Professional Documents
Culture Documents
MS - Tank Cleaning and Desludging
MS - Tank Cleaning and Desludging
CONTRACT TITLE: -
DESIGN, ENGG, PROCUREMENT, INSTALLATION, CONSTRUCTION, PRE-
COMMISSIONING, PERFORMANCE TESTING & START UP FOR CONVERSION OF 3NOS
FIXED ROOF TANKS TO FLOATING ROOF TANKS
DOCUMENT TITLE :
METHOD STATEMENT FOR OPENING OF MANHOLE AND TANK CLEANING FOR
RESIDUAL IMPURITIES FROM 3 NOS JET A1 TANK (3403FA/FB/FC)
REV 1 P0021019-GE-MS-0003
METHOD STATEMENT FOR OPENING OF MANHOLE AND TANK CLEANING FOR RESIDUAL IMPURITIES
FROM 3 NOS JET A1 TANK (3403FA/FB/FC)
TABLE OF CONTENTS
1. SCOPE ........................................................................................................................ 3
2. LIST OF ABBREVATION............................................................................................ 3
8. ATTACHMENTS ........................................................................................................ 7-
TAAWC/AID/09/01/19: DESIGN, ENGG, PROCUREMENT, INSTALLATION,
CONSTRUCTION, PRE-COMMISSIONING, PERFORMANCE TESTING & START UP
FOR CONVERSION OF 3NOS FIXED ROOF TANKS TO FLOATING ROOF TANKS
REV 1 P0021019-GE-MS-0003
METHOD STATEMENT FOR OPENING OF MANHOLE AND TANK CLEANING FOR RESIDUAL IMPURITIES
FROM 3 NOS JET A1 TANK (3403FA/FB/FC)
1.0 Scope
This document covers the procedures to be complied for opening of manhole, tank cleaning
and removal of residual impurities after tank evacuation from 3 Nos jet fuel tanks
(3403FA/FB/FC) at Doha depot.
REV 1 P0021019-GE-MS-0003
METHOD STATEMENT FOR OPENING OF MANHOLE AND TANK CLEANING FOR RESIDUAL IMPURITIES
FROM 3 NOS JET A1 TANK (3403FA/FB/FC)
i) All operatives must be briefed about JHA and Method statement prior to work
commencing.
Construction Manager The Construction manager is responsible for overall site execution
and mobilization of this scaffolding works & close coordination with construction group,
client and ensure the timely completion of project as per project specification, Quality and
safety requirements.
Project engineer Manage overall site activities including mobilization and demobilization,
manpower allocation, procurement, safety, quality, close coordination with construction
group, client and ensure the timely completion of project as per project specification
Supervisor shall be responsible for the overall implementation of Method Statement and
directly has full control over the use of the labor, plant and equipment. He ensures that the
works carried out in full compliance with the specification, quality and safety requirements
Permit Holder (PH) is responsible for ensuring that the PTW is approved and revalidated
at the start of site activities are in accordance with PTW, Method of statement and JHA.
Safety Officer is to advise that all safety regulations are observed and followed to avoid the
potential for injuries or any other form of accident that will cause loss of life, injury to
personnel or damage to assets. Reporting and investigating of incidents as per WOQOD
procedure.
REV 1 P0021019-GE-MS-0003
METHOD STATEMENT FOR OPENING OF MANHOLE AND TANK CLEANING FOR RESIDUAL IMPURITIES
FROM 3 NOS JET A1 TANK (3403FA/FB/FC)
j) Gas monitors
7.1 Isolation
a) Make sure the permit is approved and TBT conducted prior to commencing the
activity.
b) Make sure the fire extinguishers and necessary sign boards in place.
c) As per Woqod procedures as applicable isolations permits shall be made prepared.
d) Make sure all blinding at upstream and downstream of tank will be carried out as per
P&ID attached in addition to the valve isolations.
e) Electrical and instrument isolations shall be carried as applicable.
f) Blinding terminology:
a) Positive isolation shall be provided at downstream of inlet filter such a way it
will block the 3 tanks.
b) Positive isolation shall be provided at upstream of outlet filter such a way it will
block the 3 tanks.
c) Recirculation line pump inlet shall be blinded
d)
REV 1 P0021019-GE-MS-0003
METHOD STATEMENT FOR OPENING OF MANHOLE AND TANK CLEANING FOR RESIDUAL IMPURITIES
FROM 3 NOS JET A1 TANK (3403FA/FB/FC)
m) Continued good quality airflow through the tank must be ensured before personnel
entry is authorized.
n) All man ways are to be removed for proper ventilation from all internal areas.
REV 1 P0021019-GE-MS-0003
METHOD STATEMENT FOR OPENING OF MANHOLE AND TANK CLEANING FOR RESIDUAL IMPURITIES
FROM 3 NOS JET A1 TANK (3403FA/FB/FC)
q) The sludge/oil/debris if any on bottom plate of the tank shall be cleaned manually
using wooden scrappers and transferred to the tank bottom.
r) The removed sludge debris from the tank shall be collected on drum and seal it
properly.
s) The sludge debris shall be transported to the waste handling facility at Mesaieed as
per WOQOD instruction.
t) After completion of de-sludging, woqod shall be called for joint inspection.
u) Upon inspecting, if required the tank internals and roof top side including rim seal
area shall be thoroughly cleaned with degreasing agents to ensure that the plate
surfaces is free from traces of oil.
v) Internal of tank shall be inspected for further site survey.
7.6 Housekeeping
a) Proper housekeeping shall be done in work area prior to leaving the site.
8.0 Attachments
a) Marked drawings (P&ID marked on page 7 & 8, Image (Page 9), Equipment and
shelter layout (Page 10), Traffic plan (Page 11), Schematic representation (Page 12)
b) JHA (Page 13-18)