Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/241788175

Advanced Drilling Simulation Proves Managed-Pressure Drilling (MPD)


Economical in Gasfield Developments in Western Canada

Article · January 2008


DOI: 10.2118/114797-MS

CITATIONS READS

0 137

5 authors, including:

Geir Hareland
Oklahoma State University - Stillwater
174 PUBLICATIONS   658 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Drilling Optimization View project

All content following this page was uploaded by Geir Hareland on 05 March 2015.

The user has requested enhancement of the downloaded file.


SPE 114797

Advanced Drilling Simulation Proves Managed Pressure Drilling (MPD)


Economical in Gas Field Development in Western Canada
Geir Hareland, Ivan Olea, Farid Shirkavand, Robert Teichrob, Andang Kustamsi, University of Calgary

Copyright 2008, Society of Petroleum Engineers


This paper was prepared for presentation at the CIPC/SPE Gas Technology Symposium 2008 Joint Conference held in Calgary, Alberta, Canada, 16–19 June 2008.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been
reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect any position of the Society of Petroleum Engineers, its
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Society of Petroleum Engineers is prohibited. Permission to
reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.

Abstract
The application of managed pressure drilling (MPD) is technology.
becoming more widely spread throughout the world. It is
well known that MPD has less hydrostatic head during Executive Summary
drilling therefore the rate of penetration (ROP) is The well under study was broken into 5 discreet 200 mm
increased. This is due to the reduced rock confinement and diameter sections: section 1 (443 m to 447 m) was drilled
chip hold down effects. By simulating the conventional with a type 4-1-7 tricone bit (due to its short interval,
drilling and MPD of a well in advance the benefits of section 1 did not account into subsequent simulation runs),
MPD can be quantified in terms of increase in ROP and section 2 (447 m to 1944 m), section 3 (1944 m to 2805
therefore the economical benefits. Applying a m) and section 4 (2805 m to 3149 m) were all drilled with
commercially available drilling simulator (1). meter by PDC bits. Because of the presence of chert nodules in the
meter drilling performance is analyzed, first simulating lowest section, Section 5 (3149 m to 3218 m) was drilled
and optimizing a conventional drilling operation and then with a type 5-4-7 insert tricone bit. The first simulation run
performing the same procedure for a MPD operation in for the entire 2771 m section established a benchmark
Western Canada. The additional costs of the MPD drilling cost of $237.50/m or $658,110. After optimizing
operation are integrated into the economical analysis. The hydraulics then optimizing bit runs progressively
analysis shows that the ROP during MPD in the higher downward, it was found that the optimized non-MPD Case
mud weight regime of the well is improved from 60 to 80 showed a decrease in drilling cost to $183.50/m or
percent. In addition to the faster drilling during MPD the $508,295 (a decrease of 23%- as anticipated). The next
drill bits last longer due to the lesser hardness of the rock step in meeting the aforementioned objectives was to
being less confined and therefore also reducing the amount optimize the MPD Case. First, mud density was changed
of bit wear and the number of bits required and tripping from the existing optimized non-MPD profile to a constant
time. Overall the results indicate that the MPD operation 0.9 S.G. for the entire wellbore. The simulation was re-run
reduce the drilling cost of gas wells in Central Alberta and it was found that drilling costs increased to
more then 20 percent and due to the reduced time at the $199.60/m. It is interesting to note that the decrease in
location less environmental impact is seen. mud density and therefore increased ROP was offset by
the additional +/- $15,000/day estimated cost of MPD
Introduction equipment/services. The new meterage cost of $199.60/m
The first objective of this exercise was to develop a “base formed the datum from which subsequent optimized MPD
case” drilling simulation from which subsequent calculations were compared against. Again, hydraulics and
optimization simulations could be run. An apparent rock bit runs were progressively optimized to establish a new
strength log (ARSL) was developed based on actual cost per meter of $168.90/m (a further decrease of 15%).
drilling data and formed the backbone of all subsequent Finally, sections 3 and 4 were merged and an optimized
calculations. The second objective of the exercise was to suite of simulations (based on 1 bit) were run. It was found
compare the non-optimized base case (as above) with an that drilling cost decreased to $150.40/m or a total of
optimized base case. Based on previous experience, $416,750 (18% less than the optimized non-MPD case). A
drilling economics should improve by approximately 25%. final suite of simulations were run which sections 3, 4 and
The third and primary objective of this exercise was to 5 were merged and drilled with 1 bit. It was found that
compare the optimized base case with an optimized drilling costs decreased a further $9/m ($141.50/m) to a
Managed Pressure drilling (MPD) case and, if possible, to total of $392,095 (22% less than the optimized non-MPD
justify the additional cost of implementing MPD case). It should be noted that the costs to move the MPD
2 SPE 113797

equipment were not accounted into the above costs package was unavailable – it again can be reasonably
(approximately $18,000 for this specific job) and will tend assumed that a 4-phase horizontal separation vessel
to distort overall cost per meter “up”. The optimized MPD complete with a 5000 psi WP UB drilling choke manifold
Case moves from $141.50/m to $147.90/m with the would be provided. All primary flow line would be
moving cost accounted in. It should also be noted that the flanged 5000 psi (WP) x 152 mm (6”) line. Of note is the
MPD equipment could have been brought on line slightly trucking costs associated with moving the MPD/UBD
later in the drilling programme (perhaps after drilling separation package (including pipe and flare stack).
section 2). An analysis of drilling time for section 2 shows Typical horizontal UB separation packages require 4 to 6
an optimized conventional drilling time of 36 hours and an truck loads to move and require approximately 18 to 30
optimized MPD drilling time of 32 hours. If standby cost hours to rig in and pressure test (depending on crew
($8,000/day total) is accounted into total expenditures it experience, lease and weather conditions).
can be shown that it is cheaper to utilize MPD equipment Note: Rig in of the UB separation unit should be carried
from the beginning (by about $2,000). An added benefit out “off line”, minimizing additional day rate costs.
with respect to bringing MPD equipment early is that more Estimated costs:
time is provided for crews to become familiar with the • $5500/day Separation package including RCH
equipment and changed operational procedures (i.e. • $2400/day onsite engineering
connection procedures). A review of final costs to drill • $5100/day – refurbishment / inspection /
“optimized conventional” vs “optimized MPD” shows that • $18,000 flat rate - move
$100,000 can be saved if MPD equipment and drilling
techniques are utilized. The additional cost to rig in and Drilling Mud
use MPD drilling techniques/equipment is justified. It was assumed that the system volume (including surface
or active) was +/- 200 m3. Given this volume, cost of the
Well Profiles mud system for the “conventionally” drilled well with a
90/10 invert mud system was formulated as following:
The different drilling programs for conventional and MPD • $75/m3/well fluid rental
can be found in the comparative Figure 1. In this figure • $400/day system maintenance
the different schemes studied and simulated for the present • $20,000 system “refurbishment” cost at end of well
study are shown. • $2000 centrifuge cost at end of well – strip system back
from 1.4 S.G. to 0.90 S.G.
MPD Equipment Layout The cost of the mud system for the “MPD” drilled well
was formulated as following:
A descriptive diagram of the different parts of a typical • $75/m3/well fluid rental
MPD equipment configuration can be found in Figure 2. • $400/day system maintenance

Drilling Parameters Overview BHA ARSL and Lithology

BHA configuration data was unavailable at the time of The necessary information to construct the Apparent Rock
writing – neutral point calculation and therefore maximum Strength Log (ARSL) of the Alberta 1-12 well was
WOB determination was not possible. provided to the authors. The data was imported to the
Pason Drilling Simulator and the corresponding ARSL
Bit Types was automatically computed by the software. Details
about this procedure fall outside the scope of this
The subject 200 mm section was originally drilled with 5 document. It is considered that the ARSL accurately
bits. The first section (443 to 447 m) was drilled with a reflects rock strength characteristics for the targeted zones
type 4-1-7 insert bit. Sections 2 through 4 (447 to 1944 m, of interest.
1944 to 2805 m, 2805 to 3149 m) were drilled with PDC
bits. Due to the presence of chert nodules, the final section Optimization Methodology (General Discussion and
(3149 to 3218 m) was drilled with a type 5-3-7 insert bit. Model Calibration Process)

Rotating Control Head The well was drilled in 5 discreet sections as follows:
Specific information regarding the rotating control head • Section 1 443 m–447 m 200 mm 4-1-7 Tricone
was unavailable at the time of writing. However, given the • Section 2 447 m–1944 m 200 mm 999 PDC
depth of the well and the source of the cost data • Section 3 1944 m–2805 m, 200 mm 999 PDC
(Weatherford) it can reasonably assumed that a Williams • Section 4 2805 m–3149 m, 200 mm 999 PDC
Series 7100 dual element 5000 psi (static) 2500 psi • Section 5 3149 m–3218 m, 200 mm 5-4-7 Tricone
(working) rotating control head (RCH) would be used.
Notes:
Separation Package • Optimization efforts were not applied to Section 1
because of the short drilled depth interval.
Again, specific information regarding the actual separation
SPE 113797 3

• The model was not calibrated against known ROP. Section 4 - ROP to beat 10.46 m/hr
Given pore pressure and bit wear coefficients were
assumed to be correct and were not changed A 20×20 parametric was used to “bracket” bit wear to 3.0
throughout the optimization process. and rotary speed was rounded to the nearest 5. WOB was
• All optimized PDC runs were constrained to POOH changed iteratively and bit wear converged to 2.5.
by a bit wear value of 2.5, while tricone bit runs were Ultimately, cost per meter drilled was decreased to
constrained to POOH by a bit wear value of 6.0. $203.4/m based on drilling section 4 was faster.
WOB 8.5 ton Wear 2.5
First Run – Base Case Developed From Data Provided RPM 110 ROP 17.52 m/hr

The Base Case was developed to provide the datum from Section 5 - ROP to beat 1.55 m/hr
which the success of further optimization runs would be
gauged. Based on the given ARSL, fixed rheology and A 20×20 parametric was used to “bracket” bit wear to 6.0
mud pump rates, the Base Case model showed a and rotary speed was rounded to the nearest 5. Ultimately,
$237.50/m cost to drill or $658,110 total drilling cost for cost per meter drilled was decreased to $183.5/m based on
the whole interval. drilling section 5 was faster. Total cost to drill the interval
was now reduced to $509,600 – a savings of 22%.
Optimized Base Case – Hydraulics Only WOB 24 ton Wear 6.1
RPM 160 ROP 4.15 m/hr
The Base Case was further optimized by revisiting
hydraulics and adjusting jet size to yield an HSI of +/- 3.0. Merged Sections 4 & 5 – Drilled with PDC
In most cases, jet size was reduced one increment from
“given”. After optimizing each section, it was found that Next, sections 4 and 5 were merged and the combined new
drilling cost was reduced to $233.80/m or a total cost of section was drilled with a PDC bit. Because the bit was
$647,859. The saving of $11k would need to be weighed drilling to casing point, the wear factor was relaxed to 2.7.
against the perceived risk associated with plugging the Resulting cost per meter increased to $207.50/m indicating
smaller jets – unless there is no chance of mixing and that the economics of cutting a bit trip out did not
pumping LCM it would be prudent to stay with the positively affect the overall drilling cost.
“given” jet sizes. WOB 5.5 ton Wear 2.7
RPM 110 ROP 4.55 m/hr
Optimized Base Case – Bit Runs
Merged Sections 4 & 5 – Drilled with Tricone Bit
As previously mentioned – bit run optimization was not
performed on Section 1. Sections 4 and 5 were merged and the combined new
section was drilled with a 5-3-7 tricone bit. The wear
Section 2 – ROP to beat 35.7 m/hr factor was held at 6.0. Resulting cost per meter further
increased to $215.60/m indicating that saving a bit trip and
Given the 2.5 bit wear constraint, a 20×20 parametric was running a tricone bit would be a poor decision.
first used to “bracket” bit wear to 3.0. From this point,
rotary speed was rounded to the nearest 5 then fixed (i.e. Base Case MPD (Increased Dayrate Only)
118-120 RPM, 152-150 RPM) and an iterative process by
way of changing WOB was employed to converge bit As a point of interest, the first run was performed to
wear to 2.5. Ultimately, cost per meter drilled was provide an indication of what it would cost to drill the
decreased to $232.50/m based on drilling this section was section with the increased dayrate associated with
faster. additional MPD equipment but no benefit from increased
WOB 5.5 ton Wear 2.5 ROP as a function of reduced mud weight. Calculations
RPM 160 ROP 40.53 m/hr were performed based on the optimized non-MPD case.
Resulting cost per meter increased to $279.60/m. This data
Section 3 – ROP to beat 15.45 m/hr does not play a part in subsequent analysis.

Again, a 20×20 parametric was used to “bracket” bit wear Base MPD Case – Mud Weight of 0.90 SG
to 3.0 and rotary speed was rounded to the nearest 5. WOB
was changed iteratively and bit wear converged to 2.5. The second modeling run used the optimized non-MPD
Ultimately, cost per meter drilled was decreased to case parameters with a change to mud weight (changed to
$212.80/m based on drilling section 3 was faster. 0.9 SG throughout the entire interval). ROP was improved
WOB 6.5 ton Wear 2.5 dramatically and cost per meter drilled was decreased to
RPM 160 ROP 30.89 m/hr $199.60/m. Total cost to drill the interval was now
$553,090. This model formed the MPD Base Case from
which subsequent optimization efforts stemmed.
4 SPE 113797

Base MPD Case – Only Optimized Hydraulics section was drilled with a PDC bit. Bit wear was
constrained to 2.5. Resulting cost per meter decreased to
The MPD Base Case was further optimized by revisiting $150.40/m indicating that there were excellent economics
hydraulics and adjusting jet size to yield an HSI of +/- 3.0. in combining the sections and drilling with one PDC bit.
In most cases, jet size was reduced one increment from Total cost to drill the interval was now reduced to
“given” size. After optimizing each section, it was found $416,758.
that drilling cost was reduced to $186.40/m or a total cost WOB 6.0 ton Wear 2.5
of $516,514. Although the saving of +/- $37k is RPM 145 ROP 51.15 m/hr
substantial, benefits would still need to be weighed against
the perceived risk associated with plugging the smaller Merged Sections 5, 4, 3
jets. Since there is no data supporting the use of LCM, the
authors chose to use the hydraulics optimized model as a Next, sections 5, 4 and 3 were merged and the new section
data point in the optimized learning curve. was drilled with one PDC bit. Because the bit was drilling
to casing point, the wear factor was relaxed to 2.6.
Optimize Bit Runs by Section Resulting cost per meter decreased to $141.50/m or
$392,096 total cost - the best economics and new cost
Section 2 – ROP to beat 43.14 m/hr target.
Given the 2.5 bit wear constraint, a 20×20 parametric was WOB 5.0 ton Wear 2.6
first used to “bracket” bit wear to 3.0. From this point, RPM 145 ROP 33.81 m/hr
rotary speed was rounded to the nearest 5 then fixed and Though merging sections 5, 4 and 3 gave the best overall
an iterative process by way of changing WOB was economics, it should be noted that the presence of chert in
employed to converge bit wear to +/- 2.5. Ultimately, cost the section 5 creates significant risk with regards to
per meter drilled was decreased to $183.80/m based on drilling the section without incident. If the PDC
drilling this section was faster. encounters chert and is damaged as a result, an additional
WOB 6.5 ton Wear 2.6 trip plus costs related to the damaged bit would be
RPM 130 ROP 47.07 m/hr incurred. For this reason, there are two scenarios that are
considered:
Section 3 – ROP to beat 40.99 m/hr • The “Best MPD Case” which merges sections 3, 4 and
5 at $392,096 total cost, and
Again, a 20×20 parametric was used to “bracket” bit wear • The “Most Likely MPD” run which merges sections 3
to 3.0 and rotary speed was rounded to the nearest 5. WOB and 4 at a cost of $416,758 and leaves section 5 to its
was changed iteratively and bit wear converged to +/- 2.5. own short drilled section.
Ultimately, cost per meter drilled was decreased to The choice forward would be based on the drilling
$175.60/m based on drilling section 3 was faster. engineer/superintendent’s adversity to risk.
WOB 12 ton Wear 2.5
RPM 160 ROP 73.46 m/hr Learning Curve

Section 4 - ROP to beat 47.71 m/hr As discussed above and shown in Figure 11, the “upside”
to optimizing the drilling plan through the 447 to 3218 m
A 20×20 parametric was used to “bracket” bit wear to 3.0 section is considerable. Base costs of $237.50/m are
and rotary speed was rounded to the nearest 5. WOB was reduced to $183.50/m by optimization only and are further
changed iteratively and bit wear converged to 2.5. reduced to $141.50/m by reducing mud weight and drilling
Ultimately, cost per meter drilled was decreased to the section at or very near balanced.
$172.80/m based on drilling section 4 was faster.
WOB 8.5 ton Wear 2.5 Conclusions
RPM 110 ROP 84.65 m/hr The Central Alberta 1-12 well provided an excellent
opportunity to compare a well section that had been drilled
Section 5 - ROP to beat 7.45 m/hr “conventionally” with upside based on reduced mud
weight (increased ROP) and increased equipment cost
A 20×20 parametric was used to “bracket” bit wear to 6.0 associated with Managed Pressure Drilling (MPD)
and rotary speed was rounded to the nearest 5. Ultimately, operations.
cost per meter drilled was decreased to $168.90/m based
on drilling section 5 faster. Total cost to drill the interval 1. Additional cost to mobilize and utilize MPD
was now reduced to $468,021. equipment and related services were offset by the
WOB 24 ton Wear 2.3 increase in penetration rate.
RPM 160 ROP 14.28 m/hr a. Optimized conventional cost to drill was 22%
lower than non-optimized conventional drilling
Merged Sections 4 & 5 – Drilled with PDC costs.
b. Optimized MPD cost to drill was 23% less
Next, sections 4 and 5 were merged and the combined new
SPE 113797 5

than optimized conventional and 40% less than


non optimized conventional drilling costs.
2. The benefits of drilling MPD are marginalized by
“softer” drilling – the uphole section (447 m to 1944
m) showed an overall increase in P-rate of +/- 25%
while lower sections showed relative increase in P-
rate of 55%, 80% and 70% respectively.
NOTE: The above relative increases in P-rate are
comparisons between optimized P-rate non-MPD and
optimized P-rate MPD.
3. Optimizing hydraulics yielded a relative decrease in
overall drilling costs of +/- 5% - the additional “up-
tic” must be weighed against risk associated with
plugging jets due to pumping LCM etc.
4. Mud cost comparisons are higher in weighted invert
systems as compared to non-weighted systems –
however, costs are negligible in the overall picture.
5. Most MPD equipment rig in time is performed “off-
line” and does not add significantly to overall rig
costs.
6. To reduce drilling costs further, MPD, stand-by rates
should be negotiated prior to commencing operations.
7. It is in general recommended to drill the softer
formations (up hole) with optimized conventional
drilling parameters and employ the MPD
equipment/techniques as rock strength increases.

References

1. Pason System Corp, “Optimizer Version 1.20”, 2007.


6 SPE 113797
SPE 113797 7
8 SPE 113797
SPE 113797 9

View publication stats

You might also like