Professional Documents
Culture Documents
VP1, RFP For Coal Unloading Jetty Work - PSMC - Schedule
VP1, RFP For Coal Unloading Jetty Work - PSMC - Schedule
VP1, RFP For Coal Unloading Jetty Work - PSMC - Schedule
1/2
3.35 Fork Lift 5Ton 0 0 0
3.36 Generator Set 694KVA(555KW) 0 0 0
3.37 Generator Set 635KVA(508KW) 0 0 0
3.38 Generator Set 477KVA(382KW) 0 0 0
3.39 Generator Set 365KVA(292KW) 0 0 0
3.40 Generator Set 341KVA(273KW) 0 0 0
3.41 Generator Set 228KVA(182KW) 0 0 0
3.42 Generator Set 225KVA(180KW) 0 0 0
3.43 Generator Set 198KVA(158KW) 0 0 0
3.44 Generator Set 192KVA(154KW) 0 0 0
3.45 Generator Set 165KVA(132KW) 0 0 0
3.46 Generator Set 135KVA(108KW) 0 0 0
3.47 Generator Set 60KVA(48KW) 0 0 0
3.48 Man Lift(Scissor) 18M/500kg 0 0 0
3.49 Man Lift(Telescopic) 43M/230kg 0 0 0
3.50 Motor Grader 14Ft/4.3m 0 0 0
3.51 Motor Grader 12Ft/3.6m 0 0 0
3.52 Roller-Vibrating 3Ton 0 0 0
3.53 Roller-Vibrating 10Ton 0 0 0
3.54 Trailer with Tractor 70Ton 0 0 0
3.55 Trailer with Tractor 50Ton 0 0 0
3.56 Trailer with Tractor 30Ton 0 0 0
3.57 Truck-Cargo 11.5Ton 0 0 0
3.58 Truck-Cargo 3Ton 0 0 0
3.59 Truck-Dump 32Ton 0 0 0
3.60 Truck-Dump 25Ton 0 0 0
3.61 Truck-Dump 15Ton 0 0 0
3.62 Water Truck 15,000Liter 0 0 0
3.63 Hydraulic Hammer 5Ton 0 0 0
3.64 Hydraulic Hammer 7Ton 0 0 0
3.65 Hydraulic Hammer 10Ton 0 0 0
3.66 Pressing machine 0 0 0
3.67 Driving machine 0 0 0
3.68 Boring Machine 0 0 0
3.69 Auger 0 0 0
3.70 Welding 0 0 0
3.71 Others(if required) 0 0 0
NOTE :
1. This is reference only, above project schedule would be revised as per site conditions within the Subcontract Period.
2. As per experience of subcontractor, the composition of Human Resorece list can be changed.
3. Propose actual equipment capacity on "Applied Capacity" column, referring to "Reference Capacity"
4. As per experience of subcontractor, the composition of Equipment list can be changed.
5. Above monthly salary/unit rate shall be based on 10 hours/Day and 28 Days/Month
6. All of the Reports should be submitted in accordance with above schedule and each technical specification documents without delay.
2/2