CIV4286 Practice Exercise 2 - Semester1-19
CIV4286 Practice Exercise 2 - Semester1-19
Semester 1, 2019
CIV4286 – Project Management for Civil Engineers
PRACTICE EXERCISE 2
A - 3 6
B A 4 4
C A 8 4
D BC 3 6
E B 6 2
F D 3 4
G CD 4 3
H C 5 1
I HEFG 5 6
(a) Construct the project activity network using the Activity on Arrow method.
(b) Identify the critical path(s).
(c) Determine activity float.
(d) If there is a maximum of 8 resource hours per week available for the project, identify any weeks
that have resource over-commitments assuming all activities start at the early start time.
(e) Resource level the loading table. Identify the activities that can be rescheduled and
reconfigured the time-phased resource-loading table to show this re-allocation.