ACTIVITIES-MAIN TASKS SUB-TASKS PERSONNELS MATERIALS EQUIPMENTS/TOOLS EXPECTED EXPECTED

START FINISHED
DATE DATE
Construction of Emergency 8/8/2019 8/8/2019
Assembly point -Excavation -2 masons -Cement Wheelbarrow
-Casting of slab -2 helpers -Aggregate Back hoe Excavator
-Installing Pols -Sand Spades
-Fixing iron sheets -Pols Trowel
-Roofing -Roofing nails
-5inch nail
-Water
Construction of Generator shed -Excavation -2 masons -Cement 8/8/2019 8/8/2019
-Casting of slab -2 helpers -Aggregate Wheelbarrow
-Installing Pols -Sand Back hoe Excavator
-Fixing iron sheets -Pols Spades
-Roofing -Roofing nails Trowel
-5inch nail
-Water
Installation of Boulders to protect -Purchase and Transportation 2 Operators -10trips of Tipper truck 8/8/2019 9/8/2019
the diversion drift. -Installation boulders Excavator

Improvement of Kitchen floor and -Laying of Marram 1mason -1Trip of Marram Plate Compactor 8/9/2019 8/8/2019
seat Installation -Applying Moisture 2helpers -Water
-Levelling and compaction -6pcs of 8’’x1’’
-Installation of seats -8pcs of poles
Installation of Containers for -Installation of base footings 1 Operator -Belt for the High High up crane 10/8/2019 11/8/2019
workshop and store -Carrying and lifting from Nalakasi 1 Mason up crane
camp to Secondary camp
-Transporting to site
Installation of prefabricated office -Gathering and assembling from 2Carpenters -Rivet gun -Tipper truck 9/8/2019 12/8/2019
elements and fittings from the 3Helpers -Tape Measure
primary camp. -Strings
-Fixing and Installation.
Construction of Ablution for -Excavation of Foundation 2Masons -Cement Wheelbarrow 8/8/2019 12/8/2019
Senior staffs -Blinding and backfill 2helpers -Aggregate Back hoe Excavator
-Plinth wall -Sand Spades
-Floor slab -Bricks Trowel
-Superstructure wall -Roofing nails
-Roofings -5inch nail
-Plastering -Water
-Plumbing works -Iron sheet
-Timber(4x2)

Construction of Huts For Senior -Substructure wall construction 2masons -Cement Wheelbarrow 8/8/2019 17/8/2019
Staffs. -Superstructure wall construction 2helpers -Sand Back hoe Excavator
-Roofing -Bricks Spades
-Plumbing works -Grass Trowel
-Plastering -Poles
-Purlins
-Rebar
-Links
Dismantling Bailey Bridge -Measurements and taking -Rigor Team -will be requested Moverble crane 15th/8/2019 25th/8/2019
dimension by the Rigor head
-Greasing and removing primary
member
-Unbolting and lifting using a
moval crane
-Storage for use in the next repair
Steel Cutting, Bending and -Request and deliverance of Rebar Steel Gloves Welding machine 15th/8/2019 15th/10/019
formwork preparation T16,Links for the abutment Fixtures Eye protection Grinding machine
footings team wears Torque Wretch
Safty boots
Bending table
Hollow pipe
Excavation of Foundation -Taking levels 3operators Total station 25th/8/2019 5th/9/2019
Abutment -Excavation 1 Surveyor Staff
-Compaction 1Helper Tipper Truck
Laboratory test
Equipment
Ground Improvement -Request and Delivery of materials 2 operator CRR Tipper truck 6th/9/2019 14th/9/2019
at site. Masons Geogrid Jumper
-Storage and usage for backfill on Blinding Excavator
the subgrade of the foundation Hardcore Back hoe
abutment.