4 NEWSLETTER ISSUE-5, APRIL, 2016

Energy Management System:


A Holistic Approach for Energy Performance

Indian Rayon (A Unit of Aditya Birla Nuvo Ltd.) Veraval, Gujarat


– Mr. Dashrath Chouksey, Assistant Manager (IMS), Indian Rayon

About the Plant Indian Rayon is unique in many ways: 1996 onwards, Aditya Birla World Class
 It is the only company to use all 3 kinds manufacturing practices (WCM) were
Indian Rayon (IR), SBU of the Aditya Birla of technology – customers can choose initiated. Indian Rayon is accredited
Nuvo Limited, is a leading manufacturer the VFY required at one location with ISO 9001:2008, ISO 14001:2004,
of viscose filament yarn (VFY) with a  It is the first VFY business in India OHSAS 18001:2007 and SA 8000:2008
rich heritage of over 60 years. This yarn accredited with ISO 9001, ISO 14001 certifications. From 2012, Indian Rayon
is an input to the textile industry for (Environment), ISO 50001 (Energy has been working with DuPont for
manufacturing fabrics used in apparel Management), OHSAS 18001 implementing Behavior Based Safety
and home furnishings. With a turnover (Health and Safety), SA 8000, REACH
and Process Safety Management. The
of around Rs. 699 crores/annum (FY15), Compliance and OekoTex certification.
ABG WCM framework was upgraded to
Indian Rayon is a leading VFY exporter  It is the largest VFY exporter from India
with exports to 45 countries, in addition a Business Excellence framework and
and recipient of the SRTEPC export
to the lion’s share of India’s market. IR implemented from 2014. The business
awards.
played a major role in catapulting India is also working towards improving its
 It is the first company taking a VFY
to the second position worldwide, as a brand to the end consumer that will energy performance and was certified as
manufacturer of VFY, with China at first also benefit the industry as a whole, in ISO 50001:2011 compliant in year 2015.
position. India. We have a strong culture of World
The SBU owns completely integrated Journey towards Excellence Class Manufacturing practices
operations of capacity 19800 tons/ involving kaizen, various campaigns,
annum, producing Pot Spun Yarn (PSY), Indian Rayon is a system oriented plant: competitions and award schemes. In
Continuous Spun Yarn, (CSY), and the the journey towards implementing line with our Group’s vision of CSR,
unique, patented Spool Spun Yarn, Management Systems was started way Indian Rayon has established the Jan
(SSY) (acquired technology in 2013 for back in 1994 by ISO 9002, and from Seva Trust (JST) in the unit, for the cause
manufacturing and marketing in India of Education, Health care, Sustainable
Figure 1: Indian Rayon’s journey towards
from the globally reputed ENKA, Germany). implementation of Management Systems Livelihood, Infrastructure Development
It is backwardly integrated with a 34.5 MW 2020
and Women.
2015

captive power plant and a 250 TPD caustic 2010

chlorine plant (part of the Chlor-Alkali


2005

2000
ISO 50001: 2011- Implementation
SBU). The integrated complex is located in
1995

1990
at Indian Rayon
Veraval, Gujarat. Manufacturing and other 1985

1980 In July 2014, the management decided


functions are located at Veraval, and sales ISO 9002 WCM ISO 14001 OHSAS SA 8000 Behaviour Process ISO 50001
Practices 18001 Base Safety Safety and
Business to implement the ISO 50001:2011 Energy
and marketing, in Mumbai. Excellence

Management System to improve its


energy performance. A certifying body,
Table 1: Main Products and Manufacturing Capacities
DNV, was identified, who could work
Product Capacity Integrated Operation
with the company to implement the
VFY 54.5 TPD
system. Since the company had a strong
Sodium Sulphate 32 TPD
team with two decades of experience in
Sulfuric Acid (H2SO4) 100 TPD
Management Systems, no consultant was
Carbon di Sulfide (CS2) 27 TPD engaged for documentation; however,
Power 34.5 MW training and certification were within
Caustic 250 TPD the scope of DNV. With the guidance of
Newsletter Issue-5, April, 2016 5

the Unit Head, a core team was formed conducted for team members on 11th
under the leadership of FH (QA&TS) who October 2014. Thereafter, a two- day
was also appointed as Management internal auditor’s training program was
Representative for ISO 50001:2011. The also organized for a team of 20 people
core team consisted of: during 13th-14th November 2014. The
 Function Head (Caustic and Power first stage document audit was carried
plant) out by DNV during 13th to 14th March
2015. Corrective actions on the first Awareness Program – 11th Oct’14
 Department Head (Finance and
stage audit findings were completed
Accounts)
with 15 days. An internal audit was
 Department Head (Power Plant) – also carried out from during 6th - 9th April
Energy Manager 2015 and thereafter, a management
 Department Head (Caustic Plant) review was carried out on 11th April
 Department Head (Technical) 2015. Review of documentation and
preparedness for final audit was
 Section Head (Daily Report)
carried out by DNV from 13th to 14th
 Section Head (VFY Electrical) Internal Auditor Tr. Program 13-14 Oct’14
April 2015 and recommended for final
Apart from the core team, an execution audit which was conducted from 28th
team was also formed with members to 30th April 2015. After the audit was
from different sections of the plant. successfully carried out, certification
The responsibility of the core team was was recommended for Indian Rayon.
to review the progress, whereas the Dedication and the involvement of the
execution team was responsible for data team made implementation in a short
collection and documentation. period possible without a consultant.
Internal awareness program Feb-Mar’15
Implementation plan: Action Initiated During Implementation
Process:
A detailed implantation plan was
 Energy manual established as per ISO
established by the Management from
50001:2011 requirement
August 2014 to April 2015 to execute all
 Energy policy documented and
the activities.
communicated to team
The implementation started from  Procedures such as energy review,
August 2014 by finalizing the certifying energy base line, monitoring and
body and the first training program was measurement method defined Management Review – 11th Apr’15

Table 2: Action Plan for implementing the ISO 50001 Energy Management System
Activity Schedule for implementation of ISO 50001(2011) - Energy Management System
Month
S.No
Activity Responsibility Plan Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 Remarks
.
F1 F2 F1 F2 F1 F2 F1 F2 F1 F2 F1 F2 F1 F2 F1 F2 F1 F2
Plan
1 To get the quotation from various party D. P. Chouksey
Actual
Commercial and technical discussion and Samir Kapoor / D. Plan
2 negotiations with the party P. Chouksey Actual
To make the proposal and get the approval from Plan
3 Unit head
D. P. Chouksey
Actual
Form a core members team with leader to initiate Plan
4 for the project
Mgmt.
Actual
Plan
5 Organize the Implementer course on (EnMS)” D. P. Chouksey
Actual
Vision / Energy policy of the organization and Plan
6 review of existing energy condition
Core Team
Actual

Stage 1 Audit 13th - 14th Apr’15


Plan to visit any ABG unit where EnMS is already Plan Ajay M and DPC visited Nagda on 24~25
7 implemented to understand their process
A. B Sojitra
Nov.14
Actual
Preparation of EnMS Manual, Procedures, Work Plan Required documents have been made and
7 Instructions, formats etc
Execution Team
ciruclated among the team on 14.12.14
Actual
Identification, interpretation of all energy oriented Plan
8 legal requirements, preparation of legal register
Execution Team
Actual Legal register is already there
Review of existing energy condition to identify Plan
9 significant energy uses, find out OFI and Action
Core Team
Actual
Plan 1st stage review audit carried out on 09~10
First Stage review audit (Review of the documents)
10 By Certifying body Mar'15. This process was delayed about 1.5
Actual month due to auditors date
Based on the review and assessment of the Plan
11 existing energy performances, corrective actions to Core Team
Actual
Plan Internal Auditor progoram conducted from
12 Internal Auditor Training program (2 days) MR
13~14 Nov'14
Actual
Plan Internal Audit carried out from 06~09
13 Internal Audit planning and execution D. P. Chouksey
Apr'2015
Actual
Plan
14 Management review MR Management review carried out on 11-Apr'15
Actual
Data analysis after implementation of the Plan Done, further action plan is to be prepared and the
15 documented system Core Team
projection for next year by concern department
Actual
Review of all documentation and checking Plan
16 preparedness for Certification audit By Certifying body Audit carried out from 13~14 Apr 15
Actual
Audit of the implemented system as per the Plan Audit carried out from 28~30'Apr'15 and
17 standards By Certifying body
Recommended for the certificate
Actual
Plan Certficate received on 20.06.2015.
18 Issue of certificates By Certifying body
Congratulation note sent to all
Actual

Prepared By : D. P. Chouksey Approved By : A. B. Sojitra Final Audit – 28th Apr’15


6 NEWSLETTER ISSUE-5, APRIL, 2016

 Format for energy monitoring, change Figure 5: Annual Caustic Production (MT)
in facility, opportunity register, etc., Mr. H. S. Dagur
88334 86771 Unit Head,
established 90000 79687
Indian Rayon, Veraval
 Energy profile, current energy
consumptions trend and comparison 70000

with past data documented


50000
 Energy review carried out for all the
2012-13 2013-14 2014-15
processes
 Significant energy consuming process “Energy performance is the key factor in
identified and action plan initiated Figure 6: Caustic Power Consumption
sustainable development, ISO 50001 will
(Kwh/T of Production)
 Baselines established for all processes definitely add value towards our journey
 Training and awareness down the line to excellence.”
1990 1982
on regular basis established. 1979
1980
Annual Energy Consumption 1970
1968
Mr. D. R. Kamat
Trend Joint President
1960
Figure 2: Annual VFY Production (MT) 2012-13 2013-14 2014-15 Caustic & Power Plant
Indian Rayon, Veraval
20000 19181
19000 17965 Challenges Faced during
18000 implementation
16657
17000
In the absence of a consultant, “Development and increased human
16000
documentation and establishing of activities have significant impact on
15000
2012-13 2013-14 2014-15 various processes was challenging, but global environment, economy and
the strong internal team with experience society. Hence energy management
Figure 3: VFY-Power Consumption indocumentation helped. An Energy system ISO 50001:2011 is an effective tool
(Kwh/T of Yarn) Management System cannot be effectively to address climate change issue.”
5485 implemented without the involvement
5500
4892
of bottom line people and the plant is
5000 manpower intensive; three plants at one Mr. A. B. Sojitra
4500 4061 place made the process little difficult. AVP (QA & TS) – VFY
4000 Awareness programs and campaigns Indian Rayon, Veraval
3500 helpededucate people and encouraged
3000 them to participate actively.
2012-13 2013-14 2014-15

Benefits of ISO 50001: 2011


Figure 4: VFY- Steam Consumption  Improved understanding within the
(Million Kcal/T of Yarn) team
“Energy is the most important part of our
 Focus on micro level projects which
8.45 daily life and availability of the resources
8.50 8.09 could enhance productivity
is depreciating day by day. ISO 50001 is
8.00  Improvements in monitoring and
7.50
7.13 one of the steps towards journey to excel
measurement
7.00 in energy performance.”
6.50  Involvement of the team
6.00
 Reduced power consumption
2012-13 2013-14 2014-15
 Achievement of PAT targets. 