FORMWORK AREA CACULATION

Q'ty
Type L W H Volume Concrete
(pcs)

Elevated 108 pcs 47634 pcs 441 times 2.3 0.1895 0.24 0.104604 4982.707
Underground 40 pcs 6998 pcs 175 times 2.3 0.1895 0.24 0.104604 732.0188
Depot 72 pcs 16653 pcs 231 times 2.4 0.2 0.24 0.1152 1918.426
Total 220 pcs 71285 pcs 324 pcs 7633.151
shortage 3% 7862.146

11.29723
4.18416
8.2944
23.77579
CULATION
Total area
Both sides Bottom Ends form Total area
per pcs
(LxHx2) (LxW) (WxHx2) (Sqm)
(sqm)
1.104 0.43585 0.09096 1.63081 176.12748
1.104 0.43585 0.09096 1.63081 65.2324
1.152 0.48 0.096 1.728 124.416
m3 365.77588
Consumption 140 m2/kg
Consumption/1 time 2.6126849 kg
Density 0.97 g/cm3
2.6934895
shortage 10% 2.9628385
960.02701
Plastic Can 20
Q'ty of cans 48.001351