Professional Documents
Culture Documents
DW Feasibility Option Selection Rev B Jan 2 2014
DW Feasibility Option Selection Rev B Jan 2 2014
DW Feasibility Option Selection Rev B Jan 2 2014
XXX Development
Table of Contents
1 INTRODUCTION............................................................................................................. 3
1.1 FACILITY WORK PLAN SUMMARY ................................................................... 4
2 WORKPLAN................................................................................................................... 5
2.1 STUDY ACTIVITIES ............................................................................................ 5
2.2 FEASIBILITY STUDIES....................................................................................... 7
3 OPTION SCREENING (QUALITATIVE SELECTION – PHASE 1) ................................. 8
3.1 SCREENING SUMMATION............................................................................... 10
3.2 OPTION SELECTION PHASE 2 (QUANTITATIVE)........................................... 11
3.3 PHASE 2 OPTION SELECTION........................................................................ 11
3.4 HULL SELECTION ............................................................................................ 13
3.5 RISK ASSESSMENT......................................................................................... 14
3.6 PHASE 2 OPTION SELECTION RESULTS SUMMARY ................................... 15
4 VE STUDY .................................................................................................................... 16
5 FEASIBILITY & OPTION SELECTION GATE CRITERIA ............................................ 16
6 CONTRACTING AND PROCUREMENT STRATEGIES............................................... 17
7 FEED INPUT & ITT DATA ............................................................................................ 18
8 STUDY TEAM ORGANISATION .................................................................................. 19
8.1 STUDY TOOLS AND PROCEDURES ............................................................... 19
9 DEVELOPMENT SCHEDULE ...................................................................................... 25
9.1 SCHEDULING ................................................................................................... 25
1 INTRODUCTION
This document presents a Study Plan to undertake the field development facility studies (Surface
Facilities and Subsea) for YYY Development. The principles of the facility FE work will follow the
following route map:
However, the field development requires the integration of subsurface, drilling, operations,
commercial and facilities in an overall development plan – e.g. as typical below:
This document presents an example front – end plan to mature a prospect through Option
Selection, through to the FEASIBILITY gate and readiness to commence FEED and Tendering.
The document describes the following main steps:
AKER KVAERNER
Graphic representation FRONT
of study END
stages:
Field Planning
Cost estimates
Feasibility studies
Concept Selection
±40% Concept Definition
±30% Execution
Most likely
±20% to succeed Most cost
technology efficient concepts
±10% Improved
subsystems Improved
execution
Total field
Major building block level System / discipline level
development level
2 WORKPLAN
A Preliminary Functional Basis for commencement of studies would include the following
items. This functional basis will be developed thru several working sessions and data
compilation.
Establish all the building blocks and brainstorm all credible options for base
development, futures and potential 3rd parties. Requires involvement of all leading
disciplines and management:
Typical extract from Option Generator sheet including score tabulation of a rated option
Reservoir
STAND ALONE
System
Reservoir
CASE Name
Drive
HC Comment
Reservoir Operability SUM
Tool Box Relative Project Recovery Technical Installation &
Cost Schedule and Yield Risk & HUC Reliability
STA-YOL-ONS-MODU- C
A
B
IG
R
P
T
D
W
M
F
JE
O
S This scheme will require a Duplex Pipeline to shore
400 Depletion M
tA
S
o
lC
L
E
riP
e
O
xu
a
fn
p with high 11 percent CO2 and no - dewatering or
phase split offshore. Scheme will also require
FWS Onshore Im
O
o
n
R
re
a
b
P
M
A
tyxS
lD
ifscp complex and not yet proven subsea compression or
3 3 4 4 4 n
a
irp
d
g
xcu
Itw
R
O
S
e
lU
o
ksh 5 23
onshore well boost compression. Both will result in
higher well back pressure and upto 10 percent loss
fkM
u
itlS
a
d
rT
o
h
e of reserves with higher abandonment pressure.
Scheme also has a large, sophisticated gas and
f
A
O
cig
e
b
a
L
U
rtW
o
d NGL plant to be built onshore. Incurs a high capex,
o
a
fS
n
tK
ilT
d
p
re high risk and reduced recovery and operability.
fE
w
g
d
a
cL
ro
ln
R
te
t
O
rS
sd
w
ile
D
L
o
DW FEASIBILITY & OPTION SELECTION Rev B Jan 2 2014
S
fP
tN
lC
T
W
ca
n
rIh
sF
e
D
o
L
T
L
fP
G
rkN
tin
e
a
lo
w
A
cS
fP
sG
jtm
lro
d
ia
c
w
kR
h
p
o
lO
a
ie
tvd
rlo
tcu
a
G
v&
in
e
h
s
P
tlo
m
ra
e
g
in
XXX Development
Facility Feasibility Studies
Doc #: YYY-DRL-PM-PEP-0001-B
03 Jan 2014
Must confirm that the concept schemes selected are robust to uncertainties of
functional basis
Conduct Peer and Partner Reviews to confirm “buy-in”
Prepare Option Screening Report – highlight which options are more favorable,
and indicative relative cost & schedule.
Important to clearly define why certain options were rejected or not appraised, to
avoid future recycling.
Option
Option Label
Label
Selected
Selected Risk
Risk Criteria
Criteria Building
Building Blocks
Blocks Building
Building Block
Block Weighing
Weighing Factor
Factor
Risk
Risk Criteria
Criteria Weighing
Weighing Factor
Factor Risk
Risk Criteria
Criteria Score
Score
Option
Option Resulting
Resulting Score
Score
Example tabulation of the Risk Scoring and Capex estimation for the Quantitative Selection
Phase:
This final option analysis is aimed at recommending a single option to proceed into to FEED
and Execution.
3.6.2 ECONOMICS
Preliminary Execution Plan with Contracting Strategy
4 VE STUDY
Examine opportunities for cost reduction and re-confirm project efficiency through
benchmarking.
This stage gate establishes that the development is technically feasible and economically
robust, and is adequately defined to proceed into definition (FEED) phase. Typical
acceptance criteria can be summarized as follows:
Contracting strategy interacts with contractor selection, schedule duration and integration
location, and installation responsibility.
DRILLING
DRILLING
DRILLING
DRILLING
DRILLING
TOPSIDE
TOPSIDE
TOPSIDE
TOPSIDE
TOPSIDE
TOPSIDE
HULL
HULL
HULL
HULL
HULL
HULL
BUSINESS NAME
Front End Engineering Design (FEED) EPC EPC EPC EPC EPC EPC
Detail Design EPC EPC EPC EPC EPC EPC EPC EPC EPC EPC EPC EPC
Fabrication EPC EPC EPC EPC EPC EPC EPC EPC EPC
Integration EPC EPC EPC EPC EPC EPC EPC EPC EPC
Installation and Hook Up EPC EPC EPC EPC EPC EPC EPC EPC EPC
EPC CONTRACTOR
INSTALLATION CONTRACTOR
ENGINEERING CONTR
CONSULTANT IN HOUSE
OWNER
SEPARATE SUBCONTRACTS
The input to FEED or FEED EPC Tender should include typical deliverables for a floater as
follows:
8.1.3 REPORTING
A weekly report of the Study Team progress will be prepared for issue by the Project
Manager to XXX Management. The format of the Study Team weekly report may follow
XXX’s internal standard or use a DRL report format.
DRL will provide a weekly tracking report (sample below).
9 DEVELOPMENT SCHEDULE
9.1 SCHEDULING
It is important to develop an integrated plan for field development, so as to ensure all the
functions come together in a coordinated manner, and the surface and subsurface groups
develop theier respective areas inconjunction and at the required level of maturity- ie in
synch. An example deepwater FE plan is summarized below: