Schedule of Above Ground Pipe
Schedule of Above Ground Pipe
Schedule of Above Ground Pipe
May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr May June
Pipe/Steel/Supports
1st 2nd 3rd 4th 5th 6th 7th
1 Boiler Aux Cooling Water Pumps Steelwork Instruments Loop Check Flush
Foundations /Pumps install/Grout Pipe & Sup 70% / Inst 70% Hydro (10) System Precom Commissioning
3 Cooling water Return Cooling Tower Erection Steelwork Condensr Instruments Loop Check Flush
Foundations / Cooling Tower basin Hydrotest Pipe & Sup 70% / Inst Hydro (4) System Precom Commissioning
8 Compressed Air System (Package) Comp air eq Comp Shed Inst + Loop Flush
Foundation for Comp Receiver Dryer Pipe & Sup 70% Service System Precom Comm
14 Fire Protection System Pipe and Sup 70% Hydrants / Hose reels Inst + Loop Flush
Underground fire main Hydro System Precom Commission