2019.3.5 Clarification For New SPM Project
2019.3.5 Clarification For New SPM Project
The data of oil Properties as detailed as possible, such as the kind of oil, density,
2 viscosity, water content, Reid vapour pressure, pour point, wax content, solidifying point, ★★★ Please see the attachment I
H2S content, partial pressure of H2S in a wet gas phase of a gas, maximum gas:oil ratio.
3 The annual throughput or design throughput of the project ★★★ 33 Million BBL
7 The head and flowrate of the unloading pump on the tanker ★ 10000 m3/hr at 15 Barg (estimated)
The location (Better have coordinates) of the end of this project (tank farms or refinery or
8 ★★★ Please see the attachment II
other customer)
The minimum pressure demand at the end of the pipeline (inlet of the station), or the
8 ★★★ 3 Bar
minimum pressure demand of the customer (or tank farms or refinery or other customer).
9 The situation of depending on electrical ,telecommunication,etc ★★ Electrical system required for lighting, valve operation and navigation
Whether the special standards be required in this project, if no,We will use international
10 ★★★ API, DNV, ASME and other equivalent international standards
universal standards.
Note:
1. If the project is confirmed, we will organize related research work for more data or information.
2. More detailed data will be discussed in further communication.