MONASH UNIVERSITY

Department of Civil Engineering

Semester 1, 2019
CIV4286 – Project Management for Civil Engineers

PRACTICE EXERCISE 2

Consider a project with the following information:

Activity Predecessors Duration (weeks) Resource Hours/Week

A - 3 6

B A 4 4

C A 8 4

D BC 3 6

E B 6 2

F D 3 4

G CD 4 3

H C 5 1

I HEFG 5 6

(a) Construct the project activity network using the Activity on Arrow method. 

(b) Identify the critical path(s). 

(c) Determine activity float.
(d) If there is a maximum of 8 resource hours per week available for the project, identify any weeks
that have resource over-commitments assuming all activities start at the early start time.
(e) Resource level the loading table. Identify the activities that can be rescheduled and
reconfigured the time-phased resource-loading table to show this re-allocation.

Due date: 19 April 2019

CIV4286 Practice Exercise 2_semester1-19.doc-14 - 1/04/2019 Page 1 of 1