Greenfield Ganga Project
Greenfield Ganga Project
Greenfield Ganga Project
Period from
Sl. Appointed
Milestones Description Remarks
No. Date
(30.11.2011)
Shall have commenced construction of
410 days project highway and expended not less Achieved on scheduled
1 Milestone - I
(13.01.2013) than 10 % of the total capital cost set date.
forth in the financial package.
Achieved on scheduled
Shall have commenced construction of
date with condition that
830 days all bridges and expended not less than
2 Milestone - II commencement of all
(09.03.2014) 35 % of the total capital cost set forth in
other bridges shifted to
the Financial Package.
Milestone III.
Not Achieved.
Shall have commenced construction of
1240 days all Project Facilities and expanded not
3 Milestone - III Milestone III
(23.04.2015) less than 70% of the total Capital cost
rescheduled up to
set forth in the Financial Package.
31.12.2018 as per EOT
Scheduled Completion date
1642 days Shall have completed in accordance
4 Commissioning extended up to
(29.05.2016) with Agreement.
Date 31.07.2019 as per EOT
3. VGF
4. Land Acquisition:
Page No. 2 of 2