ID Task Name Duration Start Sep 30, '18

S M T
1 Site Preparation to FGL (28.6) 1 day? Mon 10/1
2 Roads except Roads G, F, J2 1 day? Mon 10/1
3 Road Side Drainage except along Roads G, F & J2 1 day? Mon 10/1
4 Main Canal (North of site) 1 day? Mon 10/1
5 Access Road from Highway going to Gate 1 1 day? Mon 10/1
6 Steam Turbine, Foundation 1 day? Mon 10/1
7 Deaerator, Foundation 1 day? Mon 10/1
8 Fuel Bunker, Foundation 1 day? Mon 10/1
9 Boiler, foundation 1 day? Mon 10/1
10 Baghouse 1 day? Mon 10/1
11 Ash silo 1 day? Mon 10/1
12 Air compressor 1 day? Mon 10/1
13 Pavement in front of Bldg #17 (Area 17A) 1 day? Mon 10/1
14 150 cum Demin water tank 1 day? Mon 10/1
15 Weighbridge & measure room 1 day? Mon 10/1
16 LP FW Heater 1 day? Mon 10/1
17 HP FW Heater 1 day? Mon 10/1
18 GSC (Gland Steam Condenser) 1 day? Mon 10/1
19 Warehouse electrical/ machine shop/ Lab 1 day? Mon 10/1
20 Safety & security building & guard house 1 day? Mon 10/1
21 Fire rescue building 1 day? Mon 10/1
22 Guardhouse & gate (Front gate) 1 day? Mon 10/1
23 Administration building 1 day? Mon 10/1
24 Centralized locker, shower, rest room 1 day? Mon 10/1
25 Boiler chemical dosing 1 day? Mon 10/1
26 Sample panel 1 day? Mon 10/1
27 Feed water pumps 1 day? Mon 10/1
28 Condesate pumps 1 day? Mon 10/1
29 FD fans 1 day? Mon 10/1
30 Blowdown sump 1 day? Mon 10/1

Task Milestone External Tasks


Project: SIC LEVEL 1 SCHEDULE
Split Summary External Milestone
Date: Tue 10/30
Progress Project Summary Deadline