depth
Cum
Head wall 2 4.35 1.40 1.20 14.62
Bed 1 4.85 1.53 0.53 3.93
Total = 18.55 102.00 115.77
2/9.7 PCC 1:3:6 in Foundation
Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course below open
foundation of Head walls as per drawings & Technical Specification Clause
1109 Cum
Levelling course below wall 2 4.35 1.40 0.15 1.83
Total = 1.83 5216.59 5920.83
3/9.2 Bedding of pipe
(ii) Type B (First Class) Bedding
Laying (First Class) bedding on well compacted sand, moorum or approved
granular material as per Clause 1105 (ii)
(ii)Granular Material
Cum
Bedding 1 4.85 1.53 0.530 3.93
Total = 3.93 1369.05 1553.87
4/9.3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per
design in Single Row:
Providing and laying reinforced cement concrete pipe NP3 for culverts on first
class bedding of granular material in single row including fixing collar with
cement mortar 1:2 but excluding excavation, protection works, backfilling,
concrete and masonry
(B)1000 mm dia
RM
3 2.50 7.50
Total = 7.50 6880.48 7809.34
Item No/ Rate
SOR Ref / Description Unit No. Length Breadth Height Quantity Rate (Including
MoRTH Ref 13.50%GST)
5/9.8 Brick Masonry Work in cement mortar in foundation of Head walls complete
exculding pointing and plastering as per drawing and technical specification
Clause 1109
(A) Brick Masonry in 1:4 cement mortar cum
Head wall 2 2.00 0.90 6.00 21.60
deduct for Pipe opening 2 0.83 1.13 -1.88
Parapet Wall 2 4.15 0.60 0.40 1.99
Total = 21.72 6464.44 7337.14

6/9.11 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in substructure


as per technical specification sqm
2 4.15 1.32 10.96
4 0.83 1.32 4.38
2 4.15 0.40 3.32
2 4.15 0.60 4.98
deduct 1.13 -1.13
Total = 22.51 121.17 137.53
7/14.1 Providing and laying boulder apron for bed protection with stone boulders of minimum size
and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per
drawing and technical specifications Clause 1301

Up stream cum 4.15 1.5 0.3 1.868


Down stream cum 4.15 3.00 0.3 3.735
Total = 5.603 1349.53 1531.71
Grand
Total =

Executive Engineer , PWD


Asstt. Executive Engineer, PWD
Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division
Goalpara
FORMAT F-7
GRAM SADAK YOJANA (PMGSY)
ROSS DRAINAGE WORKS CULVERTS AND MINOR BRIDGES
AS-07-
Goalpara

Aluvial

Amount

2147.00

10817.00

6111.00

58570.00
Amount

159333.00

3095.00

8582.00
248655.00
248660.00

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
Ann
Name of Road : Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur
Name of Block : Krishnai
Package No.: AS-07-
Rate Analysis of Citizen Information Board / Maintanance Information Board

Reference to
Sl. Rate
MORD Description Unit Quantity
No. (Rs.)
Specifications
1 1700 Providing and Fixing Citizens Information Board
Providing and fixing of typical Citizens Information Board with Logo as
per MORD specifications and drawing. Two nos. 1.6mm thick MS sheet
duly welded with 5mm thick steel plate on back on edges. The 4 nos.
steel plate will be welded horizontally with 2 nos. 75mm x 75mm of 12
SWG sheet tubes posts duly embedded in cement concrete M-15 grade
blocks of 600mm x 600mm x 750mm, 750mm below ground level. The
2 nos. steel plate will be welded vertically to 2 nos. 75mm x 75mm of 12
SWG sheet tubes posts duly welded to vertical tubes. All M.S. will be
stove enameled on both sides. Lettering and printing arrows, border etc.
will be painted with ready mixed synthetic enamel paint of superior
quality in required shade and coloue. All sections of framed posts and
steel tube will be painted with primer and two coats of epoxy paint as
per drawing Clause 1701 and Annexure 1700.1

Unit = Each
Taking out put = one typical board
(i) Excavation for foundations
As per Item No. 11.1 of Chapter 11 cum 0.270 102.00
(ii) PCC grade M15
As per Item No. 11.4 of Chapter 11 cum 0.270 5085.61
(iii)
Painting on MS Steel tubes with primer and two coats of epoxy
paint
2 x 2.45 x 0.30 = 1.47
2 x 1.00 x 0.30 = 0.60
As per Item No. 10.6 of Chapter 10 sqm 2.070 66.86
(iv) Painting new letters and figures of any shade with synthetic enamel
Top Plate :
Heading Band=90x1x10=900 per cm height per letter
Figure 7x10 = 70 per cm height per letter
Side Border 2x65x1.5=195 per cm height per letter
Lower Border 1x90x1.5=135 per cm height per letter
Words (57x2.5+245x1.7) = 559 per cm height per letter
Figure 65x20 = 1300 per cm height per letter
Bottom Plate :
Border (2x75x1.5+2x90x1.5) = 495 per cm height per letter
Words 565x1.7 = 96..50 per cm height per letter
Total 4614.50 per cm height per letter
As per Item No. 10.1 of Chapter 10
per cm
height per
letter 4614.500 0.59
a) Labour (for fixing at site)
Mate day 0.060 356.65
Mazdoor (Unskilled) day 1.000 244.56
b) Materials
MS tubes 75mmx75mm of 12 SWG sheet 8400mm long kg 100.090 127.00
5mm steel plate kg 14.600 35.15
1.6mm thick MS sheet strengthening by 25mm x 5 MS flat iron on
painting with stove enameled paint on both sides as per MORD
specifications. sqm 1.350 2500.00
Add 3% cost of MS tube and steel plate towards the cost of
fabrications, drilling holes, nuts, bolts etc.
c) Machinery
Tractor with trolley hour 0.300 409.00
d) Overheads & Contractor's profit @ 12.5% on (a+b+c)
Cost for one Board = (i+ii+iii+iv+a+b+c+d)
Say =
Note : Printing and lettering for blank spaces on the plates will be written as
required and paid separately.
Annexure - I

Amount
(Rs.)

27.54

1373.11

138.40

2722.56

21.40
244.56

12711.43
513.19

3375.00

482.59

122.70
2183.86
23916.34
23917.00
FORMAT F-9A

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


CERTIFICATE OF GROUND VERIFICATION FROM EXECUTIVE ENGINEER / HEAD OF PIU

1 a) Certified that the Land width for the road is available and that no additional land is required

2 b) Certified that no forest land is involved along the entire road way

3 Certified that the DPR has been checked by

AE AEE EE

On Date………………

(DPR wise summary in format F9-B)

Head of PIU
PRADHAN MANTRI GRAM SADAK YOJANA

ABSTRACT OF MAINTENANCE COST UNDER 5 YEAR MAINTENANCE PLAN

Krishnai Chariali Pakhriguri to NH37 via Borjuk


Name of Road :
Manikpur

Length : 0.419 km
Package No. : AS-07-

Sl No. Description of Item Unit Quantity Rate in Rs. Amount in Rs.


1 2 3 4 5 6

1 Maintenance cost for 1st year km 0.419 20005.00 8382.10

2 Maintenance cost for 2nd year km 0.419 22090.00 9255.71

3 Maintenance cost for 3rd year km 0.419 117796.00 49356.52

4 Maintenance cost for 4th year km 0.419 141125.00 59131.38

5 Maintenance cost for 5th year km 0.419 197543.00 82770.52

Total = 208896.22
Say Rs. In Lakh = 2.09
Generalised per KM Maintenance Cost for ASSAM PMGSY FOR THE YEAR 2017-
(Rates Based on SOR 2017-18)

For 1st Year


Sl. SOR ref.
Item of work Qntty Unit Rate Amount
No. No.

1 15.1 (A) Restoration of rain cuts 48.35 Cum 130.50 6309.68

Maintenance of earthen shoulder


2 15.2 (1) 250.00 Sqm 15.60 3900.00
(stripping of excess soil)

Repair of pot holes by removal of failed


3 15.3 (1) 0.00 Cum 7396.20 0.00
material and filing with 75 mm BM

Maintenance of Bituminous surface road ,


4 15.3 (IV) 0.00 Sqm 173.70 0.00
pot hole repairing, etc.)

5 15.7 (I) Maintenance of Hume pipe culverts 4 No. 1439.60 5758.40

6 15.9 Maintenance of Road signs 0.50 km 1100.90 550.45

7 15.10 (II) Maintenance of RCC railing 0.38 M 137.20 52.14

Maintenance of 200 m stones and Km


8 15.11 (I) 1.00 km 524.40 524.40
stones

9 15.12 (I) Cutting branches of trees from roadway 20 No. 100.00 2000.00

10 15.12 (II) Cutting of shrubs from roadway 40 No. 5.80 232.00

11 15.12 (III) Trimming grass and weeds from shoulder 270.00 Sqm 1.90 513.00

White washing of parapet walls of CD


12 15.13 10.00 Sqm 16.50 165.00
works

Total 20005.06
Say Rs. 20005.00
Generalised per KM Maintenance Cost for ASSAM PMGSY FOR THE YEAR 2017-
(Rates Based on SOR 2017-18)

For 2nd Year


Sl. SOR ref.
Item of work Qntty Unit Rate Amount
No No

1 15.1 (A) Restoration of rain cuts 56.97 Cum 130.50 7434.59

Maintenance of earthen shoulder


2 15.2 (1) 300.00 Sqm 15.60 4680.00
(stripping of excess soil)

Repair of pot holes by removal of failed


3 15.3 (1) 0.00 Cum 7396.20 0.00
material and filing with 75 mm BM

Maintenance of Bituminous surface road ,


4 15.3 (IV) 0.00 Sqm 173.70 0.00
pot hole repairing, etc.)

5 15.7 (I) Maintenance of Hume pipe culverts 4 no 1439.60 5758.40

6 15.9 Maintenance of Road signs 0.50 km 1100.90 550.45

7 15.10 (II) Maintenance of RCC railing 0.76 m 137.20 104.27

Maintenance of 200 m stones and Km


8 15.11 (I) 1.00 km 524.40 524.40
stones

9 15.12 (I) Cutting branches of trees from roadway 20 no 100.00 2000.00

10 15.12 (II) Cutting of shrubs from roadway 40 no 5.80 232.00

11 15.12 (III) Trimming grass and weeds from shoulder 337.50 Sqm 1.90 641.25

White washing of parapet walls of CD


12 15.13 10.00 Sqm 16.50 165.00
works

Total 22090.36

Say Rs. 22090.00


Generalised per KM Maintenance Cost for ASSAM PMGSY FOR THE YEAR 2017-
(Rates Based on SOR 2017-18)

For 3rd Year


Sl. SOR ref.
Item of work Qntty Unit Rate Amount
No No

1 15.1 (A) Restoration of rain cuts 175.00 Cum 130.50 22837.50

Maintenance of earthen shoulder


2 15.2 (1) 494.71 Sqm 15.60 7717.48
(stripping of excess soil)

Repair of pot holes by removal of failed


3 15.3 (1) 8.78 Cum 7396.20 64947.96
material and filing with 75 mm BM

Maintenance of Bituminous surface road ,


4 15.3 (IV) 70.31 Sqm 173.70 12212.85
pot hole repairing, etc.)

5 15.7 (I) Maintenance of Hume pipe culverts 4 no 1439.60 5758.40

6 15.9 Maintenance of Road signs 0.50 km 1100.90 550.45

7 15.10 (II) Maintenance of RCC railing 1.52 m 137.20 208.54

Maintenance of 200 m stones and Km


8 15.11 (I) 1.00 km 524.40 524.40
stones

9 15.12 (I) Cutting branches of trees from roadway 20 no 100.00 2000.00

10 15.12 (II) Cutting of shrubs from roadway 40 no 5.80 232.00

11 15.12 (III) Trimming grass and weeds from shoulder 337.50 Sqm 1.90 641.25

White washing of parapet walls of CD


12 15.13 10.00 Sqm 16.50 165.00
works

Total 117795.82
say Rs. 117796.00
Generalised per KM Maintenance Cost for ASSAM PMGSY FOR THE YEAR 2017-
(Rates Based on SOR 2017-18)

For 4th Year


Sl. SOR ref.
Item of work Qntty Unit Rate Amount
No No

1 15.1 (A) Restoration of rain cuts 195.00 Cum 130.50 25447.50

Maintenance of earthen shoulder


2 15.2 (1) 723.90 Sqm 15.60 11292.84
( stripping of excess soil)

Repair of pot holes by removal of failed


3 15.3 (1) 10.54 Cum 7396.20 77967.49
material and filing with 75 mm BM

Maintenance of Bituminous surface road ,


4 15.3 (IV) 93.75 Sqm 173.70 16284.55
pot hole repairing, etc.)

5 15.7 (I) Maintenance of Hume pipe culverts 4 no 1439.60 5758.40

6 15.9 Maintenance of Road signs 0.50 km 1100.90 550.45

7 15.10 (II) Maintenance of RCC railing 1.90 m 137.20 260.68

Maintenance of 200 m stones and Km


8 15.11 (I) 1.00 km 524.40 524.40
stones

9 15.12 (I) Cutting branches of trees from roadway 20 no 100.00 2000.00

10 15.12 (II) Cutting of shrubs from roadway 40 no 5.80 232.00

11 15.12 (III) Trimming grass and weeds from shoulder 337.50 Sqm 1.90 641.25

White washing of parapet walls of CD


12 15.13 10.00 Sqm 16.50 165.00
works

Total 141124.55
Say Rs. 141125.00

Generalised per KM Maintenance Cost for ASSAM PMGSY FOR THE YEAR 2017-
(Rates Based on SOR 2017-18)

For 5th Year


Sl. SOR ref.
Item of work Qntty Unit Rate Amount
No No

1 15.1 (A) Restoration of rain cuts 250.00 Cum 130.50 32625.00

Maintenance of earthen shoulder (tripping


2 15.2 (1) 1094.15 Sqm 15.60 17068.74
of excess soil)

Repair of pot holes by removal of failed


3 15.3 (1) 15.81 Cum 7396.20 116933.92
material and filing with 75 mm BM

Maintenance of Bituminous surface road ,


4 15.3 (IV) 117.19 Sqm 173.70 20355.90
pot hole repairing, etc.)

5 15.7 (I) Maintenance of Hume pipe culverts 4 no 1439.60 5758.40

6 15.9 Maintenance of Road signs 0.50 km 1100.90 550.45

7 15.10 (II) Maintenance of RCC railing 1.90 m 137.20 260.68

Maintenance of 200 m stones and Km


8 15.11 (I) 1.00 km 524.40 524.40
stones

9 15.12 (I) Cutting branches of trees from roadway 20 no 100.00 2000.00

10 15.12 (II) Cutting of shrubs from roadway 40 no 5.80 232.00

11 15.12 (III) Trimming grass and weeds from shoulder 562.50 Sqm 1.90 1068.75
White washing of parapet walls of CD
12 15.13 10.00 Sqm 16.50 165.00
works

Total 197543.25
Say Rs. 197543.00
5 years Total 498559.00
ntenance Cost for ASSAM PMGSY FOR THE YEAR 2017-18
(Rates Based on SOR 2017-18)

Remark

total 6% raincuts for 1st year

Total 10 % requiring for 1st


year

Maintenance not required at


the end of the first year

Maintenance not required at


the end of the first year

maintenance to be done twice


a year

maintenance to be done once


in 2 years

considering 2% requiring
maintenance

Considering 12% of the total


area requiring grass trimming
ntenance Cost for ASSAM PMGSY FOR THE YEAR 2017-18
(Rates Based on SOR 2017-18)

Remark

total 7.2% raincuts for 2nd


year

total 12 % for 1st year

Maintenance not required at


the end of the second year

Maintenance not required at


the end of the 2nd year

maintenance to be done twice


a year

maintenance to be done once


in 2 years

considering 4% requiring
maintenance

considering 15% of the total


area requiring grass trimming
ntenance Cost for ASSAM PMGSY FOR THE YEAR 2017-18
(Rates Based on SOR 2017-18)

Remark

Total 8.4% raincuts for 3rd


year

Total 14 % requiring
maintenance for 3rd year

total 2.5% requiring


maintenance for 3rd year

total 1.5% requiring


maintenance for 3rd year

maintenance to be done twice


a year

maintenance to be done once


in two years

considering 8% requiring
maintenance

considering 15% of the total


area requiring grass trimming
ntenance Cost for ASSAM PMGSY FOR THE YEAR 2017-18
(Rates Based on SOR 2017-18)

Remark

total 9.6% raincuts for 4th


year

total 16% requiring


maintenance for 4th year

total 3% requiring
maintenance for 4th year

total 2% requiring
maintenance for 4th year

maintenance to be done twice


a year

maintenance to be done once


in two years

considering 10% requiring


maintenance

considering 15% of the total


area requiring grass trimming
ntenance Cost for ASSAM PMGSY FOR THE YEAR 2017-18
(Rates Based on SOR 2017-18)

Remark

total 10.8% raincuts for 1st


year

total 18 % requiring
maintenance for 5th year

total 4.5 % requiring


maintenance for 5th year

total 2.5 % requiring


maintenance for 5th year

maintenance to be done twice


a year

maintenance to be done once


in two years

considering 10% requiring


maintenance

considering 25% of the total


area requiring grass trimming
Annex
ANALYSIS FOR ROAD SIDE DRAIN
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF ROAD SIDE DRAIN
Road Name: Krishnai Chariali Pakhriguri to NH37 via Borjuk Manikpur PACKAGE NO :
DISTRICT :
BLOCK : Krishnai TYPE OF SOILL:
Cosidering Length of Road side Drain = 30 m

Sl. No. /
Item Description Unit No. Length Breadth Height Quantity Rate
No.
1/11.1 Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of
side
(I) Ordinary Soil
Upto 3 m depth
Cum
Drain 1 30.000 1.10 0.70 23.10
Total = 23.10 102.00
2/12.1 Brick masonry work in cement mortar in substructure complete
excepting pointing and plastering, as per drawing and technical
specification Clauses 602, 603, 604, 1202 & 1204
ii. In 1:4 Cement mortar
Flat Soiling Sqm 1 30.00 1.00 30.00
2/12.1 Brick masonry work in cement mortar in substructure complete
excepting pointing and plastering, as per drawing and technical
specification Clauses 602, 603, 604, 1202 & 1204
ii. In 1:4 Cement mortar Cum
Drain Walls 2 30.00 0.25 0.75 11.25
Total = 41.25 6925.73
Sl. No. /
Item Description Unit No. Length Breadth Height Quantity Rate
No.
3/11.4 Providing concrete for plain/reinforced concrete in open
foundations complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203
A. With crushed stone.
I. P.C.C grade M 10
Nominal mix 1:3:6
1 30.00 0.40 0.10 1.20
Total = 1.20 5216.59
4/13.1/A Providing and laying reinforced cement concrete in
superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5
i With crushed stone
a R.C.C grade M20(Height upto 5m) 1 30.00 0.90 0.15 4.05 6997.71
5/12.9
Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and technical specification Clauses
614, 709, 1204.3.7
Nos 2 4.00 8.00 117.70
6/12.3 Plastering with cement mortar (1:4), 15 mm thick on brickwork in
substructure as per technical specification Clauses 613.4 & 1204
Sqm
Drain Inside Walls 2 30.00 0.65 39.00
Bottom 1 30.00 0.40 12.00
Top 2 30.00 0.20 12.00
Total = 63.00 121.17

7/13.2 Supplying, fitting and placing TMT (Fe-500 D) reinforcement bar .


(From Primary Producer: TATA/SAIL/Esser Steel/ Jindal
steel/Shyam steel/RINL) in superstructure complete as per
drawing and technical specifications Clauses 1002, 1010 and
1202
Transverse Direction Mt
Longitudinal Direction
0.30 56316.20
Sl. No. /
Item Description Unit No. Length Breadth Height Quantity Rate
No.
Grand Total =
Cost per RM =
Say Rs. =

Executive Engineer , PWD


Asstt. Executive Engineer, PWD
Goalpara Rural Road Division
Goalpara/Dudhnoi Rural Road Sub Division
Goalpara
Annexure - III
YSIS FOR ROAD SIDE DRAIN
NTRI GRAM SADAK YOJANA (PMGSY)
OR CONSTRUCTION OF ROAD SIDE DRAIN
AS-07-

Aluvial

Amount

2356.00

285686.00
Amount

6260.00

28340.73

235.40

7634.00

16791.13
Amount

347303.25
11576.78
11577.00

Executive Engineer , PWD


Goalpara Rural Road Division
Goalpara
no dia spac total l nos l Kg/rm Total in KGTonne
long 10 150 30 7.00 210.00 0.62 130.2 0.1302
tranvrs 10 150 0.9 301.00 270.90 0.62 167.958 0.167958
0.298158

You might also like