Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

NR 600, Ch 5, Sec 4

SECTION 4 ANCHORING EQUIPMENT AND SHIPBOARD


FITTINGS FOR ANCHORING, MOORING AND
TOWING EQUIPMENT

Symbols

ReH : Minimum yield stress, in kN/m2, defined in Ch 1, • wind speed: 50 knots (25 m/s)
Sec 2, [2] • current speed: 5 knots (2,5 m/s)
R’lim : Minimum yield stress, in kN/m2, defined in Ch 1, • the water depth for anchoring is approximately between
Sec 2, [2]. one tenth and one sixth of the chain cable length calcu-
lated according to [3.2.2], and
1 Design assumption for anchoring • the ship uses one anchor only under normal circum-
equipment stances.

1.1 General 1.3 Specific cases

1.3.1 Ships with navigation notation sheltered area


1.1.1 The requirements of the present Section only apply to
temporary anchoring of ships within a harbour or sheltered The determination of the anchoring equipment, as stipu-
area, where the ship is awaiting for berth, tide, etc. lated in [2], for ships having the navigation notation shel-
tered area is to be based on the following assumptions:
1.1.2 The equipment complying with these requirements is • wind speed: 30 knots (15,5 m/s), and
not designed to hold a ship off fully exposed coast in rough
• current speed: 5 knots (2,5 m/s).
weather nor for stopping the ship which is moving or drift-
ing. In these conditions, the loads on anchoring equipment 1.3.2 Ships with service notation seagoing launch
increase to such a degree that its components can be dam-
The determination of the anchoring equipment, as stipu-
aged or lost.
lated in [2], for ships having the service notation seagoing
1.1.3 For ships where frequent anchoring in open sea is launch is to be based on the following assumptions:
expected, Owner’s, shipyard’s and Designer’s attention is • wind speed: 27 knots (14 m/s), and
drawn to the fact that anchoring equipment should be pro- • current speed: 5 knots (2,5 m/s).
vided in excess to the requirements of this Rules.
Specific arrangements are defined in Ch 6, Sec 1, [17].
1.1.4 The equipment complying with the requirements in
[3] is intended for holding a ship in good holding sea bot- 1.3.3 Ships with service notation launch
tom, where the conditions are such as to avoid dragging of The determination of the anchoring equipment, as stipu-
the anchor. In poor holding sea bottom, the holding power lated in [2] for ships having the service notation launch is to
of the anchors is significantly reduced. be based on the following assumptions:
• wind speed: 16 knots (8,5 m/s), and
1.1.5 Anchors and chains cable components and its accesso-
ries, wire rope, etc. are to be manufactured in accordance • current speed: 5 knots (2,5 m/s).
with relevant requirements of NR216 Materials and Welding.
Specific arrangements are defined in Ch 6, Sec 1, [17].
1.1.6 The bow anchors, connected to their own chain
1.3.4 Ships with service notation ro-ro passenger
cables, are to be so stowed as to always be ready for use.
ship or passenger ship
Other arrangements of equivalent provision in security and
safety may be foreseen, subjected to Society’s agreement. For ships having L ≤ 30 m, the service notation ro-ro pas-
senger ship or passenger ship and a navigation notation
other than unrestricted navigation, the determination of the
1.2 General case anchoring equipment, as stipulated in [2], is to be based on
the following assumptions:
1.2.1 The determination of the anchoring equipment, as
stipulated in [2], for ships having the navigation notation • wind speed: 20 knots (10,5 m/s), and
unrestricted navigation or coastal area is based on the fol- • current speed: 5 knots (2,5 m/s).
lowing assumptions:

142 Bureau Veritas December 2017


NR 600, Ch 5, Sec 4

1.3.5 Ships with service notation tug, salvage tug or b) Minimum value of the dynamic force
escort tug As a rule, the dynamic force FEN is to be taken greater
For ships having the service notation tug, salvage tug or than:
escort tug, the determination of the anchoring equipment, • 1,0 KN for ships having the service notation seago-
as stipulated in [2], is to be based on the following assump- ing launch or launch
tions:
• 7,0 KN for ships having the service notation tug, sal-
• wind speed: 30 knots (15,5 m/s), and vage tug or escort tug

• current speed: 5 knots (2,5 m/s). • 2,2 KN for ships having another service notation.

2.2.2 Static force on wetted part of hull FSLPH


1.3.6 Fishing vessels having the navigation
notation coastal area The theoretical static force induced by current applied on
the wetted part of the hull, in kN, is defined according to
For fishing vessels having the navigation notation coastal the following formula:
area, the determination of the anchoring equipment, based
1 –3
F SLPH = --- ρC f S m V C 10
2
on the dynamic force FEN calculated as defined in [2], may
2
be reduced by 10%.
where:
1.3.7 Ship for dredging activity ρ : Water density, equal to 1025 kg/m3
For ships having the service notation dredger, hopper Cf : Coefficient equal to:
dredger, hopper unit, split hopper dredger or split hopper 0, 075
unit, the equipment in chain and anchor is to be as defined C f = ( 1 + k ) ------------------------------2
( log R e – 2 )
in NR467 Steel Ships, Pt D, Ch 13, Sec 2.
where:
Re : Reynolds number:
2 Anchoring equipment calculation
Re = (VC LWL) / 1,054⋅10-6
k : Coefficient equal to:
2.1 General
Cb
k = 0, 017 + 20 ------------------------------------------
2 – 0,5 – 1,5
2.1.1 All ships are to be provided with equipment in L WL ⋅ T B WL
anchors and chain cables (or cable and ropes) within the Sm : Total wetted surface of the part of the hull under
scope of classification. This equipment is determined from full load draught, in m2
the dynamitic forces due to wind and current acting on the
The value of Sm is to be given by the Designer.
ship in conditions as defined in Article [1].
When this value is not available, Sm may be
taken equal to 6 Δ2/3
2.1.2 For unmanned non-propelled units, the equipment is
not required for classification purposes. The scantlings of VC : Speed of the current, in m/s, as defined in [1].
anchors, chain cables and ropes to be fitted on board is the
2.2.3 Static force on hull FSH
responsibility of the Designer.
The theoretical static force induced by wind applied on the
upper part of the hull, in kN, is defined according to the fol-
2.2 Anchoring force calculation for monohull lowing formula:
1 –3
F SH = --- ρ ( C hfr S hfr + 0, 2S har + 0, 02S hlat )V W 10
2
2.2.1 Dynamic force FEN
2
a) Dynamic force where:
The dynamic force FEN , in kN, induced by wind and ρ : Air density, equal to 1,22 kg/m3
current acting on monohull in anchoring condition as VW : Speed of the wind, in m/s, as defined in [1]
defined in [1.2.1] may be calculated as follows: Shfr : Front surface of hull and bulwark if any, in m2,
FEN = 2 (FSLPH + FSH + FSS) projected on a vertical plane perpendicular to
the longitudinal axis of the ship
where:
Shar : Aft hull transom surface and bulwark if any, in
FSLPH : Static force on wetted part of the hull due to m2, projected on a vertical plane perpendicular
current, as defined in [2.2.2] to the longitudinal axis of the ship
FSH : Static force on hull due to wind, as defined Shlat : Partial lateral surface of one single side of the
in [2.2.3] hull and bulwark if any, in m2, projected on a
vertical plane parallel to the longitudinal axis of
FSS : Static force on superstructures due to wind, the ship and delimited according to Fig 1
as defined in [2.2.4]. Chfr = 0,8 sin α, with α defined in Fig 1.
Note 1: In Fig 1, B is the breadth of the hull, in m.

December 2017 Bureau Veritas 143


NR 600, Ch 5, Sec 4

Figure 1 : Geometry of the upper part of the hull

si

=
4hi

Ci

Sslati hi >i

2B
Shlat

2.2.4 Static forces FSS on superstructures and as the sum of the forces applied to each superstructure
deckhouses tier according to the following formula:
a) General case: 1 –3
F SS = --- ρΣ ( C hfri S hfri + C sari S sari + 0, 08S slati )V W 10
2

The theoretical static force induced by wind applied on 2


the superstructures and deckhouses, in kN, is defined as where:
the sum of the forces applied to each superstructure and
deckhouse tier according to the following formula: Shfri : Front surface of tier i of the superstructure,
in m2
1 –3
F SS = --- ρΣ ( C sfri S sfri + C sari S sari + 0, 08S slati )V W 10
2
2 Chfri : Chfri = 0,8 sinα, with α measured as defined
in Fig 1 at mid height of the superstructure
where: tier
ρ : Air density, equal to 1,22 kg/m3 ρ, VW, Ssari, Sslati, Casri: As defined in [2.2.4] a).
VW : Speed of the wind, in m/s, as defined in [1] The static force is to be added to the static force calcu-
Ssfri : Front surface of tier i (superstructure or lated for the other superstructures and deckhouses
according to [2.2.4] a).
deckhouse, including bulwark if any), in m2,
projected on a vertical plane perpendicular
to the longitudinal axis of the ship 2.3 Anchoring force calculation for multihull
Ssari : Aft surface of tier i (superstructure or deck-
2.3.1 The dynamic force, in kN, induced by wind and cur-
house, including bulwark if any), in m2, pro-
rent acting on multihull in anchoring condition as defined
jected on a vertical plane perpendicular to
in [1.2.1] may be calculated as defined in [2.2] with the fol-
the longitudinal axis of the ship
lowing particular assumptions for the calculation of the
Sslati : Partial lateral surface of one single side of static forces on the:
tier i (superstructure or deckhouse, including
• wetted part of the hull
bulwark if any), in m2, projected on a verti-
cal plane parallel to the longitudinal axis of FSLPH : As defined in [2.2.2], taking into account
the ship and delimited according to Fig 1 the two floats for the calculation of the total
wetted surface Sm
Csfri = 0,8 sin βi, with βi defined in Fig 1
• hull
Csari : Coefficient equal to:
FSH : As defined in [2.2.3], taking into account:
• if hi/si ≥ 5,00: Csari = 0,7 sin γi
- the two floats for the calculation of Shfr
• if 5,00 > hi/si ≥ 0,25: Csari = 0,45 sin γi
- the two floats transom and the aft surface
• if hi/si < 0,25: Csari = 0,2 sin γi of the aft transversal main beam between
the floats for the calculation of Shar
where hi, si and γi are defined in Fig 1 for
each tier i of superstructure or deckhouse. - one single side of one float for the calcu-
lation of Shlat (“B” on Fig 1 is to be taken
b) Superstructures in the forward part of the ship:
as the breadth of one float).
Where superstructures are located in the front of the
• superstructure
hull with front and side walls of superstructures in the
continuity of the side shell, the static force induced by FSS : As defined in [2.2.4], taking also into
wind applied on these superstructures, in KN, is defined account the frontal surface of the platform.

144 Bureau Veritas December 2017


NR 600, Ch 5, Sec 4

3 Equipment in chain and anchor to be constructed in compliance with the Society require-
ments.
3.1 Anchors A high or very high holding power anchor is suitable for use
on board without any prior adjustment or special placement
3.1.1 Mass of individual anchor on the sea bottom.
The individual mass of anchor, in kg, is to be at least equal For approval and/or acceptance as a high or very high hold-
to: ing power anchor, the anchor is to have a holding power
• for ordinary anchor: P = (FEN / 7) ⋅ 102 equal, respectively, to at least twice or four times that of a
• for high holding power anchor: P = (FEN / 10) ⋅ 102 Type Approved ordinary stockless anchor of the same mass.
• for very high holding power: P = (FEN / 15) ⋅ 102 Holding power is to be assessed by full-scale comparative
tests.
3.1.2 Number of anchors
For very high holding power anchors, the holding power
As a rule, the number of anchors to be provided on board is test load is to be less than or equal to the proof load of the
to be at least: anchor, specified in NR216 Materials and Welding, Ch 4,
a) General case Sec 1, [1.5.2].
• one anchor, when the dynamic force FEN calculated Comparative tests on Type Approved Ordinary stockless
according to [2.2] is less than 4,5 kN anchors are to be carried out at sea and are to provide satis-
• two anchors, when the dynamic force FEN calculated factory results on various types of seabeds.
according to [2.2] is between 4,5 kN and 45 kN Alternatively sea trials by comparison with a previously
Note 1: For ships with FEN between 4,5 and 9,0 kN, the second approved HHP anchor may be accepted as a basis for
anchor may also be dispensed (except for passenger ship approval.
or ro-ro passenger ship having a navigation notation unre-
stricted navigation). In this case, the weight of the anchor Such tests are to be carried out on anchors whose masses
and the length and size of the chain cable are to be calcu- are, as far as possible, representative of the full range of
lated according to [3.1.1], [3.2.1] and [3.2.2], considering sizes proposed for the approval.
FEN increased by one third. At least two anchors of different sizes are to be tested. The
• three anchors, when the dynamic force FEN calcu- mass of the greatest anchor to be approved is not to be in
lated according to [2.2] is greater than 45 kN. excess of 10 times that of the maximum size tested and the
Note 2: In this case, two anchors are to be connected to their own mass of the smallest is to be not less than 0,1 times that of
chain cables and positioned on board always ready to use. the minimum size tested.
The third anchor is intended as a spare one and is not
Tests are normally to be carried out by means of a tug, but,
required for the purpose of classification.
alternatively, shore-based tests may be accepted.
b) Ships having L ≤ 30 m, the service notation ro-ro pas- The length of the chain cable connected to the tested
senger ship or passenger ship and a navigation notation anchor, having a diameter appropriate to its mass, is to be
other than unrestricted navigation such that the pull acting on the shank remains practically
horizontal. For this purpose a scope of chain cable equal to
• one anchor
10 is deemed normal; however lower values may be
c) Ships with service notation seagoing launch or launch accepted.
Ships with FEN less than 4,7 kN are not required to carry
Three tests are to be carried out for each anchor and type of
a second anchor, except in the case of passenger launch. sea bottom. Three are the types of sea bottoms in which
For ships with FEN between 4,7 kN and 9,0 kN, the sec- tests are to be performed, e.g. soft mud or silt, sand or gravel
ond anchor may also be dispensed with, except for pas- and hard clay or similar compounded.
senger launch. In this case, the weight of the anchor is
The pull is to be measured by means of a dynamometer;
to be increased by one third and the length and size of
measurements based on the bollard pull against propeller's
the chain cable are to correspond to the increased
revolutions per minute curve may be accepted instead of
weight of the anchor according to [3.2.2].
dynamometer readings.
d) Ships with service notation tug, salvage tug or escort
tug: Anchor stability and its ease of dragging are to be noted
down, whenever possible.
A reduction of number of anchors may be accepted
according to Ch 6, Sec 1, [18.4]. Upon satisfactory outcome of the above tests, the Society
will issue a certificate declaring the compliance of high or
3.1.3 Anchor design and performance tests very high holding power anchors with its relevant Rules.
Anchors are to be from an Approved Type. Therefore, Hold-
ing power - performance - assessment, Design review and 3.1.4 Manufacturing, materials, test and examination
Tests and examination on manufactured product are to be Manufacturing and materials are to comply with the rele-
carried out. vant requirements of NR216 Materials and Welding.
Anchors are to have appropriate shape and scantlings in Tests and examination requirements are to comply with
compliance with Society requirements. Moreover, they are NR216 Materials and Welding, Ch 4, Sec 1, [1.5].

December 2017 Bureau Veritas 145


NR 600, Ch 5, Sec 4

3.2 Chain cables 3.2.2 Length of individual chain cable


The length of chain cable Lcc, in m, linked to each anchor is
3.2.1 Stud link chain cable scantling to be at least equal to:
Chain cable diameter, type and steel grades are to be as
a) General case:
defined in Tab 1, according to the minimum breaking load
BL and proof load PL, in kN, defined according to the fol- Lcc = 30 ln(P) − 42
lowing formulae: b) For ship having the service notation tug, salvage tug or
• for steel grade Q1: escort tug:
BL = 3 FEN Lcc = 0,15 P + 40
PL = 0,7 BL where:
P : Anchor weight, in kg, defined in [3.1.1] for an
• for steel grade Q2: ordinary anchor according to the considered
BL = 3,4 FEN case.
PL = 0,7 BL The minimum length of chain cable on board is to be in
• for steel grade Q3: accordance with the water depth of anchoring as specified
BL = 3,75 FEN in [1.2.1].
PL = 0,7 BL 3.2.3 Chain cables arrangements
The chain cable scantling is to be consistent with the mass Chain cables are to be made by lengths of 27,5 m each,
of the associated anchor. In case the anchor on board is joined together by Dee or lugless shackles.
heavier by more than 7% from the mass calculated in Normally grade Q2 or Q3 for stud link chain cables and
[3.1.1], the value of FEN to take into account in the present SL2 or SL3 for studless chain cables are to be used with
Article for the calculation of BL and PL is to be deduced HHP and VHHP anchors.
from the actual mass of the anchor according to the formu- The method of manufacture of chain cables and the charac-
lae in [3.1.1]. teristics of the steel used are to be approved by the Society
As a rule, the minimum diameter, in mm, corresponding to for each manufacturer. The material from which chain
a quality Q1 is not to be less than: cables are manufactured and the completed chain cables
• 11 in a general case themselves are to be tested in accordance with the appro-
• 7 for ships having L ≤ 30 m, the service notation ro-ro priate requirements.
passenger ship or passenger ship and a navigation nota- Test and examination requirements are to comply with
tion other than unrestricted navigation. NR216 Materials and Welding, Ch 4, Sec 1.

Table 1 : Proof and breaking loads for stud link chain cables (quality Q)

Grade Q1 Grade Q2 Grade Q3 Minimum mass


Chain diameter
Proof load Breaking Proof load Breaking Proof load Breaking per meter length
(mm)
(kN) load (kN) (kN) load (kN) (kN) load (kN) (kg/m)

11,0 36 51 51 72 72 102 2,7


12,5 46 66 66 92 92 132 3,6
14,0 58 82 82 115 115 165 4,4
16,0 75 107 107 150 150 215 5,7
17,5 89 128 128 180 180 255 6,7
19,0 105 150 150 210 210 300 7,9
20,5 123 175 175 244 244 349 9,1
22,0 140 200 200 280 280 401 10,5
24,0 167 237 237 332 332 476 12,4
26,0 194 278 278 389 389 556 14,5
28,0 225 321 321 449 449 649 16,7
30,0 257 368 368 514 514 735 19,2
32,0 291 417 417 583 583 833 21,9
34,0 328 468 468 655 655 937 24,7
36,0 366 523 523 732 732 1050 27,6
38,0 406 581 581 812 812 1160 30,9
40,0 448 640 640 896 896 1280 33,8

146 Bureau Veritas December 2017


NR 600, Ch 5, Sec 4

Table 2 : Proof and breaking loads for studless link chain cable (quality SL)

Grade SL1 Grade SL2 Grade SL3 Minimum mass


Chain diameter
Proof load Breaking Proof load Breaking Proof load Breaking per meter length
(mm)
(kN) load (kN) (kN) load (kN) (kN) load (kN) (kg/m)

6,0 6.5 13 9 18 13 26 0,8


8,0 12 24 17 34 24 48 1,4
10,0 18.5 37 26 52 37 74 2,4
11,0 22.5 45 32 64 45 90 2,7
12,5 29 58 41 82 58 116 3,5
14,5 39 78 55 110 78 156 4,6
16,0 47.5 95 67 134 95 190 5,6
17,5 56.5 113 80 160 113 226 6,8
19,0 67 134 95 190 134 268 7,9
20,5 78 156 111 222 156 312 9,3
22,0 90 180 128 256 180 360 10,6
24,0 106 212 151 302 212 424 12,7
25,5 120 240 170 340 240 480 14,3
27,0 135 270 192 384 270 540 16,1
28,5 150 300 213 426 300 600 17,9
30,0 166 332 236 472 332 664 19,8
32,0 189 378 268 536 378 756 22,5
33,0 201 402 285 570 402 804 24,0
35,0 226 452 321 642 452 904 27,0
37,0 253 506 359 718 506 1012 30,2
38,0 267 534 379 758 534 1068 32,0
40,0 296 592 420 840 592 1184 35,2

3.2.4 Studless link chain cables Fibre ropes are to be made of polyamide or other equivalent
For ships with FEN less than 18 kN, studless short link chain synthetic fibres, excluding polypropylene.
cables may be accepted by the Society as an alternative to
The effective breaking load PR, in kN, of the rope is to be
stud link chain cables, provided the equivalence in strength
not less than the following value:
is determined according to Tab 2 on the basis of proof loads
defined for steel grade Q in [3.2.1]. • PR = BL for wire rope

• PR = 1,2 BL for synthetic fibre rope,


3.3 Wire ropes and synthetic fibre ropes

3.3.1 As an alternative to the chain cable, wire ropes or where BL, in kN, is the required breaking load defined in
synthetic fibre ropes may be used in the following cases: [3.2.1] of the replaced chain cable.

• for both anchors, for ship length less than 30 m


3.3.2 For ships with service notation tug, salvage tug or
• for one of the two anchors, for ship length between escort tug, see Ch 6, Sec 1, [18.4].
30 m and 40 m.

The ropes are to have a length equal to 1,5 times the chain 3.4 Attachment pieces
cable length as calculated in [3.2.2].
A short length of chain cable having scantlings complying 3.4.1 Both attachment pieces and connection fittings for
with [3.2] is to be fitted between the rope and the bow chain cables are to be designed and constructed in such
anchor. The length of this chain part is not to be less than way as to offer the same strength as the chain cable and are
12,5 m or the distance from the anchor to its stowed posi- to be tested in accordance with the appropriate require-
tion to the windlass, whichever is the lesser. ments.

December 2017 Bureau Veritas 147


NR 600, Ch 5, Sec 4

4 Shipboard fittings for anchoring Where two anchor lines are fitted, the port and starboard
equipment chain cables are to be separated by a bulkhead in the locker.

The inboard ends of chain cables are to be secured to the


4.1 General structure by a fastening able to withstand a force not less
than 15% of the breaking load of the chain cable.
4.1.1 The anchor windlasses are to comply with NR626
In an emergency, the attachments are to be easily released
Anchor Windlass.
from outside the chain locker.
4.1.2 Brake capacity Where the chain locker is arranged aft of the collision bulk-
The windlass brake is to be sufficient to withstand the fol- head, its boundary bulkheads are to be watertight and a
lowing loads: drainage system provided.

• 0,8 time the breaking load BL of the chain defined in


[3.2.1], if not combined with a chain stopper, 5 Shipboard fittings for towing and
• 1,2 time the value of FEN defined in [2.2.1] if combined mooring
with a chain stopper.
5.1 General
4.1.3 Chain stopper
When a chain stopper is fitted, it is to be able to withstand a 5.1.1 The equipment for mooring and or towing are not
pull of 80% of the breaking load of the chain, without any covered within the scope of classification.
permanent deformation of the stresses parts.
However, deck reinforcements under mooring and towing
4.1.4 Deck reinforcement under windlass and chain equipment such as, bitts, bollard, fairleads, chocks... are to
stopper be examined within the scope of hull drawing examination.
Local reinforcement of deck structure are to be provided in For ships of 500 GT and above, the requirements of NR467
way of windlass and chain stopper, and designed in accord-
Steel Ships, Pt B, Ch 9, Sec 4, [5] are to be applied, consid-
ance with NR626 Anchor Windlass for steel and aluminium
ering an equivalent equipment number EN equal to five
structure.
times the value of FEN as calculated in [2.2.1].
For composite materials structure, local reinforcement
structure are to designed in accordance with:
5.1.2 Documents to be submitted
a) Windlass without chain stopper: Brake capacity as
defined in [4.1.2] taking into account safety factors Maximum safe working loads of equipment used for the
equal to SF and SFCS mooring and the towing are to be specified.

b) Windlass combined with chain stopper: A mooring and towing arrangement plan is to be submitted
to the Society for information. This plan is to define the
1) Windlass: Brake capacity as defined in [4.1.2] taking
method of use the mooring and towing lines and to include
into account safety factors equal to 0,7 SF and 0,7
SFCS the equipment location on the deck, the fitting type, the safe
working loads and the manner of applying mooring and
2) Chain stopper: Design load defined in [4.1.3] taking towing lines (including line angles).
into account safety factors equal to SF and SFCS

where: 5.1.3 Hull structure reinforcement

SF : Safety factor for structure checked with mini- As a general rule, hull structure reinforcements in way of
mum stress criteria in layers as defined in Ch 2, mooring and towing equipment are to be examined by
Sec 3, [3.2.3] direct calculation, taking into account:

SFCS : Safety factor for structure checked with com- • a tension in the mooring or towing line equal to the safe
bined stress criteria in layers as defined in Ch 2, working load of the equipment, and
Sec 3, [3.2.3].
• the permissible stresses and safety factors as defined in
Ch 2, Sec 3.
4.2 Chain locker
Note 1: When the mooring plan is not available, the equipment
4.2.1 The chain locker is to be of a capacity adequate to such as bitts and bollards (when the line may come and go from the
stow all chain cable equipment and provide an easy direct same direction) are to be loaded up to twice their safe working
lead to the windlass. loads.

148 Bureau Veritas December 2017

You might also like