Professional Documents
Culture Documents
62f PDF
62f PDF
62f PDF
Abram Kuo
Ryan Pitt
Westlake Group
900 Hwy 108
Sulphur, LA 70664
UNPUBLISHED
1
Overview
• Background
• Flare System Overview
• Event Sequence
• Root Causes / Corrective Actions
• Brittle Fracture Discussion
• Other Follow Up Actions
• Learning / Conclusions
2
Background
4
W estlake P etro 1 F lare D ru m S ystem O verview
O rig in al S ystem
Westlake Petro 1 Flare Drum System
TI
150# Carbon Steel Piping, MDMT= -10 F
Cold Flare
Overview -- Pre Event To Elevated
Superheater
Flare
Cold Vapor
Header
Warm Vapor
Header
Cold Liquid
Header
local LI
Key
70# steam
CS process piping
SS process piping
70# steam Propanol
Propanol
condensate Vaporizer
70# steam/5
condensate
Event Sequence
• The Westlake Petro 1 ethylene product went off spec on
acetylene, initiating flaring of liquid ethylene product
• With the cold flare drum overhead line running below its
minimum design temperature of -10 F, the pipe ruptured,
resulting in loss of hydrocarbon containment
7
Cold Flare Drum Overhead Line Fire
Superheater
8
Root Causes of the Fire
9
Root Cause #1: Vaporizer/Superheater Malfunction
Corrective Actions:
• 2 LI’s installed on cold flare drum w/ DCS hi alarms @ 10%
• Heavy oil pull down system installed to allow removal of heavy
oil from the cold flare drum
• Cold flare drum superheater replaced with 50% larger
exchanger and propanol piping was replaced to handle higher
throughput
10
Root Cause #2: Cold Safety Awareness/Management
• Once flaring began, the cold flare drum overhead line low
temperature was not recognized
Corrective Action:
• Plant wide training conducted to re-emphasize cold safety
awareness, including root causes and corrective actions for cold
flare line event
11
Root Cause #3: Brittle Fracture
• The “final stress” that ultimately caused the brittle fracture of the
piping has not been identified, but could have been any number
of internal or external stresses
• External stress - Hard rain that came at the time of event?
• Internal stress - Contraction of the cold flare line due to
temperature gradient?
Corrective Actions:
• Carbon steel flare system piping replaced with stainless steel,
~100' downstream of warm/cold flare drum tie-point
• Thermocouple installed on new stainless steel piping upstream
of SS to CS transition
• Stress analysis on the new flare line, FEA on flare drum
12
• See “Flare Drum System Modifications” diagram
Overhead Line Brittle Fracture
13
Carbon Steel Brittle Fracture Discussion
Stainless Steel --
Impact Energy
120
Initial fracture believed to
110 have occurred on elbow
Charpy Impact Test Energy Absorbed (ft-
40
30
20
10
0
-120 -100 -80 -60 -40 -20 0 20 40 60 80 100
Temperature (F)
Straight Pipe Elbow
16
Other Follow Up Actions
17
W estlake P etro 1 F lare D ru m S ystem M o d ificatio n s
N ew reran g ed T I, m in TI
ran g e = -200 F N ew 150# S tain less S teel P ip in g
N ew T I
TI T o E le va te d
N ew C o ld F lare
F la re
S u p erh eater
C o ld V a p o r
SS CS
H eader
W a rm V a p o r
H eader
C o ld L iq u id
H eader
2 n ew L I's LI C o ld F la re D ru m W a rm F la re
D ru m
C o ld F la re
V a p o rize r
H e a vy O il
P u lld o w n
S yste m K ey
N ew F acilities in B lack
7 0 # ste a m
7 0 # ste a m O ld F a cilitie s in B lu e
co n d e n sa te P ro p a n o l P ro p a n o l
V a p o rize r
18
7 0 # ste a m /
co n d e n sa te
Safety/Environmental Impact
• The state police, the Local Emergency Planning Commission
(LEPC), and the National Response Center (NRC) were notified
of the event.
• The fire was contained within a few hours, but it was not
completely extinguished for 1 week
• The plant was shut down for 1 month while repairs were made
to the unit
19
Key Learnings
• Event specific
– Heavy liquid introduced to the cold flare drum should be removed in
a timely manner
– Cyclopentadiene (CPD) and other components in deethanizer
bottoms streams can polymerize to foul cold flare heat exchangers
– Cold flare system fouling may not be readily identified due to
infrequency of use
• General
– Unit upsets will tend to find the “weak link” in management
systems, facilities, and personnel
– Cold safety should remain a focus for all ethylene plants
20