JSA of EXCAVATIONon
JSA of EXCAVATIONon
M Site
Fall of workmen Double access should be made for workers, either by engineer.
due to providing ladders or cutting steps on the wall of the pit or
inadequate by any appropriate means. More access/ladders shall be
access. provided at every 15m distance if there are hazards due
10. L
to underground facilities and in case of normal conditions
access/ladder should provided at every 30m distance,
when the excavated pit is large. While using the ladder, it
shall be extended 1 m above the ground.
Site
M Excavator / tractor trailor shall be kept / positioned in engineer.
13. L
levelled surface only.
General:
1. If the depth of the pit is less than one meter and if you can maintain 1 m width for walkway, then no barrication is required for the inner pits.
Overall barrication is sufficient, provided all the workmen should be explained about the hazards in that area. If 1 m width cannot be
maintained between the pits, then go for mass excavation with adequate angle of repose.
Walk Walk
way way
Overall Barrication
1m
2. If depth of the pit exceeds 1 m, then maintain adequate angle of repose and do barrication around the pit. After barricading the pit, the width of the walkway should be at
least one meter. Otherwise go for mass excavation with adequate angle of repose and proper access.
Walk Walk
way way
2m
3m