2i - 2016 Incident Lesson Learnt Poster
2i - 2016 Incident Lesson Learnt Poster
LESSON LEARNT
2 LTI 17 PD 1 LOPC 17 PROPERTY DAMAGE
ACTIVITIES DURING INCIDENT:
2 LOST TIME INJURY
ALONGSIDE/ PERSONNEL ANCHOR
TOWING MOORING
ACTIVITY DURING INCIDENT: SNATCHING TRANSFER HANDLING
Alongside / Snatching
i. To ensure the risk assessment of alongside activity include external factors such as funneling
ii. To establish the Pre-Operation information exchange & communication between the OSV and
the barge prior any alongside activity
iii. To improve on the HSE Leadership of the Master
iv. Master to execute Master Overriding Authority especially during critical situation
1 LOPC v. Master to ensure suitable size of Yokohama fenders are available prior to alongside of any
barge/FSO/FPSO
vi.
ACTIVITY DURING INCIDENT: vii. Changing of weather shall be monitored closely
viii. To establish good communication and face-to-face discussion between vessel and
TRANSFERRING SCHEDULED barge/platform/FSO/FPSO
WASTE AT THE YARD ix. SISO information shall be cascaded from barge to the vessel
x. If alongside/snatching on weather side is required, JHA shall include all risk and hazard
xi. MOPO limit shall be complied at all times and Master should take early action well before
i. To comply with Environmental reaching the MOPO limit
Quality (Scheduled Wastes)
Regulations 2005 at all time Personnel Transfer
ii. To ensure all scheduled waste
i. Master to comply with the MOPO limit
container is in the good condition,
ii. Master to exercise the Master Overriding Authority and take early action
properly label and legible
iii. Vessel size / type shall be given due consideration in relation to design limitation of the boat
iii. To use wilden pump for chemical landing
transfer in avoiding any spillage iv. To enhance & conduct PMS as per schedule (i.e. change out electronic components such as
micro switches, potentiometer, voltage check on battery, potentiometer)
v. To produce database on expiry/shelf life of electronic component onboard
Anchor Handling
i. Strict compliance to the approved pull out procedure during adverse weather
ii. Always be vigilant of changing weather patterns. Early action is required by the Master to
initiate emergency pull out if the weather is deteriorating
iii. Maintain communication between the vessel and platform for any vessel movement
iv. Maintenance of the pigtail chain and the fitting shall be done accordingly
v. Criteria for rejection of pigtail chain and the fitting shall be incoperated in the achor handling
procedure