TECHNIP INDIA LTD

CDU – 4 PROJECT BPCL REFINERY MUMBAI


JOB SAFETY ANALYSIS FOR EXCAVATION WORK FOR XXXXXXXX
JOB NO xxxxxxx Date: xxxxxx
Project Location: xxxxxxxxx JSA No.: xxxxxx
Sl. and
P&M Sequence of
Equipment, Resources Hazards Risk Safety measures / precautions Risk Responsi
No. Operation
Tools & tackles – Excavators, operator,involved
helpers at level Rev. No.: level 0 bility
Activity Steps
involved various H/M/ after Action by
steps L contr
Prepared By: ol
Mr. xxxxxx
1. Excavation
Job Description: Excavators,
Excavation Collapse of H If the excavated pit is more than 1.2 m depth, then L Site
operator, earth. appropriate preventive measure to be Reviewed By or
taken like slope engineer.
helpers benching or sheet piling etc. to avoid earth collapse as per
norms and design. The slope of excavation should not be
steeper than the angle of repose of the particular soil.
Reviewed By:
When the slope is less than the angle of repose, which
Job Classification: Civil xxxxxxxx
cannot be achieved because of limited place or
Technip FMCif it is
uneconomical to provide such aslope then shoring should
Name of the Site support the earth. Approved By:
2.Engineer: XXXXXXX M Before starting excavation, it is to be checked whether L xxxxxxxx
Site
Excavation… Crow bar, Electrocution, there is any underground utilities present Technip
like electrical engineer.
spade, mortor water flooding power cables, water pipe line or any other service line in
PPE / safety device Safety
pan. belt, Safety helmet, shoe, goggle, hand gloves,
consultation Need
with Based
the client and consultant.ForWork permit
system shall be followed. Immediate
required Implementation.
3. M Water accumulation to be dewatered regularly. So that L Site
Tractor driver, soil erosion & side collapse can be prevented. engineer.
drivers,
helpers,
M
Fall of men Excavation area should be barricaded 1meter away from Site
4. L
inside the the edge of excavation pit. engineer.
excavated pit.
5. M Barricade the area with warning tape before starting the
excavation work.
Site
L
After finishing the excavation work, barricade the engineer.
excavated pit with pipe / warning tape.

Page 1 of 5 JHA FOR EXCAVATION


Adequate area lighting shall be focused on walkways / Site
6. L
M excavation areas. engineer.
M No materials should be stacked at edge of the excavation
Material falling pit.
on the people Site
7. L
working inside engineer.
the excavated
pit.
M Use load-carrying helmet for carrying the load. Site
8. Excavation… L
engineer.
M Formwork components / excavated earth shall be stacked Site
at a Safe distance (at least equivalent to the depth of engineer.
Excavation) from the edge of the excavated pit to prevent
9.
falling of the components and landslide into the excavated L
pit. Also over stacking of the components should be
avoided.

M Site
Fall of workmen Double access should be made for workers, either by engineer.
due to providing ladders or cutting steps on the wall of the pit or
inadequate by any appropriate means. More access/ladders shall be
access. provided at every 15m distance if there are hazards due
10. L
to underground facilities and in case of normal conditions
access/ladder should provided at every 30m distance,
when the excavated pit is large. While using the ladder, it
shall be extended 1 m above the ground.

M Ramp with an angle not more than 15 degree shall be Site


Hit / run over by made if the excavated earth is to be moved by vehicles. engineer.
11. L
the vehicle.

M Maximum speed limit with in the construction area is 15- Site


12. L
km/ hour. engineer.
Site
Excavation… M Excavator/tractor trailor engaged shall be fixed with engineer.
L
reverse horn.

Site
M Excavator / tractor trailor shall be kept / positioned in engineer.
13. L
levelled surface only.

Page 2 of 5 JHA FOR EXCAVATION


M Barricade the area around the moving equipment. (Care
Moving should be taken that the persons working near by the Site
14. equipment may excavation area may not be hit by moving parts of the L
engineer.
hit the workers excavator.)

M The tipper that shifts the excavated material shall move


Toppling of the only after lowering the hull to the original position after Site
15. L
Vehicles. completion of dumping the material. engineer.

M Vehicles, like concrete mixers shall not be allowed close to


the excavated pit. At least distance equivalent to depth of
Site
16. the excavation shall be maintained between the vehicle L
engineer.
and the edge of the excavated pit.

M Proper lighting is required for work at night. Reflectors &


Fall of vehicle caution boards are to be fixed to caution outsiders. Site
17. L
inside the pit. engineer.

If toxic gases are suspected to be present in the area of


Site
18.Excavation… Asphyxiation excavation, gas test shall be made prior to starting the
engineer.
work.

General:

1. If the depth of the pit is less than one meter and if you can maintain 1 m width for walkway, then no barrication is required for the inner pits.
Overall barrication is sufficient, provided all the workmen should be explained about the hazards in that area. If 1 m width cannot be
maintained between the pits, then go for mass excavation with adequate angle of repose.

Walk Walk
way way

Overall Barrication

1m

Page 3 of 5 JHA FOR EXCAVATION


Mass excavation

2. If depth of the pit exceeds 1 m, then maintain adequate angle of repose and do barrication around the pit. After barricading the pit, the width of the walkway should be at
least one meter. Otherwise go for mass excavation with adequate angle of repose and proper access.

Walk Walk
way way

2m
3m

Reason for why we should go for mass excavation:

 The small vertical slab of earth may collapse on either side.


 Width of the access between the pits may get reduced because of side collapse.
 We can’t stack the rebar & formwork material on small access between the pit.
 Excavated earth may get dumped on the small access between the pit.
 There will be no space for keeping PDB, dewatering pump, etc.
 Workmen should get access within every 30 meters. So go for mass excavation, if walkway cannot be maintained.
 If you want to keep the PDB and formwork material then maintain the width of the walkway for 3 m. If width cannot be maintained, then go for mass excavation.

Page 4 of 5 JHA FOR EXCAVATION


Prepared By Reviewed By Approved By

Page 5 of 5 JHA FOR EXCAVATION