Control of Sewerage and Surface Water Drainage
Control of Sewerage and Surface Water Drainage
1. SCOPE
2. PROCEDURE
.1 All sewerage and surface water drainage works will be carried Project Request for
out in accordance with the contract specification and good Engineer Information
practice.
.2 Depending upon the complexity of the work, and the Project Method
requirements of the PQP, a method statement shall be prepared Engineer Statement
and approved by the Consultant which shall include:
3. DOCUMENTATION
.1 Appendix FOUN/06A and Appendix FOUN/06/B, shall be used QA/QC Check sheets
to monitor drainage construction. Approval to proceed will be
given by the QA/QC.
PROJECT: PROJECT NAME SITE NO.:
CHECK SHEET FOR SEWERAGE AND SURFACE WATER DRAINAGE Sheet No.
SUBCONTRACTOR: CLIENT
Checked
STAGE ITEM by DATE
PIPEWORK OR
CHANNEL 1. Set line and level. SU
2. Check location of underground services before
commencement of excavation. SE
CHECK SHEET FOR SEWERAGE AND SURFACE WATER MANHOLES Sheet No.
Checked
STAGE ITEM by DATE
QA/QC – Quality Assurance/Quality Control, SE – Site Engineer, SU, - Surveyor, GF – General Foreman