MOUNTING JABIRU ENGINE 2200- 05

- IMPORTANT NOTICE:
- Follow Jabiru engine mount notice in
priority for all engines connections, fuel
system, oil system, electric wiring, bolts
torque etc…

- mount the upper steel engine mount on tube 19


- adjust with washes space between tube 24 and
engine mount to avoid torsion on engine mount

- mount the V down steel engine mount


- you must open fire wall with enough space
around each tube to avoid contact

Jabiru 2200 (text fm uk manual v 3)


a) Remove the engine from its shipping box.
To get the lid off undo the 4 screws on the sides,
not the large number
of screws on the top.
The engine sits upside down on a framework.
Remove the screws
holding this framework into the box.
Tape a piece of wood to the sump ready for the
engine to rest on,
otherwise the exhaust stubs may touch the
ground.
Get a friend to help to lift the engine out of the
box and place it upright
on the bench.
b) Fit the ring shaped pieces of the standard
Jabiru rubber mounts to the
upper mounts on the aircraft, and fit the other,
larger part of the standard
Jabiru rubber mounts to the lower engine mounts
on the aircraft.
The drawings in the Jabiru manuals vary on this
arrangement, but the
text describes this arrangement. If the top mounts
are the other way
around the front half of the mount tends to get
squeezed out by the
engine thrust, whereas with this arrangement the
central part passing
through the engine mount hole prevents this
happening.
c) Fit the engine to the mount, Figure 145.
Support the engine on a bench, such as a
workmate, chock it up to the
correct height, and offer the fuselage up to it.
An engine hoist (which
can be hired from your local hire shop), or some
other method of lifting
the engine may be used as an alternative.
Be careful how you support the engine, do not
let its weight bear on any
of its many ancillary parts such as the spark
plugs, filters, exhausts etc.
d) Fit the other rubber mount parts followed by
large steel penny washers
between the rubber parts and the securing nuts.
Discard the internal spacers supplied by Jabiru,
they are not required
with this design of mount.
e) Check that the flattened parts of the lower
engine mounts lie flat against the
saddle washers on the front vertical tu14.
If they do not then support the engine and
remove them, and carefully
tweak them to get them to lie flat.
f) Remove the support from beneath the
engine.
g) Tighten the castellated nuts until they reach
the end of their thread, then
back off if necessary to secure with large split
pins
- install ram air system on engine
- adjust each box on each side on each
cylinders
- fix ram air box with bolts on external
side and special aluminium angle in
each inner side fixed with spring down
cylinders

- IMPORTANT NOTICE:
- Follow Jabiru engine mount notice
in priority for all engines
connections, fuel system, oil system,
electric wiring, bolts torque etc…
- install exhaust on each cylinder
- tighten bolts on each cylinder according
jabiru recommended torque
- fix main down exhaust with springs
- Check general fixing and symetry

- IMPORTANT NOTICE:
- Follow Jabiru engine mount notice in
priority for all engines connections,
fuel system, oil system, electric wiring,
bolts torque etc…
- mount all 5 engine cowlings parts both
together
- (see rotax pages to check chronologie)
- cut down cowling to let space to exhaust
tubes down
- put all cowlings in place and center all
cowlings to propeller hub and fix without
drilling rear parts of cowlings with
bungee down cabin TO MAINTAIN IN
NORMAL HORIZONTAL POSITION

IMPORTANT:
you need hub propeller spacer +4 or 5 CM

- cut or granny step by step carefully the


ram air boxes in order to have cowlings
+/- 3 cm rear hub
- mount and dismount cowlings to go
smoothly step by step
- check space in front inside to mount oil
radiator
OPTIONNAL AIR BOX :

- the air box is optional and must be


mounted on right side on fire wall just over
fiber cowling angle
- the part going down after the fier wall
angle must be closed with alu sheet
- make connections according jabiru notice

the oil oveflow tank can be mounted on left fire


wall side
Install the radiator :

Different types of radiators are supplied, the


thinner (2cm) is the easiest to install

- the radiator is install and fixed on the


firewall
- check position of radiator to comply with
manufacturer notice ( oil connexions up or
down)
- check that you have enough space
between cowling and engine
- check exact position on firewall and
mark to cut smaller hole in cowling
- fix the radiator on the cowling with bolts
and angles