Initia Initial Phase: 28 15-May-18 15-Jun-18

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Building Planning

Activity ID Activity Name Dur. Start Finish May 2018 June 2018
13 20 27 03 10 7

Building Planning and Design 28 15-May-18 15-Jun-18


Initial Phase
Initia 12 15-May-18 28-May-18
1 Contract Agreement 1 15-May-18 15-May-18
2 Survey Site 1 16-May-18 16-May-18
Mobilization
3 Topographic Survey 5 17-May-18 22-May-18
4 Soil Investigation 5 23-May-18 28-May-18
Planning Phase
Plan 4 29-May-18 01-Jun-18
5 Topographic Map 1 29-May-18 29-May-18
Study
6 Layout Planning 1 30-May-18 30-May-18
7 Survey Report 2 31-May-18 01-Jun-18
Design Phase
Desi 7 03-Jun-18 10-Jun-18
8 Structural Design 3 03-Jun-18 05-Jun-18
9 Drawing 2 06-Jun-18 07-Jun-18
10 Estimation 2 08-Jun-18 10-Jun-18
Reporting Phase
Repo 5 11-Jun-18 15-Jun-18
11 Draft Report 2 11-Jun-18 12-Jun-18
12 Final Report 3 13-Jun-18 15-Jun-18

Remaining Work
Summary Harmonic Engineering Pvt. Ltd.